Farewell to Jennifer

After three years with De Anza, we said goodbye to Jennifer who

accepted a promotion to San Diego.

Page 2: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

Introducing Jim Klingensmith

Jim has been with Gilbane for 20 years

His previous project was SJSU's new library. The facility is 480,000 SF, has a budget of $107M, and will encompass eight stories. Features include a public plaza, and a cafe and gift shop.

Page 3: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

Pool

Renovations began at the end of summer school last year

Page 4: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

Work included the re-plastering and re-tiling of the pools, replacement of supply and return piping, installation of new surge tanks, upgrading of the deck, as well as the purchase of new diving boards and starting blocks.

Page 5: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

This was a $1.6 million project

Page 6: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

The pool was completed at the end of March

Page 7: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

Science Center

Work is progressing well on this project

Page 8: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

The Science Center is on schedule for completion by April 04 and should be online for fall quarter 04

Page 9: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

The complex comprises one and two story buildings with a total of 46,000 SF of space. The project budget is $20 million

Page 10: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

We hope to obtain State furniture and equipment funding for this building, from the November 03 State Bond

Page 11: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

CDC Wing A

This was the first phase of the two-phase renovation of the old CDC building.

Page 12: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

Renovations started in fall 2002 and were completed in winter 2003

Page 13: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

CDC Wing BRenovations began

in March & will be completed in time for the fall quarter

The budget for this project is $600,000

Page 14: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

L 2

Work commenced on L2 in January 03 and should be complete by the end of April this year

Page 15: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego

Once L2 is complete and the classrooms have moved back from the Mod Quad, renovations to L3 will begin

Page 16: Farewell to Jennifer After three years with De Anza, we said goodbye to Jennifer who accepted a promotion to San Diego