Upload
others
View
5
Download
0
Embed Size (px)
Citation preview
+
DRAFT
Feasibility Report for
2020 Roadway Rehabilitation Project –
Savanna Oaks Area City of Woodbury
City Project No. 16-2019-03
BMI Project No. N12.118928
October 29, 2019
Submitted by:
Bolton & Menk, Inc.
2035 County Road D East
Maplewood, MN 55109
P: 651-704-9970
F: 651-704-9971
Prepared by: Bolton & Menk, Inc. Certification
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928
Certification
I hereby certify that this plan, specification or report was
prepared by me or under my direct supervision, and that I
am a duly Licensed Professional Engineer under the laws of
the State of Minnesota.
By:
Michael Nill, P.E.
License No. 26914
Date: October 29, 2019
Prepared by: Bolton & Menk, Inc. Table of Contents
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928
Table of Contents I. INTRODUCTION ...................................................................................................................... 1
II. REQUIRED IMPROVEMENTS ................................................................................................... 2
SANITARY SEWER ......................................................................................................... 2
WATER MAIN ................................................................................................................ 2
STORM SEWER.............................................................................................................. 2
STORM WATER QUALITY IMPROVEMENTS .................................................................. 2
STREETS ........................................................................................................................ 2
III. PERMITS AND EASEMENT REQUIRED .................................................................................... 3
IV. ESTIMATED COSTS .................................................................................................................. 3
V. COST ALLOCATION ................................................................................................................. 4
COMMERCIAL PROPERTIES .......................................................................................... 5
RESIDENTIAL AND PUBLIC PARK/OPEN SPACE PROPERTIES ........................................ 7
VI. FINANCING ........................................................................................................................... 12
VII. SCHEDULE ............................................................................................................................. 12
VIII. FEASIBILITY, NECESSITY, AND COST EFFECTIVENESS ........................................................... 13
IX. PUBLIC HEARING .................................................................................................................. 13
X. RECOMMENDATIONS ........................................................................................................... 14
Appendix APPENDIX A: FIGURES
APPENDIX B: PRELIMINARY OPINION OF PROBABLE COSTS
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 1
I. INTRODUCTION
The City of Woodbury is planning to rehabilitate several streets during the 2020 construction
season, in accordance with its Capital Improvement Plan. There are approximately 5 miles of
public streets scheduled for rehabilitation as part of this project, which consists of several
locations within the City. This report focuses on the Savanna Oaks area, which contains several
residential developments bounded by Pioneer Drive on the north and east, Radio Drive on the
west, and Lake Road on the south. There are approximately 3.3 miles of residential streets that
are proposed to be rehabilitated as shown on Figures 1 and 2 in Appendix A.
The majority of the streets and utilities that serve the Savanna Oaks area were constructed in the
mid to late 1990s. This neighborhood consists of a mix of single-family residential, multi-family
residential, and commercial properties, along with several public park and open space properties.
As part of the City’s pavement management program, selected neighborhoods have been
analyzed relative to pavement condition and possible improvements. The aforementioned area is
included in the City’s current Capital Improvement Plan as a 2020 Roadway Rehabilitation project.
The majority of the residential streets within the proposed project are 30 to 32 feet wide (from
face of curb to face of curb) with D412 concrete curb and gutter. The Pavement Condition Index
(PCI) of the streets ranges from 26 to 84, with an overall average of 59. These neighborhoods have
experienced high levels of stripping under chip seals. Pothole repairs and thin overlays have been
performed to keep the roads in a drivable and relatively smooth condition. A significant amount of
street maintenance funds are used or are anticipated in upcoming maintenance cycles in these
areas.
A neighborhood meeting was held with the adjacent property owners on August 1, 2019. The
proposed project scope, costs, and funding sources were discussed at the meeting. Property
owners had an opportunity to comment on the project and ask questions. Additional
neighborhood meetings will be held during the design process to allow for additional input from
the property owners and prior to the start of construction.
This report includes a discussion of the improvements required for this street rehabilitation
project. It also provides preliminary cost estimates for the proposed improvements and identifies
funding sources to finance the work.
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 2
II. REQUIRED IMPROVEMENTS
SANITARY SEWER
The existing sanitary sewer consists of polyvinyl chloride (PVC) and vitrified clay pipe (VCP).
The City has recently televised the pipe to determine their condition. Problems typically
encountered were cracked or broken pipes, roots, and leaking joints. Costs have been
included in this report to account for these minor inline repairs. The televising reports will
be reviewed during the final design process to determine the actual extent of inline repairs
needed.
The sanitary sewer manhole castings will be salvaged and reinstalled. Existing concrete
adjusting rings will be replaced with new high-density polyethylene (HDPE) adjusting rings to
conform to current City standards.
WATER MAIN
The water mains within the project area are ductile iron pipes (DIP) and are in good
condition. Valve boxes that are damaged would be replaced with a new top section as
necessary. In addition, all hydrants would be sandblasted, painted, and equipped with a
new locating flag.
STORM SEWER
The existing storm sewer consists of various sizes of reinforced concrete pipe (RCP). The City
recently televised all the pipe within the project area. Some minor repairs are needed. Costs
have been included in this report to account for cracked or broken pipes and one protruding
tap.
Structures in poor condition will be lined or replaced to conform to current city standards.
The storm sewer manhole castings and catch basin castings will be salvaged and reinstalled,
or replaced if damaged. Existing concrete adjusting rings will be replaced with new high-
density polyethylene (HDPE) adjusting rings to conform to current City standards.
STORM WATER QUALITY IMPROVEMENTS
City staff is currently reviewing stormwater quality improvement needs within the project
area. A portion of these improvements may be included in the 2020 Roadway Rehabilitation
project, with the remaining improvements constructed in the winter of 2019/2020 under a
separate project process. The scope of these improvements within the 2020 Roadway
Rehabilitation project will be determined during the design phase of the project.
STREETS
According to the record plans, the existing street section includes 8 inches of class 5 gravel
base and 3 inches of bituminous pavement. The existing street section is similar to the City's
current standard residential street section. Based on the condition of the existing
pavement, the proposed rehabilitation methods consist of a combination of full pavement
removal and replacement and 1.5-inch thick full width mill/overlay.
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 3
The condition of the existing concrete curb and gutter varies on each street. Approximately
10% of streets are recommended for full curb replacement, and 90% of the streets are
recommended for spot curb repairs.
All existing trails and pedestrian ramps have been evaluated. Costs have been included in
this report to update all pedestrian ramps to the current Americans with Disabilities Act
(ADA) standards. In addition, the 8-foot wide bituminous trails along Savanna Oaks Lane,
Timberwood Road, Prairie Oak Trail, and Woodbury Crossing would be rehabilitated by
removing and replacing the existing pavement. Where possible, the trail would be widened
to 10 feet. New trail segments are proposed along Woodbury Crossing, from Prairie Oak
Trail west to the cul-de-sac and along the east side of Magnolia Drive, from Lake Road to
Savanna Oaks Lane.
III. PERMITS AND EASEMENT REQUIRED
All streets in the project area are located within the South Washington Watershed District
(SWWD). Because there will be no disturbance to the existing subgrade, a permit is not required;
however, plans will be submitted to the watershed district for review. Because this project is
considered a maintenance project that would create less than one acre of new impervious
surfaces and would not change the existing grade, hydraulics, or purpose of the roadway, the
MPCA Construction Stormwater permit is not required. A permit from Washington County would
be required if work in performed within their right-of-way on Lori Lane or Horseshoe Road at
Radio Drive (C.S.A.H. 13).
All proposed work is located on public right-of-way or City owned land. Permanent or temporary
easements are not anticipated to be necessary to accomplish the proposed improvements.
IV. ESTIMATED COSTS
Detailed estimates of probable construction costs have been prepared for the improvements
described in this report and are included in Appendix B. All costs are based on anticipated unit
prices for the 2020 construction season and include a 25% percent allowance for engineering,
administrative costs, and financing. Following is an overall summary of the estimated costs:
Estimated Project Costs
Proposed Improvements Total Costs
Sanitary Sewer $141,100
Water Main $130,500
Storm Sewer $156,000
Storm Water Quality $145,300
Streets $2,987,600
Total Estimated Project Costs $3,560,500
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 4
V. COST ALLOCATION
All streets that are proposed to be rehabilitated are considered residential streets. The properties
adjacent to the residential streets are a mix of single-family residential, multi-family residential,
commercial, and public park/open space. Following is a discussion of the proposed assessment
policy for the properties adjacent to the residential streets.
Street and Storm Sewer: Per the City’s current assessment policy, residential properties that have
front yard frontage or private street/driveway access to a residential roadway being rehabilitated
would be responsible for 33% of the street and storm sewer costs on a per residential lot basis or
the minimum assessment as identified based on the construction cost index, whichever is greater.
Commercial properties and public park/open space properties that have frontage on a
rehabilitated roadway would be assigned 100% of the street and storm sewer costs. The costs
would be assigned to the park and open space properties on an equivalent residential unit basis.
The City would be responsible for all remaining street and storm sewer costs. The City would also
be responsible for 100% of the storm water quality improvements.
Sanitary Sewer and Water Main: The City would finance 100% of the sanitary sewer and water
main costs.
The aforementioned assessment procedure is consistent with current City policy.
There are several different types of properties adjacent to the residential streets within these
neighborhoods. A breakdown of the various types of properties is shown below and on Figure 2 in
Appendix A:
Adjacent Properties
Type of Property
Number of
Properties
Residential (Single Family) 340
Residential (Multi-Family) 136
Commercial 4
Public Park/Open Space NA
Total Number of Properties 480
As per City policy, in areas where multiple land uses exist, 50% of the proportional share would be
assigned equally to each individual residential property or equivalent residential unit without
reference to lot width, corner lot location, or subdivision. The remaining 50% of the assessment
would be based on the proportion of street frontage of each land use divided amongst the units in
that land use. This assessment method applies to the public park/open space properties as well.
This assessment method is consistent with current City policy.
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 5
Following is a discussion of how the proposed project costs would be assigned to the various
adjacent properties per the city’s current assessment policy.
COMMERCIAL PROPERTIES
As mentioned previously in this report, there are four commercial properties along Woodbury
Crossing. For these properties, the appropriate percentage of improvement costs would be
assigned based on its adjacent footage on the street being improved. The cost would be
determined by multiplying the cost per adjacent foot by the length of adjacent footage.
There are 32,218 feet of adjacent footage within this project, of which 670 feet is commercial
property. A breakdown of the commercial property frontage is shown in the following table:
Adjacent Footage of Commercial Properties
PID Owner Name
Adjacent
Footage (LF)
16-028-21-13-0085 Woodbury Crossing Offices LLP 277
16-028-21-24-0091 Robert Engstrom Companies 176
16-028-21-24-0092 Pioneer Radio Property LLC 0
16-028-21-24-0095 MSA Building Co 217
Totals 670
Dividing the estimated project costs by the total adjacent footage and applying the city’s current
assessment policy results in the following assessment per adjacent foot for the commercial
property:
Assessment Rates (Commercial Properties)
Item
Estimated
Project
Cost
Total
Adjacent
Footage
Cost Per
Adjacent
Foot
Assessable
Percent
Assessment
per
Adjacent
Foot
Sanitary Sewer $141,100 32,218 $4.38 0% $0.00
Water Main $130,500 32,218 $4.05 0% $0.00
Storm Sewer $156,000 32,218 $4.84 100% $4.84
Storm Water Quality $145,300 32,218 $4.51 0% $0.00
Streets $2,987,600 32,218 $92.73 100% $92.73
Totals $3,560,500 $110.51 $97.57
Applying the assessment rates shown in the previous table to the assessable adjacent footage
results in the following assessment summary table for the commercial property:
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 6
Assessment Summary (Commercial Properties)
Sanitary Sewer
Assessment
per
Adjacent
Foot
Total
Commercial
Assessment
(670 LF)
Remaining
Project
Costs
Total
Project Costs
Sanitary Sewer $0.00 $0.00 $141,100.00 $141,100.00
Water Main $0.00 $0.00 $130,500.00 $130,500.00
Storm Sewer $4.84 $3,242.80 $152,757.20 $156,000.00
Storm Water Quality $0.00 $0.00 $145,300.00 $145,300.00
Streets (Not Including Aprons) $92.73 $62,129.10 $2,925,470.90 $2,987,600.00
Total Project Amounts $97.57 $65,371.90 $3,495,128.10 $3,560,500.00
The total commercial assessment in the previous table would be applied to the commercial
properties based on their adjacent footage. However, there is one parcel (Pioneer Radio Property
LLC) in the southeast corner of Radio Drive and Pioneer Drive that is irregular, as it has no adjacent
frontage. Access to the site is from Woodbury Crossing via the adjacent property’s parking lot
(MSA Building Co). The City’s current assessment policy does not address this type of parcel.
Therefore, it is proposed that the assessments for these two parcels be applied to their total
frontage and divided proportionately based on their area. These two parcels are listed in the table
below, along with their adjacent footage and percent of area:
Irregular Parcels
Geocode Owner
Adjacent
Footage
Area
(SF)
Area
(%)
16-028-21-24-0092 Pioneer Radio Property LLC 0 48,787 24.8%
16-028-21-24-0095 MSA Building Co 217 147,604 75.2%
Totals 217 196,391 100%
Applying the assessment rates as previously described results in the following preliminary
assessment roll:
Preliminary Assessment Roll
Geocode Owner Name
Assessable
Footage
Area
(%)
Total
Assessment
($97.57/LF)
16-028-21-13-0085 Woodbury Crossing Offices LLP 277 NA $27,026.89
16-028-21-24-0091 Robert Engstrom Companies 176 NA $17,172.32
16-028-21-24-0092 Pioneer Radio Property LLC 217
24.8% $5,259.67
16-028-21-24-0095 MSA Building Co 75.2% $15,913.02
Totals 670 $65,371.90
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 7
RESIDENTIAL AND PUBLIC PARK/OPEN SPACE PROPERTIES
The remaining project costs of $3,495,128.10 as shown in the previous Assessment
Summary table would be assigned to the remaining residential and public park/open space
properties per the city’s current assessment policy as described in the following paragraphs.
As mentioned previously in this report in the Adjacent Properties table and as shown on
Figure 2 in Appendix A, there are a total of 476 existing residential properties in the project
area that have either front yard frontage on a roadway being improved or have direct access
via a private street to a roadway being improved and, therefore, would be assigned 33% of
the street and storm sewer project costs per the City's assessment policy. The residential
properties consist of 340 single-family homes and 136 multi-family homes. For purposes of
assessing, each residential property would be considered one equivalent residential unit
(ERU), resulting in 476 ERUs.
There are several locations where city-owned park property or open space is adjacent to a
roadway proposed to be rehabilitated. The amount of adjacent frontage of the combined
park and open space properties is 269 feet. It is proposed to convert the total adjacent
footage of the public park/open space properties to ERU’s based on an average residential
lot width within the project area of 60 feet. This results in 4 ERUs for the public park/open
space properties (269 feet of frontage ÷ 60 feet per residential lot = 4.5 ERUs). Note that the
ERU’s are rounded down to the nearest unit since the portion of an additional lot would not
be buildable. The City would be 100% responsible for all costs assigned to the 4 public
park/open space ERU’s above.
The total ERU’s to which the various remaining project costs are to be assigned is shown in
the following table:
Equivalent Residential Units (ERU's)
Type of Property ERUs
Residential (Single Family) 340
Residential (Multi-Family) 136
Public Park/Open Space 4
Total ERU's 480
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 8
Half of the remaining project costs (i.e. total project costs less the amount assigned previously in
this report to the commercial properties) would be assigned equally to each ERU. The Cost Per
ERU would be calculated by dividing 50% of the remaining project costs for each improvement by
the total number of ERUs. The City’s current assessment policy would be applied to the Cost per
ERU resulting in the following Assessment per ERU:
Table A - Assessment per ERU (50%)
(Residential and Public Park/Open Space Properties)
Item
50% of
Remaining
Project Costs
Number
of ERUs
Total Cost
per ERU
Residential Public Park/Open Space
Assessable
Percent
Assessment
per ERU
Assessable
Percent
Assessment
per ERU
Sanitary Sewer $70,550.00 480 $146.98 0% $0.00 0% $0.00
Water Main $65,250.00 480 $135.94 0% $0.00 0% $0.00
Storm Sewer $76,378.60 480 $159.12 33% $52.51 100% $159.12
Storm Water Quality $72,650.00 480 $151.35 0% $0.00 0% $0.00
Streets $1,462,735.45 480 $3,047.37 33% $1,005.63 100% $3,047.37
Totals $1,747,564.05 $3,640.76 $1,058.14 $3,206.49
The other half of the remaining project costs would be assigned equally to each residential and
public park/open space ERU based on the percentage of frontage for each property type. The
frontage calculations are shown in the following table:
Frontage Calculations
Type of Property
Length of
Frontage (LF)
% of Total
Frontage
Residential (Single Family) 26,537 84.1%
Residential (Multi-Family) 4,742 15.0%
Public Park/Open Space 269 0.9%
Totals 31,548 100%
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 9
Applying the percentage of each frontage to half of the remaining project costs and dividing by
the number of ERU’s per property type results in the following table of assessments:
Table B - Assessment per ERU Based on Property Frontage (50%)
(Residential and Public Park/Open Space Properties)
Item
50% of
Remaining
Project Cost
% of
Total
Frontage
# of
ERUs
Total Cost
per ERU
Assessable
Percent
Assessment
per ERU
Single-Family
Sanitary Sewer $70,550.00 84.10% 340 $174.51 0% $0.00
Water Main $65,250.00 84.10% 340 $161.40 0% $0.00
Storm Sewer $76,378.60 84.10% 340 $188.92 33% $62.34
Storm Water Quality $72,650.00 84.10% 340 $179.70 0% $0.00
Streets $1,462,735.45 84.10% 340 $3,618.12 33% $1,193.98
Totals - Single-Family $1,747,564.05 $4,322.65 $1,256.32
Multi-Family
Sanitary Sewer $70,550.00 15.00% 136 $77.81 0% $0.00
Water Main $65,250.00 15.00% 136 $71.97 0% $0.00
Storm Sewer $76,378.60 15.00% 136 $84.24 33% $27.80
Storm Water Quality $72,650.00 15.00% 136 $80.13 0% $0.00
Streets $1,462,735.45 15.00% 136 $1,613.31 33% $532.39
Totals - Multi-Family $1,747,564.05 $1,927.46 $560.19
Public Park and Open Space
Sanitary Sewer $70,550.00 0.90% 4 $158.74 0% $0.00
Water Main $65,250.00 0.90% 4 $146.81 0% $0.00
Storm Sewer $76,378.60 0.90% 4 $171.85 100% $171.85
Storm Water Quality $72,650.00 0.90% 4 $163.46 0% $0.00
Streets $1,462,735.45 0.90% 4 $3,291.15 100% $3,291.15
Totals - Public Park & Open Space $1,747,564.05 $3,932.01 $3,463.00
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 10
Combining the assessments per ERU from previous Table A and Table B results in the following
total assessment rates for each type of property:
Table A + B
Total Assessment Rate per Property Type
(Residential and Public Park/Open Space Properties)
Item
Single-Family
Assessment
($/ERU)
Multi-Family
Assessment
($/ERU)
Public Park/ Open
Space
Assessment
($/ERU)
Sanitary Sewer $0.00 $0.00 $0.00
Water Main $0.00 $0.00 $0.00
Storm Sewer $114.85 $80.31 $330.97
Storm Water Quality $0.00 $0.00 $0.00
Streets $2,199.61 $1,538.02 $6,338.52
Total Cost per ERU $2,314.46 $1,618.33 $6,669.49
The City of Woodbury has implemented a minimum residential assessment rate for rehabilitation
projects. The rate applies to the street and storm sewer portions only. As of August 2018, the
rates were $2,696 per single-family unit and $1,347 per multi-family unit with 3 to 4.9 units per
acre. Based on the Engineering News Record (ENR) Construction Cost Index for Minneapolis, the
current rates updated from August 2018 to August 2019 would be:
$2,696 x (13,998.80 ÷ 13031.83) = $2,689 per Single Family
$1,347 x (12,998.80 ÷ 13031.83) = $1,344 per Multi-Family
Based on a previous table, the total single-family assessment for storm sewer and streets is
$2,314.46 per unit, which is less than the minimum assessment of $2,689 per unit. Therefore, the
minimum assessment would be applied to the single-family homes.
The total multi-family assessment for storm sewer and streets is $1,618.33 per unit, which is more
than the minimum assessment of $1,344 per unit. Therefore, the minimum assessment wouldn’t
apply to the multi-family homes.
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 11
Applying the minimum single-family assessment of $2,689 proportionally to the storm sewer and
streets in the previous table results in the following table of updated assessments:
Table A + B
UPDATED - Total Assessment Rate per Property Type
(Residential and Public Park/Open Space Properties)
(Minimum Applied)
Single-Family
Assessment
($/ERU)
(Regular)
Multi-Family
Assessment
($/ERU)
Public Park/
Open Space
Assessment
($/ERU)
Sanitary Sewer $0.00 $0.00 $0.00
Water Main $0.00 $0.00 $0.00
Storm Sewer $133.44 $80.31 $330.97
Storm Water Quality $0.00 $0.00 $0.00
Streets $2,555.56 $1,538.02 $6,338.52
Total Cost per ERU $2,689.00 $1,618.33 $6,669.49
Applying the assessment rates shown in the previous table to each assessable residential property
type results in the following assessment summary table. Note that the City would be responsible
for 100% of the costs assigned to the Public Park & Open Space ERUs. Therefore, these costs are
included in the Remaining City Costs column:
Assessment Summary
(Residential and Public Park/Open Space Properties)
Single-
Family
(340 ERUs)
Multi-Family
(136 ERUs)
Remaining
City Costs
Remaining
Project Costs
Sanitary Sewer $0.00 $0.00 $141,100.00 $141,100.00
Water Main $0.00 $0.00 $130,500.00 $130,500.00
Storm Sewer $45,368.15 $10,922.16 $96,466.89 $152,757.20
Storm Water Quality $0.00 $0.00 $145,300.00 $145,300.00
Streets $868,891.85 $209,170.72 $1,847,408.33 $2,925,470.90
Total Project Amounts $914,260.00 $220,092.88 $2,360,775.22 $3,495,128.10
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 12
VI. FINANCING
Based on the previous Assessment Summary table, the total project cost to the City would be
$2,360,775.22. Various funds would be used to finance the City’s portion of each improvement
cost as shown in the following financing summary table:
Financing Summary
Item City Costs Fund
Sanitary Sewer $141,100.00 Water and Sewer Utility Fund
Water Main $130,500.00 Water and Sewer Utility Fund
Storm Sewer $96,466.89 Storm Water Utility Fund
Storm Water Quality $145,300.00 Storm Water Utility Fund (Non-Degradation Retrofit for
Street Rehabilitation Projects allocation)
Streets $1,847,408.33 Street Reconstruction / Maintenance Fund
Sub-Total (City
Costs) $2,360,775.22
Assessments $1,199,724.78
Total Project Costs $3,560,500.00
Assessments would be levied against the benefitting residential properties in accordance with the
City’s current assessment policy.
VII. SCHEDULE
The following schedule allows for construction to be completed during the 2020 construction
season:
Proposed Project Schedule
Order preliminary report June 26, 2019
Neighborhood meeting #1 August 1, 2019
Neighborhood meeting #2 October 29, 2019
Approve preliminary report, public improvement hearing, order
project, authorize plans/specs November 6, 2019
Approve plans/specs, set bid date December 2019
Advertise in local paper January 2020
Open bids January 2020
Neighborhood meeting #3 March 2020
Assessment hearing, award contract March 2020
Neighborhood meeting #4 April 2020
Begin construction May 2020
Complete construction October 2020
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 13
VIII. FEASIBILITY, NECESSITY, AND COST EFFECTIVENESS
The following table compares the cost per linear foot of this project versus the costs shown in the
preliminary reports of other similar rehabilitation projects recently constructed within the City:
Project Cost Comparison
Project
Cost per
Linear Foot
Preliminary
Report
Updated Per
Construction
Cost Index
2017 Roadway Rehabilitation - Residential (West Area) $154 $167
2018 Roadway Rehabilitation - Eagle Valley Area $148 $153
2019 Roadway Rehabilitation - Meadowood Area $175 $175
2020 Roadway Rehabilitation - Savanna Oaks Area $206 $206
Based on the previous table, the cost to rehabilitate the streets within the proposed 2020 project
area is higher than previous projects. This is due to the fact that costs for concrete and pavement
have increased substantially over the last year, and these costs have been adjusted when
estimating 2020 construction costs.
This project is financially feasible. Financial responsibilities have been determined based on
estimated project costs and adopted City policy. Funding sources consist of assessments to
benefitted properties and use of existing designated City funds.
The deteriorated condition of the pavement surface, stable condition of the subgrade, and
relatively good condition of the concrete curb and gutter suggest that a combination of full
pavement removal and replacement and mill/overlay be performed. The improvements are cost
effective as they utilize the existing subgrade and keep existing curb and pavement wherever
possible.
From an engineering standpoint, this project is feasible, necessary, and cost effective.
IX. PUBLIC HEARING
This project will be partially funded by assessing the benefitted properties. Therefore, the City will
need to hold a public improvement hearing to receive comments on the proposed project and to
determine what further action should be taken. For purposes of the hearing, the following
information should be utilized:
Estimated Cost: $3,560,500.00
Total Assessed Cost: $1,199,724.78
Prepared by: Bolton & Menk, Inc.
2020 Roadway Rehabilitation Project – Savanna Oaks Area ǀ BMI Project No. N12.118928 Page 14
Benefited Area:
All parcels within the southeast quarter of the northwest quarter of Section 21, the southwest
quarter of the northeast quarter of Section 21, the southwest quarter of Section 21, and the west
half of the southeast quarter of Section 21, Township 28N, Range 21W, City of Woodbury, County
of Washington, State of Minnesota that have direct driveway or private street access to Aldrich
Trail, Lori Lane, Horseshoe Road, Horseshoe Lane, Timberwood Court, Timberwood Road, Prairie
Oak Trail, Woodbury Crossing, Oak Ridge Trail, Savanna Oaks Lane, Savanna Oaks Alcove, Savanna
Oaks Bay, or Magnolia Drive.
X. RECOMMENDATIONS
It is recommended that this report be used as a guide for the layout, design and cost allocation for
the public improvements to be made as part of the 2020 Roadway Rehabilitation – Savanna Oaks
Area project. It is further recommended that the owners of properties within the project limits be
properly notified of the proposed improvements in order to provide comment.
APPENDIX A: FIGURES
Radio D
rive (C
SAH 13
)
Lake Road
Pione
er Dr
ive
Timbe
rlea D
rive
T. Ct
Inter
lache
n Park
way
R. Ct
Afton Road R. A
lc
Sava
nna O
aks L
ane
Juniper Lane
Sequoia Road
B. Ct
Torrey Drive
Magno
lia
Brittany Lane
W. Crsg
Timber
wood
M.C.
Alco
veLori L
ane
Boulder Ridge Road
Tower Drive
Ambe
rwoo
d Driv
e
North
View
B.R. Ln
S. CtH. Rd
Acadia Road
Oak R
idge T
rail
Horseshoe Lane
A. B
ay
T. Cir
Aldrich Trail
Hidden Glen Cove
S.O. Bay
Timberwood Road
Prairie Oak Trail
LegendSavanna Oaks Area
2020 ROADWAY REHABILITATION PROJECTFIGURE 1 - LOCATION MAP
SAVANNA OAKS AREA F
MSA Building Co.1602821240095
Pioneer Radio Property LLC1602821240095
Woodbury Crossing Offices LLP1602821130085
Robert Engstrom Companies1602821240091
Lake Road
Pione
er Dr
ive
Towe
r Driv
e
Timbe
rlea D
rive
T. Ct
Interl
ache
n Park
way
Afton Road
R. Ct
R. Al
c
Savanna Oaks Lane
Juniper Lane
B. Ct
Torre
y Driv
e
Brittany Lane
Magnolia
W. Crsg
Boulder Ridge Road
Timberw
ood
M.C. A
lcove
Lori L
ane
Sequ
oia Ro
ad
B.R. Ln
North
View
Marsh Creek Road
S. Ct
H. Rd
Oak R
idge T
rail
Horsesh
oe Lan
e
Mead
ow B
rook A.
Bay
T. Cir
Aldrich Trail
B.R. L
ane
S.O. Alc
Hidden Glen Cove
Acadia Road
S.O. Bay
Timberw
ood Road
S.O. Pass
Promenade Lane
A. Trl
N.V. A
bbey
Marsh Creek Road
Document Path: K:\Mike H\2020 RRP\2020 Roadway Rehab Areas - Savanna Oaks Benifitted Properties.mxd
LegendSavanna Oaks AreaSingle Family Home (340)Multi-Family Home (136)Commercial Property (4)Park and Open Space
2020 ROADWAY REHABILITATION PROJECTFIGURE 2 - BENEFITTED PROPERTIES
SAVANNA OAKS AREA F
APPENDIX B: PRELIMINARY OPINION OF
PROBABLE COSTS
ITEM
NO. ITEM UNIT QTY. UNIT PRICE COST
1 ADJUST MANHOLE CASTING, INCLUDING NEW HDPE ADJUSTING RINGS EA 115 $750.00 $86,250.00
2 ADJUST MANHOLE CASTING, INCLUDING NEW HDPE ADJUSTING RINGS (BOULEVARD) EA 5 $650.00 $3,250.00
3 INSTALL MANHOLE DROP SHELF EA 0 $500.00 $0.00
4 REMOVE STEEL ADJUSTING RING EA 55 $100.00 $5,500.00
5 INSTALL 12" (4' DIA) BARREL SECTION EA 2 $1,500.00 $3,000.00
6 PATCH GRAVEL STREET SY 50 $30.00 $1,500.00
7 PATCH STRUCTURE EA 1 $500.00 $500.00
8 CLEAN OUT INVERT EA 2 $500.00 $1,000.00
9 4' CIPP, 8" PVC EA 1 $1,600.00 $1,600.00
10 ADJUST VALVE BOX EA 45 $350.00 $15,750.00
11 ADJUST VALVE BOX (BOULEVARD) EA 15 $250.00 $3,750.00
12 REPLACE TOP SECTION OF VALVE BOX, INCLUDING COVER EA 40 $400.00 $16,000.00
13 RECONSTRUCT VALVE BOX LF 50 $225.00 $11,250.00
14 PATCH GRAVEL STREET SY 160 $20.00 $3,200.00
15 HYDRANT RECONDITIONING AND PAINTING EA 45 $250.00 $11,250.00
16 HYDRANT FLAG EA 45 $50.00 $2,250.00
17 EXTEND HYDRANT BARREL LF 1 $1,500.00 $1,500.00
18 INSTALL HYDRANT…need to verify with City if they want to do this. EA 4 $7,500.00 $30,000.00
19 EROSION CONTROL INSPECTOR LS 1 $5,000.00 $5,000.00
20 ADJUST MANHOLE CASTING, INCLUDING NEW HDPE ADJUSTING RINGS EA 21 $750.00 $15,750.00
21 ADJUST MANHOLE CASTING, INCLUDING NEW HDPE ADJUSTING RINGS (BOULEVARD) EA 5 $650.00 $3,250.00
22 ADJUST CATCH BASIN CASTING, INCLUDING NEW HDPE ADJUSTING RINGS EA 101 $350.00 $35,350.00
23 FURNISH MH COVER (R-1642) EA 2 $350.00 $700.00
24 FURNISH CASTING (R-3067-VB) EA 1 $500.00 $500.00
25 REMOVE AND REPLACE 8' OF 18" RCP LS 1 $2,000.00 $2,000.00
26 INLINE CIPP, 24" RCP LF 108 $80.00 $8,640.00
27 4' CIPP, 12" RCP EA 1 $2,200.00 $2,200.00
28 4' CIPP, 15" RCP EA 1 $2,500.00 $2,500.00
29 4' CIPP, 24" RCP EA 1 $8,000.00 $8,000.00
$94,950.00
PART 3 - STORM SEWER
+ 10% CONTINGENCY
CITY PROJECT NO. 16-2019-03
PART 1 - SANITARY SEWER
$102,600.00
PART 2 - WATER MAIN
$141,100.00
+ 25% INDIRECT COSTS
ESTIMATED CONSTRUCTION COSTS
WATER MAIN - ESTIMATED PROJECT COSTS $130,500.00
SANITARY SEWER - ESTIMATED PROJECT COSTS
ESTIMATED CONSTRUCTION COSTS $104,400.00
$26,100.00
PRELIMINARY OPINION OF PROBABLE COST2020 ROADWAY REHABILITATION PROJECT - SAVANNA OAKS AREA
$10,300.00
$112,900.00
SUBTOTAL
+ 10% CONTINGENCY $9,450.00
+ 25% INDIRECT COSTS
SUBTOTAL
$28,200.00
ITEM
NO. ITEM UNIT QTY. UNIT PRICE COST
30 REMOVE PROTRUDING TAP EA 1 $1,500.00 $1,500.00
31 PATCH STRUCTURE EA 10 $350.00 $3,500.00
32 REMOVE DEBRIS (REBAR) LS 1 $1,500.00 $1,500.00
33 INSTALL STEP EA 1 $350.00 $350.00
34 INSTALL 12" HIGH (4' DIA) BARREL SECTION EA 3 $1,500.00 $4,500.00
35 INSTALL 18" HIGH (4' DIA) BARREL SECTION EA 1 $1,800.00 $1,800.00
36 INSTALL 12" HIGH (2'X3') RISER SECTION EA 2 $1,000.00 $2,000.00
37 INSTALL 18" HIGH (2'X3') RISER SECTION EA 1 $1,300.00 $1,300.00
38 PATCH BITUMINOUS STREET SY 175 $75.00 $13,125.00
39 REMOVE CATCH BASIN OR MANHOLE EA 7 $700.00 $4,900.00
40 5' DIA STORM SEWER MH, 8' DEEP, INCL 4' SUMP & R-1642 CSTG (DETAIL PLATE STO-4) EA 2 $9,000.00 $18,000.00
41 6' DIA STORM SEWER MH, 8' DEEP, INCL 4' SUMP & R-1642 CSTG (DETAIL PLATE STO-4) EA 5 $10,500.00 $52,500.00
42 CONNECT EXISTING PIPE TO NEW STRUCTURE EA 14 $1,000.00 $14,000.00
43 PATCH GRAVEL STREET SY 140 $30.00 $4,200.00
44 PATCH BITUMINOUS STREET SY 105 $75.00 $7,875.00
45 REMOVE AND REPLACE CONCRETE CURB AND GUTTER LF 60 $50.00 $3,000.00
46 TOPSOIL/COMPOST MIXTURE CY 16 $50.00 $800.00
47 SEEDING, MNDOT MIX 25-151 LB 3 $5.00 $15.00
48 HYDRAULIC MATRIX, TYPE MULCH SY 75 $5.00 $375.00
49 MOBILIZATION LS 1 $100,000.00 $100,000.00
50 TRAFFIC CONTROL LS 1 $20,000.00 $20,000.00
51 TEMPORARY MAILBOX EA 75 $50.00 $3,750.00
52 SALVAGE AND REINSTALL MAILBOX CLUSTER EA 25 $125.00 $3,125.00
53 SALVAGE AND REINSTALL SIGN EA 9 $300.00 $2,700.00
54 CLEAR AND GRUB TREE EA 4 $750.00 $3,000.00
55 SAWING BITUMINOUS PAVEMENT LF 575 $3.00 $1,725.00
56 SAWING BITUMINOUS TRAIL LF 80 $3.00 $240.00
57 SAWING BITUMINOUS DRIVEWAY PAVEMENT LF 2,150 $3.00 $6,450.00
58 SAWING CONCRETE DRIVEWAY PAVEMENT LF 925 $5.00 $4,625.00
59 CRACK REPAIR, 1.5' WIDE MILL AND BITUMINOUS PATCH LF 1,030 $15.00 $15,450.00
60 MILL BITUMINOUS PAVEMENT, FULL WIDTH (1.5" THICK) SY 18,000 $1.75 $31,500.00
61 REMOVE BITUMINOUS STREET PAVEMENT SY 41,300 $3.00 $123,900.00
62 REMOVE BITUMINOUS TRAIL PAVEMENT SY 1,700 $4.00 $6,800.00
63 REMOVE BITUMINOUS DRIVEWAY PAVEMENT SY 1,070 $7.50 $8,025.00
64 REMOVE CONCRETE DRIVEWAY PAVEMENT SY 600 $10.00 $6,000.00
65 REMOVE CONCRETE PEDESTRIAN RAMP SF 1,300 $2.00 $2,600.00
$31,200.00
ESTIMATED CONSTRUCTION COSTS $124,800.00
+ 25% INDIRECT COSTS
+ 10% CONTINGENCY $11,335.00
STORM SEWER - ESTIMATED PROJECT COSTS $156,000.00
SUBTOTAL $113,465.00
STORM WATER QUALITY - ESTIMATED PROJECT COSTS
PART 4 - STORM WATER QUALITY
$116,200.00
+ 25% INDIRECT COSTS
$145,300.00
$29,100.00
SUBTOTAL $105,665.00
+ 10% CONTINGENCY $10,535.00
PART 5 - STREETS
ESTIMATED CONSTRUCTION COSTS
ITEM
NO. ITEM UNIT QTY. UNIT PRICE COST
66 REMOVE SIGN EA 6 $100.00 $600.00
67 REMOVE EXISTING GRAVEL BASE CY 1,150 $17.50 $20,125.00
68 REMOVE AND REPLACE CONCRETE CURB & GUTTER, HIGH EARLY - HAND PLACED LF 5,900 $28.00 $165,200.00
69 REMOVE AND REPLACE CONCRETE CURB & GUTTER, HIGH EARLY - MACHINE LAID LF 7,200 $20.00 $144,000.00
70 COMMON EXCAVATION - TRAIL CY 450 $35.00 $15,750.00
71 SUBGRADE EXCAVATION - TRAIL CY 300 $35.00 $10,500.00
72 AGGREGATE BACKFILL - TRAIL TN 700 $16.00 $11,200.00
73 AGGREGATE BASE, CLASS 5 TN 2,300 $14.00 $32,200.00
74 AGGREGATE BASE, CLASS 5 - TRAIL TN 700 $18.00 $12,600.00
75 FINISH GRADING - STREET SY 41,500 $1.50 $62,250.00
76 FINISH GRADING - TRAIL SY 3,220 $2.00 $6,440.00
77 BITUMINOUS MATERIAL FOR TACK COAT GL 4,200 $2.00 $8,400.00
78 TYPE SP 12.5 WEARING COURSE MIXTURE (3,C) TN 7,300 $71.00 $518,300.00
79 TYPE SP 9.5 WEARING COURSE MIXTURE (3,C) TN 4,400 $76.00 $334,400.00
80 TYPE SP 9.5 WEARING COURSE MIXTURE (3,B) TN 1,850 $68.00 $125,800.00
81 TYPE SP 9.5 WEARING COURSE MIXTURE (2,C) - TRAIL TN 580 $80.00 $46,400.00
82 PATCH BITUMINOUS DRIVEWAY SY 500 $35.00 $17,500.00
83 PATCH BITUMINOUS TRAIL SY 75 $35.00 $2,625.00
84 CONCRETE PEDESTRIAN CURB RAMP SF 2,310 $10.00 $23,100.00
85 TRUNCATED DOME PANEL SF 390 $52.00 $20,280.00
86 6" THICK CONCRETE DRIVEWAY APRON (RESIDENTIAL), HIGH EARLY SY 1,200 $62.00 $74,400.00
87 7" THICK CONCRETE DRIVEWAY APRON (COMMERCIAL), HIGH EARLY SY 230 $72.00 $16,560.00
88 MODULAR BLOCK RETAINING WALL SF 400 $45.00 $18,000.00
89 STORM DRAIN INLET PROTECTION PER STANDARD DETAIL ERO-4C EA 100 $150.00 $15,000.00
90 STREET SWEEPER WITH OPERATOR HR 120 $150.00 $18,000.00
91 SKIDSTEER (BOBCAT) WITH OPERATOR HR 120 $125.00 $15,000.00
92 TOPSOIL/COMPOST MIXTURE CY 1,450 $40.00 $58,000.00
93 SEEDING, MNDOT MIX 25-151 LB 300 $5.00 $1,500.00
94 HYDRAULIC MATRIX, TYPE MULCH SY 6,600 $1.50 $9,900.00
95 WEED CONTROL SY 6,600 $0.50 $3,300.00
96 APPLICATION OF WATER FOR TURF ESTABLISHMENT HR 175 $100.00 $17,500.00
97 WATER FOR DUST CONTROL MG 100 $50.00 $5,000.00
98 12" SOLID LINE, WHITE THERMOPLASTIC (BY OWNER) LF 260 $12.00 $3,120.00
$597,500.00
SUBTOTAL $2,172,840.00
STREETS - ESTIMATED PROJECT COSTS $2,987,600.00
+ 10% CONTINGENCY $217,260.00
ESTIMATED CONSTRUCTION COSTS $2,390,100.00
+ 25% INDIRECT COSTS