Upload
others
View
15
Download
0
Embed Size (px)
Citation preview
Farewell Bend Bridge Final Assessment and Recommendations
February 29, 2016
October 2015 │ Project No. 297-7414-001
DRAFT
Farewell Bend Park
Type, Size, and Location Report
Farewell Bend Bridge
Prepared for
Bend Parks & Recreation Dist.
799 SW Columbia St
Bend, OR 97702
Prepared by
Parametrix
595 SW Bluff Drive, Suite B
Bend, OR 97702
T. 541.508.7710 F. 1.855.542.6353
CITATION
Parametrix. 2015. DRAFT
Farewell Bend Park
Type, Size, and Location Report
Farewell Bend Bridge.
Prepared by Parametrix, Bend, Oregon. October 2015.
DRAFT
Farewell Bend Park
Type, Size, and Location Report
Farewell Bend Bridge Bend Parks & Recreation Dist.
October 2015 │ Project No. 297-7414-001
CERTIFICATION
The technical material and data contained in this document were prepared under the supervision and
direction of the undersigned, whose seal, as a professional engineer licensed to practice as such, is
affixed below.
____________________________________________
Prepared by Daniel J. McIntier, PE
____________________________________________
Checked by Barry Johnson, PE
____________________________________________
Approved by Daniel J. McIntier, PE
DRAFT
Farewell Bend Park
Type, Size, and Location Report
Farewell Bend Bridge Bend Parks & Recreation Dist.
October 2015 │ Project No. 297-7414-001 i
TABLE OF CONTENTS
1. BACKGROUND ..................................................................................................................... 1
1.1 INTRODUCTION ........................................................................................................................ 1
1.2 PROJECT DESCRIPTION ............................................................................................................. 1
1.3 LOCATION ................................................................................................................................ 1
1.4 RIGHT-OF-WAY RESTRICTIONS................................................................................................. 1
1.5 EXISTING CONDITIONS ............................................................................................................. 1
1.6 UTILITY CONFLICTS OR RESTRICTIONS ..................................................................................... 1
1.7 DESIGN CRITERIA AND SPECIFICATIONS .................................................................................. 2
2. ENVIRONMENTAL ................................................................................................................ 2
3. DESIGN CONCEPTS RATIONALE ............................................................................................. 2
3.1 ALTERNATIVE DISCUSSIONS ..................................................................................................... 2
3.2 COST ESTIMATES ...................................................................................................................... 4
3.3 ALTERNATIVE SELECTION ......................................................................................................... 4
4. GEOMETRY AND LAYOUT ..................................................................................................... 5
4.1 STRUCTURE LENGTH ................................................................................................................ 5
4.2 PLAN AND PROFILE .................................................................................................................. 5
5. FOUNDATIONS ..................................................................................................................... 5
6 CONCLUSIONS AND RECOMMENDATIONS ............................................................................ 5
LIST OF TABLES
3-1 Superstructure Evaluation .................................................................................................... 3
3-2 Superstructure Alternative Selection ................................................................................... 4
3-2 Superstructure Cost Estimates .............................................................................................. 4
FIGURES
Figure 1. Vicinity Map
DRAFT
Farewell Bend Park
Type, Size, and Location Report
Farewell Bend Bridge Bend Parks & Recreation Dist.
TABLE OF CONTENTS (CONTINUED)
ii October 2015 │ Project No. 297-7414-001
APPENDICES
A Existing Trail Plan and Profile
B Preliminary Bridge Plan & Elevation Drawing
C Detailed Cost Estimates
DRAFT
Farewell Bend Park
Type, Size, and Location Report
Farewell Bend Bridge Bend Parks & Recreation Dist.
October 2015 │ Project No. 297-7414-001 iii
ACRONYMS PARKS Bend Park & Recreation District
LRFD load resistance factor design
AASHTO American Association of State Highway and Transportation Officials
ODOT Oregon Department of Transportation
TS&L Type, Size, and Location
ROW right-of-way
1. BACKGROUND
1.1 Introduction
This report documents the decisions for determining the appropriate structure type, size, and location
for replacing the existing Farewell Bend Bridge with a longer clear span structure.
1.2 Project Description
The bridge is a vital part of the Park’s trail network in Deschutes County (County). It serves as a primary
pedestrian route for the parks on each side of the Deschutes River, recreation and event uses.
The original Farewell Bridge was built in 1940s with an out-to-out width of 15 feet. The existing longest
span is 81 feet with a bridge length of 136 feet. The river is near perpendicular to the pedestrian bridge
and the bridge is oriented on a north-south axis.
The river active channel width is defined at 136 feet requiring a new bridge span of 155 feet. The
Ordinary High Water Mark (OHWM) is at Elevation 3604.19. The 50-year flow elevation is XXXX.XX feet.
1.3 Location
The project site is in central Bend in the Old Mill District, where the Deschutes River transects Farewell
Bend Park and Riverbend Park The bridge is at latitude N44°02'31", longitude W121°19'30" in Township
18S, Range 12E, Section 6, west side, Willamette Meridian. See Figure 1 – Vicinity Map.
1.4 Right-of-Way Restrictions
There are no anticipated right-of-way restrictions for the project. The replacement bridge will be on the
same alignment as the existing bridge.
1.5 Existing Conditions The northern portion of the area is located within Riverbend Park and includes a rocky shoreline lined
with riprap. The northern terminus of the area is delineated by a paved bike/pedestrian trail (which
historically was used as a logging road) and a rock cliff.
The southern portion is located within an area that was historically used as a log deck before being
converted to Farewell Bend Park. This area consists of an artificial shoreline constructed of fill and riprap
and a paved bike/pedestrian trail.
The Deschutes River within the area is highly regulated by dams upstream and downstream. Also, the
river is regulated to flow higher during the summer and lower during the winter draw-down period.
1.6 Utility Conflicts or Restrictions
Presently, there are no overhead or underground utilities within the bridge footprint. A relocation plan,
as required, will be developed during final design. The proposed bridge can allow for attachment of
utilities such as irrigation lines or conduits for future use.
1.7 Design Criteria and Specifications
Preliminary designs have been developed in accordance with the AASHTO LRFD Guide Specification for
the Design of Pedestrian Bridges, December 2009.
Assumptions and design criteria used to establish this Type, Size, and Location (TS&L) study are:
• Plans, specifications and cost estimates will be prepared in English units.
• Design Live Load shall be 90 psf (pedestrian) and a H10 Vehicular Live Load.
• Unit costs for estimates are based on ODOT unit bid prices and previous pedestrian bridge
projects.
• Minimum clearance from the water will be 7’ with a desired minimum of over 8’.
• Bridge grades will be set to allow for accessible grades on the approaches as well as the bridge.
Bridge railing height follows the AASHTO Guide for the Development of Bicycle Facilities, 2012, 4th
edition and is planned at 48 inches in height utilizing vertical pickets to deter climbing and jumping.
Additional railing treatment may include stainless steel cables above and/or outside the hand railing to
further deter jumping.
The proposed bridges shall be designed for a 75 year life with maintenance on an as needed basis for
bridge elements that wear with use, ie. timber decking and bearing pads.
2. ENVIRONMENTAL
It is understood that there are several environmentally sensitive areas located in the proximity of the
structure. However, it is assumed that environmental concerns will not influence the type, size, or
location of the proposed structure.
3. DESIGN CONCEPTS RATIONALE
3.1 Alternative Discussions
The Farewell Bend Bridge is a vital part of the trail network in Bend. Based on a review of the existing
trail corridor, maintaining the existing alignment is proposed in order to minimize environmental and
length of span impacts. Therefore, differences between each alternative where evaluated on cost,
constructability, construction schedule, and aesthetics.
Four superstructure types were evaluated for span capacity, availability, and cost. The girder types are
shown in Appendix D-1. The girder types evaluated were:
1. Pre-engineered truss bridge – Constant depth Pratt through truss with timber deck. The bottom
chord of the truss is about 3 feet below the deck with a majority of the truss above the deck. This
alternative increases clearance from the river and maintains or lowers the trail profile. Readily
available in the Pacific Northwest.
2. Pre-engineered bowstring arch truss bridge- Bowstring arch through truss with timber deck. The
bottom straight chord is about 2 feet below the deck with the arch shape above the deck. This
alternative increases clearance from river and maintains or lowers the trail profile. Readily available
in the Pacific Northwest.
3. Prestressed Bulb Tee Girders with concrete composite deck – BT84 prestressed girders with a cast in
place concrete deck 9 inches thick. The girder is below the deck with the bottom flange about 8 feet
below. Structure mass will require larger footing/piling. This alternative either reduces the vertical
clearance or requires more extensive modifications to the approach trail slopes. Girders may come
from Harrisburg, Oregon or Caldwell Idaho.
4. Steel plate girders with concrete composite deck – Steel plate girders were evaluated for
completeness. Steel girders are typically not desirable due to the higher costs, higher maintenance,
and availability. The steel beams would be made composite using a formed cast-in-place concrete
deck a minimum of 9 inches thick. The bottom flange is about 10 feet below the deck. This also
reduces the vertical clearance or requires more extensive modifications to the approach trail slopes.
Structure mass will require larger footing/piling. Steel girders can be fabricated in Portland,
Oregon, Deer Park, Washington or Salt Lake City, Utah.
Each girder has construction and design issues as shown in Table 3-1.
Table 3-1. Superstructure Evaluation
The following selection matrix, Table 3-2, rates each alternative by category by ranking from 4 to 1. A 4
is the highest rank (most favorable) and a 1 the lowest (least favorable). In the event of an equal
comparison each alternative is given the same rank. The values are summed with the highest score
being most favorable. To clarify the criteria, the following provides a short explanation of decision
factors.
• Issues –effort in preparing a design for alternative.
• Efficiency –structural capacity versus mass of alternative.
• Availability –fabricator location and shipping to site
• Spliceable –being delivered in shorter sections and assembled on site.
• Shipping –difficulty in delivering, storing, and erecting.
• Schedule –amount of time to erect alternative (impact to users).
• Equipment –type and size of erection equipment.
• Cost –estimated cost of structure not including any other cost.
Girders Deck
Stay in
Place Form Construction Issues Design Issues
Pratt Truss Timber N/A Splicing Jump
deterrent
Bowstring Arch
Truss
Timber N/A Splicing Jump
deterrent
PS girders Concrete No Weight Cost Delivery Depth Max Span Aesthetics
Steel girders Concrete No Weight Cost Splicing Depth Maintenance Aesthetics
• Site –work zone footprint needed to complete the structure.
• Jumping –deterrent to jumping from the bridge, climbing the bridge, etc.
• Trail –impact to existing trail plan and profile.
• View from –the amount of visual obstructions of the river from the bridge.
Table 3-2 Superstructure Alternative Selection
Selection Criteria
Design Construction Impacts
Superstructure Issues Efficiency Availability Spliceable Shipping Schedule Equipment Cost Site Jumping Trail View
Pratt Truss 4 4 4 Yes 4 4 4 4 4 3 4 4
Bowstring Truss 4 3 4 Yes 4 4 3 3 4 4 4 3
PS Girder 2 2 3 No 1 2 1 4 2 1 1 4
Steel Girder 1 1 3 Yes 2 2 2 1 2 1 1 4
The Pratt Truss and the Bowstring Truss are nearly equal in rankings with scores of 43 and 40
respectively. The PS girder and steel girder bridges total 23 and 20, respectively.
3.2 Cost Estimates
The tables below provide a preliminary construction cost estimate for each of the alternatives based on
the bid item unit cost per ODOT unit bid tabulations based on 3 low bids through December 2014 and
historic project costs for pedestrian bridges. These are summarized in the Table as cost per square foot.
The cost estimate does not include costs of trail work, environmental or erosion control, preliminary
and final design, or construction engineering.
This is a preliminary estimate for comparison of superstructure types and, therefore, has a 15 percent
contingency added to the estimated quantities. A detailed estimate is in Appendix C. A summary of
costs is shown in Table 3-3.
Table 3-3
Superstructure Bridge Cost
Range
Approx.
Cost/SF
Remarks
Pratt Truss $495k – 545k $257 Recommended
Bowstring Truss $570k – 625k $298
PS Girder $505k – 555k $263 Does not include cost to raise trail
Steel Girder $810k – 890k $423 Does not include cost to raise trail
3.3 Alternative Selection
From a cost perspective, Alternatives 1 through 3 are about equal cost per square foot if you add in the
cost of raising the trail for Alternative 3 knowing that raising the trail may impact the ADA allowable
slopes. In comparison, the pre-engineered truss alternatives will require smaller cranes and less time for
construction than the bridge girder alternatives. See Appendix B for preliminary Plan and Elevation
drawing.
4. GEOMETRY AND LAYOUT
4.1 Structure Length
The river’s active channel width is 136 feet. Typically, a single span bridge length is determined by the
active channel width multiplied by 1.5. This would require a span length of 200 feet. There is a steep
rocky outcrop near the river on the north side and a steep bank to an elevated fill on the south side. In
addition, due to the significant control of flows through upstream dams, the variation in maximum flows
is relatively minor. A reduction in total span length is appropriate. Therefore, the estimated span length
is 160 feet.
4.2 Plan and Profile
The bridge will be located to match to the existing trail plan and profile.
5. FOUNDATIONS
A geotechnical investigation is being performed for the TS&L by Wallace Group. It is anticipated that the
foundation system would be small-diameter pipe piles. With the long span, seat abutments using
elastomeric bearings for thermal displacements are anticipated. Approach slabs are not anticipated.
The backfill at the abutments will have geotextiles placed at each lift to minimize approach settlement.
The final foundation and abutment fixity will be determined during final design. For estimating
purposes, it is assumed the piling will be 80 feet in length.
6. CONCLUSIONS AND RECOMMENDATIONS
The increased bridge span and location of the bridge in the trail alignment have resulted in some ideal
bridge geometry with minimal impact to the environment. The bridge is on a tangent with a crest curve
vertical profile. The long span minimizes impacts to the Deschutes and eliminates timber piling or any
other structures in the river. The pre-engineered truss is commonly used for pedestrian bridges and
can be found in use near this site. There are several customizations that can be accommodated by the
fabricators for aesthetics and user safety.
Based on the assessment and rankings, the prefabricated truss options are relatively equal. The
following is a list of comparisons between the two truss options.
Description Pratt Truss Bowstring Truss
Cost Most Economical About 15% more than Pratt
Stiffness (Bounce) Most noticeable movement Stiffer than Pratt but not as stiff as
girder bridges
Jump Deterrence Can be modified to add extensions to
rail that angle away. Will be more
pronounced than Bowstring Truss
Can be accommodated with addition
of cables between structural
members. No “appendages” needed
Aesthetics Simple structure that has the least
visual obstruction
Bowstring truss style was used in
many of the old mill buildings. Is
more interesting and open.
View From Bridge No obstruction above eye height.
Has a large structural member (about
12” x 12”) at top of railing
Structural member varies in height
across the length with the bottom of
member about 9’ above the deck at
mid-span. Varies from about 7.5’ to
9’ over main channel.
Either truss option meets the design criteria identified. The importance of the various factors shown
above will dictate the preferred alternative.
EXISTING BRIDGE
PRATT TRUSS