Upload
hongyuan
View
216
Download
3
Embed Size (px)
Citation preview
ORIGINAL PAPER
Experimental Study on Cracking, Reinforcement, and OverallStability of the Xiaowan Super-High Arch Dam
Peng Lin • Weiyuan Zhou • Hongyuan Liu
Received: 17 November 2013 / Accepted: 11 April 2014
� Springer-Verlag Wien 2014
Abstract The Xiaowan super-high arch dam has faced
challenging construction problems. Here, we provide a
scientifically-based reference for applying geomechanical
model testing to support the nonlinear design of super-high
arch dams. We applied experimental similarity theory and
techniques. Based on four 3D geomechanical model tests,
the dam stress characteristics, deformation distribution, and
the safety factors of the dam foundation were identified and
compared. We also analyzed cracking characteristics of the
up- and downstream dam surfaces and induced joints in the
dam heel, the rock mass failure process of the dam-foun-
dation interface, and the abutments. We propose founda-
tion reinforcement measures for weak rock masses,
alteration zones, and other faults in the abutments based on
the 3D and plane tests each at a different elevation. The
results show that all dam deformations remained normal
with no yielding or tensile cracking under a normal water
load. The reinforced rock mass increased the crack initial
safety in the dam heel and toe by *20 %. The minimum
crack initial safety factor (K1) of the dam heel was 1.4. The
induced joint in the dam heel contributed to a reduction in
tensile stress at the upstream dam heel, improving K1.
Compared with similar projects following reinforcement
measures, the abutment stiffness and overall stability of the
Xiaowan arch dam satisfy operational requirements. Four
years of monitoring operations show that key areas near the
dam remained normal and the dam foundation is func-
tioning well. Our results may also be applicable to the
design and construction of similar projects worldwide.
Keywords Xiaowan super-high arch dam �Geomechanical model � Overall safety factor �Cracking � Reinforcement
1 Introduction
Geomechanical model tests can be used to simulate both
the engineering structural features and the influence of
geological defects, such as weathered rock, bedding joints,
and faults, on overall engineering stability. They are also
an important way of evaluating dam foundation stability in
hydraulic engineering (Fumagalli 1979; Zhou et al. 2008a)
and excavations, slope stability (Zhou et al. 2008c; Zhu
et al. 2011), and mining engineering (Heuer and Hendron,
1971; Li et al. 2005, 2011; Wong et al. 2006; Li and Liu
2013). With the development of high-performance com-
puters, three-dimensional (3D) numerical simulations are
now applied widely to analyze the integrity and stability of
high arch dams (Pan 2004; Lin et al. 2004, 2011) and
underground tunnels (Liu et al. 2009; Barla et al. 2012; Lin
et al. 2013b). Dams, however, are always associated with
complex foundations involving steep slopes, weathered
rock masses, and intersecting joints and faults. Geome-
chanical model experiments are still necessary to analyze
the overall stability and reinforcement measures for super-
high arch dams (Zhou et al. 2008a, b; Lin et al. 2011).
P. Lin (&)
State Key Laboratory of Hydroscience and Engineering,
Tsinghua University, Beijing 100084, China
e-mail: [email protected]
W. Zhou
Department of Hydraulic Engineering, Tsinghua University,
Beijing 100084, China
e-mail: [email protected]
H. Liu
School of Engineering and ICT, The University of Tasmania,
Hobart, Australia
e-mail: [email protected]
123
Rock Mech Rock Eng
DOI 10.1007/s00603-014-0593-x
Based on similarity theory, geomechanical model tests can
accurately represent the spatial relationships of geological
structures at dam abutments and engineering structures
when simulating the influence of construction procedures,
and can reveal failure scenarios more directly. It is easier
for engineers to understand the stress characteristics,
deformation trends, and overall stability of the dam foun-
dation. Such physical model simulations, in conjunction
with or complementing numerical models, are effective in
optimizing the design of dams, subsidiary structures and
foundation reinforcement.
Early geomechanical model tests designed to analyze
the failure of arch dams were performed in the 1950s (Li
1958; Jerome 1960). In the 1970s and 1980s, dam model
tests were widely conducted in, for example, the United
States, Germany, Yugoslavia, Sweden, Switzerland, Rus-
sia, Japan, and Italy (Fumagalli 1979; Chow and Yang
1984; Chen et al. 1984). These countries have now passed
their peak period of dam construction and, with the
development of numerical simulations, few geomechanical
tests have been conducted in the past 30 years. In the late
1950s, some R&D institutions in China began research into
geomechanical model testing (Li 1958, 2004; Zhou et al.
2008a). Starting in 1956, the Tsinghua University of Bei-
jing has performed model tests on dam foundations and on
the abutment stability of most of the high dams in China.
The overall stability results and safety coefficients were
compiled into the official design criteria for concrete arch
dams in China (the PSCG of PRC 2007). A series of high
arch dam 3D model tests have also been carried out by a
research group led by Prof. Zhou (Zhou et al. 2008a).
In recent years, a series of super-high arch dams, such as
the Xiaowan (height 294.5 m), Xiluodu (height 285.5 m),
Jinping I (height 305 m), and Laxiwa (height 251 m) dams,
have been constructed in China. Along with an increase in
the height and complexity of arch dams, the geological
foundation at the dam sites has also proved more complex.
Some of these issues (Lin et al. 2011, 2013a) include the
mechanical parameters themselves and the strength models
required to deal with problems of jointed rocks cracking in
the dam heel and toe, reinforcement measures for atypical
faults, weak rock masses and alteration zones, grouting for
the dam-foundation interface, and anchorage force damage
and nonlinear evaluation of the overall stability. To solve
these key problems, advanced testing methods and tech-
niques of scale model experiments have achieved impor-
tant results through 3D experimental tracking studies
(Zhou et al. 2008a, c). For example, Jiang et al. (2002)
carried out overloading tests on the overall stability of the
Goupitan high arch dam (height 232 m) using a 3D geo-
mechanical model. A deep sliding stability assessment of
the monolith of the Three Gorges Dam foundation was
made in 2003 (Liu et al. 2003) using physical model tests.
The stability of the slopes (Zhang et al. 1994) and of the
Xiaowan dam was analyzed using strength reduction based
on rupture model tests (Fei et al. 2010).
The Xiaowan high dam (Fig. 1) is an arch dam on the
Meigong River in Nanjian County, Yunnan Province,
southwest China. The dam is a concrete double curvature
arch with a maximum height of 294.5 m, and a dam crest
length of 905 m. It is the highest arch dam in operation in
the world and the related hydroelectric power station is the
third largest one in China, after the Three Gorges and the
Xiluodu dam projects (Wang et al. 2007; Lin et al. 2012).
The primary purpose of the Xiaowan hydroelectric power
station is to generate 4,200 MW of hydroelectric power.
The complex geo-conditions of the Xiaowan arch dam led
to dam rock mass relaxation and destressing as excavation
unloaded the pre-existing high-ground stresses (Wu et al.
2009; Fei et al. 2010). It is therefore important to study the
reinforcement solutions, stability, and safety of the dam
with the aid of geomechanical model tests. Dam abutment
reinforcement was tested in a systematic fashion in the pre-
feasibility and feasibility studies and during the project
tendering and construction processes.
In this paper, we first explain the basic theory and the
geomechanical model testing simulations, and describe the
preparation of the modeling materials, the model scale, and
the geo-condition abutments, as well as the bed foundation
modeling of five different 3D and plane tests of the
Xiaowan arch dam. Based on the experimental results, we
identify and compare the dam stress characteristics,
deformation distribution, and the overall safety factors of
the dam foundation. The dam cracking, abutment failure
process, reinforcement schedule, and the dam overall sta-
bility are analyzed and studied. It should be noted that the
Xiaowan arch dam has encountered basic problems never
before seen in dam construction processes. The test results
provide a scientific basis for optimizing the design and can
also be used globally as an important reference for the safe
design of dams in general.
2 Test Design of the Xiaowan Arch Dam
2.1 Basic Similarity Theory and Simulation
Technology
2.1.1 Similarity Principles
Geomechanical model testing of high arch dams involves
taking into account some basic theories and methods,
including similarity principles, dimensional measurements
and loadings, and measuring and loading principles. The
principle of similarity in model tests means that the phys-
ical features of the model should be similar to the prototype
P. Lin et al.
123
in that the model material, shape and loadings must follow
certain rules.
For a linear elastic model, similarity is obtained from the
theory of elasticity. Each point inside the model must
follow the equilibrium, compatibility, and geometrical
equations. The points on the model surface should satisfy
the boundary conditions. The physical entities ratio of
prototype (p) to model (m) is called the similarity constant
(C). For a model subjected to damaging forces, the stress
and strain should be the same as in the prototype in the
elastic range and beyond it until the point of failure. In the
post-elastic phase, the residual strains should be the same
as e0p ¼ e0
m, where e0 is the residual strain. In some situa-
tions, the effect of time should also be considered. The
similarity criteria for a linear elastic model and a damage
test model are shown in Table 1.
2.1.2 Dam Safety Factors
The safety evaluation methods for high arch dams consist
mainly of (1) overloading, (2) strength reduction, and (3)
comprehensive tests.
Overloading tests assume that the mechanical founda-
tion rock mass parameters remain constant while the water
pressure is increased until the dam and the foundation fail.
The ratio of failure load to the normal load is called the
overloading safety factor. Overloading tests include the
excess normal water level (rectangular load) and the excess
volume-weight of normal water (triangular load), as illus-
trated in Fig. 2. Kc, the coefficient of excess water density,
is defined as:
Kc ¼DPc þ P0
P0
¼ Dcþ c0
c0
¼ cc0
; ð1Þ
where DPc is the triangular load, p0 is the normal water
load, c is the excess water density, c0 is the original water
density, and Dc is the difference between c and c0.
Fig. 1 Xiaowan arch dam in
operation
Table 1 Model test linear elastic and damage similarity criteria
Test type Similarity
criteria
Similarity criteria of concrete
dam under self-weight
and water pressure
Linear elastic
model
(1) Cr=CXCL ¼ 1 (1) Cc ¼ Cp
(2) Cl ¼ 1 (2) Cr ¼ CcCL
(3) CeCE=Cd ¼ 1 (3) Ce ¼ CcCL=CE
(4) CeCL=Cd ¼ 1 (4) Cd ¼ CcC2L=CE
(5) C �r=Cr ¼ 1
Damage model (1) Cr=CXCL ¼ 1
(2) Cu ¼ 1
(3) Ce ¼ 1
(4) CE=Cr ¼ 1
(5) Cd=CL ¼ 1
(6) Cd =Cr ¼ 1
(7) Cs=CtR ¼ 1
(8) CcR=Ct
R ¼ 1
(9) Cr=CtR ¼ 1
(10) Cf ¼ 1
(11) C0e ¼ 1
(12) Cce ¼ 1
(13) Cte ¼ 1
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
In this study, the volume-weight of normal water
method is employed to analyze the dam cracking and
failure process. Three safety factors are defined to evaluate
the overall stability of the dam and the foundation as
follows:
1. Kc ¼ K1 represents the dam onset of cracking safety
factor; a crack is initiated at K1 p0, generally at the dam
heel.
2. Kc ¼ K2 represents the onset of structural nonlinear
behavior safety factor. At the nonlinear phase, the dam
displacement shows large deformations and nonlinear
behavior. The cracks in the dam propagate quickly and
multiple cracks coalesce.
3. Kc ¼ K3 represents the maximum loading safety factor
of the dam-foundation system. At K3 p0, the dam
foundation fails and the undertaking capacity is lost.
Strength reduction tests involve varying the coefficient
of friction f and the cohesion c of the jointed abutment rock
mass or rock structural plane during testing. Kt is the shear
strength varying coefficient. The dam model fails when the
shear strength is lower than the shear strength coefficient of
the rock mass (Zhou et al. 2008a; Zhang et al. 1994). If
affected by underground water owing to flooding, the rock
mass strength may decrease.
Comprehensive tests combine the above two tests. Both
overloading and strength reduction of the abutment rock
mass during reservoir operation are assumed.
2.1.3 Simulation Technology
Geomechanical model simulation technology experiences
some key problems with combined load testing systems,
model material preparations, measuring instruments, and
test methods. A brief introduction to the topic is given
below.
In general, the loading is simulated by a combination of
water and sediment pressure, and the dam’s gravity. The
water pressure can be simulated with hydraulic jacks or by
a gas bag, which simulates the increase in water density c,
maintaining a triangular distributed load of the appropriate
height (Fig. 2b); the gas bag is kept in contact with the dam
surface during loading. The weight of the dam and its base
gravity are simulated with dead weights.
In the model, small blocks are used to simulate the rock
mass and the concrete dam structure, while the block
binder provides the strength. The small blocks are bonded
using various proportions of polyvinyl alcohol and water to
simulate different friction coefficient f and cohesion c val-
ues for the rock mass and dam concrete. As both the
material and model tests are performed at room tempera-
ture, the effect of temperature change on the strength of the
glue is not considered. Therefore, the selection of the
model materials is very important, where the main factors
include: (1) low cost, environmentally friendly materials,
stability, good workability before solidifying, and ease of
manufacture. (2) After machining the small blocks, to
assure credibility of the results, only very small tempera-
ture and humidity changes are permitted. (3) The chosen
material should have no creep characteristics. (4) The stress
versus strain relationship for the model material should be
identical to that of the prototype structure material both in
the elastic and the post-elastic ranges.
For the simulated reinforcement concrete plugs, the
replacement and cement grouting can be simulated by
changing the modeling material, if the simulated model on
the supporting systems relates to the abutments. The
working loads of the bolts and anchor cables are simulated
to carry scaled values of the real loads and are all manu-
factured to the appropriate scaled dimensions. In this study,
the scale ratio is 1:250. The main types of measurements
include displacement, strain, and cracking behavior. We
used the latest measuring methods that use instrument
miniaturization and automatic remote reading of instru-
ments to ensure high accuracy and reliability.
2.2 Xiaowan Geomechanical Model
2.2.1 Geo-Conditions of the Xiaowan Arch Dam
The Xiaowan arch dam is located on complex rock foun-
dations. The canyon is narrow with high, steep walls. The
foundation geological cross-section of the dam is shown in
Fig. 3. The dam rests on granite and dolomite. The rocks at
the dam site are Triassic granitic gneiss and amphibolite
gneiss, which are massive and dense. Rock masses with
28–35� bedding planes dip towards the river bed. Uniaxial
compression strength testing indicated strengths of
127–172 MPa. Geo-stress testing using discs from the drill
cores situated at a depth of 85 m at the dam site indicated
maximum principal stresses in the horizontal plane varying
from 22 to 35 MPa. This would imply a maximum of
44–57 MPa at the stress concentration zone in the valley
Fig. 2 Illustration of overloading tests
P. Lin et al.
123
floor. Such high stresses are commonly encountered in the
very strong rocks of the tectonically active regions of
southwest China where high mountains and gorges are
present (Wu et al. 2009).
Several large faults (such as F7, F5, F11, F10, and F20),
geological altered rock zones (for example E1, E4, E5, E8,
and E9), and other small faults (f12 and f19) are found in
the river bed (Fig. 4a). These abutment defects have been
strengthened by reinforcement measures, such as replace-
ment with concrete plugs, reinforced bolts, or cement
grouting. The most challenging problems were found in the
river bed when high geo-stresses in the rocks were released
(Lin et al. 2011; Wu et al. 2009). This caused the excavated
river bed elevation to fall by 2.5 m, and the dam height to
increase from 292 m (design value) to 294.5 m. Addi-
tionally, large and deep stress-release zones occurred in the
dam foundations when inbuilt, high geo-stresses were
released by the excavation. Figure 4b shows the excavation
of the abutments in 2005. The excavations are important to
prevent the dam foundations from sliding. Another
important precaution to preventing cracking is the con-
struction of an induced joint in the upstream dam heel.
In this study, four 3D and one plane multi-elevation
geomechanical models were tested to investigate some key
problems. The objectives of the study included: (1)
investigating the influence of the main large faults (F7, F5,
F11, F10, F20), geological altered rock zones (E1, E4, E5,
E8, E9), and other small faults (f12 and f19) in the abut-
ment rock on the overall dam stability; (2) examining the
dam overloading stability capacity with the abutment
reinforcement; (3) deriving the crack growth characteristics
in the dam heel after setting an induced joint, and (4) the
Fig. 3 The foundation geological cross-section of Xiaowan arch dam
Fig. 4 Plane geo-map and snapshot of abutment excavation
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
influence of the excavation and the unloading of the
foundation stability.
2.2.2 Geomechanical Models
The different characteristics of the five models are shown
in Table 2. The first model test took place during the pre-
design study stage in 1995 and was intended to test the
natural foundation. The second test was conducted during
the bidding design study stage in 2000, with modeling of
the reinforced abutments and riverbed. The third test was
conducted during the construction design stage in 2008,
along with studies of the problems caused by the shallow
excavation of the relaxed rocks in the foundation and the
peripheral joints, and their influence on the integrity and
stability of the dam after reinforcement. The fourth test was
conducted during the construction design stage in 2009, to
study the cracking inside the dam caused by thermal stress,
and its influence on the integrity and stability of the dam.
The plane tests, conducted in 2004, were to assist with the
optimization analysis of the scheme to reinforce the fault
zones in both abutments. The geological rock resistance
conditions in the abutments are complex, and depend upon
the rock properties, geological structures, and a weak
structural plane. It was therefore necessary to take techni-
cal measures. The safety of the dam was studied under
natural conditions and after treatment at elevation levels
(ELs) of 1,245, 1,210, and 1,170 m.
Applying the similarity principles, the modeling mate-
rial chosen to represent the dam concrete was plaster. The
first step was to cast an oversized block, which was sub-
sequently machined to the final shape of the dam body. The
foundation model was constructed with thousands of small
spar gypsum blocks (5 9 5 9 10 cm), taking into account
the geological structure of the site. In addition, all the
structural mechanics parameters were simulated according
to the mechanical similarity principle (Table 3). Figure 5
shows the model design including the overall simulation
scale and the measurement instruments distributed on the
down- and upstream surfaces. A box-shaped test frame was
used to manufacture the final geomechanical model by
masonry that was made of plaster (Zhou et al. 2008a). The
displacement sensors and strain gauges were installed in
the downstream dam surface (Fig. 5a) and the overloading
system of jacks was installed in the upstream surface
(Fig. 5b). Fifty-eight hydraulic jacks were arranged in
seven horizontal lines to simulate the different levels of
water pressure (Fig. 5b). The load was first applied on the
bottom levels and then gradually extended to the upper
area. Multiple-stage and single loads were applied in the
elastic state, and then continuous loads followed until the
failure of the dam and abutment. The scale of the 3D model
to the prototype was 1:250.
The 3D model of the simulating prototype was 163 m
high, approximately 0.56H (H represents dam height) in
the upstream direction (Fig. 5c) and 780 m, approximately
2.65H in the downstream direction; 250 m, approximately
0.85H from the bottom of the dam to the bottom of the
foundation; and 550 m, approximately 1.87H in both
abutments. Figure 5d shows the distribution of the dis-
placement sensors and strain gauges on the downstream
surface. A total of 32 displacement sensors were installed
on the downstream surface for monitoring deformation
along and across the river. Additionally, 268 strain gauges
Table 2 Features of the Xiaowan geomechanical model types
Model type Dam geometrical characteristics Foundation simulation conditions
Model A: Year 1995
Original condition of foundation
Height 292 m, crest thickness and bottom of
crown cantilever are 12 and 72.9 m,
respectively
Natural foundation, including faults F7, F11, F5, F19, F23,
F10, F22, F27, F2, f12, f19 and alteration zones E1, E4,
E5, E8 (including f30)
Model B: Year 2000
Foundation reinforced
Same as Model A Based on Model A, reinforcement including concrete faults
replacement F11, F1, and alteration zones. Total 345 pre-
stressed anchorage cables and 940 anchorage cables
around the plunge pool
Model C: Year 2008
Dam with no cracks
Height 294.5 m, thickness in crest and
bottom of crown cantilever are 12 and
73.3 m, respectively.
Based on Model B, geological layers, weathering and
unloading rock layer areas affected by dam interface
excavation. Above EL 975 m, unloading rock layer:
0–7.5 and 7.5–20 m; Below EL 975 m, unloading rock
layer: 0–5, 5–10, 10–15 m. Fillets, peripheral joint, thrust
block, and concrete replacement and plug were installed
Model D: Year 2009
Dam has cracks
As Model C Based on Model C, total of 38 cracks from dam stage 13# to
30# were simulated
Model E: Year 2004
Abutment reinforcement plane
tests
Elevation level 1,170 m Based on Model A, abutment reinforcement transmission
blocks on the right, the long replacement concrete block
was 145 m long and 14 m wide. The short block was
55 m long and 8 m wide
P. Lin et al.
123
were installed on the down- and upstream surfaces for
monitoring the stress distribution under overloading con-
ditions. These monitoring instruments were connected to a
data logger, and a high-precision data acquisition system.
The loading process could be accurately adjusted in
response to feedback from the monitoring and data acqui-
sition system. A digital video monitor system was used to
observe the dam cracking process and foundation failure.
During testing, an auxiliary lighting and power system was
used to check for dam cracking and failure.
3 Dam Cracking Analysis
Based on the results of the four 3D geomechanical model
tests, the cracking characteristics of the up- and down-
stream surfaces of the dam, and the induced joint in the
dam heel, are analyzed below.
3.1 Analysis of the Dam Cracking Process
Figure 6 shows the cracking process and final damage
profile of the up- and downstream surfaces under different
states of overload in the four 3D model tests. Figure 7
shows the final cracking and failure of the up- and down-
stream dam surfaces. Table 4 shows the dam cracking
process analysis based on Fig. 6. Table 5 gives the main
experimental stress, the displacement results, and the
overall safety factors pertaining to the different models.
Based on Figs. 6, 7 and Table 4, the dam cracking
analysis is summarized as follows:
1. Dam heel cracking occurred at 1.2 p0 (the minimum
loading) with the dam toe cracking at 2.5–3 p0. The
interface rock mass was reinforced and this increased
the safety factor for the initial cracking in the dam heel
and toe. The minimum dam heel safety factor for the
initial cracking K1 increased to 1.4.
2. Because the dam has a long arch, its cantilever effect is
stronger than that of the arch above EL 1,100 m. Most
of the cracks propagated along the cantilever direction
and fewer in the direction along the arch, more on the
right and less on the left. As the right-hand abutment
was still weak after reinforcement, the transverse
displacements were large, causing many vertical
tensile cracks and reducing the arching effect. The
right-hand cracks occurred along the cantilever section
across the dam from up- to downstream. Below EL
1,100 m, the shear cracks were perpendicular to the
dam-foundation interface, showing the effectiveness of
the arch.
3. Model D simulated 38 internal cracks caused by
incorrect temperature control during the concrete
pouring stage (Fig. 8). These cracks were observed at
monoliths 13–30 inside the dam at the final stage. Test
results show that the 38 internal cracks of the dam did
not propagate, and the dam remains linearly elastic
under normal water loading (p0). These temperature
cracks had a very small effect on the dam body
(Fig. 6g, h). These internal cracks begin to propagate
internally under a loading of 4.0 p0 and meet cracks in
the crown cantilever, affecting the cracking zone and
lowering the values of K2, K3, and the safety factor
down to 5.0 p0.
Table 3 Mechanical and
geomechanical model test
parameters of Xiaowan arch
dam
Material
property
Young’s modulus E (MPa) f c (MPa) Poisson’s
ratio lPrototype 9 103 Model Prototype Model Prototype Model 9 10-3
Dam concrete 22.4 89.6 1.4 1.4 1.6 6.4 0.22
I 25 100 1.5 1.5 2.2 8.8 0.22
II
II1 22 88 1.5 1.5 2 8 0.26
II2 20 80 1.4 1.4 1.8 7.2 0.27
II3 18 72 1.4 1.4 1.6 6.4
III
IIIa 14 56 1.2 1.2 1.2 4.8 0.28
IIIb1 10 40 1.15 1.15 1.0 4 0.29
IIIb2 6 24 1.1 1.1 0.7 2.8 0.3
IV
IVa 5 20 1.0 1.0 0.6 2.4 0.32
IVb 3 12 0.9 0.9 0.5 2 0.34
IVc 1.3 5.2 0.8 0.8 0.3 1.2 0.35
Va 1.0 4.0 0.5 0.5 0.15 0.6
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
4. The dam cracking zones are similar for Models D and
C, which were characterized by a stiff foundation and
nonconforming deformations between the dam and the
foundation. The internal cracks only propagated
locally within a local confined zone close to the
abutments.
(a) Downstream surface model (b) Upstream surface model
(c) Simulating scale (H represents dam height)
(d) Diagram showing displacement sensors and strain gauges distribution on the downstream surface
250
m,0
.85H
550 m, 1.87H
780m, 2.65H
163m,0.56H
550 m, 1.87H
Right abutment
Left abutment
Dam
Dam
Displacement Sensors
Dam
Jacks
Abutment
Anti-steel frame
Pad
Strain gauge
Displacement Sensorinstalled at crown cantilever
1Y
2Y
3Y
4Y
5Y
Fig. 5 3D geomechanical
model design of the Xiaowan
arch dam
P. Lin et al.
123
3.2 Cracking Analysis of the Induced Joint in Dam
Heel
Another key problem of the Xiaowan arch dam is that an
induced joint was set in the dam heel when large tensile
stresses occurred in the zone between EL 957.5 and
999.5 m (Fig. 9). Linear elastic numerical calculations
(Wang et al. 1998, 2007) showed that the dam heel would
have a higher tensile stress of about 5–7 MPa in the local
stress concentration zone under normal water loading, if no
joint had been created in the dam heel with the possibility
of generating dam heel cracking. The high tensile stress
value is only used as a reference for the dam design,
because the linear elastic numerical simulation in general
does not take into account rock joints at the dam heel,
where local stress concentration can easily form. The
results of two geomechanical model tests (Models A and
B) show that the cracking load at the Xiaowan dam heel is
not high (Table 5), approximately 1.6–1.8 MPa. The
physical Models A and B include the natural joints at the
dam heel, but not the peripheral (induced) joint. The
obtained tensile stress can affect the stability of the dam
heel according to the train gauge monitoring analysis. To
ensure the safety of the Xiaowan arch dam, an engineering
solution is needed to decrease the dam heel tensile stress
and improve the upstream stress distribution.
In dam projects worldwide, in addition to optimizing the
arch dam body to improve the stress state, peripheral joints
are built, generally in the dam heel or bottom seam, to
decrease the dam heel tensile stress. Examples of con-
structing the bottom and edge seam include the 86-m-high
Toules arch dam in Switzerland and the Hongrin arch dam
Fig. 6 Cracking process under different overload states for upstream and downstream dam surfaces (the number represents Kc, excess normal
water load times)
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
(125 m high), which is a double hyperbolic arch dam.
Dams with a bottom seam include the Verwoerd, LeRoux,
and Katze dams in South Africa and the Deji arch dam
(181 m high) in Taiwan. Other examples of peripheral
joints to improve the tensile stress distribution include the
272-m-high Inguri arch dam in Georgia (Ashikhmen and
Pronina 1995), and the 262-m-high Vajont arch dam in
Italy, among others. These arch dams have worked well so
far, with no cracking at the dam heel. The Toules arch dam
was the first to have a bottom seam installed and has been
working safely for 40 years (Hagin 2012). Although con-
structing an induced joint in a dam heel can improve the
tensile stress distribution state, it is bound to weaken the
overall stiffness of the arch dam, decreasing its capacity for
overloading. In addition, with different elevations of the
induced joints, seam depths, and the working behavior of
the contact surfaces between the pouring blocks, the stress
distributions and overload capacities will also be different.
In Model D, the induced (peripheral) joint in the bottom
of the crown cantilever was placed at a height of EL
957.5–999.5 m. Strain gauges were installed to monitor the
stress and strain changes at the induced fracture during the
failure tests (Fig. 9). Based on the experimental results, the
induced joint contributed effectively to reducing the tensile
stress in the upstream dam heel, thus improving the dam
safety factor K1 with respect to cracking. The internal joint
(a) Upstream surface (Model A) (b) Downstream surface(Model A)
(c) Upstream surface (Model B) (d) Downstream surface (Model B)
(e) Upstream surface (Model C) (f) Downstream surface (Model C)
(g) Upstream surface (Model D) (h) Downstream surface (Model D)
Dam crack
Foundation crack
Dam crack
Foundation crack
Foundation crack
Dam crack Dam crack
Foundation crack
Dam crack
Foundation crack
Dam crack
Foundation crack
Dam crack
Foundation crack
Dam crack
Anchor cable andbolt treatment
Anchor cable andbolt treatment
Anchor cable andbolt treatment
Anchor cable andbolt treatment
Fig. 7 Final failure image of
upstream and downstream dam
surfaces
P. Lin et al.
123
endpoints were installed inside the drainage gallery, pre-
venting the cracks from extending through the dam anti-
seepage curtain.
The effect and working condition can be seen from the
following test results:
1. The monitoring results at the internal measuring point
2 (Fig. 10) at a height of 957.5 m showed some tensile
stress around the induced joint. Positive strain indi-
cates tensile stress. Under an overload of 1.5 p0, the
induced joint opened (internal point 2, Fig. 10).
2. Under an overload of 3–5 p0, however, the induced
joint compressed up to a 6 p0 load, still in compres-
sional shear (Fig. 10). The fracture at a height of
998 m (internal monitoring point 1, Fig. 10) was in a
state of compression at all times.
3. The final cracking images at the dam heel and around
the induced joint are shown in Fig. 11. The drainage
gallery prevented cracks extending through the dam
anti-seepage curtain. The final cracking occurred at the
dam-foundation interface (Fig. 11b).
Table 4 Dam cracking process comparisons using four 3D test models
Model
type
Upstream surface cracking Downstream surface cracking
A The dam heel cracking occurred at 1.2 p0. Cracking occurred at
EL 1,020 m in left interface (see Fig. 6a). Under 2–3.5 p0, the
horizontal cracks propagated from abutment to arch crest, some
cracks propagated along the interface in both abutments. Some
vertical crack growth appeared along the beam direction
Cracks initiated at EL 1,020 m at both abutments under 2.5–3 p0
load. The main cracks propagated along the beam direction with
fewer along the arch, more on the right and less on the left.
Under a 2 p0 load, the horizontal cracks propagate from the
abutment to the arch crest at a 3.5 p0 load (see Fig. 6b). The
right cracks occurred along the beam section across the dam
from upstream to downstream. Overload increased, and
coalesced with horizontal cracks at the limitation load of 6.5 p0
B Upstream dam crack initiated from 1.25 p0 to 2.5 p0 (see
Fig. 6c).The tensile stress scale downstream of the dam was
large. The overall safety can meet the requirements of common
computation and safety factors, K3 was 6.5–7.0. As the right
abutment was still weak after reinforcement, the transverse
displacements were large, causing many vertical tensile cracks,
lowering the arch effect
Under a 2.5–3 p0 load, the downstream surface begins to crack in
the dam toe. Vertical cracks were found in the crown cantilever.
Some cracks along the dam interface propagate from the dam
bottom to the upper part. Under a 3–3.5 p0 load, a vertical crack
occurred in the upper direction (Fig. 6d). This crack paralleled
the first crack, initiated at the crest. At this loading step, the dam
had nonlinear mechanical deformations and many cracks
propagated and coalesced in the vertical direction of the
downstream right-hand surface (see Fig. 6d). Under limitation
loading of 6–6.5 p0, the expansion of cracks accelerated radially.
Dam structures deformed rapidly and approached the limitation
C Under normal water loading, fictitious cracks upstream are
compressed, here no cracking appeared in the dam and
abutment. Under a 1.4 p0 load, the dam heel and foundation
upstream began to rupture and the cracking depth was about
4.5 m under 1.9 p0 load (see Fig. 6e). Under a 4–5 p0 load, more
cracking, perpendicular to foundation interface occurred. It
propagated towards the foundation between EL 1,100 m and EL
1,170 m at the left abutment. Under a limitation load, 5 p0 to 7
p0, crack propagation accelerated and coalesced through
downstream cracks
Under a 3 p0 load, the dam downstream surface begins to crack
(see Fig. 6f). Under a 3.5–4 p0 load, the dam had nonlinear
deformations and cracks. A vertical tensile crack in the interface
continuously propagated at EL 1,050 m. Cracks from 1,070 m
turned at 1,130 m and formed horizontal cracks. Under a 4–5 p0
load, horizontal tensile cracks appeared and propagated along
EL 1,130 m. Around EL 1,090 m of the right abutment, new
tensile cracks initiated perpendicular to the foundation interface.
At EL 1,100-1,170 m of the left abutment, more cracks occurred
perpendicular to the foundation interface and propagated
towards the foundation. The lateral tensile crack appeared at
1,150 m elevation in the horizontal direction. Cracks also
occurred in some dam toe blocks. Under a 5–7 p0 load, cracks
coalesced horizontally. The overall dam structure deformed
rapidly
D The dam does not crack and stays elastically linear under normal
loads. Crack initiation begins at a loading of 1.4 p0, crack
growth with excess water loading occurs from 1.7 p0 to 3.0 p0
(see Fig. 6g). Under limitation loads of 5.5–6.0 p0, crack
propagation accelerates and coalesces through downstream
cracks
After a 3.5 p0 load, the dam started cracking. These cracks
propagated internally under a 4 p0 load, meeting cracks in the
crown cantilever (see Fig. 6h). Under a 4.0–5.0 p0 load,
cracking occurred. Downstream of the abutment surfaces, cracks
grew from surface cracks and propagated internally, and were
not coalesced with any dam internal cracks. Opened cross-
sections showed no internal crack propagation. As with the first
model of the dam, a limitation cracking state is likely. Similar
cracking zones occurred in the middle and along the edges of the
model
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
4 Reinforcement Foundation Analysis
4.1 Analysis of the Abutment Failure Process
Figure 12 shows the rock mass failure process at the dam-
foundation interface and abutments observed in the four 3D
model tests. The main analysis results are as follows:
1. Because of the foundation reinforcement, the founda-
tion deformations of Model B are clearly smaller than
those of Model A. Fault F11 was located in the right
abutment, with much higher strength because of the
change of body shape and concrete backfill. However,
the overall dam foundation safety factors are not
affected as a result of the altered zone. Since the dam
axis rotates 3� to the right abutment, fault F11 on the
right crosses over the dam at a height of 1,200 m and
the rock in the abutment becomes thicker. However,
the left abutment becomes closer to F11 and because of
the additional influence of the left-hand alteration zone
E8 (including f30) and the #4 ridge, the left abutment
rock mass ruptured earlier and more strongly than the
right abutment. The sides became ruptured surfaces
along the river bank and quickly slid downstream. A
particularly broken zone formed between fault F11 on
the left and the dam heel (Fig. 12b), which began to
crack at 2.5–3.0 times the normal water load. The dam
heel deformed noticeably under loads of between 3 p0
and 3.5 p0. Affected by alteration zone E8 (including
f30), the tangential deformation of the foundation was
caused mainly by the large tangential displacement of
the left abutment, in particular at the top.
2. Model C results show that deformations in both
abutments meet the regulatory requirements. Under
3.0 p0 loading, cracks appear on the downstream
surface at EL 1,160 m on the left and at EL 1,150 m
on the right (Fig. 12c). Under 4.0 p0 loading, cracks in
the foundation began to propagate and extend along
the left side of the abutment. Under 5 p0 loading, the
rock mass near the interface between the dam and the
foundation clearly moved and sheared at the height of
EL 1,160 m. Under 6 p0 loading, even though the
downstream foundation was reinforced by anchors, the
downstream foundation surfaces were heavily sheared,
especially in the river bed foundation. The anchorage
zone on both abutments collapsed at 6.5 p0. The left
side deformed linearly before 3 p0 and non-linearly
after 4 p0. In the right abutment, linear deformation
occurred up to 2 p0 with nonlinear deformation after
3 p0.
3. Model D, tested in 2009 to simulate the internal cracks
produced during the concrete pouring period, showed
that the abutments began cracking downstream under
3 p0 and 3.5 p0 loads. These cracks expanded from
outside to inside, and were not caused by internal
cracks (Fig. 12d). In the dam section, no internal
cracks propagated. Comparing these tests, the crack
distributions are similar. Internal cracks begin to grow
between 4.0 p0 and 6.0 p0 loads. The growing internal
cracks meet the external ones, resulting in a 20 %
lower maximum load with respect to dams with no
temperature cracks. After 4.0 p0 loading, the internal
cracks begin to influence crack propagation, with
coalescence occurring in the arch crown zone. Con-
sidering the anchor and consolidation grouting to be
effective, the abutments have a much higher stiffness
and fewer cracks in the abutment (Fig. 12d).
4.2 Reinforcement Analysis with Plane Tests
In Sect. 4.1, the reinforcement effects were evaluated based
on the four 3D tests. A series of demonstration plane model
tests was also carried out before the installation of the
proposed abutment reinforcement measures. The main
purpose of these plane experiments was to study the
abutment foundation performance and failure modes at EL
1,170 m and EL 1,245 m, and to identify the relationship
between the replacement blocks and the reinforcement,
which works to increase the main weak structural plane as
the load changes. In this study, only the foundation rein-
forcement requirement and the influence on the overall
safety are discussed by comparing the results of the rein-
forced design and the original plane test at EL 1,170 m.
For the EL 1,170 m plane model tests the actual simu-
lations are as follows. The model scale is fixed at 1:500.
The model simulates a prototype of 175 m length,
approximately 0.6H in the upstream direction, and 725 m,
approximately 2.5H, in the downstream direction. Both
abutments are 830 m in total width (right abutment 430 m
and left abutment 400 m). The model scale was chosen to
ensure that the main faults and altered zones were simu-
lated (Table 2). The model bottom was kept smooth using
wax and two sides were constrained by a steel frame. The
two plane test results are shown in Fig. 13 for the natural
and reinforced foundations.
Figure 13a shows the final cracking and failure results
of the natural foundation at EL 1,170 m. The left abutment
joints and cracks became dislocations under 2–3 p0 load-
ing, eventually leading to a large sliding mass with E8,
F11, f19, and F20 (Fig. 13a). The two abutment founda-
tions were damaged by both cracking and sliding. The
damage zones are approximately 50–60 m from the dam-
foundation interface. The right abutment failure developed
along fault F11 and the alteration zone E1 at less than
1.8 p0 loading, and propagated, forming a composite
P. Lin et al.
123
sliding mass at fault f11 under 2 p0 loading. The right
sliding zone included E1, F11, E4, E5, and f11, and most of
the cracking occurred around the boundary of E4 and E5.
Therefore, improving the stiffness of the zones where the
cracking and sliding occurred is essential for the Xiaowan
dam. Apart from reinforcing, replacement with a concrete
pedestal should also be considered.
Figure 13b shows cracking and failure of the reinforced
foundation at EL 1,170 m. Under 2.4 p0 loading, both
upstream abutments showed transverse cracks, which
Table 5 Comparison of stresses, displacements and safety factors using four 3D test models
Model
type
Max.
longitudinal
Disp. (mm)
Max.
transverse
Disp.
(mm)
Displacement
distribution
characteristics
Tensile
stress at
dam
heel/
MPa
Max.
compressive
stress in
downstream
surface/MPa
Stress distribution
characteristics
K1 K2 K3
A 205 24 Greater on left arch
than on right arch
1.8 13.4 High stress
concentration at local
zone
1.2 3.0 5.0
B 192 19 Greater on the left
arch. A similar
deformity is found
on both abutments
1.6 12.8 Stress on the
downstream surface
changes steeply,
giving a weak
foundation and arch
effect.
1.3–2.5 3.0 6.5–7.0
C 179 20 Displacement in the
lower part of dam is
greater on the left
arch. Reinforcement
of the left abutment
strengthens the
stiffness
0.95 12 Tensile stress at the dam
heel decreases due to
the peripheral joint
1.4–2.0 2.9–3.5 6.5
D 181 18 Dam deformation is
symmetric. Under
overloading
conditions, dam
crack deformation
increases due to the
decrease of stiffness
1.12 12.5 Compressive stress on
the downstream
surface concentrates
on the two sides.
Upstream surface
tensile stress
distribution has a more
average
1.4–1.7 2.7–3.0 5.5–6.0
Table 6 3D geomechanical model tests of safety factors for different typical high arch dams
Dam Operation
date
Dam height
(m)
Arc length
(m)
Bottom
thickness
(m)
Ratio of
thickness
to height
Ratio of
arc
to height
K1 K2 K3
Ertan 2000 240 775 55.7 0.23 3.16 2 4 11–12
Jinping I (natural foundation) 2014 305 698.1 72 0.24 2.29 1.5–2 3–4 5–6
Jinping I (foundation
reinforcement)
305 552.2 63 0.21 1.81 2.5 4–5 7.5
Xiaowan (Model A) 2010 292 937.3 72.9 0.25 3.21 1.2 3 5
Xiaowan (Model B) 292 937.3 72.9 0.25 3.21 1.3–2.5 3 6.5–7
Xiaowan (Model C) 294.5 892.8 72.9 0.25 3.03 1.4–2 2.9–3.5 6.5
Xiaowan (Model D) 294.5 892.8 72.9 0.25 3.03 1.4–1.7 2.7–3.0 5.5–6
Goupitan 2011 232.5 552.6 50.3 0.22 2.38 2.4 4.4 8.6
Laxiwa 2011 250 545 49 0.20 2.18 2.18 3.5–4 7–8
Xiluodu (824 dam body) 2014 278 710 69 0.25 2.55 1.8 5 6.5–8
Xiluodu (03 dam body) 278 650 62 0.22 2.34 1.8–2 4.5 7–8.5
Xiluodu (03 dam body) 285.5 681.5 60 0.22 2.45 2 4.5 8.5
Dagangshan 2015 210 622.4 52 0.25 2.97 2 4.5 9.5
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
eventually formed a tensile area upstream of the arch-side.
A compression and shear zone occurred in the right
abutment near the foundation surface under 3–5 p0 load-
ing. The main fracture on the edge of E4 (close to the
river) formed a partial sliding zone under 5 p0 loading.
The shear sliding zone in the right abutment was limited
to a range of 60 m near the arch-side, which is a key
reinforced area. The analysis also showed that the force
transfer was effective in both abutments within 50 m. A
tensile cracking zone formed in the left abutment along
the joints and E8.
In summary, the experiment illustrates that the length of
the transmission blocks should be kept at approximately
50 m. The shear fracture zone in the right abutment is the
key area governing the behavior of the alteration zone and
abutments. To overcome the influence of the faults on the
stability of the Xiaowan arch, we recommend that a foot
pad and anchors are combined downstream of the arch-side
near the river to accurately determine the safe range of E1,
E4, E5, and E8. Replacing the altered zones, faults, and
anchors in the IIIb and IVb reinforcement zones can
improve the stability of the abutment. These recommen-
dations were adopted by the designer and are reflected in
Models C and D. Figure 14a, b show a classic anchor cable
and bolt treatment section of the abutment downstream. A
current image of the reinforced left abutment can be seen in
Fig. 1.
Fig. 8 Distribution of internal
temperature cracks in the
Xiaowan arch dam
Vertical cross-section of dam heel
A-A cross-section
Internal strain gauges 3 Internal strain gauges 1
Internal strain gauges 2
Internal strain gauges 2 isinstalled at induced joints arch
crown 957.5
(a)
(b)
Fig. 9 Set of induced joint in
the upstream dam surface and
internal strain gauges for
monitoring cracking around the
induced joint
0
1
2
3
4
5
6
7
-600 -400 -200 0 200 400Tim
es o
f o
ver
no
rmal
wat
er lo
ad(p
0)
Strain
internal monitoring point 1
internal monitoring point 2
Fig. 10 Relationship between strain and the excess normal water
load time for upstream induced joint (monitoring point shown in
Fig. 9)
P. Lin et al.
123
5 Analysis of the Overall Stability of the Xiaowan Arch
Dam
5.1 Results of the 3D Model Test
Based on the four 3D rupture model test results, compar-
ative analyses were done on the displacement, stress dis-
tribution characteristics and overall stability of the dam.
Table 5 shows the main experimental stress, displacement
results and overall safety factors. Considering that the
Xiaowan arch dam has been operating for approximately
four years, Models C and D are compared. Figure 15
shows the up- and downstream dam surface stress distri-
bution characteristics under a normal water load. Similarly,
Fig. 16 shows the relationship between the crown cantile-
ver displacement along the river and overloading factor Kc
for the downstream surface. Displacement sensors 1Y, 2Y,
3Y, 4Y, and 5Y were installed at EL 1,240 m, EL 1,170 m,
EL 1,090 m, EL 1,010 m, and EL 960 m, respectively
(Fig. 5d).
Based on the test results (Table 5), the largest dam dis-
placements along the river are between 179 and 205 mm
under normal water loading. The deformations and stiffness
for both the abutments are symmetrically distributed, given
the overall foundation reinforcement. Figure 16 shows that
the displacement of the crown cantilever above EL 1,170 m
is much larger than that at the lower position (Fig. 16a, b).
In Model C, when the overloading factor Kc is greater than
2.9, the cantilever displacement is greater than 600 mm and
the dam structure shows a nonlinear response. Model D
shows nonlinear states at Kc = K2 [ 2.7. When Kc is
greater than 5.5, the displacement along the river on the
cantilever increases sharply, and the dam fails at 6.5 p0 in
Model C and 6.0 p0 in Model D.
Under normal water loading, the stress distribution on
both the up- and downstream surfaces exhibits the expected
behavior of a double curvature arch dam. The highest
compressive stresses are between 10 and 13 MPa on the
downstream surface and 1.0 and 1.9 MPa tensile stresses
were observed on the upstream surface. The test results
show that the tensile stress on the upstream surface is a
little higher than that on the downstream surface. After
foundation reinforcement optimization, the tensile stress at
the dam heel decreased by approximately 48 and 38 % in
Models C and D, respectively (Table 5; Fig. 15).
Based on the experimental results, the factor of safety
against the onset of dam cracking is not high. The lowest
K1 is under 1.5, the safety factor against the onset of
nonlinear behavior, K2, is approximately 3.0 and the factor
of safety for the maximum load, K3, is no more than 7.0.
For Model B, which allows for different reinforcement
measures and geological conditions, such as weathering
and altered zones in both abutments, the strength of the
rock foundation is weak. The tensile stress in the dam heel
upstream is large and the tensile stress parallel to the
downstream bank is also high, particularly in the tensile
zone below EL 1,050 m on the left abutment. The safety
factor for crack onset has a lower value of 1.25–2.5 for the
upstream surface and 2.5–3.0 for the downstream surface.
After reinforcement, the dam longitudinal displacement is
shown to be smaller. Although the stability requirements of
dam abutments under a normal water load are satisfied, the
final overloading safety factor is the same as for the rein-
forced test of Model A, K3 = 6.5–7.
Model C contains geological features, including faults
f19, f17, f12, and f34 on the left bank, ruptured rocks
caused by released stresses owing to high ground removal,
and no reinforcement of f19 in the left abutment below EL
1,160 m. Therefore, the cracks in the left abutment and the
downstream foundation are more prevalent than those that
appear in Model B. The shallow unloaded part of the
foundation somehow affects the dam deformation. Cracks
propagate along the river, starting from upstream tension
cracks and turning into compression shear cracks, and
some cracks coalesce. The safety factor, however, becomes
acceptable after the reinforcement measures. An anchorage
block at the downstream toe of the dam keeps the rock
mass intact and the anchoring proves effective. The
installation of measures to induce controlled fracturing
helps improve K1, which contributes to restricting the size
of the upstream tensile area. The overall stability safety
parameters, therefore, are K2 [ 2.9 p0 and K3 [ 6.5 p0.
Cracking in the dam heel
(b)
(a)
Cracking around the induced joint adjacent to the inspection tunnel
Inspector tunnel of induced joint
Induced joint
Cracking along dam and foundation interface
Induced joint
Fig. 11 Cracking in the dam heel and induced joint
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
Fig. 12 Failure of abutments
for four 3D model tests (red line
indicates cracking) (color figure
online)
P. Lin et al.
123
Mel D simulated the 38 internal temperature flaws
existing within the Xiaowan dam. We analyzed the
influence of the internal cracking on dam stability, in
particular the induced joint and elastic deformations of
the dam under conditions of overloading. The results
show that under normal water loading, the internal
cracks have only a small effect on the stress distribution.
In general, shear compression cracks are formed. Fol-
lowing a load of 3.0 p0, cracking occurs in the local
zones of the dam. Overall, cracks then spread and
eventually coalesce at the cantilevered crown at loading
of up to 5 p0, thus lowering K2, K3, and the overall
safety factor. As a result, K1 = 1.4–1.7, K2 = 2.7–3.0,
and K3 = 5.5–6.0.
In summary, after a series of reinforcement measures,
including foundation reinforcement, installation of an
induced joint, construction of a fillet at the dam toe and
high-strength anchoring and grouting, the integrity and
stability of the Xiaowan arch dam can satisfy the opera-
tional requirements (the PSCG of PRC 2007).
Fig. 13 Cracking and failure of
the natural and reinforcement
foundation at EL 1,170 m
(F large faults, f small fault,
E altered rock zones)
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
5.2 Comparison with Other Super-High Arch Dams
In recent years, geomechanical model tests have been
widely used for the analysis of structural failure and
abutment stability of high dams, with many advances in
this field (Zhou et al. 2008a; Lin et al. 2011; Jiang et al.
2002; Zhang et al. 1994). So far, no specific rules or criteria
have emerged for the evaluation of the results of design
specification tests. How to interpret and evaluate model
dam test results is still an engineering question of concern.
The Department of Hydraulic Engineering at Tsinghua
University has summarized the overload safety coefficients
that apply to many super-high arch dams in China (Zhou
et al. 2008; Lin et al. 2011). These have been adopted in the
various engineering specification documents. The safety
coefficients include K1 (onset of cracking safety factor), K2
(onset of structural nonlinear behavior safety factor), and
K3 (dam-foundation maximum loading safety factor), as
shown in Table 6. These values are often compared with
numerical simulation results when checking proposed
designs. Based on Table 6 and comparing the results with
those of similar projects, the overall stability of the Xiao-
wan arch dam satisfies the operational requirements (the
PSCG of PRC 2007).
5.3 Comparison with Numerical Simulation and Site
Monitoring Results
Some numerical simulation studies have also been carried
out. In this paper, we present a simple comparative analysis
with the numerical and experimental results of Model D.
Figure 17 shows the main numerical results, including
the dam displacements along the river, the maximum dam
stress, and the dam safety factors under normal water
loading. Note that the deformations and stiffness for both
the abutments, following the reinforcement measures, are
Horizontal cross section(EL 1028m)
Vertical cross section (0+125.00)
(a)
(b)
Fig. 14 A classic anchor cable
and bolt treatment section of
downstream abutment
P. Lin et al.
123
Upstream surface (Model C)
Downstream surface (Model C)
Upstream surface (Model D)
Downstream surface (Model D)
Left right
Right Left
1245
1210
1170
1130
1190
1050
1010
975
960
950.5
-5.4-30
-13.2-46.3
-15.1-33.2
-10.2-25.1
-4.2-22
-5.4-30
-3.4-12
-5.4-30
-5.4-30
-5.4-30
-5.4-30
-5.4-30
-2-10.6
-2-10.6
-3.6-13.2
-3.6-13.2 -5.3
-15.1
-5.3
-15.1
-5.1
-16.6
-5.1
-16.6
-4.2
-14.4
-4.2
-14.4
-2
-93.9 -4
4.0
5.1
8.0-5.6
-5
9.5
-3
10.2
-4
7.2
-3
4.7
1.2-10
-2.8 -41.8
-3.6 -48.2
-4.5 -36.6
-2.8 -41.8
-7.2-57.2
-7.8 -40.5-35.6
-6.8 -47.4
-4.0 -54.2 -5.0-44.8
-3.3
-30.8-6.8
-45.8
-12.8
-78.4
-6.0
-88.8
-5.0
-95.2 4.4
-83.6
2.5
-95
2
-112.2
6.2
-120.8
4
-108.5
2.0
-104
2.0
-104
6.3
-74.2
3.0
-1.0
-87.8
-82.8
-2.2
-50.5
1245
1210
1170
1130
1190
1050
1010
975
960
950.5
Right Left
Left right
(a)
(b)
(c)
(d)
Fig. 15 Stress distribution
characteristics of Model C and
Model D (unit: kg/cm2)
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
symmetrically distributed, with reasonably good agreement
between the numerical and physical results (Table 5).
Figure 17a shows that the greatest crown cantilever
displacement is approximately 194.17 mm at EL 1,245 m
and the maximum transverse displacement is 21.5 mm at
EL 1,010 m on the left side of the dam. Under normal
water loading, The dam heel principal tensile stress is
approximately 0.9 MPa and the compression stress at EL
1,030 m of downstream surface is approximately 10.3 Pa
(Fig. 17b, c). With the increase in water loading to 3.5 p0,
the tensile stress gradually increases to more than 1.5 MPa.
The dam point safety factors are between 1.2 and 2.0
(Fig. 17d).
To date, the dam (Model D) has been operating for four
years. Field monitoring results show little change in the
horizontal displacement of the foundation. On September
7, 2013, the reservoir water level was at 1,228.96 m. The
maximum cumulative radial displacement (along the river)
is 94.75 mm (EL 1,174 m) and the maximum cumulative
tangential displacement (across the river) is 12.57 mm (EL
1,190 m). When the water level increased, the pressure at
the induced joints became high, reducing the compression
stress, and some surface sliding occurred. The monitoring
of the dam cracking showed that the internal cracks
remained largely stable. Both abutments have remained
stable, and there have been no abnormal deformations and
seepage pressures during the operational period of the dam.
The monitoring results of the dam displacement, stress, and
seepage indicated no anomalies at the key areas near the
dam, and showed that overall the dam is working properly
and in accordance with the designers’ expectations.
The difference in the maximum cumulative radial dis-
placement between the field monitoring and numerical and
experimental results is approximately 50 %. The main
reason for this relates to the assumed values of the geo-
mechanical parameters. In general, the design parameters
used in China for rock mass and concrete are conservative
compared with the actual parameters (Luo et al. 2014). The
feedback analysis shows that the actual parameter values
are higher by nearly 40–50 % compared with the design
values. Furthermore, after impounding, the dam reservoir
basin can withstand the weight of the water, the dam heel
vertical deformation, and the effect of the dam hung
upside-down increases. In numerical and physical analysis
their role is often ignored.
6 Conclusions
The Xiaowan arch dam has faced challenging construction
problems. In this paper, we studied the test results of four
3D geomechanical models and a series of plane models.
The displacements, distribution of stresses, overall safety
factors, cracking, and the failure processes of the dam
foundations were analyzed. The main conclusions are as
follows.
1. This work provides a scientifically-based reference for
geomechanical model testing that can serve as a
guideline for nonlinear design of super-high arch
dams. The key problems that affect the construction
processes and the safety factors of the Xiaowan arch
dam have been analyzed. The model studied cracking,
its spread and distribution, and the effects of various
types of abutment reinforcement measures and foun-
dation design alternatives.
2. Based on the results of four 3D model tests, under
normal loading conditions all deformations were
normal without any yielding or tensile cracking. The
first cracking occurred at the heel of the dam at 1.2
times the normal water load. Cracking at the dam toe
occurred downstream at 2.5–3 times the normal water
load. When the rock mass was reinforced, the dam heel
safety factor K1 increased to 1.4. The crack propaga-
tion safety factor of the dam was 2.5–3.0 p0 for the up-
and downstream surfaces, respectively. Nonlinear
deformation of the dam also occurred at 2.5–3.0 p0
/ mmδ(a) Model C
(b) Model D
0
1
2
3
4
5
6
7
0
1
2
3
4
5
6
7
0 500 1000 1500 2000 2500 3000
0 500 1000 1500 2000 2500 3000
1Y EL.1240m
2Y EL.1170m
3Y EL.1090m
4Y EL.1010m
5Y EL.960m
1Y EL.1240m
2Y EL.1170m
3Y EL.1090m
4Y EL.1010m
5Y EL.960m
Kγ
Kγ
/ mmδ
Fig. 16 Relationship between the crown cantilever displacement
along the river and the overloading factor Kc
P. Lin et al.
123
Fig. 17 The main results of
numerical simulation on Model
D under normal water loading
Table 1. Model test linear
elastic and damage similarity
criteria
Experimental Study on Cracking, Reinforcement, and Overall Stability
123
load p0. Therefore, the safety factor against the onset
of structural nonlinear behavior, K2, is approximately
2.5–3.0. After reinforcement, the dam longitudinal
displacement became smaller. Although the stability
requirement of the dam abutments under a normal
water load was satisfied, the final overloading safety
factor was the same as for the reinforced test of Model
A, K3 = 6.5–7.
3. An artificially-induced (peripheral) joint at the bottom
of the crown cantilever contributed to a reduction of
the tensile stress in the upstream dam heel, thus
improving the margin of safety against cracking, K1.
The fracture ends were designed to occur inside the
drainage gallery to prevent the cracks extending
through the curtain.
4. The series of 3D and plane model tests on abutment
failure were very important in allowing recommenda-
tions to be made concerning the detailed and complex
reinforcement measures needed at faults in various
weak and localized zones (E1, E4, E5, and E8), and for
IIIb and IVb type rock mass. Comparing the perfor-
mance of similar high-arch dams in China, after taking
reinforcement measures (including foundation rein-
forcement, setting an induced joint in the dam heel and
a fillet at the toe, and providing high-strength anchor-
ing and grouting for the abutments), it is evident that
complex reinforcement measures are effective in
increasing the abutment stiffness and the overall
stability of the Xiaowan arch dam. The overall stability
of the dam can satisfy the operational margin of the
safety requirements. The field monitoring results over
the four years of operation show nothing abnormal in
the key areas near the dam, indicating that the dam is
working properly.
Acknowledgments This research work was supported by National
Natural Science Foundation of China (No. 11272178), the National
Basic Research Program of China (973 Program) Grant No.
2011CB013503, and the Tsinghua University Initiative Scientific
Research Program. The authors are very grateful to Prof. Yang RQ and
Shen DL, and the Kunming Hydroelectric Investigation and Design
Institute, China Hydropower Engineering Consulting Group Co. for
support this study. The authors are also very grateful to Prof .Giovanni
Barla, Anson Elaine and two reviewers for their critical recommen-
dations which helped the author to improve this paper significantly.
References
Ashikhmen VA, Pronina LE (1995) Regrouting joints and its effect on
the stress-strain state of the Inguri Arch Dam. Hydrotech
Construct 28(10):569–580 (translated from: Gidrotekhnicheskoe
Stroitel’stvo (10):1–9)
Barla G, Debernardi D, Sterpi D (2012) Time-dependent modeling of
tunnels in squeezing conditions. Int J Geomech 12:697–710
Chen XH et al (1984) Structure model test of brittle materials. China
Water Power Press, China, pp 1–10
Chow WY, Yang RQ (1984) Determination of stability of arch dam
abutment using finite element method and geomechanical models.
In: Proc 4th Australia–New Zealand conference on geomechanics,
vol 2, Perth, pp 595–600. Publ Barton, Inst of Engineers
Fei WP, Zhang L, Zhang R (2010) Experimental study on a
geomechanical model of a high arch dam. Int J Rock Mech
Min Sci 47(2):299–306
Fumagalli E (1979) Geomechanical model of the dam foundation.
ISRM geomechanical model of the international symposium,
Bergamo
Hagin B (2012) Hydropower in Switzerland. Reference module in
earth systems and environmental sciences. Compr Renew
Energy 6:343–354
Heuer RE, Hendron AJ (1971) Geomechanical model study of the
behavior of underground openings in rock subjected to static
loads (Report 2)—tests on unlined openings in intact rock. AD
report, USA
Jerome MR (1960) Structural model investigations for Oroville dam.
Struct Material Res 100(6)
Jiang XL, Cao JG, Sun SW (2002) Geomechanical model test of
integrity stability of the Goupitan hyperbolic arch dam. Yangtze
River Sci Res Inst 19(6):21–24
Li GR (1958) The Liuxi River Xiaoche arch dam structure model test
and stress analysis. Hydroelectric power, pp 1–8
Li TB (2004) Geomechanical model test on abutment stability of arch
dam. Chin J Rock Mech Eng 23(6):1670–1676
Li LC, Liu HH (2013) A numerical study of the mechanical response
to excavation and ventilation around tunnels in clay rocks. Int J
Rock Mech Min Sci 59:22–32
Li ZK, Liu H, Dai R, Su X (2005) Application of numerical analysis
principles and key technology for high fidelity simulation to 3-D
physical model tests for underground caverns. Tunn Undergr
Space Technol 20:390–399
Li LC, Yang TH, Liang ZZ, Tang CA (2011) Numerical investigation
of groundwater outbursts near faults in underground coal mines.
Int J Coal Geol 85:276–288
Lin P, Zhou WY, Yang Q, Hu YJ (2004) A new three-dimensional
FEM model on arch dam cracking analysis. Key Eng Mater
261–263:1569–1574
Lin P, Wang RK, Kang SZ, Zhang HC, Zhou WY (2011) Key
problems of foundation failure, reinforcement and stability for
super high arch dams. Chin J Rock Mech Eng 30(10):1945–
1958
Lin P, Kang SZ, Li QB, Wang RK, Wang ZL (2012) Evaluation of
rock mass quality and stability of Xiluodu arch dam under
construction phase. Chin J Rock Mech Eng 31(10):2042–2052
Lin P, Liu XL, Hu Y, Xu WB, Li QB (2013a) Deformation and
stability analysis of Xiluodu arch dam under stress-seepage
coupling condition. Chin J Rock Mech Eng 32(6):1137–1144
Lin P, Zhou YN, Liu HY, Wang C (2013b) Reinforcement design and
stability analysis for large-span tailrace bifurcated tunnels with
irregular geometry. Tunn Undergr Space Technol
38(9):189–204. doi:10.1016/j.tust.2013.07.011
Liu J, Feng XT, Ding XL, Zhang J, Yue DM (2003) Stability
assessment of the Three-Gorges Dam foundation, China, using
physical and numerical modeling—Part I: physical model tests.
Int J Rock Mech Min Sci 40:609–631
Liu HY, Small JC, Carter JP, Williams DJ (2009) Effects of
tunnelling on existing support systems of perpendicularly
crossing tunnels. Comput Geotech 36:880–894
Luo D, Lin P, Li QB, Wang C (2014) Performance analysis of
Xiluodu super-arch dam in impounding period. Chin J Hydraul
Eng 45(1):18–26
P. Lin et al.
123
Pan JZ (2004) Ultra-high arch pivot and key issues. China Electric
Power Press, pp 1–2 (prefaced by Lizan, Chenfei, Zheng Jianbo
et al.)
the PSCG of PRC 2007 Design criteria for concrete arch dam.
National Development and Reform Commission of the People’s
Republic of China, Beijing, pp 128–129
Wang GL, Zhan CH, Guo ZS, Jin F (1998) Study On upstream bottom
joint for improving the stress conditions of high arch dam.
J Hydraul Eng 1:69–75
Wang RK, Lin P, Zhou WY (2007) Study on cracking and stability
problems of high arch dams on complicated foundations. Chin J
Rock Mech Eng 26(10):1951–1958
Wong RHC, Lin P, Tang CA (2006) Experimental and numerical
study on splitting failure of brittle solids containing single pore
under uniaxial compression. Mech Mater 38:142-159
Wu FQ, Liu T, Liu JY, Tang XL (2009) Excavation unloading
destruction phenomena in rock dam foundations. Bull Eng Geol
Environ 68:257–262. doi:10.1007/s10064-009-0202-5
Zhang L, Ma YQ, Hu CQ (1994) 3D geomechanical model test of
high slope stability. Design Hydroelectr Power Stn 10(3):39–50
Zhou WY, Lin P, Yang RQ, Yang Q (2008a) Geomechanical model
test methods and application of high arch dam. China Water
Power Press, Beijing, pp 190–204
Zhou WY, Lin P, Zhou YN, Yang Q (2008b) Research on concrete
socket and peripheral joint for high arch dam foundation. Chin J
Rock Mech Eng 27(10):1959–1967
Zhou WY, Lin P, Yang Q, Yang RQ, Zhou Z (2008c) Experimental
research on stability of Jinping high slope with three-dimen-
sional geomechanical model. Chin J Rock Mech Eng
27(5):893–901
Zhu WS, Li Y, Li SC, Wang SG, Zhang QB (2011) Quasi-three-
dimensional physical model tests on a cavern complex under
high in situ stresses. Int J Rock Mech Min Sci 48(2):199–209
Experimental Study on Cracking, Reinforcement, and Overall Stability
123