26
Experiences of Hungary's new NPP project János Krutzler Hungarian Atomic Energy Authority Department of Project Affairs

Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Experiences of Hungary's new NPP project

János Krutzler Hungarian Atomic Energy Authority

Department of Project Affairs

Page 2: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Content

• Hungary’s new NPP project

• Hungarian legal framework

• Recent update of the legal framework

• Recent and ongoing challenges

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 2

Page 3: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Hungary’s new NPP project

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 3

Page 4: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Hungary’s new NPP project so far • The idea of NPP extension has been on the agenda

since the 80’s (2*1000 MW additional capacity was planned for the site);

• 2008: energy policy conception: based on supply security and climate-protection objectives, the decision preparation work for new units started;

• 30th March, 2009: decision-in-principle of the Hungarian Parliament;

• January 2014: Intergovernmental agreement on the peaceful use of nuclear energy by Russia and Hungary:

Two VVER-1200 type reactors at the Paks site;

Russian loan for the 80% of construction costs;

• 7th December, 2014: Implementation agreements singed:

EPC contract;

Operation and maintenance support contract;

Agreement detailing fuel supply and the handling of spent fuel.

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 4

28 March 2014

12 February 2014

14 January 2014

Intergovernmental Agreement (IGA)

About the cooperation on the peaceful use of nuclear energy

Act II/2014

About the announcement of the IGA, in force on 12 February

7 December 2014

Intergovernmental Agreement (Financial IGA)

About the interstate loan for the extension of Paks NPP

23 June 2014

Implementation agreements signed by Paks II Nuclear Power Plant

Development C-JSC and the Russian Joint-Stock Company

Nizhny Novgorod Engineering Company Atomenergoproekt

Act XXIV/2014

About the announcement of the FIGA

Page 5: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Paks NPP site

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 5

Source: Paks 2 Environmental Impact Assessment Report

Operating units 4 x VVER-440

Page 6: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 6

Planned milestones of the licensing process:

2014: site assessment licence

2015: environmental licence

2015: licence in principle of the Hungarian Energy and Public Utility Regulatory Authority

2016: site permit

2017: construction licence

Planned milestones of the design and construction process:

2014: EPC contract

2015: general design and detailed design by the general contractor

2016: review of design

2018: start of construction

2025: start of commercial operation at Unit 1

2026: start of commercial operation at Unit 2

Environmental

licence

Site permit

Construction

licence

EPC

contract

general design by the general

contractor

Review of design

Detailed design

Site

assessment

licence

Licence of

MEKH

Start of construction

start of

commercial

operation at

Unit 1

2014 2017 2015 2016 2018 2021 2019 2020 2022 2025 2023 2024

Project schedule*

*Source: Dr. Attila Aszódi (Government Commissioner, Paks-2 project)

Page 7: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Hungarian legal framework

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 7

Page 8: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Gov. Decree

No. 118/2011

Act No.

CXVI/1996 on

Atomic Energy

Nuclear Safety Code

Safety Guidelines

Internal procedures

Other regulations

1 2 3 … 10 9 …

22-25 June 2015 8 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS

The Nuclear Safety

Regulation

in Hungary

Page 9: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

NPPs Research and

Training Reactors

Spend Fuel Storage Facilities

Volume 1. – Nuclear safety authority procedures of nuclear facilities

Volume 2. – Management systems of nuclear facilities

Volume 3. Design require-

ments for operating NPPs

Volume 4. Operation of NPPs

Volume 5. Design and

Operation of Research and

Training Reactors

Volume 6. Design and

Operation of Spend Fuel

Storage Facilities

Volume 7. – Siting of Nuclear Facilities

Volume 8. – Decommissioning of Nuclear Facilities

Volume 10. – Terminology

Volume 9. – Construction of New Nuclear Facilities

22-25 June 2015 9 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS

Structure of the Nuclear Safety

Code Volume 3A. Design

requirements for new NPPs

Page 10: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 10

Lifecycle stages of a NPP and the corresponding license

Page 11: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Recent update of the legal framework

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 11

Page 12: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

NPPs Research and

Training Reactors

Spend Fuel Storage Facilities

Volume 1. – Nuclear safety authority procedures of nuclear facilities

Volume 2. – Management systems of nuclear facilities

Volume 3. Design require-

ments for operating NPPs

Volume 4. Operation of NPPs

Volume 5. Design and

Operation of Research and

Training Reactors

Volume 6. Design and

Operation of Spend Fuel

Storage Facilities

Volume 7. – Siting of Nuclear Facilities

Volume 8. – Decommissioning of Nuclear Facilities

Volume 10. – Terminology

Volume 9. – Construction of New Nuclear Facilities

22-25 June 2015 12 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS

Volume 3A. Design

requirements for new NPPs

Design requirements for NPPs (both for existing and new) where originally in a single NSC Volume. After careful consideration we concluded that it would be beneficial to separate requirements.

Recent review of the NSC

Page 13: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Existing vs. New NPPs (1/3)

Reasons for separating design requirements:

• it represented a significant challenge to create design requirements, that are fully applicable for exiting and new units at the same time without being either too strict or too permissive;

• the new units will have a design life of at least 60 years, so in order to meet future challenges we decided to create (in close cooperation with interested parties) requirements that are reasonably stricter than prevailing national and international requirements at that time (2013-2014);

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 13

Page 14: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Existing vs. New NPPs (2/3)

Reasons for separating design requirements (cont.):

• the scope of design and analysis activities are different in chase of an exiting unit and a new unit (plant level initial design of new NPPs vs. modification of an existing plant/technology);

• design codes and standards have evolved (Gen II vs. Gen III+);

• some situations that are considered as “beyond design” for existing plants, are considered in the design of new plants (e.g. core melt);

• etc.

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 14

Page 15: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Existing vs. New NPPs (3/3)

There was a need to differentiate design requirements for existing and new NPPs, so after convincing the PR and legal expert community, we created NSC 3. and 3a.

As a result of that, there are significant differences in (among others):

• Concept of Defense in-Depth (DiD);

• Probability based design basis event selection;

• Acceptance criteria;

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 15

Page 16: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Example (1/4): DiD for existing NPP

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 16

Level of DiD

Objective Associated plant condition

categories

1. Prevention of abnormal operation and

failures Normal operation

2. Control of abnormal operation and

detection of failures Anticipated operational

occurrences

3. Control of accident within the design basis DBA (single initiating event)

4.

Control of severe plant conditions, including prevention of accident progression and

mitigation of the consequences of severe accidents

Multiple failures

Severe accidents

5. Mitigation of radiological consequences of significant releases of radioactive material

-

Page 17: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Example (2/4): DiD for new NPP

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 17

Level of DiD

Objective Associated plant condition

categories

1. Prevention of abnormal operation and

failures Normal operation (DBC1)

2. Control of abnormal operation and failures Anticipated operational

occurrences (DBC2)

3.

3.A Control of accident to limit radiological releases and prevent escalation to core melt

conditions

Postulated single initiating events (DBC3-4)

3.B Postulated multiple failure

events (DEC1)

4. Control of accidents with core melt to limit

offsite releases

Postulated core melt accidents (short and long

term) (DEC2)

5. Mitigation of radiological consequences of significant releases of radioactive material

-

Page 18: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Example (3/4): Determination of the design basis

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 18

Plant type

Cut-off frequency values for design basis events

Internal initiating event due to the failure of a system, structure or component,

and/or human error [1/year]

Event resulting from external human activity

typical of the site [1/year]

Frequency of initiating events due to a recurring natural hazards [1/year]

New NPP 10e-6 10e-7 10e-5

Existing NPP 10e-5 10e-7 10e-4

Page 19: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Example (4/4): Acceptance criteria

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 19

Plant type

Acceptance criteria

Loss of heat removal to the ultimate heat sink (primary

and alternative) [1/year]

CDF [1/year]

Collective frequency of

large and early releases [1/year]

New NPP <10e-7 <10e-5 <10e-6

Existing NPP - <10e-4 <10e-5

Page 20: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Practical example (molten core management)

Existing NPP (retrofitted) New NPP

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 20

Source: http://www.world-nuclear-news.org/

Page 21: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Recent and ongoing challenges

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 21

Page 22: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

On the topic of this meeting...

For detailed information regarding experiences and practices in Hungary on the issues of interest please see the presented paper!

It includes:

• new concept of DiD, independence of DiD levels;

• requirements for practical elimination;

• requirements for DBA and DEC analysis;

• requirements on the use of non-permanent safety related equipment.

22-25 June 2015

SAFETY CHALLENGES FOR NEW NUCLEAR POWER PLANTS

22

Page 23: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Interpretation of DEC (new NPPs)

Operating condition

Description Frequency of event

(f [1/year])

DBC1 normal operation –

DBC2 anticipated operational occurrences f >10e-2

DBC2 low frequency design basis accidents 10e-2 > f >10e-4

DBC4 very low frequency design basis accidents 10e-4 > f >10e-6

DEC1 complex accidents without melting of the fuel in the core and the spent fuel pool

<10e-6 (indirect requirement)

DEC2 severe accidents resulting in a significant fuel melting

<10e-6 (indirect requirement)

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 23

„3a.2.2.0400. It shall be demonstrated by probabilistic safety analyses for every design basis accidents that the multiplication product of the frequency of a given initiating event and the probability of failure of any safety function required for meeting the acceptance criteria for DBC4 operating conditions during a transient caused by the given initiating event does not exceed 10e-6/year.”

Page 24: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Determination of design extension

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 24

Frequency of event [1/year]

10e-6 10e-7

DB „design extension” Practically eliminated, if <10e-7 @ „95/95”

Minimum list of events to be considered (requirement)

DEC selection by deterministic analyses supplemented by probabilistic methods and engineering judgement

DEC to be considered in the design

Acceptance criteria (e.g. LRF<10e-6)

Page 25: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Recent safety related challenges

• Multi unit PSA;

• Safety classification of SSCs;

• EPC contract vs. licensees ultimate responsibility;

• „Lessons not learned”;

• Effect of construction on the safe operation of existing units;

• Challenges for the regulatory body;

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 25

Page 26: Experiences of Hungary's new NPP project - Nucleus...Hungary’s new NPP project so far •The idea of NPP extension has been on the agenda since the 80’s (2*1000 MW additional capacity

Thank you for your attention!

Questions?

22-25 June 2015 SAFETY CHALLENGES FOR NEW NUCLEAR

POWER PLANTS 26