1 FACT SHEET FIN NO. 440858-1-58-01: Turnpike Feeder Road at NW 199 Street Pedestrian Overpass FIN NO. 440858-2-54-01: City of Miami Gardens Pedestrian Safety Improvements – Bridge/Tunnel PROJECT SCOPE This project involves the design and construction (Design/Build) of a pedestrian bridge over the Florida Turnpike exit ramp (Exit #2X) for the Hard Rock Stadium. A pedestrian bridge over NW 199 Street and two tunnels under Don Shula Drive, the stadium perimeter road, will also be constructed as part of the project to improve pedestrian access and enhance public safety. The Scope of Work includes the construction of a steel bridges, Mechanically Stabilizing Earth (MSE) or retaining walls, drainage improvements, curb and gutter, ADA sidewalk and ramp reconstruction, roadway reconstruction, parking lot modification and resurfacing and construction of two tunnels under the stadium perimeter road. PROJECT MAP

FACT SHEET - Hard Rock Pedestrian Bridge Project · City of Miami Gardens Pedestrian Safety Improvements – Bridge/Tunnel . PROJECT SCHEDULE . The design phase of this project began

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: FACT SHEET - Hard Rock Pedestrian Bridge Project · City of Miami Gardens Pedestrian Safety Improvements – Bridge/Tunnel . PROJECT SCHEDULE . The design phase of this project began

1

FACT SHEET FIN NO. 440858-1-58-01:

Turnpike Feeder Road at NW 199 Street Pedestrian Overpass

FIN NO. 440858-2-54-01: City of Miami Gardens Pedestrian Safety

Improvements – Bridge/Tunnel

PROJECT SCOPE This project involves the design and construction (Design/Build) of a pedestrian bridge over the Florida Turnpike exit ramp (Exit #2X) for the Hard Rock Stadium. A pedestrian bridge over NW 199 Street and two tunnels under Don Shula Drive, the stadium perimeter road, will also be constructed as part of the project to improve pedestrian access and enhance public safety. The Scope of Work includes the construction of a steel bridges, Mechanically Stabilizing Earth (MSE) or retaining walls, drainage improvements, curb and gutter, ADA sidewalk and ramp reconstruction, roadway reconstruction, parking lot modification and resurfacing and construction of two tunnels under the stadium perimeter road. PROJECT MAP

Page 2: FACT SHEET - Hard Rock Pedestrian Bridge Project · City of Miami Gardens Pedestrian Safety Improvements – Bridge/Tunnel . PROJECT SCHEDULE . The design phase of this project began

2

FACT SHEET FIN NO. 440858-1-58-01:

Turnpike Feeder Road at NW 199 Street Pedestrian Overpass

FIN NO. 440858-2-54-01: City of Miami Gardens Pedestrian Safety

Improvements – Bridge/Tunnel

PROJECT SCHEDULE The design phase of this project began in August 2018. The construction phase of the project is slated to begin in January 2019 and scheduled for completion in September 2019. AFFECTED MUNICIPALITIES City of Miami Gardens LANE CLOSURE AND DETOUR INFORMATION This project is designed to have two lanes always open in each direction. All lane closures on NW 199 Street will be coordinated with Miami-Dade County Traffic Engineering Department. All lane closures on the Turnpike Connector Road will be coordinated with Florida’s Turnpike Enterprise. During construction, complete closures will be limited to off-peak hours between 11:00 p.m. and 5:00 a.m., Monday through Friday. ALWAYS PUT SAFETY FIRST For your safety and the safety of others, please use caution when driving around any construction zone. While driving, wearing a seat belt is the single most effective way to protect people and reduce fatalities in motor vehicle crashes. While the Florida Department of Transportation, the City of Miami Gardens and Hard Rock Stadium take steps to reduce construction impacts, you might experience travel lane closures, increased dust and noise and workers and equipment moving around the work zone. PUBLIC INFORMATION Our public information team is here to answer your questions and address any concerns regarding this project. We've made it easy to get in contact with us 24 hours a day, seven days a week. CONTACT: CONTACT: Myrick Mitchell Tasha Cunningham Public Information Specialist Senior Public Information Specialist The Brand Advocates The Brand Advocates 305-301-1053 305-335-8466 [email protected] [email protected] PROJECT WEBSITE A website has been created to give stakeholders the opportunity to get the latest information about the project. Visit www.HardRockPedestrianBridgeProject.com at any time to sign up for weekly updates, request a project presentation or contact a member of the Public Information Team. PROJECT PARTNERS