1
Objectives GBRS Algeria experienced, through their incumbent slickline services company, a number of miss-run plugs and incorrectly set gas lift valves 33 runs had been undertaken by the incumbent to plug the well and change out various dummy injection valves from the side pocket mandrels After many failures, Expro were called for advice and to find a solution for the challenge Expro Excellence Expro undertook an audit, reviewed previous slickline reports, and quickly established: Incorrect tools had been previously run in the well A dummy valve had been damaged in one of the gas lift pockets - previous operations had been to trying pass by this to gain access to the plug below Pressure was rising in the tubing and the annulus Despite the challenges associated with the well, Expro proposed and undertook to deliver a solution Expro personnel prepared one of the client’s gas lift mandrels in the Expro workshop to show a setting and retrieval of the dummy valve with the correct tools Innovative approach: various Expro slickline tools were modified to aid the retrieval Full step-by-step support was given to the client as well as supporting them by explaining the correct running and pulling procedures which should be used Value to client Expro provided a solution that the incumbent service provider could not The well was successfully returned to a usable condition after retrieval of the deformed dummy valve Without Expro’s expertise, the well would have been shut in and a costly work-over performed Contact For further information, please contact: Hatem Sbeta Product Line Manager, MENA Well Intervention hate[email protected] www.exprogroup.com/wellintervention Well Intervention / Expro Excellence Expro’s Well Intervention team provides solution to a new client, saving rig time and a costly work-over Well Intervention Expro is proud of the strong reputation that we have built in Hassi Messaoud as a leading well intervention services provider. We have a proven track record and the team is renowned as a first-choice solutions provider when our clients have challenging situations. Dave Bowman Vice President, Well Intervention, Expro ’’ Expro Excellence exprogroup.com Deformed dummy valve which Expro recovered

Expro Excellence Well Intervention… · Hassi Messaoud as a leading well intervention services provider. We have a proven track record and the team is renowned as a first-choice

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Expro Excellence Well Intervention… · Hassi Messaoud as a leading well intervention services provider. We have a proven track record and the team is renowned as a first-choice

Objectives

• GBRS Algeria experienced, through theirincumbent slickline services company, anumber of miss-run plugs and incorrectlyset gas lift valves

• 33 runs had been undertaken by theincumbent to plug the well and changeout various dummy injection valves fromthe side pocket mandrels

• After many failures, Expro were called foradvice and to find a solution for thechallenge

Expro Excellence

• Expro undertook an audit, reviewedprevious slickline reports, and quicklyestablished:

– Incorrect tools had been previouslyrun in the well

– A dummy valve had beendamaged in one of the gas liftpockets - previous operations hadbeen to trying pass by this to gainaccess to the plug below

– Pressure was rising in the tubingand the annulus

• Despite the challenges associated withthe well, Expro proposed and undertookto deliver a solution

• Expro personnel prepared one of theclient’s gas lift mandrels in the Exproworkshop to show a setting and retrievalof the dummy valve with the correct tools

• Innovative approach: various Exproslickline tools were modified to aid theretrieval

• Full step-by-step support was given tothe client as well as supporting them byexplaining the correct running and pullingprocedures which should be used

Value to client• Expro provided a solution that the

incumbent service provider could not

• The well was successfully returned to ausable condition after retrieval of thedeformed dummy valve

• Without Expro’s expertise, the well wouldhave been shut in and a costly work-overperformed

ContactFor further information, pleasecontact:

Hatem SbetaProduct Line Manager, MENA Well Intervention

[email protected]

www.exprogroup.com/wellintervention

Well Intervention

/ Expro Excellence

Expro’s Well Intervention team providessolution to a new client, saving rig timeand a costly work-over

Well Intervention

Expro is proud of thestrong reputationthat we have built inHassi Messaoud asa leading wellintervention servicesprovider. We have aproven track recordand the team isrenowned as afirst-choice solutionsprovider when ourclients havechallengingsituations.Dave BowmanVice President, Well Intervention, Expro ’’

Expro E x c e l l e n c e exprogroup.com

Deformed dummy valve which Exprorecovered