1/15/2018 Page 1 MTR Corporation Presented by YS Ho Senior Construction Engineer Express Rail Link (XRL) Overhead Line System – A Step Forward

Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 1MTR Corporation

Presented byYS HoSenior Construction Engineer

Express Rail Link (XRL)

Overhead Line System – A Step Forward

Page 2: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

Slide 2

XRL Alignment

Route length ≈ 26km, both tracks along mainline tunnels & stationOpen area at Emergency Rescue Siding (ERS) and Shek Kong Stabling Sidings (SSS)Maximum operating speed = 200kph

West Kowloon Station

Futian Station

Shek Kong Stabling Sidings

Emergency Recuse Sidings

Page 3: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

Slide 3

Generation from Local Power Company

HV Transmission System -

through OHL/Cables

District Primary/Zone Stations -

Step down to 1-Ph 25kV Supply

Traction Power System-

Via cables/OHL to XRL Trains

Power Supply Feeding Arrangement

Page 4: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 4MTR Corporation

General 25kV Traction Power and Earth Systems

Page 5: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

XRL OHL and Traction Power Configuration

好港牽引變電所

Haogang Feeder Station

米埔通風樓MPV TSC

石崗牽引變電所

SHK Feeder Station

城門通風樓MPV TSC

旺角西牽引變電所MKW Feeder Station

深港分界

Hong Kong /

Shenzhen

Boundary

西九龍West Kowloon

Station

Page 5MTR Corporation

廣深港內地段Mainland Section

160m

Neutral section

8 km9.6km16.52km 6.6km

SSS Feeders

~1.4 km

Neutral Section

Page 6: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 6MTR Corporation Slide 6

Typical Earthing and Bonding System

Page 7: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

Slide 7

Basic OHL Equipment

Contact Wire (150mm2, AgCu , grooved) Cantilever (complete with aluminum

tubes and porcelain insulators)

Section insulator (electrical sectionization)

Balance Weight Anchor (Auto-tension)

Page 8: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 8MTR Corporation

Special Design Features

25kV Simple Catenary System

• CW - 150 mm2, AgCu• MeW – 120 mm2, BZII• AEW – 185 mm2, AL• 20kN tension for Mainline• 15kN tension for trolley wire system in SSS• Sectionization by isolators and section insulators• Neutral Section with 6 span 2 overlap arrangement

Page 9: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 9MTR Corporation Slide 9

Neutral Section to isolate two different sources

6-Span 2-Overlap Arrangement

Conventional

Phase Break Assembly

S1 S3 S4

Overlap 2

S5 S6S2

Overlap 1

Page 10: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 10MTR Corporation

OHL Construction Highlights

• 1st Fix Installationsurvey, anchor installation, pull-out tests, installation and cantilever installation

• 2nd Fix Installation wire stringing, isolator installation, cut-in BWA and insulators, registration

• T&C Workstagger and height, functional tests, cold running test and insulation test

• Commissioning Tests sectioning Proving tests and short circuit tests

• Dynamic T&C work – hot running tests upto 140 kph

• Integrated T&C work – dynamic tests upto 200kph

Page 11: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

Slide 11

Special OHL Work train Constant Tension Drum Carrier

wire drum and rack

Tension unit High level platform

Control Cab

3-D moving arm

Page 12: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

Slide 12

Special OHL Work train

1. Pre-set tension (6kN~30kN)

2. Computerized control for stringing speed

and tension

3. 3-Dimensional controllable direction

4. Automatic alarm systems

Breakthrough Features

Page 13: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 13MTR Corporation Slide 13

OHL Speed Verification Test

1st stage upto 140kph (DF11) 2nd stage upto 217kph (CIT)

Page 14: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 14MTR Corporation Slide 14

OHL Speed Verification Test1st stage upto 140kph (DF11) 2nd stage upto 217kph (CIT)

Page 15: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 15MTR Corporation Slide 15

OHL Speed Verification Test

Train Roof-top measuring equipment

Page 16: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 16MTR Corporation Slide 16

OHL Speed Verification Test

Data transfer schematic

Page 17: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 17MTR Corporation Slide 17

OHL Speed Verification Test

Page 18: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 18MTR Corporation

Typical graphical display output

Page 19: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 19MTR Corporation Slide 19

Key success for future High Speed Railways

Collaboration/

Sharing

IDEA

Knowledge

SKILL

Technology

Page 20: Express Rail Link (XRL) · Overhead Line System –A Step Forward. Slide 2 ... Section insulator (electrical sectionization) Balance Weight Anchor (Auto-tension) MTR Corporation 1/15/2018

1/15/2018 Page 20MTR Corporation

Q & A