28
F-CDM-MR Monitoring report form (Version 03.1) Monitoring report Title of the project activity Kocaeli Landfill Gas to Electricity Project Reference number of the project activity GS1013 Version number of the monitoring report V7.0 Completion date of the monitoring report 22/04/2014 Registration date of the project activity 06/12/2013 Monitoring period number and duration of this monitoring period 1 st Monitoring Period 01/03/2012 – 30/06/2013 (first and last days are included) Project participant(s) Körfez Enerji A.Ş. Host Party(ies) Turkey Sectoral scope(s) and applied methodology(ies) Sectoral Scope 13, Waste Handling and Disposal ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0 Estimated amount of GHG emission reductions or net anthropogenic GHG removals by sinks for this monitoring period in the registered PDD 126,773.5 tCO 2 e Actual GHG emission reductions or net anthropogenic GHG removals by sinks achieved in this monitoring period 01/03/2012 – 31/12/2012 1 26,645tCO 2 e 01/01/2013 – 30/06/2013 2 47,563 tCO 2 e 01/03/2012 – 30/06/2013 74,208 tCO 2 e 1 The monitoring period which falls under the first commitment period of Kyoto Protocol 2 The monitoring period which falls under the second commitment period of Kyoto Protocol Version 03.1 Page 1 of 28

F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Monitoring report form

(Version 03.1)

Monitoring report

Title of the project activity Kocaeli Landfill Gas to Electricity Project Reference number of the project activity GS1013 Version number of the monitoring report V7.0 Completion date of the monitoring report 22/04/2014 Registration date of the project activity 06/12/2013 Monitoring period number and duration of this monitoring period

1st Monitoring Period 01/03/2012 – 30/06/2013 (first and last days are included)

Project participant(s) Körfez Enerji A.Ş. Host Party(ies) Turkey Sectoral scope(s) and applied methodology(ies) Sectoral Scope 13, Waste Handling and

Disposal ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0

Estimated amount of GHG emission reductions or net anthropogenic GHG removals by sinks for this monitoring period in the registered PDD

126,773.5 tCO2e

Actual GHG emission reductions or net anthropogenic GHG removals by sinks achieved in this monitoring period

01/03/2012 – 31/12/20121 26,645tCO2e 01/01/2013 – 30/06/20132 47,563 tCO2e 01/03/2012 – 30/06/2013 74,208 tCO2e

1 The monitoring period which falls under the first commitment period of Kyoto Protocol 2 The monitoring period which falls under the second commitment period of Kyoto Protocol

Version 03.1 Page 1 of 28

Page 2: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

SECTION A. Description of project activity

A.1. Purpose and general description of project activity

Landfill is a significant source of global warming as it contains a high share of methane (CH4), which is a potent greenhouse gas. The Kocaeli Landfill Gas to Electricity Project contributes to the reduction of greenhouse gas through destruction and avoidance of methane in the landfill area. The project activity developed by Körfez Enerji A.Ş., is a landfill gas recovery and utilization project at the site of Solaklar Landfill Area in Solaklar District, Kocaeli Province, Turkey. Solaklar Landfill Area has been built in 1997 as a sanitary landfill area under the responsibility of İZAYDAŞ and is the biggest landfill area in Kocaeli Municipality. On 13/07/2010, İZAYDAŞ has transferred the right of use of the closed lots to the Project Participant. The Project Participant has the right to recover the landfill gas and generate electricity by utilization of the LFG from the closed lots. On 22/03/2011 the construction has started and started operation on 01/03/2012 and is operational since then.

The project activity is planned to destroy methane through landfill gas extraction from the landfill area. The landfill gas is furthermore used for the purpose of electricity generation via gas engines. The electricity generated is delivered to the national grid system, substituting the baseline energy fuel which is mainly based on fossil fuels.

Brief description of the installed technology and equipment:

The proposed project activity involves:

- gradual covering of the landfill area

- a gas extraction system which can support gas engines for electricity generation

- a flaring system

- gas engines

During the first monitoring period from 01/03/2012 – 30/06/2013, the total emission reduction achieved is 74,208 tCO2eq.

Version 03.1 Page 2 of 28

Page 3: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

A.2. Location of project activity

Host Party: Republic of Turkey

The province is located at the Gulf of İzmit in the Sea of Marmara, about 100 km east of Istanbul, on the north western part of Anatolia. The city center has a population of 294,875 (2009 census). The population of the province (including rural areas) is about 1,500,000. The Solaklar Landfill is the largest landfill area within Kocaeli Province and is located within the headquarter facilities area of IZAYDAŞ. The GSP coordinates of the project are 40°47'14.83"N / 30°1'33.60" E

Version 03.1 Page 3 of 28

Page 4: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

A.3. Parties and project participant(s)

Party involved

((host) indicates a host Party)

Private and/or public entity(ies) project participants (as applicable)

Indicate if the Party involved wishes to be considered as project participant (Yes/No)

Turkey (host country) Körfez Enerji A.Ş. No

Name of the person/entity completing the monitoring report:

The monitoring report has been prepared by Mr. Ömer Akyürek from OakDanışmanlık in association with Mr. Hinrich Bornebusch.

Company Name OakDanışmanlık Ecoblu

Visiting Address Acıbadem Mah. Şemibey Sok. Belkıs Apt. N:3 D:6 Kadıköy / Istanbul, TURKEY

Gerhart-Hauptmann-Weg 76 A, 41469 Neuss, Germany

Contact Person Ömer Akyürek Hinrich Bornebusch

Telephone number +90 216 3471671 +49 2137 148 9065

E-mail [email protected] [email protected]

OakDanışmanlık is the carbon consultant for the project activity.

A.4. Reference of applied methodologyApplied approved baseline and monitoring methodologies:

• Approved consolidated baseline methodology ACM0001 “Flaring or Use of Landfill Gas” Version 12.0.0;

Used tools:

• “Combined tool to identify the baseline scenario and demonstrate the additionality” version 03.0.1;

• “Tool to determine project emissions from flaring gases containing methane “version 01;

• “Tool to determine the mass flow of a greenhouse gas in a gaseous stream” version 02.0.0

• “Emissions from solid waste disposal sites" version 06.0.0;

• “Tool to calculate the emission factor for an electricity system” Version 02.2.1,

• ‘Tool to calculate baseline, project and/or leakage emissions from electricity consumption’ version 01.

For more information regarding the methodology please refer to

http://cdm.unfccc.int/methodologies/PAmethodologies/approved

A.5. Crediting period of project activity

The project was registered on 06/12/2012 with a renewable crediting period. The first crediting period starts from 01/03/2012 to 28/02/2019.

Version 03.1 Page 4 of 28

Page 5: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

SECTION B. Implementation of project activity

B.1. Description of implemented registered project activity

Currently the project is operational with two sets of gas engines with a total capacity of 2.23 MW installed capacity. One of the installed engines is MWM TCG2020 v12 type engine4 manufactured by the German Company MWM GmbH, and the second engine is Jenbacher Type 3 J320 GS engine5 manufactured by GE. Both engines are dedicated to LFG utilization. At the time of PDD development, it was envisaged that two set MWM engine with an approximate capacity of 1.2 MW (depending on the availability of the LFG) will be installed. The PP has decided to install Jenbacher Type 3 J320 GS engine of 1 MW instead of the second engine. The total capacity of the project activity is still lower than the mentioned capacity under the PDD and the Generation License.

The most important milestones of project activity are summarised as follows:

Table 1. Important milestones of the project activity

Date Milestone

22/03/2011 Start of Construction

01/03/2012 Start of operation of the first PGU (GM-1 MWM TCG2020)

01/03/2012 Start of first crediting period

06/12/2012 Registration of the project activity under GS

15/10/2012 Start of operation of the second PGU (GM-2 GE J320GS)

01/01/2013 Start of the second commitment period of Kyoto Protocol

30/06/2013 End of first monitoring period

There has been no major incident or failure of equipment throughout the monitoring period.

Description of the LFG activity:

The landfill gas is collected with the horizontal channels and vertical wells in the landfill. These two different methods horizontal and vertical collection are explained in detail below:

The first one is the collection of the LFG with series of vertical wells, which helps the collection of the LFG from deep points in the landfill body. Wells are drilled till to a certain depth and then HDPE pipes are installed to the holes. After the installation of each well, the collected LFG via wells will be transferred to the main collection system.

The second system is the horizontal collection system, which intercept LFG migrating offsite in the subsurface. Vertical wells are installed at the horizontal pipe to convey the gas.

Active gas collection system is applied for degassing of the landfill. The main pipe is connected to the intake pipe of the landfill gas blower and the outgoing pipe from the blower is then finally connected to the LFG utilization system.

B.2. Post registration changes

B.2.1. Temporary deviations from registered monitoring plan or applied methodology

There are no temporary deviations from the registered monitoring plan or applied methodology within this monitoring period.

3 The technical capacity of both engines add up to 1,200 kWe (MWM) + 1,063 kWe (Jenbacher) = 2,263 kWe according to the specifications provided by the manufacturers.

4 Reference: http://issuu.com/mwm_energy/docs/mwm_lb_tcg_2020_en?mode=window&backgroundColor=%230065A6

5 Reference: http://www.ge-energy.com/content/multimedia/_files/downloads/ETS_E_T3_12_screen.pdf

Version 03.1 Page 5 of 28

Page 6: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

B.2.2. Corrections

Under the registered PDD, the calibration frequency of ID.25 “Temperature of the gaseous stream”; ID.26 “Net amount of electricity generated using LFG”; ID.27 “Quantity of electricity consumed” are set as follows:

“Calibration and frequency of calibration is according to manufacturer’s specifications”.

However during the monitoring plan it was not possible for the PP to retrieve calibration frequencies from the manufacturers (for ID.25) or the calibration practices within the context of regulatory requirements were not suitable to follow as stated under the registered PDD (ID.26 and ID.27). Therefore the calibration frequencies for ID.25, ID.26 and ID.27 has been revised as follows:

“In accordance with the “Regulation on “Measurement and Measuring Tools”, the meters have to be calibrated within a frequency of once per 10 years”.

B.2.3. Permanent changes from registered monitoring plan or applied methodology

There are no permanent changes from the registered monitoring plan or applied methodology within this monitoring period.

B.2.4. Changes to project design of registered project activity

There are no changes to project design of registered project activity within this monitoring period.

B.2.5. Changes to start date of crediting period

There are no changes to start date of crediting period.

B.2.6. Types of changes specific to afforestation or reforestation project activity

This section is not applicable to the project activity.

SECTION C. Description of monitoring system

The monitoring system has been developed in a way to cover all the procedures required as per the approved methodology ACM0001 validated monitoring plan.

The electricity meters are bi directional and measure both the electricity generated by the project activity and the electricity consumed by the facility. The meters are sealed by the electricity distribution/transmission company and the Project Participant cannot intervene with the devices. The Grid Company submits monthly a protocol to the project owner. The monthly electricity data are transferred to the excel sheet used for the emission reduction calculations.

The calculation of GS VERs for the first monitoring period is carried out through a separate spreadsheet. The project owner is Körfez Enerji A.Ş. and therefore responsible for the operation and the monitoring of the project activities. The data is archived and stored electronically during the crediting period and two years after. Roles and responsibilities Mr Serdar Eruysal is responsible for the site and the system while the VER team is managed by Mr. Fethullah Demircan. Involvement of Third Parties Support and consultancy regarding the development of monitoring report is provided by Ömer Akyürek (OakDanışmanlık) in association with Mr. Hinrich Bornebusch (Ecoblu). Internal audits and control measures There are daily checks if the data from the day before was stored successfully on the servers. Aggregation of data and cross checks takes place periodically.

Version 03.1 Page 6 of 28

Page 7: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

SECTION D. Data and parameters

D.1. Data and parameters fixed ex ante or at renewal of crediting period

Data / Parameter: ID.1 / OXtop-layer

Unit: Dimensionless Description: Fraction of methane that would be oxidized in the top layer of the

SWDS in the baseline Source of data: Consistent with how oxidation is accounted for in the

methodological tool “Emissions from solid waste disposal sites” Value(s) applied): 0.1 Purpose of data: Calculation of the baseline emissions Additional comment:

Data / Parameter: ID.2 / GWPCH4

Unit: tCO2e/tCH4 Description: Global warming potential of CH4 Source of data: IPCC Value(s) applied): Under the PDD the GWPCH4 has been considered as 21 for ex-

ante calculations. During the monitoring period the following GWPCH4 values have been used. 21 between 01/03/2012 to 31/12/2012 25 between 01/01/2013 to 30/06/2013

Purpose of data: Calculation of the baseline emissions Additional comment: In line with the requirements of GS6:

21 for the monitoring period that falls within the first commitment period (to 31/12/2012), and; 25 for the monitoring period that falls within the second commitment period (from 01/01/2013)

Data / Parameter: ID.6 / nflare,h Unit: - Description: Flare efficiency in hour h Source of data: Registered PDD

6 Reference: GS TAC&Rule update published on January 2013: http://www.cdmgoldstandard.org/wp-content/uploads/2011/09/Global-Warming-Potentials-for-Gold-Standard-Project-Activities-2013.pdf

Version 03.1 Page 7 of 28

Page 8: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Value(s) applied): • 0% if the temperature in the exhaust gas of the flare (Tflare) is below 5000C for more than 20 minutes during the hour h.

• 50%, if the temperature in the exhaust gas of the flare (Tflare) is below 5000C for more than 40 minutes during the hour h, but the manufacturers specifications on proper operation of the flare are not met at any point in time during the hour h.

• 90%, if the temperature in the exhaust gas of the flare (Tflare) is below 5000C for more than 20 minutes during the hour h and the manufacturers specifications on proper operation of the flare are met continuously in during the hour h.

Purpose of data: Calculation of the baseline emissions Additional comment: Due to the fact that there are only hourly measurements of the

flare temperature, it is assumed for conservative reason that the flare efficiency is always = 0%

Data / Parameter: ID.7 / pCH4,n Unit: kg/m3 Description: Density of methane under normal conditions Source of data: Registered PDD Value(s) applied): 0.716 Purpose of data: Calculation of the baseline emissions Additional comment:

Data / Parameter: EFEL,y

Unit: tCO2eq/MWh Description: Emission factor for the production of the electricity in the project

activity Source of data: Registered PDD Value(s) applied): 0.542 Purpose of data: Calculation of the baseline and project emissions Additional comment: The value is calculated ex-ante and has been fixed throughout the

first crediting period.

Data / Parameter: SD.1 / wH2S Unit: Fraction Description: Fraction of sulphide within the LFG determined ex-ante for SD.1

“Air quality” Source of data: Registered Gold Standard Project Passport Value(s) applied): 0.5% Purpose of data: Used for Gold Standard Sustainable Development Monitoring

Parameter SD.1 “Air Quality” Additional comment: -

Version 03.1 Page 8 of 28

Page 9: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

D.2. Data and parameters monitored

Data / Parameter: ID.22 / Operation of the energy plant Unit: Hr Description: Operation of energy plant Measured/ Calculated / Default:

measured

Source of data: The amount of hours is registered by a counting device in each power generation unit.

Value(s) of monitored parameter:

GM1: 10,030.5 h GM2: 5,706.8 h

Monitoring equipment:

Counting devices of each power generation unit

Measuring/ Reading/ Recording frequency:

The counting devices of the engines are counting the operational hours continuously as the operational hours are also used for maintenance reasons. The operational hours of the MWM engine are recorded by the monitoring system, the operational hours of the Jenbacher engine are recorded manual at least monthly.

Calculation method (if applicable):

N/A

QA/QC procedures: - Purpose of data: Calculation of baseline emission Additional comment:

Data / Parameter: ID.23 / Vt,db Unit: m³ dry gas / h Description: Volumetric flow of the gaseous stream (to the electricity

generating units) in time interval t on a dry basis Measured/ Calculated / Default:

Measured

Source of data: Measured continuously through a mass flow meter Value(s) of monitored parameter:

2012: 3,261,599 2013: 4,887,227

Monitoring equipment:

Thermal mass flow measuring system by Endress & Hause, Proline t-mass 65I, Serial number E8044E02000. The accuracies of the measurement are 1.0%.

Measuring/ Reading/ Recording frequency:

The monitoring system works with continuous measurement devices. It is programmed to automatically save hourly values. The data are stored automatically at the server.

Calculation method (if applicable):

N/A

Version 03.1 Page 9 of 28

Page 10: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

QA/QC procedures: In accordance with the manufacturers specifications a calibration is interval of every 3 years is recommended.. The meter was initially calibrated on 22/08/2011 and is valid for 3 years.

Purpose of data: Baseline emission calculation Additional comment: As the measuring device convert the flow direct to normal

conditions, no separate measurement of pressure and temperature is required as described in equation (5) and footnote 41 of the PDD.

Data / Parameter: ID.24 / vCH4,t,db

Unit: m³ gas CH4/ m³ dry gas Description: Volumetric fraction of CH4 in a time interval t on a dry basis Measured/ Calculated / Default:

measured

Source of data: The methane fraction in the LFG is measured continuously by a gas analyser.

Value(s) of monitored parameter:

The weighted averages of this monitoring period are7: 2012: 52.87% 2013: 54.07%

Monitoring equipment:

For the measurement a Siemens Ultramat-23, Serial number 7MB2337-2CR10-3DR1 is used. The accuracies of the measurement are 0.2%.

Measuring/ Reading/ Recording frequency:

The monitoring system works with continuous measurement devices. It is programmed to automatically save hourly values. The data are stored automatically at the server.

Calculation method (if applicable):

N/A

QA/QC procedures: In accordance with the Manufacturers specifications the calibration frequency has been recommended as 12 month.

Purpose of data: Calculation of baseline emissions Additional comment: The meter is installed as pre-calibrated from the factory. In

accordance with the Manufacturers specifications the calibration frequency has been recommended as 12 month. However the PP is unable to find the document for initial calibration of the meter ID.30. The meter was sent to calibration on 23.07.2013. According to the calibration report, the meter does not show any errors in the measuring equipment. As a conservative approach, the maximum permissible error of 0.2% of the equipment is applied to all the measurement result of this equipment. This approach is also in line with the CDM validation and verification standard v.04.0 paragraph 238.This parameter is identical to ID.30

7 The figures represent the result of the readings without taking into account the error margin as described under Additional Comments. However the result baseline emissions are calculated taking into account the error margin.

Version 03.1 Page 10 of 28

Page 11: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Data / Parameter: ID.25 / Tt

Unit: K Description: Temperature of the gaseous stream in a time interval t Measured/ Calculated / Default:

measured

Source of data: Temperature measure Value(s) of monitored parameter:

The maximum values during the monitoring period are: 2012: 47.98°C (321.13 °K) 2013: 43.72°C (316.87 °K) Since all parameters are converted to normal conditions during the monitoring process, this temperature is only monitored to verify the applicability condition for dry gas is met by a gas temperature below 60°C.

Monitoring equipment:

The measurement is carried out by a temperature meter WIKA TR-10_H, serial number 1102D580. The accuracy class of the device is class B which does mean a tolerance of +/- (0.3 + 0.0050 * |t|). |t| is the value of the temperature in °C without consideration of the sign.

Measuring/ Reading/ Recording frequency:

The monitoring system works with continuous measurement devices. It is programmed to automatically save hourly values. The data are stored automatically at the server.

Calculation method (if applicable):

N/A

QA/QC procedures: In accordance with the “Regulation on “Measurement and Measuring Tools”, gaseous stream meters have to be calibrated within a frequency of once per 10 years8.

Purpose of data: Calculation of baseline emissions Additional comment: The sensor tolerance value per DIN EN 60751 is Class B as could

be seen on the nameplate of the device (1 x Pt100 / B / 2: One Pt100 Sensor, accuracy class B, 2-wire connection method). For a thin film sensor (F), this mean a tolerance of +/- (0.3 + 0.005 |t|). |t| is the value of the temperature in °C without consideration of the sign. For a temperature of 60°C the tolerance is +/-(0.3 + 0.005*60) = +/- 0.6 which is equivalent to 1%. Therefore the measurement is conservative.

Data / Parameter: ID.26 / ECBL,y

Unit: MWh Description: Net amount of electricity generated using LFG Measured/ Calculated / Default:

measured

Source of data: monthly meter reading protocols

8 Reference: http://www.mevzuat.gov.tr/Metin.Aspx?MevzuatKod=7.5.6381&MevzuatIliski=0&sourceXmlSearch= (Article 9.b)

Version 03.1 Page 11 of 28

Page 12: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Value(s) of monitored parameter:

The values of this monitoring period are: 2012: 6,021.42 MWh 2013: 9,092.38 MWh

Monitoring equipment:

The measurements are carried out by electricity meters of the grid company. At the project site a device of the manufacturer Elster, A1500 Serial number 00443932-2011 is used. The accuracy class of the device is 0.5s

Measuring/ Reading/ Recording frequency:

The monitoring system works with continuous measurement devices. It is programmed to automatically save hourly values. The data are stored automatically at the server.

Calculation method (if applicable):

N/A

QA/QC procedures: The grid company is responsible for maintenance and calibration of the device. In accordance with the “Regulation on “Measurement and Measuring Tools”, electricity meters have to be calibrated within a frequency of once per 10 years9. The meter was initially calibrated on 13/04/2011 and is valid for 10 years.

Purpose of data: Calculation of baseline emissions Additional comment:

Data / Parameter: ID.27 / ECPJ,y

Unit: MWh Description: Quantity of electricity consumed by the project activity Measured/ Calculated / Default:

measured

Source of data: monthly meter reading protocols Value(s) of monitored parameter:

The values of this monitoring period are: 2012: 6.36 MWh 2013: 1.42 MWh

Monitoring equipment:

The measurements is carried out by electricity meters of the grid company. At the project site a device of the manufacturer Elster, A1500 Serial number 00443932-2011 is used. The accuracy class of the device is 0.5s

Measuring/ Reading/ Recording frequency:

The monitoring system works with continuous measurement devices. It is programmed to automatically save hourly values. The data are stored automatically at the server.

Calculation method (if applicable):

N/A

9 Reference: http://www.mevzuat.gov.tr/Metin.Aspx?MevzuatKod=7.5.6381&MevzuatIliski=0&sourceXmlSearch= (Article 9.b)

Version 03.1 Page 12 of 28

Page 13: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

QA/QC procedures: The grid company is responsible for maintenance and calibration of the device. In accordance with the “Regulation on “Measurement and Measuring Tools”, electricity meters have to be calibrated within a frequency of once per 10 years10. The meter was initially calibrated on 13/04/2011 and is valid for 10 years.

Purpose of data: Calculation of baseline emissions Additional comment:

Data / Parameter: ID.28 / TDLk,y; TDLj,y

Unit: - Description: Average technical transmission and distribution losses in year y Measured/ Calculated / Default:

default value

Source of data: As no reliable information could be found for this period, a default factor of 20% is used for TDLj,y (used to calculate PEEC) and a default factor of 3% is used for TDLk,y (used to calculate BEEC), which is in line with the “Tool to calculate baseline, project and/or leakage emissions from electricity consumption” Version 01, EB 37 Annex 7.

Value(s) of monitored parameter:

20%; 3%

Monitoring equipment:

N/A

Measuring/ Reading/ Recording frequency:

N/A

Calculation method (if applicable):

N/A

QA/QC procedures: Purpose of data: Calculation of project emissions Additional comment:

Data / Parameter: ID.29 / FVRG,h Unit: m³ / h Description: Volumetric flow of the residual gas (to the flare) in dry basis in the

hour h Measured/ Calculated / Default:

Measured

Source of data: Measured continuously through a mass flow meter

10 Reference: http://www.mevzuat.gov.tr/Metin.Aspx?MevzuatKod=7.5.6381&MevzuatIliski=0&sourceXmlSearch= (Article 9.b)

Version 03.1 Page 13 of 28

Page 14: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Value(s) of monitored parameter:

2012: 116,439 2013: 74,769

Monitoring equipment:

Thermal mass flow measuring system by Endress & Hause, Proline t-mass 65I, Serial number E8044D02000. The accuracies of the measurement are 1.0%.

Measuring/ Reading/ Recording frequency:

The monitoring system works with continuous measurement devices. It is programmed to automatically save hourly values. The data are stored automatically at the server.

Calculation method (if applicable):

N/A

QA/QC procedures: In accordance with the manufacturers specifications a calibration is interval of every 3 years is recommended.. The meter was initially calibrated on 22/08/2011 and is valid for 3 years The meter was initially calibrated on 22/08/2011 and is valid for 3 years.

Purpose of data: Baseline emission calculation Additional comment: As the measuring device convert the flow direct to normal

conditions, no separate measurement of pressure and temperature is required as described in equation (5) and footnote 41 of the PDD.

Data / Parameter: ID.30 / fvCH4,RG,h

Unit: m³ gas CH4/ m³ dry gas Description: Volumetric fraction of CH4 in the residual gas on dry basis Measured/ Calculated / Default:

measured

Source of data: The methane fraction in the LFG is measured continuously by a gas analyser.

Value(s) of monitored parameter:

The weighted averages of this monitoring period are11: 2012: 53,37% 2013: 55,49%

Monitoring equipment:

For the measurement a Siemens Utramat-23, Serial number 7MB2337-2CR10-3DR1 is used. The accuracies of the measurement are 0.2%.

Measuring/ Reading/ Recording frequency:

The monitoring system works with continuous measurement devices. It is programmed to automatically save hourly values. The data are stored automatically at the server.

Calculation method (if applicable):

N/A

QA/QC procedures: The calibration of the monitoring equipment was carried out according to the information provided in the PDD.

Purpose of data: Calculation of baseline emissions

11 The figures represent the result of the readings without taking into account the error margin as described under Additional Comments. However the result baseline emissions are calculated taking into account the error margin.

Version 03.1 Page 14 of 28

Page 15: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Additional comment: The meter is installed as pre-calibrated from the factory. In accordance the manufacturers specifications the calibration frequency has been recommended as 12 month. However the PP is unable to find the document for initial calibration of the meter ID.30. The meter was sent to calibration on 23.07.2013. According to the calibration report, the meter does not show any errors in the measuring equipment. As a conservative approach, the maximum permissible error of 0.2% of the equipment is applied to all the measurement result of this equipment. This approach is also in line with the CDM validation and verification standard v.04.0 paragraph 238.This parameter is identical to ID.24

Data / Parameter: ID.31 / Tflare

Unit: °C Description: Temperature in the exhaust gas of the enclosed flare Measured/ Calculated / Default:

measured

Source of data: Temperature meter Value(s) of monitored parameter:

About 1,000°C when flare is operational.

Monitoring equipment:

For the measurement a Krom Schroder, VAS120R/NW, serial number 88000004 is used.

Measuring/ Reading/ Recording frequency:

The monitoring system works with continuous measurement devices. It is programmed to automatically save hourly values. The data are stored automatically at the server.

Calculation method (if applicable):

N/A

QA/QC procedures: The meter was not calibrated since no emission reductions were claimed.

Purpose of data: Calculation of baseline emissions Additional comment: Due to the fact that there are only hourly measurements of the

flare temperature, it is assumed for conservative reason that the flare efficiency is always = 0%. Therefore the measurement of the flare temperature is not taking into account. No emission reduction for flaring are claimed.

Data / Parameter: Other flare operational parameters

Unit: - Description: Data and parameters that are required to monitor whether the

flare operates within the range of operating conditions according to manufacturer’s specifications

Measured/ Calculated / Default:

measured

Version 03.1 Page 15 of 28

Page 16: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Source of data: - Value(s) of monitored parameter:

-

Monitoring equipment:

No further equipment required

Measuring/ Reading/ Recording frequency:

Continuously

Calculation method (if applicable):

N/A

QA/QC procedures: - Purpose of data: Calculation of baseline emissions Additional comment: Due to the fact that there are only hourly measurements of the

flare temperature, it is assumed for conservative reason that the flare efficiency is always = 0%. No emission reduction for flaring are claimed.

Data / Parameter: Gold Standard Toolkit Annex C / Methane Utilization Ratio Unit: Ratio Description: In accordance with Annex C of the GS Toolkit v2.1, the methane

utilization ratio will be monitored over the monitoring period. The utilization ratio will be calculated as LFG utilized by the engines over the total amount of LFG extracted (LFG utilized + LFG flared). This ratio will at least correspond to 65%.

Measured/ Calculated / Default:

Calculated

Source of data: Flow meters (ID.23 & ID.29) Value(s) of monitored parameter:

2012: 96.55% 2013: 98.51%

Monitoring equipment:

N/A

Measuring/ Reading/ Recording frequency:

Calculation method (if applicable):

QA/QC procedures: Purpose of data: Additional comment:

D.3. Implementation of sampling plan

There are no data or parameter determined by a sampling approach.

Version 03.1 Page 16 of 28

Page 17: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

SECTION E. Calculation of emission reductions or GHG removals by sinks

E.1. Calculation of baseline emissions or baseline net GHG removals by sinks

The emission reductions resulting from the proposed project are calculated according to ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0.

According to the referred methodology the emission reductions are calculated with the following equation:

Yyy PEBEER −= (1)12

Where:

ERy Emission reductions in year y (tCO2e/year)

BEy Baseline emissions in year y (tCO2e/year)

PEy Project emissions in year y (tCO2e/year)

Baseline emissions

In accordance with ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0, baseline emissions are calculated as follows:

yECyCHy BEBEBE ,,4+=

(2)13

Where:

BEy Baseline emissions in year y (tCO2e/yr)

BECH4,y Baseline emissions of methane from SWDS in year y (tCO2e/yr)

BEEC,y Baseline emissions associated with electricity generation in year y (tCO2eq/yr)

Step (A): Baseline emissions of methane from the SWDS (BECH4,y)

Baseline emissions of methane from the SWDS are determined as follows, based on the amount of methane that is captured under the project activity and the amount that would be captured and destroyed in the baseline. In addition, the effect of methane oxidation that is present in the baseline and absent in the project is taken into account.

4444*)(*)1( ,,,,, CHyBLCHyPJCHlayertopyCH GWPFFOXBE −−= − (3)14

Where:

BECH4,y Baseline emissions of LFG from SWDS in year y (tCO2e/yr)

OXtop-layer Fraction of methane in the LFG that would be oxidized in the top layer of the SWDS in the baseline (dimensionless)

FCH4,PJ,y Amount of methane in the LFG that which is flared and/or used in the project activity in year y (tCH4/yr)

FCH4,BL,y Amount of methane in the LFG that would be flared in the baseline in year y (tCH4/yr)

Step A.1: Ex-post determination of FCH4,PJ,y

During the crediting period FCH4,PJ,y is determined as the sum of quantities of methane flared and used in

12 This equation is referred as (#22) under ACM0001 13 This equation is referred as (#1) under ACM0001 14 This equation is referred as (#2) under ACM0001

Version 03.1 Page 17 of 28

Page 18: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

power plant(s) as follows:

yELCHyflaredCHyPJCH FFF ,,,,, 444+=

(4)15

Where:

FCH4,PJ,y Amount of methane in the LFG that which is flared and/or used in the project activity in year y (tCH4/yr)

FCH4,flared,y Amount of methane in the LFG which is destroyed by flaring in year y (tCH4/yr)

FCH4,EL,y Amount of methane in the LFG which is used for electricity generation in year y (tCH4/yr)

The amount of methane destroyed by electricity generation (FCH4,EL,y)

FCH4,PJ,y is determined using the “Tool to determine the mass flow of a greenhouse gas in a gaseous stream” version 02.0.0.

The tool provides procedures to determine the following parameter: Parameter SI Unit Description Fi,t

16 kg/h Mass flow of greenhouse gas i (CO2, CH4, N2O, SF6 or a PFC) in the gaseous stream in time interval t.

The mass flow of CH4 in LFG is determined through measurement of the flow and volumetric fraction of the gaseous stream (LFG). The “Tool to determine the mass flow of a greenhouse gas in a gaseous stream” version 02.0.0 provides 6 different ways to make these measurements and the corresponding calculation option for Fi,t.

Table 2 Measurement options for Fi,t Option Flow of Gaseus Stream Volumetric Fraction A Volume flow-dry basis Dry or wet basis B Volume flow-wet basis Dry basis C Volume flow-wet basis Wet basis D Mass flow-dry basis Dry or wet basis E Mass flow-wet basis Dry basis F Mass flow-wet basis Wet basis

Option A is applied in the proposed project activity.

Option A:

According to the “Tool to determine the mass flow of a greenhouse gas in a gaseous stream” version 02.0.0, flow measurement on a dry measurement is not doable for a wet gaseous stream. Therefore it will be demonstrated that the temperature of the gaseous stream (Tt) is less than 600C (333.15 K) at the flow measurement point.

The mass flow of CH4 (FCH4,t)17 is determined as follows:

tCHdbtCHdbttCH vVF ,,,,, 444** ρ=

(5) 18

Where: FCH4,t Mass flow of CH4 in the gaseous stream in time interval t (kg gas/h) Vt,db Volumetric flow of the gaseous stream in time interval t on a dry basis (m3 dry gas/h) vCH4,t,db Volumetric fraction of CH4 in the gaseous stream in a time interval t on a dry basis (m3

gas CH4/m3 dry gas) pCH4,t Density of CH4 in the gaseous stream. Since all the parameters are converted to

normal conditions during the monitoring process, pCH4,n which is equal to 0.716 kg/m3 (kg gas CH4/ m3 gas CH4) will be used for equation (5) for ex-post-calculation as

15 This equation is referred as (#3) under ACM0001 16 The parameter (Fi,t) under the “Tool to determine the mass flow of a greenhouse gas in gaseous stream” corresponds

to the parameter (FCH4,EL,y) under ACM0001. 17 FCH4,t described under the “Tool to determine the mass flow of a greenhouse gas in a gaseous stream” corresponds to

FCH4,EL,y described under ACM0001 “Flaring or use of a landfill gas”. 18 This equation is referred as (#5) under the “Tool to determine the mass flow of a greenhouse gas in a gaseous stream”

Version 03.1 Page 18 of 28

Page 19: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

described in the registered PDD, equation (5) and footnote 41.

The amount of methane destroyed by flaring (FCH4,flared,y)

According to ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0, FCH4,flared,y is determined as the difference between the amount of methane emissions from flare(s), as follows:

4

44

,,_,,,

CH

yflareyflaresentCHyflaredCH GWP

PEFF −=

(7) 19

Where: FCH4,flared,y Amount of methane in the LFG which is destroyed by flaring in year y (tCH4/yr) FCH4,sent flare,y Amount of methane in the LFG which is sent to the flare in year y (tCH4/yr) PEflare,y Project emissions from flaring of the residual gas stream in year y (tCO2e/yr) GWPCH4 Global Worming potential of CH4 (tCO2e/tCH4)

In line with the requirements of ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0, FCH4,sent flare,y is determined directly using the “Tool to determine the mass flow of a greenhouse gas in a gaseous stream” using option A as described under the relevant tool20.

In accordance with the requirements of ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0, PEflare,y will be determined using the “Tool to determine project emissions from flaring gases containing methane”. If the LFG is flared through more than one flare, then PEflare,y is the sum of the emissions for each flare determined separately.

In line with the requirements of the “Tool to determine project emissions from flaring gases containing methane”, PEflare,y will be calculated as follows:

)1000/(*)1(*4,

8760

1,, CHhflare

hhRGyflare GWPTMPE η−= ∑

= (8) 21

Where: PEflare,y Project emissions from flaring of the residual gas stream in year y (tCO2e) TMRG,y Mass flow rate of methane in the residual gas in hour h (kg/h) nflare,h Flare efficiency in hour h. In line with the “Tool to determine project emissions from

flaring gases containing methane” v 01, a default value of 90% will be used for the flare efficiency22.

GWPCH4 Global Warming Potential of methane valid for commitment period

TMRG,h will be calculated as follows:

nCHhRGCHhRGhRG fvFVTM ,,,,, 44** ρ= (9) 23

Where: TMRG,y Mass flow rate of methane in the residual gas in hour h (kg/h) FVRG,h Volumetric flow rate of the residual gas in dry basis at normal conditions in hour h

(m3/h). fvCH4,RG,h Volumetric fraction of methane in the residual gas on dry basis in hour h (fraction) pCH4,n Density of methane at normal conditions (0.716 kg/m3)

Step A.2: Determination of FCH4,BL,y

The situation at the start of the project activity falls under case 1 since there are no legal requirements in

19 This equation is referred as (#4) under the ACM0001 20 Since the method and equations to determine the amount of methane in the LFG which is sent to flare is the same to

determine the amount of methane in the LFG which is sent to electricity generation, the procedures are not re-explained here however will be applicable. FCCH4,sent flare is calculated in the same manner as parameter FCCH4,

21 This equation is referred as (#15) under the “Tool to determine project emissions from flaring gases containing methane”

22 An enclosed system is used in the Project Activity. 23 This equation is referred as (#13) under the “Tool to determine project emissions from flaring gases containing

methane”

Version 03.1 Page 19 of 28

Page 20: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Turkey to destroy methane and the LFG was not captured prior to the proposed project activity.

Therefore:

FCH4,BL,y=0

Step B: Baseline emissions associated with electricity generation (BEEC,y)

The baseline emissions associated with electricity generation in year y (BEEC,y) is calculated in accordance with the “Tool to calculate baseline, project and leakage emissions from electricity consumption” version 1. The electricity source k in the tool corresponds to the sources of electricity generated by the grid, which is identified as the most plausible baseline scenario. ECBL,k,y in the tool is equivalent to the net amount of electricity generated using LFG in year y.

Generic approach

In the generic approach, baseline emissions from consumption of electricity are calculated based on the quantity of electricity consumed, an emission factor for electricity generation and a factor to account for transmission losses, as follows:

∑ +=k

ykykELykBLyEC TDLEFECBE )1(** ,,,,,, (12) 24

Where: BEEC,y Baseline emissions from electricity consumption in year y (tCO2e/yr) ECBL,k,y Net amount of electricity generated using LFG in year y (MWh/yr) EFEL,k,y Emission factor for electricity generation source k in year y ((tCO2e/MWh) TDLk,y Average technical and transmission and distribution losses for providing electricity to

source k in year y k the sources of electricity generated by the grid

Determination of the emission factor for electricity generation (EFEL,k,y)

The emission for electricity generation is calculated ex-post as 0.542 tCO2eq/MWh and has been fixed through the first crediting period.

Table 3. Baseline Emissions Month/Year ACM001 Electricity

FCH4,EL FCH4,Flared FCH4,PJ BECH4 ECBL,y BEEC Total BE

tCH4 tCH4 tCH4 tCO2eq MWh tCO2eq tCO2eq

March 2012 101.43 0 101.23 1,913.17 545.21 304.37 2,217.54

April 2012 87.38 0 87.21 1,648.20 439.61 245.42 1,893.62

May 2012 98.31 0 98.11 1,854.35 491.45 274.36 2,128.71

June 2012 107.80 0 107.59 2,033.37 534.66 298.48 2,331.85

July 2012 107.94 0 107.72 2,035.93 515.94 288.03 2,323.96

August 2012 95.73 0 95.54 1,805.72 446.60 249.32 2,055.04

September 2012 84.82 0 84.65 1,599.83 396.11 221.13 1,820.96

October 2012 77.19 0 77.03 1,455.90 355.12 198.25 1,654.15

November 2012 150.12 0 149.82 2,831.58 725.31 404.91 3,236.49

December 2012 323.95 0 323.30 6,110.42 1,571.41 877.26 6,987.68

January 2013 323.19 0 322.54 7,257.14 1,568.31 875.52 8,132.67

24 This equation is referred as (#2) under the “Tool to calculate baseline, project and leakage emissions from electricity consumption”

Version 03.1 Page 20 of 28

Page 21: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

February 2013 302.43 0 301.82 6,791.02 1,440.52 804.18 7,595.20

March 2013 345.13 0 344.44 7,750.00 1,583.88 884.22 8,634.22

April 2013 325.16 0 324.51 7,301.56 1,529.00 853.58 8,155.14

May 2013 312.50 0 311.87 7,017.10 1,517.68 847.26 7,864.36

June 2013 283.75 0 283.18 6,371.55 1,452.99 811.15 7,182.70

Total 2012 (01/03/2012-31/12/2012)

1,234.66 0 1,232.19 23,288.48 6,021.42 3,361.52 26,650.00

Total 2013 (01/01/2013-30/06/2013)

1,892.16 0 1,888.37 442,488.38 9,092.38 5,075.91 47,564.29

Total Monitoring Period

(01/03/2012-30/06/2013)

3,126.82 0 3,120.57 65,776.86 15,113.80 8,437.43 74,214.29

E.2. Calculation of project emissions or actual net GHG removals by sinks

In accordance with ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0, the project emissions are calculated as follows:

yECy PEPE ,= (17) 25

Where: PEEC,y Emission from consumption of electricity due to the project activity in year y (tCO2e/yr).

Since there are no consumption of fossil fuels due to the project activity, for the purpose other than electricity generation, there are no emissions from fossil fuel consumption and therefore PEFC,y is equal to “0” and has not been included in equation (17).

The project emissions from consumption of electricity by the project activity PEEC,y shall be calculated using the “Tool to calculate baseline, project and/or leakage emissions from electricity consumption” version 1. When applying the tool, electricity sources j in the tool corresponds to the sources of electricity consumed due to the project activity.

PEEC,y is calculated as follows:

∑ +=j

yjyjELyPJyEC TDLEFECPE )1(** ,,,,,

(18) 26

Where: PEEC,y Project emissions from electricity consumption in year y (tCO2e/year) ECPJ,y Quantity of electricity consumed by the project electricity consumption source j in year

y (MWh/year) EFEL,j,y Emission factor for electricity generation for source j in year y (tCO2e/MWh) TDLj,y Average technical transmission and distribution losses for providing electricity to

source j in year y

Table 4. Project Emissions Month/Year Electricity Total PE

25 This equation is referred as (#21) under ACM0001 26 This equation is referred as (#1) under “Tool to calculate baseline, project and/or leakage emissions from electricity

consumption”

Version 03.1 Page 21 of 28

Page 22: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

ECPJ,y*(1+TDL) PEEC

MWh tCO2eq tCO2eq

March 2012 1.51 0.82 0.82

April 2012 1.01 0.55 0.55

May 2012 0.07 0.04 0.04

June 2012 0.17 0.09 0.09

July 2012 1.32 0.72 0.72

August 2012 1.94 1.05 1.05

September 2012 0.67 0.36 0.36

October 2012 0.67 0.36 0.36

November 2012 0.23 0.12 0.12

December 2012 0.04 0.02 0.02

January 2013 0.17 0.09 0.09

February 2013 0.08 0.05 0.05

March 2013 0.10 0.05 0.05

April 2013 0.26 0.17 0.17

May 2013 0.23 0.15 0.15

June 2013 0.65 0.42 0.42

Total 2012 (01/03/2012-31/12/2012) 7.63 4.14 4,14

Total 2013 (01/01/2013-30/06/2013) 1.71 0.93 0.93

Total Monitoring Period (01/03/2012-30/06/2013) 9.34 5.06 5.06

E.3. Calculation of leakage

In accordance with ACM0001 “Flaring or Use of Landfill Gas” version 12.0.0, no leakage effects are accounted.

E.4. Summary of calculation of emission reductions or net anthropogenic GHG removals by sinks

Item

Baseline emissions or baseline net

GHG removals by sinks (t CO2e)

Project emissions or

actual net GHG removals

by sinks (t CO2e)

Leakage (t CO2e)

Emission reductions or

net anthropogenic GHG removals

by sinks27 (t CO2e)

Total 2012 (01/03/2012-31/12/2012)

26,650.00 4.14 0.00 26,645

27 The total sums are rounded down.

Version 03.1 Page 22 of 28

Page 23: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Total 2013 (01/01/2013-30/06/2013)

47,564.29 0.93 0.00 47,563

Total Monitoring Period (01/03/2012-30/06/2013)

74,214.29 5.06 0.00 74,208

E.5. Comparison of actual emission reductions or net anthropogenic GHG removals by sinks with estimates in registered PDD

Item Values estimated in ex-ante calculation of registered PDD

Actual values achieved during this monitoring period

Emission reductions or GHG removals by sinks (t CO2e)

141,105 74,208

E.6. Remarks on difference from estimated value in registered PDD

Not applicable as there is no increase in the actual GHG emission reduction achieved during this monitoring period comparing to the registered PDD.

E.7. Actual emission reductions or net anthropogenic GHG removals by sinks during the first commitment period and the period from 1 January 2013 onwards

Item Actual values achieved up to 31 December 2012

Actual values achieved from 1 January 2013

onwards Emission reductions or GHG removals by sinks (t CO2e)

26,645 47,563

SECTION F. Gold Standard Sustainable Development Indicators

According to the requirements of Gold Standard, the project activity must be assessed a matrix of sustainable development indicators. The contribution of the proposed project activity to the sustainable of the country is based on indicators of local/global environment sustainability, social sustainability & development and economic & technological development.

With regards to the project activity, 9 indicators were added to the monitoring plan under the registered GS Project Passport. All documents regarding these additional parameters can be presented to the DOE during the verification process.

F.1 Sustainability Monitoring Plan

No SD.1 Indicator: Air Quality Chosen Parameter Levels of sulphide combusted in the landfill gas engines

Version 03.1 Page 23 of 28

Page 24: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Estimation of baseline situation of parameter

No sulphide is combusted in the baseline situation

Way of Monitoring

How In line with the registered GS Project Passport, the amount of sulphide is calculated based on the amount of landfill gas combusted in the engines as followed: V sulphide destroyed=VLFG destroyed * 0.005 Where “V” represents the volume of LFG in m3.

When Annually By who Project Participant

Monitoring Result Vintage Amount of LFG

destroyed28 Amount of H2S destroyed

m3 m3

01/03/2012 – 31/12/2012

3,378,037 16,890

01/01/2013 – 30/06/2013

4,961,997 24,809

TOTAL 8,340,034 41,699 It is calculated that 41,699 cubic meters of H2S has been reduced due to the project activity within this monitoring period.

Additional comment: -

No SD.2 Indicator: Quality of employment Chosen Parameter Provided trainings Estimation of baseline situation of parameter

Trainings will be offered to employees (such as occupational health and safety instructions)

Way of Monitoring

How Attendance to trainings When Annually By who Project Participant

28 The amount of LFG destroyed is the sum of LFG sent to the engines and flare.

Version 03.1 Page 24 of 28

Page 25: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Monitoring Result The following trainings have been provided to the employees:

Training Personnel Date Instructor Fire and Fire Safety

11 personnel from Körfez Enerji San. Ve Tic. A.Ş.

18/03/2013 Environmental Engineer Turan Ümit Kargın

Occupational Health and Safety

7 personnel from Körfez Enerji San. Ve Tic. A.Ş.

15/12/2012 Occupational Health and Safety Expert (C Class) Environmental Engineer Turan Ümit Kargın

Occupational Health and Safety Expert

Environmental Engineer Turan Ümit Kargın

14/11/2012 Ministry of Labor and Social Security, General Directorate of Health and Safety Department

Occupational and Technical Training

Mehmet Hakan Kaya

09/03/2013 Ahmet Elginkan Occupational and Technical Training Centre

Occupational and Technical Training

Turan Ümit Kargın

09/03/2013 Ahmet Elginkan Occupational and Technical Training Centre

Additional comment: -

No SD.3 Indicator: Human and Institutional Capacity Chosen Parameter Improvements to the school library Estimation of baseline situation of parameter

The school library is in bad condition and the locals have requested support for improvement.

Way of Monitoring

How Visual observation and through interview of the village muchtar When Yearly (The frequency of the monitoring is set to “yearly”

to ensure to ensure that the contributions to library, etc. remains positive every year).

By who Project Participant and Village Muchtar

Version 03.1 Page 25 of 28

Page 26: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Monitoring Result During the stakeholders meeting held on 08.07.2011, the locals have requested the project owners help with regards to the primary school library. The primary school holds 168 students, which also includes students from other villages. According to the locals the library is in bad condition and is hardly usable29. Ortadoğu Enerji has agreed to provide any necessary help/support/donation to the village on this issue. In October – November 2011 the renovation work of the Solaklar Primary School has been finalized by the Project Participant.

Additional comment:

No SD.4 Indicator: Quantitative employment and income generation Chosen Parameter Number of contracts Estimation of baseline situation of parameter

The project activity will result in employment opportunities. It is estimated that approximately 8-10 people will be hired for the proposed project activity.

29 Reference: Solaklar Village Muhtar Mr. Burhan Tuğtekin

Version 03.1 Page 26 of 28

Page 27: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

Way of Monitoring

How Through documentation of contracts When Annually By who Project Participant

Monitoring Result More than 12 people have been provided employment under the project activity.

Additional comment:

# Designation Name Surname Position

1 Head Office / Istanbul

MEHMET ATA CEYLAN General Manager

2 Head Office / Istanbul ATIF DÜZGÜN Logistics

3 Head Office / Istanbul DURSUN ALİ TÜYLÜ Account

4 Solaklar SERDAR ERUYSAL Plant Manager 5 Solaklar TURAN ÜMİT KARGIN Environmental Engineer

6 Solaklar RIDVAN ALTIOK Heavy Duty Vehicle Operator

7 Solaklar GÖKHAN BAYRAMOĞLU Heavy Duty Vehicle Operator

8 Solaklar SİNAN ERYILMAZ Plant Technician 9 Solaklar ENGİN ATEŞ Plant Technician

10 Solaklar SERVET BAYRAK Plant Technician 11 Solaklar CİHAN ARABACI Plant Technician 12 Solaklar ERAY ALTUNTAŞ Plant Technician 13 Solaklar MURAT BAŞER Plant Technician 14 Solaklar FURKAN DURMUŞ Plant Technician 15 Solaklar ÖZKAN GİRGİN Plant Technician 16 Solaklar MURAT BULUT Plant Technician 17 Solaklar CEMALETTİN KESKİN Electricity Generation /

Technician

18 Solaklar FARUK ÖZGÜR Electricity Generation / Technician

19 Solaklar GÜRKAN SUAN Electricity Generation / Technician

20 Solaklar MURAT KOÇAR Electricity Generation / Technician

No SD.5 Indicator: Management of leachate Chosen Parameter Management of leachate Estimation of baseline situation of parameter

The leachate is collected and sent to treatment by IZAYDAS.

Way of Monitoring

How Evidences that the leachate is collected and is being treated by IZAYDAS (such as documentation or interviews with İZAYDAŞ)

When Annually By who Project Participant

Monitoring Result The leachate is collected and sent to treatment by IZAYDAS. Additional comment:

SECTION G. Forward Action Requests

Version 03.1 Page 27 of 28

Page 28: F-CDM-MR Monitoring report form (Version 0 3.1) - SustainCERT

F-CDM-MR

G.1 Forward Action Requests from DOE

No Forward Action Requests have been formulized by the DOE for this monitoring period.

G.1 Forward Action Requests from GS

No Forward Action Requests have been formulized by the GS for this monitoring period.

- - - - -

Document information

Version Date Description

03.1 2 January 2013 Editorial revision to correct table in section E.5.

03.0 3 December 2012 Revision required to introduce a provision on reporting actual emission reductions or net anthropogenic GHG removals by sinks for the period up to 31 December 2012 and the period from 1 January 2013 onwards (EB70, Annex 11).

02.0 13 March 2012 Revision required to ensure consistency with the "Guidelines for completing the monitoring report form" (EB 66, Annex 20).

01 28 May 2010 EB 54, Annex 34. Initial adoption.

Decision Class: Regulatory Document Type: Form Business Function: issuance Keywords: monitoring report, performance monitoring

Version 03.1 Page 28 of 28