9
Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings Page no. : 1 /9 RRCAT, RF Ion Source Test Jig Fabrication, assembly and supply of Faraday Cup, HV Deck Conduits, and Test Jig mounting stand as per the specifications and drawing attached. 1 Set. 1. Scope:- This specification covers the technical requirements for fabrication of various parts, as per the drawing given, of Faraday Cup, HV Deck Conduits, and Test Jig mounting stand, its assembly, test and supply of the same to RRCAT, Indore. 2. List of applicable drawings: - The following drawings contain the assembly as well as detailed drawings of different parts. (Page no. 3 to 8 of this document). The soft copy of detailed drawing of the same will be given to the successful bidder, while placing the PO. Table I, One set of parts include the following parts and quantity: Sr. No. Item name Quantity in one set including spares 1. Faraday Cup (Type 1) ( page no. 3 & 4 of this document ) RRCAT/PAG/PLDD/LCDL/M468 1 SET 2. Faraday Cup (Type 2) ( page no. 5 & 6 of this document ) RRCAT/PAG/PLDD/LCDL/M468.02 2 SET 3. High Voltage Deck Conduits (page no. 7 of this document) RRCAT/PAG/PLDD/LCDL/M467 1 SET 4. Test Jig mounting stand (page no. 8 of this document) RRCAT/PAG/PLDD/LCDL/M470 3 SET 3. Materials, to be used for fabrication of Faraday Cup, HV Deck Conduits, and Test Jig mounting stand, and relevant terms and conditions are as follows:- 3.1 SS316L as per IS: ASTM A240 3.2 Alumina AL995 as per IS: ASTM B209 M-14 3.3 All necessary screws/ bolts/ nuts/ washers/ spring washers etc should be of SS316L/SS304 and should be arranged by party. 3.4 The fabricator/ supplier has to provide test certificate of material used, issued by the manufacturer of the raw material or certificate issued by reputed govt. or national laboratory. 4. Welding processes:- 4.1 For mild steel base structure: - Shielded metal tig/arc welding (SMAW) 5. Cleaning and assembly process:- 5.1 All metal parts should be free from oil and dust. Should be assembly in clean room.

Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Embed Size (px)

Citation preview

Page 1: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 1 /9

RRCAT, RF Ion Source Test Jig

Fabrication, assembly and supply of Faraday Cup, HV Deck Conduits, and Test

Jig mounting stand as per the specifications and drawing attached. 1 Set.

1. Scope:- This specification covers the technical requirements for fabrication of various

parts, as per the drawing given, of Faraday Cup, HV Deck Conduits, and Test Jig mounting

stand, its assembly, test and supply of the same to RRCAT, Indore.

2. List of applicable drawings: - The following drawings contain the assembly as well as

detailed drawings of different parts. (Page no. 3 to 8 of this document). The soft copy of

detailed drawing of the same will be given to the successful bidder, while placing the PO.

Table –I, One set of parts include the following parts and quantity:

Sr. No. Item name Quantity in one

set including

spares

1. Faraday Cup (Type 1) ( page no. 3 & 4 of this document )

RRCAT/PAG/PLDD/LCDL/M468 1 SET

2. Faraday Cup (Type 2) ( page no. 5 & 6 of this document )

RRCAT/PAG/PLDD/LCDL/M468.02 2 SET

3. High Voltage Deck Conduits (page no. 7 of this document)

RRCAT/PAG/PLDD/LCDL/M467 1 SET

4. Test Jig mounting stand (page no. 8 of this document)

RRCAT/PAG/PLDD/LCDL/M470

3 SET

3. Materials, to be used for fabrication of Faraday Cup, HV Deck Conduits, and

Test Jig mounting stand, and relevant terms and conditions are as follows:-

3.1 SS316L as per IS: ASTM A240

3.2 Alumina AL995 as per IS: ASTM B209 M-14

3.3 All necessary screws/ bolts/ nuts/ washers/ spring washers etc should be of

SS316L/SS304 and should be arranged by party.

3.4 The fabricator/ supplier has to provide test certificate of material used, issued

by the manufacturer of the raw material or certificate issued by reputed govt. or

national laboratory.

4. Welding processes:-

4.1 For mild steel base structure: - Shielded metal tig/arc welding (SMAW)

5. Cleaning and assembly process:-

5.1 All metal parts should be free from oil and dust. Should be assembly in clean

room.

Page 2: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 2 /9

RRCAT, RF Ion Source Test Jig

6. Workmanship and cleaning: -

6.1 All workmanship shall be first class high grade quality and accordance with the

best approved methods of fabrication of different components. The surfaces of

fabricated parts should be free from burrs, pits, scratches, weld ripples and scales.

7. Metal part surface buffing/electro polishing:-

7.1 All metal parts sharp-edged should be removed by grinding, and buffing.

Electrode parts surface finish should be done by electro polishing.

8. Inspection Clause:-

8.1 Pre dispatch inspection (PDI) of each part of the Faraday Cup, HV Deck

Conduits, and Test Jig mounting stand, will be carried out. Inspection will be

carried out for variation in material, surface finish, dimensions and geometrical

tolerances shall be as per drawing. Bidder should arrange required instruments in

order to carry out inspection and testing.

8.2 The manufacturer shall be solely responsible for ensuring all the material

properties, dimensional accuracy, surface profile tolerances, quality of various

components and soundness of joints.

9 Assembly work of Faraday Cup, HV Deck Conduits, and Test Jig mounting

stand, at site (RRCAT Indore):-

9.1 Each parts of the Faraday Cup, HV Deck Conduits, and Test Jig mounting stand

have to be assembled by supplier before dispatch at suppliers’ site and also at

RRCAT Indore. (as per the drawing given along with the PO).

10. Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits, and

Test Jig mounting stand parts:-

10.1 Dimensions of all the components of Faraday Cup, HV Deck Conduits, and

Test Jig mounting stand, assembly shall be as per our given drawings.

10.2 Compatible mounting nut, bolts, screws, or viton”O” rings should be supplied

with assembly.

10.3 Minor change in the drawing/assembly should be done free of cost, after

purchase order release / during PDI.

Page 3: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 3 /9

RRCAT, RF Ion Source Test Jig

Page 4: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 4 /9

RRCAT, RF Ion Source Test Jig

Page 5: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 5 /9

RRCAT, RF Ion Source Test Jig

Page 6: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 6 /9

RRCAT, RF Ion Source Test Jig

Page 7: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 7 /9

RRCAT, RF Ion Source Test Jig

Page 8: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 8 /9

RRCAT, RF Ion Source Test Jig

Page 9: Fabrication, assembly and supply of Faraday Cup, HV … processes:- ... pits, scratches, weld ripples and scales. 7. ... Acceptance Criteria of assembly of Faraday Cup, HV Deck Conduits,

Faraday Cup, HV Deck Conduits and test jig Mounting specifications and drawings

P a g e n o . : 9 /9

RRCAT, RF Ion Source Test Jig

MANDATORY COMPLIANCE SHEET (MCS) (To be filled in by the bidder & submitted along with the offer)

Instruction-1 Table A.1 : The rightmost column should be filled in by the

Bidder.

Instruction-2 Failure to submit a fully completed, duly signed and stamped

questionnaire may result in the rejection of the offer.

Table A.I

Item description of the specification sheet Response of

bidder for

Compliance

Is the offer includes quotation for all items as per

Table-I?.

YES/ NO

Is the item offered, a standard product of reputed

manufacturer?

YES/ NO

Years of experience, your company possess in supply of

similar items to public or government departments.

Whether copies of certificate are attached? YES/ NO

Previous experience in supplying similar items to

DAE/Public sector purchase order photo copy

Sr. No. Item name Quantity offered

in quotation

1. Faraday Cup (Type 1) RRCAT/PAG/PLDD/LCDL/M468

2. Faraday Cup (Type 2) RRCAT/PAG/PLDD/LCDL/M468.02

3. High Voltage Deck Conduits

RRCAT/PAG/PLDD/LCDL/M467

4. Test Jig mounting stand RRCAT/PAG/PLDD/LCDL/M470

The offer includes compatible VITON ‘O’ rings or mounting

SS nut, bolts screws given in the drawing sheet

YES/ NO

The offer includes electro polishing of Faraday Cup given in

the drawing sheet

YES/ NO

# Additional remarks may also be put in the last column of the above table by the

bidder, if they are necessary.

Please note that, with incomplete information the offer will get rejected.

Name of the person signing this compliance sheet (Bidder):

Mr./Ms.____________________________________________________

Signature

Bidder's company address:

M/s _______________________________________________________

__________________________________________________________

__________________________________________________________

Company Seal

RRCAT enquiry reference : DPS/IRPU/___________________________

Quotation no. :_____________________________________