32
Grange BackUp Power Industrial Emissions Licence Application 349512/EDE/DDX/1/A 20 October 2015 77 F.1 Treatment, Abatement and Control Systems F.1.1 Atmospheric Emissions Treatment, Abatement and Control A comprehensive air emission impact assessment was prepared for this power plant as part of the Environment Report submitted with the planning application to South Dublin County Council. This Environmental Report is included in Attachment B.6 of this licence application. Natural gas is a clean fuel resulting in negligible emissions of particulate matter and Sulphur Dioxide (SO 2 ). The main atmospheric pollutant of concern for the power plant firing on natural gas is Nitrogen Oxide (NO x ). The plant will comprise proven pollution prevention and control technology which will limit the emission of NO x i.e. the Selective Catalytic Reduction (SCR) technique. In the SCR system the NO X is reduced with the help of a reducing agent such as urea which will be stored on-site in a dedicated tank with a volume of 150m³. The engine stacks (A2-1, A2-2) will incorporate an in-situ proprietary Continuous Emission Monitoring System (CEMS). The selection, installation, calibration, ongoing quality assurance and annual surveillance testing of the CEMS will be undertaken in accordance with EN 14181 – Quality Assurance of Automated Measuring Systems and all relevant standards referred to therein. The requirements of EN 14181 will be incorporated into the planned preventive maintenance programme (PPMP). The number of potential sources of leaks from the plant will be minimised through plant design, for example the gas pipe will be welded thereby avoiding the use of flanges and valves wherever possible. Where appropriate, valves and flanges will be fitted with leak detection alarms connected to the main control room ensuring a rapid response in the event of an abnormal occurrence. The plant will only operate on low sulphur distillate oil in emergency situations and for short duration testing as required by the Commission for Energy Regulation (CER) and EirGrid. In accordance with the CER Decision Paper Secondary Fuel Obligations on Licensed Generation Capacity in the Republic of Ireland (2009) it is anticipated that approximately 2000m³ of low sulphur distillate oil will be stored on site in a bunded vertical cylindrical steel tank. Tank loading and unloading will be undertaken in accordance with standard operating procedures, manufacturer’s specifications and best practice guidelines, including IPC Guidance Note on Storage and Transfer of Materials for Scheduled Activities, EPA (2004). Losses will be minimised through effective site management techniques and training. Grange BackUp Power Limited will enter into a Long Term Services Agreement (LTSA) with the supplier to service the gas engine and main auxiliaries at pre-determined intervals. The PPMP will also be developed, in accordance with manufacturer’s specifications, incorporating all abatement and control systems as well as plant, pipes, valves and flanges with a potential atmospheric emission source as deemed appropriate. All defects will be prioritised. Defects associated with health and safety and environmental equipment will be given highest priority and action will be taken immediately. F Control and Monitoring For inspection purposes only. Consent of copyright owner required for any other use. EPA Export 11-11-2015:00:54:23

F Control and Monitoring

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

77

F.1 Treatment, Abatement and Control Systems

F.1.1 Atmospheric Emissions Treatment, Abatement and Control

A comprehensive air emission impact assessment was prepared for this power plant as part of the

Environment Report submitted with the planning application to South Dublin County Council. This

Environmental Report is included in Attachment B.6 of this licence application.

Natural gas is a clean fuel resulting in negligible emissions of particulate matter and Sulphur Dioxide (SO2).

The main atmospheric pollutant of concern for the power plant firing on natural gas is Nitrogen Oxide

(NOx). The plant will comprise proven pollution prevention and control technology which will limit the

emission of NOx i.e. the Selective Catalytic Reduction (SCR) technique. In the SCR system the NOX is

reduced with the help of a reducing agent such as urea which will be stored on-site in a dedicated tank with

a volume of 150m³.

The engine stacks (A2-1, A2-2) will incorporate an in-situ proprietary Continuous Emission Monitoring

System (CEMS). The selection, installation, calibration, ongoing quality assurance and annual surveillance

testing of the CEMS will be undertaken in accordance with EN 14181 – Quality Assurance of Automated

Measuring Systems and all relevant standards referred to therein. The requirements of EN 14181 will be

incorporated into the planned preventive maintenance programme (PPMP).

The number of potential sources of leaks from the plant will be minimised through plant design, for

example the gas pipe will be welded thereby avoiding the use of flanges and valves wherever possible.

Where appropriate, valves and flanges will be fitted with leak detection alarms connected to the main

control room ensuring a rapid response in the event of an abnormal occurrence.

The plant will only operate on low sulphur distillate oil in emergency situations and for short duration testing

as required by the Commission for Energy Regulation (CER) and EirGrid. In accordance with the CER

Decision Paper Secondary Fuel Obligations on Licensed Generation Capacity in the Republic of Ireland

(2009) it is anticipated that approximately 2000m³ of low sulphur distillate oil will be stored on site in a

bunded vertical cylindrical steel tank. Tank loading and unloading will be undertaken in accordance with

standard operating procedures, manufacturer’s specifications and best practice guidelines, including IPC

Guidance Note on Storage and Transfer of Materials for Scheduled Activities, EPA (2004). Losses will be

minimised through effective site management techniques and training.

Grange BackUp Power Limited will enter into a Long Term Services Agreement (LTSA) with the supplier to

service the gas engine and main auxiliaries at pre-determined intervals. The PPMP will also be developed,

in accordance with manufacturer’s specifications, incorporating all abatement and control systems as well

as plant, pipes, valves and flanges with a potential atmospheric emission source as deemed appropriate.

All defects will be prioritised. Defects associated with health and safety and environmental equipment will

be given highest priority and action will be taken immediately.

F Control and Monitoring

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 2: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

78

The total electricity output will be 115 MW during optimum conditions reaching thermal efficiencies in

excess of approximately 47%, which is higher than for any other gas engine available on the market. The

high rate of thermal efficiency, and subsequent reduction in greenhouse gases, is in accordance with the

requirements of BAT. Operation of the power plant will incorporate the following measures in order to

ensure thermal efficiency:

� The plant will operate on an advanced computerised control system which will ensure optimum

combustion conditions that support the reduction of emissions;

� Natural gas and feedwater will be filtered before use;

� The plant design will minimise the amount of heat lost due to unburned gases and excess air;

� The plant will operate under optimum pressure and temperature conditions whenever possible. The

plant design will employ the use of advanced materials capable of reaching the levels required;

� Inlet air will be fitted with a self-cleaning fabric filter in order to prevent the ingress of particulate matter.

� Operation of the plant will include maintenance measures such as raw water pre-treatment and

chemical treatment of the cooling water thereby optimising efficiency and minimising energy

consumption.

During a start-up or shut down of the power plant, the engine will ramp up or decrease its stable

operational load. This period is expected to be approximately 10 minutes in total for both scenarios.

During these periods the volume of exhaust gas exiting the exhaust stack will be reduced and its

temperature will be lower compared to standard operating levels. In addition, as an engine starts up, higher

emission concentrations of NOx and CO can be emitted.

When exhaust gas volumes and temperatures are reduced during start up and shut down the exit velocity

of the exhaust gas and its thermal buoyancy from the tip of the stack are reduced compared to normal

operation which can reduce the effectiveness of dispersion from the stack. However, as the primary fuel for

the project is natural gas the main pollutant of concern is NOx which has air quality standards for 1 hour

and annual mean averaging periods. Given the short period of time when start up and shut down occurs

the changes in dispersion characteristics and emission concentrations would have negligible effects on the

predicted level of impacts presented averaged over a 1 hour an annual mean periods and are therefore

start-ups and shut downs are not considered to have a significant effect on air quality.

The power plant will operate in accordance with the requirements of Directive 2010/75/EU on industrial

emissions (the Industrial Emissions Directive) and the BAT Guidance Note on Best Available Techniques

for the Energy Sector (Large Combustion Plant Sector), EPA, 2008. In addition, the plant will operate in

accordance with the relevant air quality standards and relevant emission limit values as specified in

Section 50 and Section 51 respectively of the Air Pollution Act 1987. Furthermore the plant will operate in

accordance with the Air Quality Standards Regulations 2011 (S.I. No. 180 of 2011) came into force and

transposed EU Directive 2008/50/EC on ambient air quality and cleaner air for Europe into Irish law. A

summary of the emissions is provided in Tables E.1(ii) and E.1(iii).

Table F.1(i) shows the treatment, abatement and control systems implemented for the main emission

points identified in Attachment E.1, which are:

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 3: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

79

� Engine Stack 1 (A2-1);

� Engine Stack 2 (A2-2);

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 4: F Control and Monitoring

80 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.1(i): ABATEMENT / TREATMENT CONTROL

Emission point reference number: A2-1 (Engine Operating on Natural Gas)

Control1 parameter Monitoring to be carried

out2

Equipment 3 Equipment back-up

NOx Continuous (via in situ

proprietary Continuous

Emissions Monitoring

System {CEMS})

Selective Catalytic

Reduction (SCR)

Demineralised Water

CEMS

Maintenance supplies

Stock of demineralised

water stored on site

CO As above Controlled combustion /

CEMS

Maintenance supplies

Temperature As above As above / CEMS Maintenance supplies

SO2 As above CEMS Maintenance supplies

Particulate Matter As above CEMS Maintenance supplies

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 5: F Control and Monitoring

81 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.1(i): ABATEMENT / TREATMENT CONTROL

Emission point reference number: A2-1 (Engine Operating on Low Sulphur Distillate Oil)

Control1 parameter Monitoring to be carried

out2

Equipment 3 Equipment back-up

NOx Continuous (via in situ

proprietary Continuous

Emissions Monitoring

System {CEMS})

Selective Catalytic

Reduction (SCR)

Demineralised Water

CEMS

Maintenance supplies

Stock of demineralised

water stored on site

CO As above Controlled combustion /

CEMS

Maintenance supplies

Temperature As above As above / CEMS Maintenance supplies

SO2 As above CEMS Maintenance supplies

Particulate Matter As above CEMS Maintenance supplies

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 6: F Control and Monitoring

82 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.1(i): ABATEMENT / TREATMENT CONTROL

Emission point reference number: A2-2 (Engine Operating on Natural Gas)

Control1 parameter Monitoring to be carried

out2

Equipment 3 Equipment back-up

NOx Continuous (via in situ

proprietary Continuous

Emissions Monitoring

System {CEMS})

Selective Catalytic

Reduction (SCR)

Demineralised Water

CEMS

Maintenance supplies

Stock of demineralised

water stored on site

CO As above Controlled combustion /

CEMS

Maintenance supplies

Temperature As above As above / CEMS Maintenance supplies

SO2 As above CEMS Maintenance supplies

Particulate Matter As above CEMS Maintenance supplies

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 7: F Control and Monitoring

83 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.1(i): ABATEMENT / TREATMENT CONTROL

Emission point reference number: A2-2 (Engine Operating on Low Sulphur Distillate Oil)

Control1 parameter Monitoring to be carried

out2

Equipment 3 Equipment back-up

NOx Continuous (via in situ

proprietary Continuous

Emissions Monitoring

System {CEMS})

Selective Catalytic

Reduction (SCR)

Demineralised Water

CEMS

Maintenance supplies

Stock of demineralised

water stored on site

CO As above Controlled combustion /

CEMS

Maintenance supplies

Temperature As above As above / CEMS Maintenance supplies

SO2 As above CEMS Maintenance supplies

Particulate Matter As above CEMS Maintenance supplies

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 8: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

84

F.1.2 Surface Water Emissions Treatment, Abatement and Control

As described in Attachment E.4 surface water will be collected from two catchment areas within the site –

the western catchment and the eastern catchment.

Surface water from the western catchment will be passed through a Class 1 full retention Enviroceptor.

This catchment includes the fuel oil unloading bay and the fuel storage tank which is located within a

bunded area. The rainwater which falls here is likely to be clean in the absence of an oil spill or leak. As a

result, a sump and pumping arrangement located within the bund will allow clean rainwater to be pumped

into the collection system when required. Pumping will be manually activated and will pass through to

avoid pumping potentially contaminated water. Surface water from the eastern catchment, which will

include run-off from the engine house and paved areas will be passed through a Bypass Separator.

The Class 1 Enviroceptor and the Bypass Separators will be fitted with visual and audible alarms to ensure

containment facilities are adequately maintained. In addition, this alarm will be linked to auto dial facilities

such that relevant staff can be alerted.

Gullies and drains entry points will incorporate silt traps to remove any grit or silt which may be washed

into the surface water drainage system.

The western and eastern catchment areas will have their own surface water attenuation tanks. The

western catchment attenuation tank will have a storage volume of 80m³ and the eastern catchment

attenuation tank will have a storage capacity of 150m³.These tanks have been designed to accommodate

a 1:100 year storm event and will discharge via hydro-brakes to the existing surface water drainage system

within the Grange Castle Business Park.

It should be noted also that the grant of planning permission issued by South Dublin County Council

(Planning Register: SD15A/0061) reinforces many of the above treatment, abatement and control

measures through the following conditions which Grange Back Up Power will ensure are fully complied

with:

� Drainage infrastructure will comply with the requirements of the Planning Authority or Irish Water;

� All drainage works will comply with the Greater Dublin Regional Code of Practise for Drainage Works

and the South Dublin County Council Specification for the Laying of Watermains and Drinking Water

Supply Guidance Document (2012);

� No development is authorised to take place until such time that Grange BackUp Power has provided

details to the Planning Authority of pollution monitoring and control mechanisms required to contain fire

water run-off within the site and to prevent pollution of the Griffeen River (which the Business Park

attenuation pond ultimately discharges to).

� There will be complete separation of the surface water and foul wastewater drainage systems; and

prior to the occupation of the development, details of tests and surveys demonstrating full separation

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 9: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

85

will be required to be submitted to the Planning Authority along with confirmation from the Councils

Waster Services Department that these tests and surveys fully meet with their requirements;

� Silt traps will be incorporated prior to the intakes to the surface water attenuation tanks;

� The hydrobrake proposed to restrict flow to the east of the site shall be relocated closer to the outfall in

order to restrict flow to all of the eastern section of the site (it should be noted that the relocated of the

hydrobrake has been updated as per this condition and the location of same is illustrated on Figure

F.2.1); and

� Only clean, uncontaminated water shall be discharged into the Griffeen River network. The specific

details of any discharges to watercourses will be agreed with Inland Fisheries Ireland. Class 1 petrol/oil

interceptors and hydrobrake controls should be provided on primary surface water discharges to

protect receiving freshwater in terms of water quality.

Table F.1(i) indicates the treatment, abatement and control systems implemented for the main emission

points identified in Attachment E.3, which are:

� Location Downstream of Surface Water Attenuation Tank 1 (SW1);

� Location Downstream of Surface Water Attenuation Tank 2 (SW2).

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 10: F Control and Monitoring

P1 29/09/15 SHY For PlanningMMcC PK

Key to symbols

App’dCh’k’dDescriptionDrawnDateRev

RevStatus

Drawing Number

Scale at A0

Eng check

Approved

Coordination

Dwg check

Drawn

Designed

Title

Notes

Client

Reference drawings

Security

P:\Dublin\MPD\349512 - Grange Power\CAD\Figure F.2.1.dwg Oct 2, 2015 - 8:46AM hea38245

TFW

©

Figure F.2.1

Emissions Monitoring Sampling Points

Grange Back Up Power Ltd

Others

S. Healy

M.McCarthy

Others

P.Kelly

1:200 APR

MMD-349512-N-DR-00-XX-0011

P1 STD

Mott MacDonald

South Block, Rockfield,

Dundrum, Dublin 16,

Ireland

+353 (0)1 2916700

+353 (0)1 2916747

www.mottmac.com

This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

Mott MacDonald

1:200

0 25m10m

1

2

3

4

5

6

8

9

10

11

13

16

17

18

19

20

7

14

21

15

22

23

24

25

26

1. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH

ALL RELEVANT ARCHITECTS AND ENGINEERS DRAWINGS

AND SPECIFICATIONS.

2. DO NOT SCALE, USE FIGURED DIMENSIONS ONLY.

3. ANY DISCREPANCIES TO BE REPORTED TO THE

ARCHITECT.

4. ALL DIMENSIONS ARE IN MILLIMETERS.

5. ALL LEVELS ARE IN METRES RELATIVE TO ORDNANCE

SURVEY DATUM MALIN HEAD.

28

29

30

31

32

33

34

ENGINE HALL

ANCILLIARY TANKS, PLANT, EQUIPMENT AND BUILDINGS

MONITORING & SAMPLING POINT

1

22

22

22

22

22

22

6

5

18

10

11

16

8

9

4

19

25

17

19

2423

21

26

14

3

7

20

15

2

14

17

³

³ 33

34

B

0008

A

0008

A

0008

A

0008

A

0008

B

0008

0008

N

26

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 11: F Control and Monitoring

86 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.1(i): ABATEMENT / TREATMENT CONTROL

Emission point reference number: SW1

Control1 parameter Monitoring to be carried

out2

Equipment 3 Equipment back-up

Total Petroleum

Hydrocarbons (TPH)

Weekly Visual inspection N/A

Suspended Solids Weekly Visual inspection N/A

Total Petroleum

Hydrocarbons (TPH)

Monthly Standard Method N/A

Suspended Solids Monthly Visual inspection N/A

Conductivity Monthly (as flow permits)

Standard Method Maintenance supplies

TOC Monthly Standard Method Maintenance supplies

pH Monthly Standard Method Maintenance supplies

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 12: F Control and Monitoring

87 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.1(i): ABATEMENT / TREATMENT CONTROL

Emission point reference number: SW2

Control1 parameter Monitoring to be carried

out2

Equipment 3 Equipment back-up

Total Petroleum

Hydrocarbons (TPH)

Weekly Visual inspection N/A

Suspended Solids Weekly Visual inspection N/A

Total Petroleum

Hydrocarbons (TPH)

Monthly Standard Method N/A

Suspended Solids Monthly Standard Method N/A

Conductivity Monthly (as flow permits)

Standard Method Maintenance supplies

TOC Monthly Standard Method Maintenance supplies

pH Monthly Standard Method Maintenance supplies

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 13: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

88

F.1.3 Domestic Wastewater Emissions Treatment, Abatement and Control

As described in Attachment E.5, foul wastewater from the power plant will consist of domestic effluent from

the toilets, sinks, etc. on-site. This wastewater will be discharged from the site via an appropriately sized

pumping station and will connect to the existing foul drainage system in Grange Castle Business Park

which in turn discharges to the South Dublin County Council foul drainage system which ultimately

discharges to the Ringsend Wastewater Treatment Plant.

It should be noted also that the grant of planning permission issued by South Dublin County Council

(Planning Register: SD15A/0061) states that here will be complete separation of the surface water and foul

wastewater drainage systems; and prior to the occupation of the development, details of tests and surveys

demonstrating full separation will be required to be submitted to the Planning Authority along with

confirmation from the Councils Waster Services Department that these tests and surveys fully meet with

their requirements.

Due to its small volume and the small operational workforce, it is not proposed to monitor foul wastewater.

F.1.4 Process Wastewater Emissions Treatment, Abatement and Control

Process wastewater to be generated from the facility will consist of the waste stream arising from the

treatment of purified water for injection into the engine during the combustion process to control NOx

emissions. This wastewater will have a volume of approximately 0.5m3/hr which will be collected in an

underground storage tank before its treatment and release (at SE2) to the existing foul drainage system in

Grange Castle Business Park which in turn discharges to the South Dublin County Council foul drainage

system which ultimately discharges to the Ringsend Wastewater Treatment Plant.

The process wastewater will be dosed automatically, if required, to regulate the pH to pH 6-9. Any solids

collected in the water treatment plant will be removed from site by authorised contractors.

All chemical conditioning materials required for water treatment or for corrosion control will be stored in the

chemical storage room. Spills and leaks will be cleaned by appropriately experienced personnel using

absorbent materials. The arising waste will be disposed of off-site by appropriately authorised contractors.

All elements of the treatment systems will be monitored on a regular basis to ensure optimum performance

and maintenance. The water treatment plant effluent will be monitored for pH. If the pH is outside the

range of 6-9, or as permitted by the EPA, the discharge will automatically stop until the failure is corrected.

Monitoring equipment will be included in the PPMP in accordance with manufacturer’s specifications and

best practice guidelines. Records of checks, calibrations and maintenance checks will be retained on site.

Pipes, bunds and storage facilities will be regularly checked for deterioration, damage and leaks. Integrity

testing and the maintenance of all waste water abatement, control and monitoring equipment will be

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 14: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

89

incorporated into the on-site maintenance programmes. All equipment will be maintained and calibrated in

accordance with manufacturer’s specifications.

TABLE F.1(i): ABATEMENT / TREATMENT CONTROL

Emission point reference number: SE2 (Process Wastewater)

Control1

parameter

Monitoring to be

carried out2

Equipment 3 Equipment back-up

Flow Continuous Discharge line

flowmeter

Maintenance supplies

pH Continuous Standard laboratory

Analysis

In accordance with

manufacturers

requirements

Temperature As above As above As above

BOD As above As above As above

Dissolved Oxygen As above As above As above

Suspended Solids As above As above As above

Nitrate (as N) As above As above As above

Ammonia (as N) As above As above As above

Chloride As above As above As above

TPH As above As above As above

Total Phosphorus (as

P)

As above As above As above

Conductivity As above As above As above

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 15: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

90

F.2 Emissions Monitoring and Sampling Points

F.2.1 General

A traceable and transparent monitoring, sampling and reporting programme will be developed by Grange

Back Up Power to ensure that emissions from the facility are within the relevant emission limit values and

irregularities and malfunctions are detected, and corrective actions implemented as soon as practicable.

The monitoring and sampling frequency implemented will be proportionate to the level of risk to the

environment.

Monitoring and sampling points will be limited to emissions to atmosphere, emissions to the sewer,

emissions to surface water and noise.

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 16: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

91

F.2.2 Atmospheric Emissions Monitoring and Sampling Points

Exhaust gases will be emitted to atmosphere through the engine stacks (A2-1 and A2-2). The stack will

incorporate an in-situ proprietary Continuous Emission Monitoring System (CEMS). The CEMS will

continuously monitor NOx, CO, Temperature and O2. Additional monitoring of SO2 and Particulate Matter

will be undertaken in accordance with the requirements of the EPA.

Minor emissions from the facility are not considered to be significant. Therefore, it is not proposed to

undertake additional atmospheric emissions monitoring for the minor emission points identified in

Attachment E.1 Emissions to Atmosphere.

Tables F.2(i) identifies the monitoring and sampling parameters associated with A2-1 and A2-2. The

location of these monitoring points is illustrated on Figure F.2.1.

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 17: F Control and Monitoring

92 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.2(i) : EMISSIONS MONITORING AND SAMPLING POINTS

Emission Point Reference No. : A2-1 (Engine Operating on Natural Gas)

Parameter Monitoring frequency Accessibility of Sampling

Points

Sampling method Analysis method/

technique

NOx Continuous Accessible Continuous On line flue gas analyser

and recorder

CO Continuous As above As above On line flue gas analyser

and recorder

Temperature Continuous As above As above On line flue gas analyser

and recorder

Pressure Continuous As above As above On line flue gas analyser

and recorder

Oxygen Content Continuous As above As above On line flue gas analyser

and recorder

Water Vapour Continuous As above As above On line flue gas analyser

and recorder

O2 Continuous As above As above On line flue gas analyser

and recorder

SO2 Bi-annually As above Standard Method Flue gas analyser

Particulate Matter Bi-annually As above As above Standard Method

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 18: F Control and Monitoring

93 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS

Monitoring Point Reference No: A2-1 (Engine Operating on Distillate Oil)

Parameter Monitoring frequency Accessibility of Sampling

Points

Sampling method Analysis method/ technique

NOx Continuous Accessible Continuous On line flue gas analyser

and recorder

CO Continuous As above As above On line flue gas analyser

and recorder

Temperature Continuous As above As above On line flue gas analyser

and recorder

O2 Continuous As above As above On line flue gas analyser

and recorder

SO2 *Annually As above Standard Method Flue gas analyser

Particulate Matter *Annually As above As above Standard Method

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 19: F Control and Monitoring

94 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.2(i) : EMISSIONS MONITORING AND SAMPLING POINTS

Emission Point Reference No. : A2-2 (Engine Operating on Natural Gas)

Parameter Monitoring frequency Accessibility of Sampling

Points

Sampling method Analysis method/

technique

NOx Continuous Accessible Continuous On line flue gas analyser

and recorder

CO Continuous As above As above On line flue gas analyser

and recorder

Temperature Continuous As above As above On line flue gas analyser

and recorder

Pressure Continuous As above As above On line flue gas analyser

and recorder

Oxygen Content Continuous As above As above On line flue gas analyser

and recorder

Water Vapour Continuous As above As above On line flue gas analyser

and recorder

O2 Continuous As above As above On line flue gas analyser

and recorder

SO2 Bi-annually As above Standard Method Flue gas analyser

Particulate Matter Bi-annually As above As above Standard Method

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 20: F Control and Monitoring

95 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS

Monitoring Point Reference No: A2-2 (Engine Operating on Distillate Oil)

Parameter Monitoring frequency Accessibility of Sampling

Points

Sampling method Analysis method/ technique

NOx Continuous Accessible Continuous On line flue gas analyser

and recorder

CO Continuous As above As above On line flue gas analyser

and recorder

Temperature Continuous As above As above On line flue gas analyser

and recorder

O2 Continuous As above As above On line flue gas analyser

and recorder

SO2 *Annually As above Standard Method Flue gas analyser

Particulate Matter *Annually As above As above Standard Method

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 21: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

96

F.2.3 Emissions to Surface Water Monitoring and Sampling Points

All hardstanding areas will drain by gravity to the surface water attenuation tanks. These will discharge via

hydro-brakes to the existing surface water drainage system within the Grange Castle Business Park.

Details of the proposed monitoring and sampling points of emissions to surface water drainage system are

indicated in Table F.2(ii).

Two monitoring and sampling locations are proposed at SW1 and SW2 as illustrated in Figure F.2.1

Emissions Monitoring Sampling Points. Sampling and analysis will be conducted in accordance with the

requirements of the EPA through the industrial emissions licence.

Tables F.2(i) identifies the monitoring and sampling parameters associated with SW1 and SW2. The

location of these monitoring points is illustrated on Figure F.2.1.

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 22: F Control and Monitoring

97 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS

Monitoring Point Reference No: SW1

Parameter Monitoring frequency Accessibility of Sampling

Points

Sampling method Analysis method/ technique

Total Petroleum

Hydrocarbons (TPH) Daily Accessible

Grab sample / Visual

inspection

Sample and inspect for

colour and odour

Suspended Solids Daily As above As above As above

TPH Monthly As above

Grab sample Laboratory Analysis

Suspended Solids Monthly As above

As above As above

Conductivity Monthly (as flow permits)

As above

As above As above

TOC Monthly As above

As above As above

pH Monthly As above

As above As above

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 23: F Control and Monitoring

98 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS

Monitoring Point Reference No: SW2

Parameter Monitoring frequency Accessibility of Sampling

Points

Sampling method Analysis method/ technique

Total Petroleum

Hydrocarbons (TPH) Daily Accessible

Grab sample / Visual

inspection

Sample and inspect for

colour and odour

Suspended Solids Daily As above As above As above

TPH Monthly As above

Grab sample Laboratory Analysis

Suspended Solids Monthly As above

As above As above

Conductivity Monthly (as flow permits)

As above

As above As above

TOC Monthly As above

As above As above

pH Monthly As above

As above As above

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 24: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

99

F.2.4 Emissions to Foul Sewer Monitoring and Sampling Points

Emissions to foul sewer will consist of process wastewater (SE2). Process wastewater emissions will be

discharged to the existing foul drainage system in Grange Castle Business Park which in turn discharges

to the South Dublin County Council foul drainage system which ultimately discharges to the Ringsend

Wastewater Treatment Plant. Details of the proposed monitoring and sampling point are indicated in Table

F.2(ii).

Tables F.2(i) identifies the monitoring and sampling parameters associated SE2. The location of this

monitoring points are illustrated on Figure F.2.1.

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 25: F Control and Monitoring

100 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS

Emission Point Reference No. SE-2

Parameter Monitoring frequency Accessibility of

Sampling Points

Sampling method Analysis method/

technique

Flow Weekly Accessible n/a

Discharge line

flowmeter

pH Weekly As above

On-line monitoring and

automatic sampler

On-line monitoring and

automatic sampler

Temperature Weekly As above As above As above

BOD Weekly As above As above As above

Dissolved Oxygen Weekly As above As above As above

Suspended Solids Weekly As above As above As above

Nitrate (as N) Weekly As above As above As above

Ammonia (as N) Weekly As above As above As above

Chloride Weekly As above As above As above

TPH Weekly As above As above As above

Total Phosphorus (as

P) Weekly As above As above As above

For in

spec

tion p

urpo

ses o

nly.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 26: F Control and Monitoring

101 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

Conductivity Weekly As above As above As above

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 27: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

102

F.2.5 Ambient Noise Monitoring and Sampling Points

Grange Back Up Power propose to undertake ambient noise monitoring at 6 no. locations on an annual

basis. The monitoring points selected correspond to those same location used in the preparation of the

noise impact assessment contained in the Environmental Report which is included in Attachment B.6.

These locations are illustrated on Figure F.2.2 Ambient Noise Monitoring Locations.

In addition to the above monitoring Grange Back Up Power will carry out secondary monitoring at a

number of fixed locations on the boundary of the power plant facility. These locations will be agreed as

required with the EPA prior to the operation of the power plant.

Details of the proposed ambient monitoring points are provided in Table F.2(ii).

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 28: F Control and Monitoring

P1 29/09/15 SHY For PlanningMMcC PK

Key to symbols

App’dCh’k’dDescriptionDrawnDateRev

RevStatus

Drawing Number

Scale at A0

Eng check

Approved

Coordination

Dwg check

Drawn

Designed

Title

Notes

Client

Reference drawings

Security

P:\Dublin\MPD\349512 - Grange Power\CAD\Figure F.2.2.dwg Sep 30, 2015 - 11:55AM hea38245

TFW

©

Figure F.2.2

Noise Monitoring Locations

Grange Back Up Power Ltd

Others

S. Healy

M.McCarthy

Others

P.Kellly

1:2500 APR

MMD-349512-N-DR-00-XX-0012

P1 STD

Mott MacDonald

South Block, Rockfield,

Dundrum, Dublin 16,

Ireland

+353 (0)1 2916700

+353 (0)1 2916747

www.mottmac.com

This document is issued for the party which commissioned it and for specific purposes connected with the captioned project only. It should not be relied upon by any other party or used for any other purpose.

We accept no responsibility for the consequences of this document being relied upon by any other party, or being used for any other purpose, or containing any error or omission which is due to an error or omission in data supplied to us by other parties.

Mott MacDonald

1. THIS DRAWING IS TO BE READ IN CONJUNCTION WITH

ALL RELEVANT ARCHITECTS AND ENGINEERS DRAWINGS

AND SPECIFICATIONS.

2. DO NOT SCALE, USE FIGURED DIMENSIONS ONLY.

3. ANY DISCREPANCIES TO BE REPORTED TO THE

ARCHITECT.

4. ALL DIMENSIONS ARE IN MILLIMETERS.

5. ALL LEVELS ARE IN METRES RELATIVE TO ORDNANCE

SURVEY DATUM MALIN HEAD.

Ordnance Survey Ireland Government of Ireland

Ordnance Survey Ireland Licence No. EN 0003415

c

Ordnance Survey Map Ref No:

3261 - C , 3260 - D , 3325 - B & 3326 - A

1:2500

0 250m100m

OS MAPPING

1:50000

MONITORING & SAMPLING POINT

GRAND CANAL

FOOTBRIDGE

F

U

T

U

R

E

R

1

2

0

A

L

IG

N

M

E

N

T

ESB

SUBSTATION

110KV

N

SITE LOCATION

GRAND CANAL

FOOTBRIDGE

F

U

T

U

R

E

R

1

2

0

A

L

I

G

N

M

E

N

T

ESB

SUBSTATION

110KV

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 29: F Control and Monitoring

103 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

TABLE F.2(ii): AMBIENT ENVIRONMENT MONITORING AND SAMPLING POINTS

Monitoring Point Reference No : ANL-1 (North ern Site Boundary)

Grid Reference: 303627E 232128N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Method Standard Monitoring

Techniques

Monitoring Point Reference No : ANL-2(Eastern Site Boundary)

Grid Reference: 303705E 232085N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Equipment Standard Monitoring

Techniques

Monitoring Point Reference No : ANL-3 (Southern Site Boundary)

Grid Reference: 303626 E 232050N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Method Standard Monitoring

Techniques

For in

spec

tion p

urpo

ses o

nly.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 30: F Control and Monitoring

104 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

Monitoring Point Reference No : ANL-4 (Western Site Boundary)

Grid Reference: 303545E 232094N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Method Standard Monitoring

Techniques

Monitoring Point Reference No : ANL-5(Canal Footbridge)

Grid Reference: 303726E, 232285N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Method Standard Monitoring

Techniques

Monitoring Point Reference No : ANL6 (SDCC Attenuation Pond)_

Grid Reference: 304025E, 232210N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Method Standard Monitoring

Techniques

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 31: F Control and Monitoring

105 349512/EDE/DDX/1/A 20 October 2015

Grange BackUp Power Industrial Emissions Licence Application

Monitoring Point Reference No : ANL7 (Adjacent Residential Property)_

Grid Reference: 303333E, 232222N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Method Standard Monitoring

Techniques

Monitoring Point Reference No : ANL8 (Grange Caste Business Park Location 1)_

Grid Reference: 303412E, 231791N 303995E,231815N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Method Standard Monitoring

Techniques

Monitoring Point Reference No : ANL9 (Grange Caste Business Park Location 2)_

Grid Reference: 303995E, 231815N

Parameter Monitoring frequency Accessibility of

Sampling point

Sampling method Analysis method / technique

Noise Annual Accessible Standard Method Standard Monitoring

Techniques

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23

Page 32: F Control and Monitoring

Grange BackUp Power Industrial Emissions Licence Application

349512/EDE/DDX/1/A 20 October 2015

106

F.3 Tabular Data on Monitoring and Sample Points

Point Code Point Type Easting Northing Verified Emission

A2-1 Atmospheric 303681 232116 No N0x, S02, CO2, CO, PM

A2-2 Atmospheric 303656 232117 No N0x, S02, CO2, CO, PM

SW-1 Surface Water 303696 232052 No Stormwater

SW-2 Surface Water 303607 232055 No Stormwater

SE-2 Sewer 303598 232079 No pH, BOD, Suspended

Solids, Nitrate (as N),

Ammonia (as N), Chloride, Mineral Oil,

Total Phosphorous

(as P).

ANL1 Noise 303627 232128 No Noise

ANL2 Noise 303705 232085 No Noise

ANL3 Noise 303626 232050 No Noise

ANL4 Noise 303545 232094 No Noise

ANL5 Noise 303726 232285 No Noise

ANL6 Noise 304025 232210 No Noise

ANL7 Noise 303333 232222 No Noise

ANL8 Noise 303412 231791 No Noise

ANL9 Noise 303995 231815 No Noise

For

insp

ectio

n pur

pose

s only

.

Conse

nt of

copy

right

owne

r req

uired

for a

ny ot

her u

se.

EPA Export 11-11-2015:00:54:23