Upload
deepak3030ei
View
218
Download
0
Embed Size (px)
Citation preview
7/27/2019 Feasibility Study2
1/7
1
ERECTION CONDITIONS
In wind farms construction at least 2 cranes are
needed:
1. A main crane to lift component such as tower
segments, blades and rotor
2. An Auxiliary crane that help the main craneduring the lift operations
Cranes are designed especially to hoist 75-100tonnes gondolas up to hub heights of between 90
and 130 meters above ground level
Project Management
7/27/2019 Feasibility Study2
2/7
7/27/2019 Feasibility Study2
3/7
FINANCIALS
Component Cost (Crores of
Rs/MW)
% of Total Capital
Cost
Wind Turbines 3.8 69
Civil works 0.61 11
Electrical
Infrastructure
0.5 9
Power Conditioning
and Grid Integration
0.39 7
Installation 0.1 2
Others 0.1 2
3
Project Management
7/27/2019 Feasibility Study2
4/7
GOVERNMENT SUPPORT
Sales Tax Exemption Soft Loans From IREDA
Excise duty exemption
Generation Based Incentive: This is a promotionincentive given by government. If the generator is
not availing the facility of accelerated depreciation
then, GBI for wind is 50 paise per unit provided that
the power plant should has a capacity of at least
5MW
4
Project Management
7/27/2019 Feasibility Study2
5/7
GOVERNMENT SUPPORT
CDM Benefits: As per the Kyoto protocol, CDM
benefits can be claimed if an activity is helpful inreducing carbon Emissions. Wind Energy does thesame so CDM benefits can be claimed as per AMS-ID calculation method
MNRE benefits: MNRE has the provision ofproviding some incentives to the wind energygenerators if it is falling under grid interactive
power programmes. Formulae used in thecalculation is : Rs 1.50crores *(c) ^0.646 (Where, cis capacity and ^ stands for raise to power)
5
Project Management
7/27/2019 Feasibility Study2
6/7
ENVIRONMENTAL SUPPORT
These governmental levels view wind power as anefficient means of meeting both environmental and
part of the energy needs of the region
In the Kosta, pressure from nearby port
unfavourably impacted by pollution and support
has helped encourage receptivity towards
renewable energy projects
The Kosta actively and successfully involved inattracting substantial foreign investment
6
Project Management
7/27/2019 Feasibility Study2
7/7
CONCLUSION The steps necessary to proceed with the
implementation of the project include:
1. The land acquisition process
2. Necessary permits, approvals and licenses
3. Closing of financing Project built in a location with good wind resource
and good financial and fiscal incentives for wind
farm development to enhance the projects
financial viability
Project will break even shortly after the repayment
of its cost and will continue to generate profits
over the remainder of its life 7
Project Management