21
Failures of Line Capacitors: Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University IEEE PES General Meeting Boston, MA USA 18 July 2016 1

Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Failures of Line Capacitors: Selected Case Studies

Jeffrey Wischkaemper, Ph.D.Texas A&M University

IEEE PES General MeetingBoston, MA USA

18 July 2016

1

Page 2: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Distribution Fault Anticipation

• Distribution Fault Anticipation (DFA) is a system of waveform analytics developed at Texas A&M University over the past 15 years.

• DFA uses sophisticated waveform recording devices, installed at substations on a one-per-feeder basis connected to standard CTs and PTs to monitor the health and status of distribution circuits and line apparatus.

• DFA technology has been demonstrated on over 150 distribution feeders at 20 utility companies.

2

Page 3: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Line recloser*tripped 8% ofphase-A load twice,but reclosed and didnot cause outage

Breaker lockout caused by fault-induced conductor slap

Inputs: Substation CT and PT Waveforms

*Analytics applied to high-fidelity substation waveforms report on hydraulic line reclosers, switched line capacitors, apparatus failures, etc, without requiring communications to line devices.

OutputsWaveform Analytics

Failing hot-lineclamp on phase B*

Failed 1200 kVARline capacitor*(phase B inoperable)

On-Line Signal Processing and

Pattern Recognition

Analytics

(Performed by DFA Device in

Substation)

Distribution Fault Anticipation – Block Diagram

Copyright © 2014, The Texas A&M University System

Page 4: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Documented Failures•Voltage regulator failure•LTC controller maloperation•Repetitive overcurrent faults•Lightning arrestor failures•Switch and clamp failures•Cable failures

– Main substation cable

– URD primary cables

– URD secondary cables

– Overhead secondary cables

•Tree/vegetation contacts– Contacts with primary

– Contacts with secondary services

•Pole-top xfmr bushing failure•Pole-top xfmr winding failure•URD padmount xfmr failure•Bus capacitor bushing failure•Capacitor problems

– Controller maloperation

– Failed capacitor cans

– Blown fuses

– Switch restrike

– Switch sticking

– Switch burn-ups

– Switch bounce

– Pack failure

Copyright © 2014, The Texas A&M University System

Page 5: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Why Capacitors?

• Given the fact that DFA detects a wide variety of failures, why focus on capacitors?

– Capacitors are common on distribution systems and fail relatively often.

– Capacitor failures can cause other devices on the same circuit or other circuits to fail.

– Capacitor failures demonstrate important lessons for design of waveform analytics systems.

5

Page 6: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• “Normal” capacitor switching operations are characterized by distinct waveform phenomena:

– A high frequency voltage transient

– A step change in voltage, visible at the bus

6

Page 7: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• Capacitor switching is generally controlled based on time of day, temperature, and / or voltage.

• Line capacitors typically switch ON and OFF one, or perhaps two times per day.

7

Page 8: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• In 2004, a capacitor controller on a DFA monitored feeder began switching excessively, logging over 4,000 operations in a period of two months.

8

0

20

40

60

80

100

120

140

160

180

200

01/01/2004

03/01/2004

05/01/2004

07/01/2004

09/01/2004

11/01/2004

13/01/2004

15/01/2004

17/01/2004

19/01/2004

21/01/2004

23/01/2004

25/01/2004

27/01/2004

29/01/2004

31/01/2004

02/02/2004

04/02/2004

06/02/2004

08/02/2004

10/02/2004

12/02/2004

14/02/2004

16/02/2004

18/02/2004

20/02/2004

22/02/2004

24/02/2004

26/02/2004

28/02/2004

Capacitor Operations per day

>

Page 9: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• TAMU informed the utility company of the excessive operations, but because DFA was a “research” project, the utility allowed the capacitor to continue to failure.

• Initially, each individual switching event could be considered “normal” if viewed in isolation (i.e. none of the individual events by themselves suggested anything was amiss – they were identical to a “healthy,” “normal” capacitor switching event).

• Taken together, however, it was clear even from the first day that a capacitor controller was failing (i.e. four “normal” operations in one day are truly normal – forty “normal” operations in one day are notnormal).

9

Page 10: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• After several weeks of excessive switching, one phase of the capacitor bank failed in a short-circuit, resulting in a fuse operation. The other two phases continued switching “normally,” resulting in dozens of unbalanced capacitor switching operations each day.

• After two months and thousands of switching operations, the switch on one of the two remaining phases degraded to the point where it failed to make a good connection, resulting in inter-contact arcing.

10

February 16, 2004 16:36:58

-4,000

-3,000

-2,000

-1,000

0

1,000

2,000

3,000

4,000

1.95 2.00 2.05 2.10

Time (seconds)P

rim

ary

Am

ps

Ia Ib Ic

Page 11: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• Recall that each time a capacitor switches ON, it results in a large voltage transient, which in turn creates a significant voltage transient.

• Electrically, contact arcing is similar to the switch operating many times a second, resulting in many high frequency transients in a short period of time.

• These transients create significant voltage distortion, creating serious power quality problems, and damaging other line apparatus.

11

February 29, 2004 04:57:45

100

150

200

0.00 1.00 2.00 3.00 4.00

Time (seconds)P

rim

ary

RM

S A

mp

s

Ia Ib Ic

Total customer complaints: 0!

Page 12: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• After several days of inter-contact arcing, the switch failed in an open-circuit state, at which point the utility company investigated and documented failures.

• After two months of excessive switching, voltage transients caused by the malfunctioning capacitor controller resulted in the failure of:

– The capacitor bank it was responsible for controlling

– Another capacitor bank on the same feeder

– A third capacitor bank on an adjacent feeder.

12

Page 13: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• Lessons:

– Don’t ignore “normal” events!• Shortly after this event, DFA detected 22 capacitor operations in a

single day at a different utility.

• Prompt response by the utility company in the second case avoided the escalation seen in the first case.

• Each individual operation was “normal” but the 22 taken together were a failure!

13

Page 14: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 1: Capacitor Controller Failure

• Lessons:

– Don’t ignore “normal” events!

– Capacitor failures can cause other equipment to fail (including equipment on other circuits!).• Voltage transients affect all customers on the bus.

• In this case, the failing capacitor controller caused the failure of three separate capacitor banks, including one on an adjacent feeder.

• This is not an isolated incident. DFA has documented multiple examples of sympathetic equipment failure caused by capacitor misoperations.

14

Page 15: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 2: Vacuum Switch Failure

• On 11 May 2014, a DFA device detected a capacitor OFF switching operation with severe restrike.

• Capacitor restrike is a condition that occurs when a bank switches OFF, caused by a breakdown in the dielectric integrity of the switch, which allows current flow to resume momentarily.

• The following day, the capacitor switched OFF without incident.

15

Page 16: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 2: Vacuum Switch Failure

• On 13 May 2014, the capacitor experienced severe restrike again, which this time escalated into an overcurrent fault, shown in the graph on the right.

• After being informed of the event, the utility serviced the capacitor, and found a blown fuse and blown lightning arrestor.

16

Page 17: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 2: Vacuum Switch Failure

• Surprisingly, when the line crew performed a high potential test on the switch, it passed.

• The event began when a capacitor switch failed to open cleanly, which caused high frequency transients, which caused a lightning arrestor to go into conduction and a fuse operation.

17

Page 18: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 2: Vacuum Switch Failure

• Lessons:

– Waveform analytics often provide the first (and sometimes only!) notification of incipient problems.• In this case, the utility uses a sophisticated capacitor

switching system, which would (and did) detect the next, unbalanced, switching event - but it does not (and cannot) detect abnormal switching events like a switch bounce or restrike.

• Notification must be timely! The failure could have happened on any restrike. Prompt action was necessary.

18

Page 19: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Case Study 2: Vacuum Switch Failure

• Lessons:

– Waveform analytics often provide the first (and sometimes only!) notification of incipient problems.

– Waveform records often provide a more complete picture than field investigation alone.

• Because the switch passed its initial hi-pot test, it is likely that absent DFA information, the utility would have simply returned the switch to service, which would create further problems.

19

Page 20: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Conclusions

• Labels like “normal” and “abnormal” are contextual.

– You cannot know a priori whether an event that looks “normal” at the time will later become important – and thus you cannot ignore it.

– The “normal” event you just ignored (and didn’t save) may become “abnormal” five minutes from now.

• Reporting possible incipient events needs to be automated, prompt, and actionable.

– You can’t wait for a customer complaint to assign an engineer to analyze data from the past two weeks hoping they will discover a problem.

20

Page 21: Failures of Line Capacitors: Selected Case Studiesgrouper.ieee.org/groups/td/pq/data/PS_2016/16PESGM2413.pdf · Selected Case Studies Jeffrey Wischkaemper, Ph.D. Texas A&M University

Conclusions

• Waveform recordings of incipient failures have limited value after the failure occurs.

– Forensic analysis after the failure (“I have waveforms from three weeks ago that would have let me avoid the problem... if I had looked at them…”) is much easier than predictive analysis before the failure happens (“This waveform from five minutes ago indicates that ______ may be about to fail…”).

• Systems that require humans to classify waveforms or analyze data will not scale beyond “research” projects.

21