Facilities Project Management Monthly Report by Building
Tuesday, June 05, 2018 153Approved Project
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
1 Leavitt Lane Projects in Building 1
1 Leavitt Lane ‐ 123 renovation
3‐ IN CONSTRUCTION
FCRPOLITANO, FRANK
5/30/18_ Work has been completed, customer has asked for a change.
Design Firm: Contractor: External Contractor Name: Milestone
2016‐0429
10 Pettee Brook Lane Projects in Building 1
10 Pettee Brook Lane ‐ Renovations to Space
3‐ IN CONSTRUCTION
FCRROULEAU, RICHARD A
6/4/2018 Update: Construction is underway. Addressing submittals and RFIs. Substantial
completion anticipated for mid to late‐August. Furniture is being finalized and will be ordered
soon.
Design Firm: Manypenny Murphy Archite Contractor: External Contractor Name: Landlord
2017‐0472
11 Brook Way Projects in Building 1
11 Brook Way ‐ Building Demolition
2.5‐ IN PROCUREMENT
FCRRINES, DANIEL M
5‐21‐18: pcb testing came back negative, bids will be awarded 5‐30‐18.
Design Firm: Contractor: Contractor Name:
2016‐0437
121 Technology Drive Projects in Building 3
121 Technology Drive ‐ Advanced Manufacturing Center
3‐ IN CONSTRUCTION
FCRBRICKETT, ALEXANDER J
5/30/18_Punchlist items in progress.
Design Firm: JSA, Inc. Contractor: External Contractor Name: Careno Construction
2016‐0301
121 Technology Drive ‐ Fit Up of Unassigned Suite
3.1‐ SUBSTANTIAL COMPLETION
FCRBRICKETT, ALEXANDER J
5/30/18_Update ‐ Please refer to ID 2016‐0186 for updates.
Design Firm: Contractor: External Contractor Name: Careno Construction
2018‐0062
Tuesday, June 05, 2018 Page 1 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
121 Technology Drive ‐ Interior Lease Space Renovations
3.1‐ SUBSTANTIAL COMPLETION
FCRBRICKETT, ALEXANDER J
5/30/18_Project is substantially complete. Punchlist and completion items ongoing.
Design Firm: Cowan‐Goudreau Contractor: External Contractor Name: Careno Construction
2016‐0186
5 Leavitt Lane Projects in Building 1
5 Leavitt Lane ‐ Library Storage Building Structure Investigation
1.1‐ PLAN/EST
RRRINES, DANIEL M
6‐5‐18 PM will reach out to customer, and Term Structural consultants
Design Firm: Contractor: Contractor Name:
2018‐0363
88 Commercial Street Projects in Building 1
88 Commercial Street ‐ Mechanical Tech Lab
3.1‐ SUBSTANTIAL COMPLETION
FCRROULEAU, RICHARD A
6/4/2018 Update: Many tools and some larger pieces of equipment purchased and in place.
Need to close out 1850 Associates purchase order to determine how much funding is available
for additional tools and equipment.
Design Firm: John Jordan Contractor: External Contractor Name: 1850 PDRA Associates
2016‐0428
9 Madbury Road Projects in Building 1
9 Madbury Road ‐ Lease Space Office Fit Up
3‐ IN CONSTRUCTION
SIROULEAU, RICHARD A
6/4/2018 Update: Construction is well underway. Completion anticapate for late‐June or early‐
July. Furniture has been ordered and expected in mid‐July.
Design Firm: Harriman Contractor: External Contractor Name: Milestone
2018‐0092
Adams Tower Projects in Building 1
Adams Tower ‐ Verizon Wireless Antenna Upgrade
1.1‐ PLAN/EST
FCRPOLITANO, FRANK
5/30/18_ We are coordinating work with Verizon for summer execution.
Design Firm: Contractor: External Contractor Name: Verizon
2018‐0310
Barton Hall & Cole Hall Projects in Building 1
Tuesday, June 05, 2018 Page 2 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Cole Hall ‐ HVAC HU‐3 EQ5389 Cat Walks and Accessibility Modifications
2.5‐ IN PROCUREMENT
RRHOUDE, DONALD A
5‐22‐18 This project went out to bid. Not happy with results. Still in discussion with the Bidder.
Design Firm: Oak Point Contractor: External Contractor Name: Milestone E & C
2018‐0086
Building Interior Projects in Building 2
Thompson Hall ‐ Graduate Student Center
2‐ IN DESIGN
SIHECKLER, BARBARA K
5/25/2018: S. Thorne directing design. Goal is to implement by September
Design Firm: Contractor: External Contractor Name:
2017‐0212
Campus ‐ UNH Fire Damper Study
3.1‐ SUBSTANTIAL COMPLETION
FCRHENRY, PAUL A
5‐22‐18 buildings Survey complete, for first 4 buildings.
Design Firm: Harriman Contractor: Contractor Name:
2017‐0205
Chase Ocean Engineering Lab Projects in Building 4
Chase Ocean Engineering Lab ‐ Tank Room Ceiling Restoration and Replacement of
HV‐3
2.5‐ IN PROCUREMENT
RRGEUTHER, MARK E
05‐29‐2018: HV‐3 replacement scheduled to start the week of June 4.
Design Firm: HL Turner Contractor: External Contractor Name: Milestone
2017‐0153
Chase Ocean Engineering Lab ‐ Installation of CCURE Card Swipe
2.5‐ IN PROCUREMENT
FCRHOUDE, DONALD A
5‐22‐18 This project has been estimated and the client has the FCR, we are waiting o funding.
Design Firm: Contractor: External Contractor Name: Yates Electric
2018‐0314
Chase Ocean Engineering Lab ‐ Tank Room Ventilation System
3.1‐ SUBSTANTIAL COMPLETION
SIGEUTHER, MARK E
05‐29‐2018: Substantially Complete. Noise reduction scope complete.
Design Firm: HL Turner Contractor: External Contractor Name: Milestone
2016‐0147
Tuesday, June 05, 2018 Page 3 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Chase Ocean Engineering Lab ‐ Expansion
3.1‐ SUBSTANTIAL COMPLETION
FCRGEUTHER, MARK E
05‐29‐2018: Substantially Complete
Design Firm: HL Turner Contractor: FCT Contractor Name: Milestone Engineer & Construction
2015‐2755
Childhood Study & Development Center Projects in Building 1
Childhood Study & Development Center ‐ Roof Repair and Misc Repairs
2‐ IN DESIGN
RRPOLITANO, FRANK
5/30/18_ Drawings are due by Friday 6/1
Design Firm: SMRT Contractor: External Contractor Name:
2018‐0159
Combined Heat & Power Plant Projects in Building 1
Combined Heat & Power Plant ‐ Structural Floor Modifications
3.1‐ SUBSTANTIAL COMPLETION
FCRPOLITANO, FRANK
5/30/18_ Work is complete, I am looking for a new contractor, our term whom was under a P/O
is not compliant. I have asked Careno to price this for us waiting on proposal.
Design Firm: Contractor: Contractor Name:
2017‐0189
Conant Hall Projects in Building 2
Conant Hall ‐ DDC Controls Installation
3.1‐ SUBSTANTIAL COMPLETION
RRHENRY, PAUL A
5‐22‐18 need to fiinish commissioning
Design Firm: Harriman Contractor: Contractor Name:
2018‐0192
Conant Hall ‐ Minor Interior Renovations
3.1‐ SUBSTANTIAL COMPLETION
SIHENRY, PAUL A
5‐22‐18 Building occupied Working on punch List, and finishing MEP improvements
Design Firm: Mannypenny Murphy Contractor: External Contractor Name: Trumbell Nelson
2016‐0410
Dimond Library Projects in Building 3
Tuesday, June 05, 2018 Page 4 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Dimond Library ‐ Minor Renovation for Customer Service and Addison Areas
1.1‐ PLAN/EST
FCRHECKLER, BARBARA K
8/16/2017: Deferred pending approval from Dimond Deanʹs Office.
5/23/18=Barbarah Please reach out to the customer and work the plan to to proceed with this
project.
Design Firm: Contractor: External Contractor Name:
2017‐0423
Dimond Library ‐ Interior Painting of Main Lobby
2.5‐ IN PROCUREMENT
RRBOIE, GREGG J
05/30 /18, APC will commence painting on June 11th.
.
Design Firm: Contractor: External Contractor Name: APC Services of New England
2018‐0307
Dimond Library – Room 221 Renovation
3‐ IN CONSTRUCTION
SIHECKLER, BARBARA K
5/25/2018: Work started on 5/21 and on track to be complete by 8/1.
Design Firm: Contractor: Contractor Name:
2018‐0179
DPW Grounds & Roads Projects in Building 1
DPW Grounds & Roads ‐ Garage
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
5‐22‐18 poring slab on Thursday this week
Design Firm: Careno Contractor: External Contractor Name: Careno
2013‐1610
Elliott Alumni Center Projects in Building 1
Elliott Alumni Center ‐ HHW Conversion to Natural Gas Boiler
3‐ IN CONSTRUCTION
FCRPOLITANO, FRANK
5/30/18_ GSP has been awarded the major portion of the project and we are looking to start on
6/6
Design Firm: SMRT Contractor: External Contractor Name: Granite State Plumbing
2017‐0443
Field House Projects in Building 3
Tuesday, June 05, 2018 Page 5 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Field House ‐ New Ski Locker Room/Team Area
2‐ IN DESIGN
FCRBRICKETT, ALEXANDER J
5/30/18__Working with design team for final space renderings.
Design Firm: Harriman Contractor: Contractor Name:
2017‐0251
Field House ‐ Womens Team Locker Room Upgrades ‐ Planning Only
2‐ IN DESIGN
SIHECKLER, BARBARA K
5/25/2018: Will schedule June meeting with Harriman.
Design Firm: Contractor: Contractor Name:
2018‐0198
Field House ‐ Steam to Domestic Hot Water System Replacement
3‐ IN CONSTRUCTION
RRPARSONS, STEPHANIE E
5/24/18: This project has been awarded to Northern Peabody. Preconstruction meeting will be
scheduled in the near future to work on project timeline and schedule coordination with athletics.
Design Firm: Harriman Contractor: External Contractor Name: Northern Peabody
2017‐0325
Gables Building A Projects in Building 1
Gables Buildings A, B & C ‐ Replace the EPDM roof tops
2.5‐ IN PROCUREMENT
FCRPOLITANO, FRANK
5/30/18_ Project awarded to Viking Roofing will begin 6/4
Design Firm: ARM Contractor: External Contractor Name: Viking
2018‐0118
Gables Building B Projects in Building 1
Gables A,B,C ‐ Boiler Plant Replacement
2.5‐ IN PROCUREMENT
FCRPOLITANO, FRANK
5/30/18_ awarded to Charters Brothers and will begin 6/4
Design Firm: SMRT Contractor: External Contractor Name: Charters Brothers
2018‐0076
Gregg Hall Projects in Building 3
Tuesday, June 05, 2018 Page 6 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Gregg Hall ‐ Chiller Replacement
2.5‐ IN PROCUREMENT
RRPARSONS, STEPHANIE E
5/25/18: RFB request has been submitted to procurement. Anticipate make ready work to occur
July /August with chiller replacement to occur October / November after primary cooling season.
Design Firm: Harriman Contractor: External Contractor Name: TBD
2017‐0281
Gregg Hall ‐ Chiller Replacement ‐ Funding for Construction
2.5‐ IN PROCUREMENT
RRPARSONS, STEPHANIE E
5/25/18: Please refer to project 2017‐0281 for updates on construction.
Design Firm: Harriman Contractor: External Contractor Name: TBD
2017‐0250
Gregg Hall ‐ Basement Flood Restoration
3‐ IN CONSTRUCTION
RR
Emergency Repair
BRICKETT, ALEXANDER J
5/30/18_Drywall work to be competed when pump station upgrades are installed. Work to be
coordinated with John OʹRourke.
Design Firm: Contractor: External Contractor Name:
2018‐0132
Hamel Recreation Center Projects in Building 1
Hamel Recreation Center ‐ Expansion & Renovations
3‐ IN CONSTRUCTION
CPPARSONS, STEPHANIE E
5/25/18: AWF installation is 60% complete. Sanding / striping and sanding will beging early
June. This project is scheduled to be complete by 6/30.
Design Firm: HGA Contractor: FCT Contractor Name: Shawmut / Charters Brothers
2013‐1176
Hamilton Smith Hall Projects in Building 1
Hamilton Smith Hall ‐ Major Renovation Project
3.5‐ WARRANTY REPAIRS
SIROULEAU, RICHARD A
6/4/2018 Update: Meeting with Skanska and subcontractors for warranty review on 6/11.
Working with Milestone to do some small follow‐up work. Bi‐directional amplifier per Town
ordinance split off as separate project (2018‐0223).
Design Firm: DiMella Shaffer Associates Contractor: External Contractor Name: Skanska USA, Inc.
2012‐1851
Health & Wellness Building Projects in Building 2
Tuesday, June 05, 2018 Page 7 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Health & Wellness Building ‐ Physical Reorganization of Services
1.1‐ PLAN/EST
FCRHECKLER, BARBARA K
5/25/2018: Final estimate and schedule for additional work expected by 5/25. Work will be
complete by 8/3.
Design Firm: Harriman A/E Contractor: Contractor Name:
2017‐0340
Health & Wellness Building ‐ Fire Alarm System Upgrade
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
5/25/18: Final acceptance testing and review with SFMO to occur after commencement. Will
schedule walk through with SFMO early June.
Design Firm: Contractor: External Contractor Name: Norris
2018‐0182
Holloway Commons Projects in Building 2
Holloway Commons ‐ Retro‐Commissioning Repairs
1.1‐ PLAN/EST
FCRBRICKETT, ALEXANDER J
5/30/2018 ‐ RFS has been contacted to establish scope of repairs needed.
Design Firm: Contractor: External Contractor Name:
2016‐0500
Holloway Commons ‐ Expansion Project
3.5‐ WARRANTY REPAIRS
CPROULEAU, RICHARD A
6/4/2018 Update: There remain just a few project items that need to be resolved.
Design Firm: Miller Dyer Spears Contractor: External Contractor Name: North Branch Construction
2014‐1657
Hood House Projects in Building 4
Hood House ‐ Side Portico Structure and Roof Replacement
3.1‐ SUBSTANTIAL COMPLETION
RRHENRY, PAUL A
5‐22‐18 Hood House Renovation, 98% complete.
Design Firm: Contractor: Contractor Name:
2014‐1705
Hood House ‐ Minor Renovation for Career and Professional Success Center
3.1‐ SUBSTANTIAL COMPLETION
SIHENRY, PAUL A
5‐22‐18 Project in punch list, occupants in the building.
Design Firm: Mannypenny Murphy Contractor: External Contractor Name: Trumbell Nelson
2016‐0409
Tuesday, June 05, 2018 Page 8 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Hood House ‐ Supplemental MEP Repairs
3.1‐ SUBSTANTIAL COMPLETION
RRHENRY, PAUL A
5‐22‐18 99% complete, in puhch list
Design Firm: MpM Contractor: External Contractor Name: Trumbull Nelson
2018‐0140
Hood House ‐ Rear Entrance Canopy and Stair Replacement
3.1‐ SUBSTANTIAL COMPLETION
RRHENRY, PAUL A
5‐22‐18 Hood House Renovation, 98 % complete.
Design Firm: Contractor: Contractor Name:
2013‐1775
Horton Social Science Center Projects in Building 2
Horton Social Science Center ‐ 3rd Floor Daiken Unit Recommissioning
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
5‐22‐18 Operations locked out the Heat, checking to see if we still want to Retro‐Commission the
system.
Design Firm: Harriman / RFS Contractor: External Contractor Name: RFS / Harriman
2018‐0295
Horton Social Science Center ‐ 1st Floor Renovation ‐ Phase 2
3‐ IN CONSTRUCTION
SIHENRY, PAUL A
5‐22‐18 Started construction 5‐17
Design Firm: Harriman Contractor: External Contractor Name: Milestone
2008‐0203
Huddleston Hall Projects in Building 2
Huddleston Hall ‐ Roof Replacement Design Only
2‐ IN DESIGN
RRHENRY, PAUL A
5‐22‐18 Harriman working with ARM to include the design. Starting roof investigation 2013‐
1155 Huddleston Egress project.
Design Firm: ARM Contractor: External Contractor Name: Harriman
2016‐0165
Huddleston Hall ‐ Design of Egress Modifications
2‐ IN DESIGN
RRHENRY, PAUL A
5‐22‐18 Harriman working on MEP Systems evaluation Construction 2021.
Design Firm: Harriman Contractor: External Contractor Name: Harriman
2013‐1155
Tuesday, June 05, 2018 Page 9 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Jackson Lab Projects in Building 1
Jackson Lab ‐ Autoclave Replacement
2.5‐ IN PROCUREMENT
RRHOUDE, DONALD A
5‐22‐18 A PO has been provided to the contractor for this work. Equipment has been ordered. I
am waiting for an ETA on equipment to schedule a const start. Expected in June.
Design Firm: Contractor: FCT Contractor Name:
2017‐0377
James Hall Projects in Building 3
James Hall ‐ Heat Exchanger Replacement
2.5‐ IN PROCUREMENT
RR
Emergency Repair
PARSONS, STEPHANIE E
5/28/18: This project was awarded to Northern Peabody. Preconstruction / schedule /
coordination meeting will be scheduled in June to discuss possible interruption of service.
Design Firm: Harriman Associates Contractor: External Contractor Name: NPI
2017‐0393
James Hall ‐ HVAC Modifications Investigation and Design
3‐ IN CONSTRUCTION
RRPOLITANO, FRANK
5/30/18_ We have found a missing gasket which seperates the compartments of the AHU, we
will schedule the repair after commencement. We are still investigating the fans as a potential
cause as well.
Design Firm: Contractor: Contractor Name:
2018‐0270
James Hall ‐ AHU‐3 Failure Investigation and Repair
3‐ IN CONSTRUCTION
RR
Emergency Repair
BRICKETT, ALEXANDER J
5/30/18_ Repairs and room reconditioning in progress.
Design Firm: Contractor: Contractor Name:
2018‐0309
Kendall Hall Projects in Building 2
Kendall Hall ‐ Levels 3‐ 5 Repurposing CE and COLSA ‐ Design Only
1.1‐ PLAN/EST
SIPOLITANO, FRANK
5/30/18_ Update ‐ Working with Campus Planning to review scope required to allow this
occupant to relocate to Kendall Hall in FY 18.
Design Firm: Contractor: External Contractor Name:
2017‐0186
Tuesday, June 05, 2018 Page 10 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Kendall Hall ‐ Upgrade the Nutrition Assessment & Teaching Labs
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
5/25/18: Awaiting furniture delivery.
Design Firm: A Contractor: FCT Contractor Name:
2017‐0235
Leavitt Cntr Transportation Center Projects in Building 1
Leavitt Cntr Transportation Center ‐ Bus Maintenance Lift Replacements
2.5‐ IN PROCUREMENT
FCRHOUDE, DONALD A
5‐22‐18 Working with Steve, Dirk and Ray. I am meeting with the UNH Purchasing dept to put
this out to bid. We had a funding glitch, I believe we have solved that issue. I am working with
Purchasing to put this out to bid.
Design Firm: Contractor: External Contractor Name: Design build
2017‐0447
McConnell Hall Projects in Building 1
McConnell Hall ‐ Water Intrusion Investigation
1.1‐ PLAN/EST
FCRPOLITANO, FRANK
5/30/18_ We have funds left for the repairs and I will secure a term contractor for repairs when
the weather warms up to allow for proper conditions on repairs.
Design Firm: Contractor: External Contractor Name:
2016‐0297
Memorial Union Building Projects in Building 6
Memorial Union Building ‐ Granite State Room Exterior Deck
3‐ IN CONSTRUCTION
BARROULEAU, RICHARD A
6/4/2018 Update: Staging erection underway. Some work may start soon; however, loud work
cannot start until after freshmen orientation.
Design Firm: Hoyle Tanner Contractor: Contractor Name: Charters Bros.
2017‐0352
Memorial Union Building ‐ Bookstore Flood Restoration and Repairs
3‐ IN CONSTRUCTION
BAR
Emergency Repair
POLITANO, FRANK
5/30/18_ Immediate repairs are complete facilities to repair valve. Other work such as carpet
and office work to be scheduled when the bookstore slows down.
Design Firm: Contractor: Contractor Name:
2018‐0229
Tuesday, June 05, 2018 Page 11 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Memorial Union Building ‐ Exterior Deck Recoating
3‐ IN CONSTRUCTION
BARROULEAU, RICHARD A
6/4/2018 Update: Work to commence soon.
Design Firm: Contractor: External Contractor Name: Charters Bros.
2017‐0139
Memorial Union Building ‐ Strafford Room Wood Flooring Repair
3‐ IN CONSTRUCTION
BARPOLITANO, FRANK
5/30/18_ Old floor has been removed, Sprague will begin new floor around 7/1. Some sub floor
work will begin prior.
Design Firm: Contractor: External Contractor Name: Sprague
2018‐0299
Memorial Union Building ‐ Strafford Room Chillers and AHUʹs
3‐ IN CONSTRUCTION
BARPOLITANO, FRANK
5/30/18_ Demo has begun, new unit is scheduled to arrive 6/15
Design Firm: SMRT Contractor: External Contractor Name: Careno
2018‐0143
Memorial Union Building ‐ Granite Square Station Mail Boxes
3.5‐ WARRANTY REPAIRS
FCRPOLITANO, FRANK
5/30/18_ Warranty issues, working with Armstrong and contractor for resolution. Looking to
begin mid June.
Design Firm: Contractor: FCT Contractor Name:
2015‐2517
Morrill Hall Projects in Building 1
Morrill Hall ‐ Rm 209 Replacement Light Fixtures
2.5‐ IN PROCUREMENT
FCRHOUDE, DONALD A
5‐03‐18 The customer has show interest in additional work. I have sent an updated FCR. The
customer is trying to appropriate the additional funding.
Design Firm: Contractor: External Contractor Name: Yates
2017‐0304
Morse Hall Projects in Building 4
Morse Hall ‐ HVAC Evaluation and Feasibility Study
1.1‐ PLAN/EST
RRPOLITANO, FRANK
5/30/18_ I will be scheduling a meeting with RFS to review scope and ask for a proposal
Design Firm: Contractor: Contractor Name:
2017‐0317
Tuesday, June 05, 2018 Page 12 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Morse Hall ‐ Security Upgrades Including Card Readers and Video Cameras
1.1‐ PLAN/EST
FCRHOUDE, DONALD A
5‐22‐18 This project has been estimated and a proposal with several options was presented to the
client. I am waiting on feedback. They are waiting to see if they get any SAARC funding.
Design Firm: Contractor: External Contractor Name: Yates, Burns
2018‐0322
Morse Hall ‐ Third Floor Tempid Water Loop
3.1‐ SUBSTANTIAL COMPLETION
RRBRICKETT, ALEXANDER J
5/30/18_Basix to install monitoring equipment week of 6/4.
Design Firm: Contractor: External Contractor Name: GSPH
2017‐0004
Morse Hall ‐ Rm 345 Renovations
3.1‐ SUBSTANTIAL COMPLETION
FCRHENRY, PAUL A
5‐22‐18 Contacted stakeholder, he would like to wait and expand the system. Working with
EHS on details of new control panel to be located in the corridor.
Design Firm: Harriman Contractor: External Contractor Name: TBD
2015‐2384
Murkland Hall Projects in Building 1
Murkland Hall ‐ Exterior Painting
2.5‐ IN PROCUREMENT
RRBOIE, GREGG J
05/31/18, Met with Kevin Sousa on scheduling and will get back with info.
Design Firm: Contractor: Contractor Name:
2018‐0305
Nesmith Hall Projects in Building 7
Nesmith Hall ‐ Room Improvements G00CRA, G17‐G22, G24‐G26 (including G25B)
1.1‐ PLAN/EST
SIHECKLER, BARBARA K
5/25/2018: Project on track for Summer.
Design Firm: Contractor: External Contractor Name: milestone
2018‐0173
Nesmith Hall ‐ Upward Bound / Talent Search Relocation
2‐ IN DESIGN
SIHECKLER, BARBARA K
5/28/2018: Careno on board as GC; will provide details week of 5/28.
Design Firm: Contractor: External Contractor Name: Careno
2018‐0202
Tuesday, June 05, 2018 Page 13 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Nesmith Hall ‐ Phone‐a‐thon Fit Out
2.5‐ IN PROCUREMENT
SIBRICKETT, ALEXANDER J
5/30/18_Design completed. Work to begin week of 6/4.
Design Firm: Harriman Contractor: External Contractor Name:
2018‐0166
Nesmith Hall ‐ Bathroom Renovations
3‐ IN CONSTRUCTION
RRBRICKETT, ALEXANDER J
5/25/18_Construction in progress.
Design Firm: Cowan & Goudreau Contractor: External Contractor Name: Greenleaf Construction
2015‐2341
Nesmith Hall ‐ Bathroom Renovations DESIGN ONLY
3‐ IN CONSTRUCTION
RRBRICKETT, ALEXANDER J
5/30/18__See project 2015‐2341
Design Firm: Cowan & Goudreau Contractor: Contractor Name:
2018‐0096
Nesmith Hall ‐ Bathroom Improvements and ADA Accessibility Modifications
3‐ IN CONSTRUCTION
SIBRICKETT, ALEXANDER J
5/25/2018_See project 2015‐2341 for updates.
Design Firm: Cowan & Goudreau Contractor: External Contractor Name: Greenleaf Construction
2018‐0339
Nesmith Hall ‐ South Roof Replacement
3.1‐ SUBSTANTIAL COMPLETION
RRPOLITANO, FRANK
5/30/18_ P/O written looking to schedule ASAP
Design Firm: ARM Contractor: External Contractor Name: Viking
2010‐0433
New England Center Projects in Building 2
New England Center ‐ Adams Tower ‐ Separation of HHW and DHW Design Only
2‐ IN DESIGN
RRHENRY, PAUL A
5‐22‐18 Finalizing design in the next few months, project slated for Summer 2019
Design Firm: Harriman Contractor: External Contractor Name: TBD
2016‐0402
Tuesday, June 05, 2018 Page 14 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
New England Center ‐ Flood Damage Restoration and Repairs
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
HENRY, PAUL A
5‐22‐18 waiting for fin tube covers
Design Firm: Contractor: External Contractor Name: Milestione
2018‐0228
New Hampshire Hall Projects in Building 1
New Hampshire Hall ‐ Window Replacements and Exterior Painting
1.1‐ PLAN/EST
RRBOIE, GREGG J
05/30/2018, E‐Mailed Brian Gehris for status on window/paint quote.
Design Firm: Contractor: Contractor Name:
2018‐0306
Northwest Heat Plant Projects in Building 1
Northwest Heat Plant ‐ New Construction
3‐ IN CONSTRUCTION
FCRPARSONS, STEPHANIE E
5/25/18: Foundation is complete, undergroud utitlies at the building are ongoing. Pipe in the
shop at Putnam is ongoing to be complete by 6/18 when the violin program starts.
Design Firm: Wilson Engineering Contractor: External Contractor Name: Froling Energy
2018‐0002
Old Dairy Barn Projects in Building 1
Old Dairy Barn ‐ Demolition
3.1‐ SUBSTANTIAL COMPLETION
RRRINES, DANIEL M
5‐21‐18: Final coat of paint installed, waiting for loam, and seed, then final closeout.
Design Firm: Contractor: External Contractor Name: Milestone
2012‐1085
Outdoor Facility Projects in Building 2
Outdoor Facility ‐ New Soccer/Lacrosse Field
2.5‐ IN PROCUREMENT
FCRGEUTHER, MARK E
05‐29‐2018: Contract signed by contractor, and VPFA, hand delivered to USNH. Construction
scheduled to start on or about August 1, 2018.
Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports
2017‐0285
Tuesday, June 05, 2018 Page 15 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Mooradian Field ‐ Subsurface Improvements and Turf Replacement
3.1‐ SUBSTANTIAL COMPLETION
RRGEUTHER, MARK E
05‐29‐2018: Substantially complete. Waiting on As‐Builts
Design Firm: Tighe & Bond Contractor: FCT Contractor Name: RAD Sports
2017‐0149
Outdoor Pool Projects in Building 1
Outdoor Pool ‐ Reconstruction of Outdoor Pool Facility
3.1‐ SUBSTANTIAL COMPLETION
CPPARSONS, STEPHANIE E
5/25/18 Preparing for project closeout. Final items required for the project will be purchased
and this project closed out by August 2018.
Design Firm: water technologies Contractor: External Contractor Name: Shawmut
2014‐2059
Parsons Hall Projects in Building 4
Parsons Hall ‐ Rms N104, N108 Classroom Renovation Iddles Lecture Halls Design
Only
2‐ IN DESIGN
RRBRICKETT, ALEXANDER J
5/30/18_ Harriman has begun design work on new lecture halls.
Design Firm: Harriman Contractor: External Contractor Name:
2018‐0145
Parsons Hall ‐ Processed Chilled Water System Replacement
2‐ IN DESIGN
RRBRICKETT, ALEXANDER J
5/30/18_ Design work in progress.
Design Firm: Contractor: Contractor Name:
2018‐0048
Parsons Hall ‐ Rm S128 Ammonia Gas Control System
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
5/25/18: Awaiting Norris schedule to install FA module to supervise the ammonia system.
Design Firm: AirGas Contractor: External Contractor Name: AirGas
2017‐0431
Parsons Hall ‐ Rm S222 Minor Renovations
3.1‐ SUBSTANTIAL COMPLETION
FCRBRICKETT, ALEXANDER J
5/30/18_Work completed. Punchlist items in progress.
Design Firm: Harriman Contractor: External Contractor Name: Yates & GSPH
2018‐0058
Tuesday, June 05, 2018 Page 16 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Paul College Projects in Building 1
Paul College ‐ HVAC and Control Modifications from Original Construction
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
5/25/18. Further work may be required, will not have an assessment until cooling season.
Design Firm: RFS Contractor: External Contractor Name: TBD
2016‐0295
Paul Creative Arts Center Projects in Building 2
Paul Creative Arts Center ‐ Stair Egress Modifications
3.1‐ SUBSTANTIAL COMPLETION
RRPOLITANO, FRANK
5/30/18_ 1st phase is complete, except some door hardware for egree doors. Scheduled to be
delivered 6/4/18
Design Firm: Harriman Contractor: Contractor Name:
2017‐0232
Paul Creative Arts Center ‐ New Main Domestic Hot Water System Installation
3.5‐ WARRANTY REPAIRS
RRROULEAU, RICHARD A
6/4/2018 Update: Water heater installation completed. Equipment list submitted. O&M
manuals to be uploaded to Meridian shortly. Domestic water booster pump design received and
may be implemented as part of this project or possibly as a separate follow‐on project.
Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.
2018‐0249
Pettee Hall Projects in Building 2
Pettee Hall ‐ Rm G18 Mold Remediation and Investigation
3‐ IN CONSTRUCTION
RR
Emergency Repair
HECKLER, BARBARA K
5/252018: Project on track to be complete by 6/22.
Design Firm: Contractor: Contractor Name:
2018‐0251
Pettee Hall ‐ Slate Roof Repairs
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
ROULEAU, RICHARD A
6/4/2018 Update: Repairs completed pending final drone verification.
Design Firm: Contractor: External Contractor Name: Skyline Roofing
2018‐0098
Philbrook Hall Projects in Building 4
Tuesday, June 05, 2018 Page 17 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Philbrook Hall ‐ Boiler Forensic Investigation
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
5/25/18: Dye testing cannot begin until the refrigeration demo / floor cuts are complete. RFP is
being drafted for forensic analysis of the building infrastructure to determine cause of boiler
failure.
Design Firm: TBD Contractor: External Contractor Name: TBD
2018‐0162
Philbrook Hall ‐ Kitchen Modifications
2‐ IN DESIGN
FCRHENRY, PAUL A
5‐22‐18 Selected Charter Brothers as CMAR, will start Pre‐Construction Services to explor the
site this summer
Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers
2017‐0399
Philbrook Hall ‐ Refrigeration Rack System
3‐ IN CONSTRUCTION
FCRHENRY, PAUL A
5‐22‐18 in construction
Design Firm: Harriman Assoc. Contractor: External Contractor Name: Charter Brothers
2015‐2492
Philbrook Hall ‐ Boiler Replacement
3‐ IN CONSTRUCTION
BARPARSONS, STEPHANIE E
5/25/18: Boiler is not being installed until 2018‐0162 forensic review is complete.
Design Firm: Harriman Contractor: External Contractor Name: Eckhardt Johnson
2018‐0149
Presidents House Projects in Building 1
Presidents House ‐ Major Site Repairs President Transition
2.5‐ IN PROCUREMENT
RRRINES, DANIEL M
4‐24‐18: Quotes have been obtained from contractors, working on final schedule and budgets.
Work is set to begin on exterior work 5‐21‐18.
Design Firm: Contractor: External Contractor Name: Bell and Flynn/ Chapman
2013‐1274
Presidentʹs House Projects in Building 1
Tuesday, June 05, 2018 Page 18 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Presidentʹs House ‐ Building Exterior and Interior Painting and Repairs
1.1‐ PLAN/EST
RRBRICKETT, ALEXANDER J
5/30/2018 Exterior work has begun. Interior work to begin 6/4.
Design Firm: Contractor: Contractor Name:
2013‐1032
Ritzman Hall Projects in Building 1
Ritzman Hall ‐ First Floor Reconfiguration
3.1‐ SUBSTANTIAL COMPLETION
FCRGEUTHER, MARK E
05‐29‐2018: Substantial Complete. New office chairs on order.
Design Firm: Contractor: External Contractor Name: Milestone
2018‐0292
Roads/Grounds Projects in Building 11
FY19 Sidewalk and Walkway Repairs
1.1‐ PLAN/EST
RRHENRY, PAUL A
5‐22‐18 Have estimates, working on POʹs
Design Firm: Contractor: External Contractor Name: T&S / JTI
2017‐0027
FY19 Site Stair Repairs
1.1‐ PLAN/EST
RRHENRY, PAUL A
4‐30‐18 Working on estimates
Design Firm: Contractor: External Contractor Name: TBD
2017‐0026
FY19 Road Repairs and Crack Sealing
1.1‐ PLAN/EST
RRHENRY, PAUL A
5‐22‐18 Working on estimates, may not do this summer
Design Firm: Contractor: External Contractor Name: TBD
2017‐0024
Campus ‐ Huddleston Fairchild Hetzel Site Stairs Design
1.1‐ PLAN/EST
RRGEUTHER, MARK E
05‐29‐2018 Entering into an agreement with Hoyle‐Tanner for design.
Design Firm: Hoyle‐Tanner Contractor: External Contractor Name: TBD
2018‐0294
Tuesday, June 05, 2018 Page 19 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Campus ‐ Main Street South Sidewalk
2‐ IN DESIGN
SIRINES, DANIEL M
5‐21‐18: NTP obtained from NHDOT, CMA/USNH contract finalized, obtaining signatures.
Design Firm: CMA Engineering Contractor: Contractor Name:
2017‐0384
Memorial Union Building ‐ Driveway and Sidewalk ‐ Design Only
2‐ IN DESIGN
SIRINES, DANIEL M
5‐21‐18: meeting this week with, team to discuss drainage, and 60% plans from Hoyle Tanner.
Design Firm: Hoyle Tanner Contractor: Contractor Name:
2009‐0078
South Drive ‐ Design Advancement
2‐ IN DESIGN
SIHENRY, PAUL A
5‐22‐18 T&B recently estimated project at DD, up dated estimate
Design Firm: Tighe & Bond Contractor: External Contractor Name:
2013‐1115
Campus Wayfinding ‐ Phase 2
2.5‐ IN PROCUREMENT
SIRINES, DANIEL M
5‐21‐18: sign copyʹs being finalized, installation expected in July/August.
Phase 1 punch list to begin 6‐11‐18
Design Firm: Contractor: External Contractor Name: Barlo Signs
2016‐0157
Campus ‐ South Drive ‐ Temporary Connection to Colovos Road
2.5‐ IN PROCUREMENT
SIGEUTHER, MARK E
05‐29‐2018‐Project on hold pending funding.
Design Firm: Tighe & Bond Contractor: External Contractor Name: R.A.D. Sports
2018‐0267
Campus ‐ Wayfinding ‐ Phase 1
3.1‐ SUBSTANTIAL COMPLETION
SIKING, KATHLEEN M
4/27/18: Change order issued for punch list completion, to be completed in early summer.
Design Firm: Roll Barresi & Associates Contractor: FCT Contractor Name: Barlo Signs International
2017‐0211
Tuesday, June 05, 2018 Page 20 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Wildcat Stadium Parking Lot ‐Pay & Display Meter Installation & Pad
3.1‐ SUBSTANTIAL COMPLETION
FCRHOUDE, DONALD A
5‐22‐18 The project is 90% complete waiting for Bollard covers.
Design Firm: Contractor: External Contractor Name: T&S const
2018‐0150
Rudman Hall Projects in Building 15
Rudman Hall ‐ Conversion to DDC Controls
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
5/25/18 ‐see ID 2010‐0479 for updates.
Design Firm: Contractor: External Contractor Name: TBD
2015‐2336
Rudman Hall ‐ DDC Controls Backstop
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
5/25/18 ‐ see ID 2010‐0479 for updates
Design Firm: Contractor: Contractor Name:
2017‐0288
Rudman Hall ‐ Fire Alarm Replacement DESIGN
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
5/25/18 ‐ Design review ongoing, installation of fire alarm is scheduled for Summer 2019.
Design Firm: SFC Engineering Contractor: External Contractor Name: TBD
2013‐1149
Rudman Hall ‐ Laboratory Fume Hood Control System Replacement
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
5/25/18 ‐ Project is currently in preliminary design will need to coordinate this work closely with
COLSA and Rudman occupants. Make ready work for AHU isolation is being scheduled for
December 2018 with new HVAC control improvements to begin summer 2019.
Design Firm: SMRT, Inc. Contractor: External Contractor Name: TBD
2010‐0479
Rudman Hall ‐ Fire Alarm Replacement
1.1‐ PLAN/EST
RRPARSONS, STEPHANIE E
5/25/18 ‐ Please see ID 2010‐0479 for updates.
Design Firm: SFC Contractor: External Contractor Name: TBD
2015‐2352
Tuesday, June 05, 2018 Page 21 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Rudman Hall ‐ Level G Instruction Lab Support Expansion
1.1‐ PLAN/EST
SIPARSONS, STEPHANIE E
5/25/18: Working on design to enclose portion of the loading dock area to expand the lab support
facility.
Design Firm: TBD Contractor: External Contractor Name: TBD
2017‐0418
Rudman Hall ‐ Rm 148 Replacement Environmental Room Humidifier
1.1‐ PLAN/EST
RRBOIE, GREGG J
05/30/18, Contacted Harris Environmental systems(problem with PO) for replacement
Humidifier.
Design Firm: Contractor: External Contractor Name: Harris Environmental Systems Inc.
2018‐0354
Rudman Hall ‐ Vivarium Upgrades Phase 2 DESIGN ONLY
2‐ IN DESIGN
SIPOLITANO, FRANK
5/30/18_ Design in process review drawings due by 6/15
Design Firm: Harriman Contractor: Contractor Name:
2017‐0214
Rudman Hall ‐ ARO Autoclave Replacement
2.5‐ IN PROCUREMENT
RRBRICKETT, ALEXANDER J
5/30/18_Design documentation received.Obtaining quotes for work from contractors.
Design Firm: Contractor: Contractor Name:
2016‐0148
Rudman Hall ‐ Steam Domestic Hot Water Exchanger
3‐ IN CONSTRUCTION
RRPOLITANO, FRANK
5/30/18_ Work is underway, old unit is removed new one is being installed , scheduled to be
completed 6/8
Design Firm: Contractor: External Contractor Name: GSP
2017‐0366
Rudman Hall ‐ Water Booster Pump Replacement
3‐ IN CONSTRUCTION
RRPOLITANO, FRANK
5/30/18_ P/O is written work will be a Summer project
Design Firm: Contractor: External Contractor Name: GSP
2017‐0367
Tuesday, June 05, 2018 Page 22 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Rudman Hall ‐ G Level Flood Restoration and Repair
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
BRICKETT, ALEXANDER J
5/30/18_All affected areas have been repaired. Equipment replacement in progress.
Design Firm: Contractor: Contractor Name:
2018‐0230
Rudman Hall ‐ Dishwasher Fire/ Sprinkler Flood Restoration
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
KING, KATHLEEN M
4/27/18: Restoration is complete, project is also labeling fire sprinkler valves and considering
modifying ventilation of space behind washer.
Design Firm: Contractor: Contractor Name:
2018‐0252
Rudman Hall ‐ Rm G51 Flood Restoration
3.1‐ SUBSTANTIAL COMPLETION
RR
Emergency Repair
BRICKETT, ALEXANDER J
5/30/18_ Ceiling tiles completed. Old refrigerator to be removed when contents are moved.
Design Firm: Contractor: FCT Contractor Name: Sprague
2017‐0293
Rudman Hall ‐ Steam Back Pressure Turbine
3.1‐ SUBSTANTIAL COMPLETION
FCRPARSONS, STEPHANIE E
5/25/18: All control interface is complete. Steam turbine will start 5/25/18. This will be final
report on this project.
Design Firm: Waldron Engineering Contractor: External Contractor Name: Ewing Controls / TVC
2016‐0162
Service Building Projects in Building 3
Service Building ‐ Dispatch Center Keltron System
3‐ IN CONSTRUCTION
FCRPARSONS, STEPHANIE E
5/25/18: Gregg Hall ʹnodeʹ will be populated May 2018. This will remove 6 accounts from
Service Building. Upon completion, the team will assess the next node to popluate, Paul College
or PMS.
Design Firm: Contractor: External Contractor Name: Norris / UNH Telecom
2016‐0123
Service Building ‐ Replacement and Installation of Isolation valves
3‐ IN CONSTRUCTION
RRPARSONS, STEPHANIE E
5/25/18 ‐ Please see project ID 2009‐0064 for updates and budget.
Design Firm: N/A Contractor: External Contractor Name: TBD
2013‐1465
Tuesday, June 05, 2018 Page 23 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Service Building ‐ Fire Alarm Replacement and Building System Upgrades
3‐ IN CONSTRUCTION
RRPARSONS, STEPHANIE E
5/25/18 Heating line replacement and isolation valve installation has started. Fire alarm is
substantially complete. One final walk through will be conducted with SFC / DFD or SFMO and
UNH. Date / time to be determined.
Design Firm: Harriman Contractor: External Contractor Name: Charters Brothers
2009‐0064
Spaulding Hall Projects in Building 1
Spaulding Hall ‐ Expansion & Renovations ‐ Biological Science Initiative
2‐ IN DESIGN
CPROULEAU, RICHARD A
6/4/2018 Update: CM has been selected. Notice to be made tomorrow. Design direction is to
design the full addition and, if state funds are not forthcoming, do less in the existing building.
Design Firm: Ellenzweig Contractor: External Contractor Name: TBD
2016‐0278
Stoke Hall Projects in Building 3
Stoke Hall ‐ Registrarʹs Office Minor Renovation
2‐ IN DESIGN
SIHECKLER, BARBARA K
5/25/2018: Will meet with RO in June.
Design Firm: Contractor: Contractor Name:
2018‐0175
Stoke Hall ‐ Business Service Center Exterior Wall Repairs
3‐ IN CONSTRUCTION
RRBRICKETT, ALEXANDER J
5/30/18_ Construction in progress.
Design Firm: Contractor: Contractor Name:
2018‐0213
Stoke Hall ‐ Elevator upgrade
3‐ IN CONSTRUCTION
FCRROULEAU, RICHARD A
6/4/2018: Work is in progress and is to be complete prior to the fall semester.
Design Firm: Elevator Consulting Assoc. Contractor: External Contractor Name: Careno Construction
2018‐0117
Thompson Hall Projects in Building 3
Tuesday, June 05, 2018 Page 24 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Thompson Hall ‐ Retaining Wall Replacement and Walkway
2.5‐ IN PROCUREMENT
RRHENRY, PAUL A
5‐22‐18 Project out to bid second time
Design Firm: Harriman Contractor: External Contractor Name: TBD
2016‐0065
Thompson Hall ‐ Moisture Repair and Window Repair
3‐ IN CONSTRUCTION
RRPOLITANO, FRANK
5/30/18_ FCT to paint 3 remaining windows
Design Firm: Contractor: FCT Contractor Name:
2017‐0164
Thompson Hall ‐ Card Access and Security Camera Cable Pathways
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
5‐22‐18 This project is funded and the contractor has started. I have checked and the contractor
has made good progress.
Design Firm: Contractor: External Contractor Name: Yates
2018‐0246
Tirrell Light Horse Stable Projects in Building 1
Tirrell Light Horse Stable ‐ Replace 39 stall lighting fixtures with new LED fixtures
3‐ IN CONSTRUCTION
FCRHOUDE, DONALD A
5‐22‐18 This project was reviewed and we found it was a good for the new FCT division. Jeff
mcGrath has acceptet the project, John Dube is ordering material.
Design Firm: Contractor: FCT Contractor Name:
2018‐0334
Utility Distribution Projects in Building 12
Utility Distribution ‐ HHW Line Replacement Service Building to Zais Hall
1.1‐ PLAN/EST
RRRINES, DANIEL M
5‐21‐18 Meeting with Leo and team next week to discuss, Obtaining prcing and schedules from
RH White, and Charter Bros.
Design Firm: Contractor: Contractor Name:
2017‐0354
Utility Distribution ‐ Library Way Tunnel Design
1.1‐ PLAN/EST
RRKING, KATHLEEN M
4/27/18: PM is waiting on final direction from asset management and utilities
Design Firm: Contractor: Contractor Name:
2017‐0005
Tuesday, June 05, 2018 Page 25 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Utility Distribution ‐ College Brook Culvert Repair
2‐ IN DESIGN
RRHENRY, PAUL A
5‐22‐18 Exposted site, have to remove electrical duct bank to do work, working with Energy to
incluce some High Voltage work to take atvanatve of moving the switches above ground,
meeting next week.
Design Firm: Tighe & Bond Contractor: External Contractor Name: TBD
2018‐0100
UNH Utility Master Plan
2‐ IN DESIGN
SIKING, KATHLEEN M
4/27/18: Final comments returned to consultants and final report due May 11, followed by
presentations by consultants.
Design Firm: RMF Contractor: Contractor Name:
2017‐0169
Utility Distribution ‐ Edgewood Water Tank ‐ Decomissio
2.5‐ IN PROCUREMENT
FCRBRICKETT, ALEXANDER J
5/30/18_PO for demolition issued to Charter Bros. Work to occur 8/1/18.
Design Firm: Contractor: External Contractor Name: Charter Brothers
2010‐0729
Utility Distribution ‐ Waterworks Road Water Main Repair
2.5‐ IN PROCUREMENT
FCRHENRY, PAUL A
5‐22‐18 T&B submitted an After the Fact Wetlands Permit to cover the emergency repair.
Design Firm: Tighe & Bond Contractor: External Contractor Name: Tighe & Bond
2018‐0250
Utility Distribution ‐ Reconfigure and Relocation of Colovos SSL0109 and SSL0486
2.5‐ IN PROCUREMENT
RRGEUTHER, MARK E
05‐29‐2018 Plans have been finalized. Waiting for price and schedule from Term Contractor.
Design Firm: Tighe & Bond Contractor: External Contractor Name: T&S Construction
2018‐0183
Utility Distribution ‐ Horton to PCAC HHW Line Replacements and Pit Repairs
3‐ IN CONSTRUCTION
RRROULEAU, RICHARD A
6/4/2018 Update: Construction is well underway. Pipe should start going in this week.
Unforeseen/hidden conditions and structural issues with existing vaults are being addressed.
Design Firm: Harriman Associates Contractor: External Contractor Name: Charters Bros.
2017‐0094
Tuesday, June 05, 2018 Page 26 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Utility Distribution ‐ HV ‐ Circuit 11 Hamilton Smith to Memorial Union Phase II
3‐ IN CONSTRUCTION
SIHOUDE, DONALD A
5‐22‐18 The contractor has a PO. Site preparation is taking place this week and excavation
should start soon.
Design Firm: Contractor: External Contractor Name:
2018‐0067
Utility Distribution ‐ Main Street Tunnel Corrective Repair and Design
3‐ IN CONSTRUCTION
RRRINES, DANIEL M
5‐21‐18: RH White mobilized, concrete repair underway this week. Exterior tunnel work to be
completed the week of 5‐28‐6‐11.
Design Firm: Simpson Gumpertz & Heger Contractor: External Contractor Name: R.H. White Construction
2018‐0155
Utility Distribution ‐ HHW and Sewer Line Replacement College Road to Kendall and
Nesmith
3‐ IN CONSTRUCTION
RRGEUTHER, MARK E
05‐29‐2018: Work underway. Waterline not as anticipated. Working on alternate plan.
Design Firm: Harriman/Tighe & Bond Contractor: External Contractor Name: Waterline Industries
2017‐0093
Utility Distribution ‐ Gables Distribution Line Replacements
3.1‐ SUBSTANTIAL COMPLETION
RRKING, KATHLEEN M
4/27/18: Project is substantially complete, waiting on final invoicing.
Design Firm: Harriman Contractor: External Contractor Name: RH White
2017‐0348
Water Treatment Plant Projects in Building 1
Water Treatment Plant ‐ New Construction
3‐ IN CONSTRUCTION
SIGEUTHER, MARK E
05‐29‐2018: Concrete tank work ongoing. Site work on going. Masonry gearing up for mock up
wall.
Design Firm: Woodard & Curran Contractor: External Contractor Name: Waterline Industries
2008‐0038
Whittemore Center ‐ Arena Projects in Building 3
Tuesday, June 05, 2018 Page 27 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management
PROJECT TITLEPM
AccountableProject
Code
Project
Number:
Whittemore Center ‐ Arena ‐ Ice System Engineering Evaluation
1.1‐ PLAN/EST
RRBRICKETT, ALEXANDER J
5/30/18_Meeting on 3/2 indicated that ice system needs replacement. Initial design phase in
progress.
Design Firm: Stevens Engineering Contractor: Contractor Name:
2018‐0235
Whittemore Center ‐ Arena ‐ Engineering Evaluation for Exterior Concrete and Interior
Mechanical Room Slab
1.1‐ PLAN/EST
RRRINES, DANIEL M
5‐21‐18: PM coordinating with SGH to begin investigations.
Design Firm: SGH Contractor: Contractor Name:
2017‐0394
Whittemore Center ‐ Arena ‐ Concessions Stand Electrical Work
3‐ IN CONSTRUCTION
FCRBRICKETT, ALEXANDER J
5/30/18_Yates has finished electrical work. Telecom work in progress.
Design Firm: Contractor: External Contractor Name: Yates
2018‐0157
Woodside ABC Projects in Building 1
Woodsides Complex ‐ Boiler Replacements and Modifications
3‐ IN CONSTRUCTION
FCRPOLITANO, FRANK
5/30/18_ Work has begun, all existing boilers have been removed, concrete pads are being
poured 5/30‐6/4. New boiler install begins 6/4
Design Firm: SMRT Contractor: External Contractor Name: Careno
2017‐0408
Tuesday, June 05, 2018 Page 28 of 28University of New Hampshire
Brenda Whitmore, Director Facilities Project Management