Experience from the commissioning of Andasol 3

Dr. Rainer KistnerUTE Andasol 3 / Ferrostaal

E-Mail: [email protected]

Page 2: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

(1) Project Structure / Plant Overview

(2) Different Project Phases

(3) TOP

(4) Partial Commissioning

(5) Commissioning of SF

(6) Commissioning of TES

(7) Further Key Commissioning Milestones

Overview of Presentation

Page 3: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

September 2011 | 3Andasol III

Project Structure

Marquesado Solar

EPC-Contractor

Plant O&M

Royal Decree 661/2007:

48,9%

26%

Project Sponsor

Project Sponsors

Owner

Project Sponsors

25,1%

Investment of foreign strategic investors:

• 100% balance sheet financed by investors

• No bank financing

LSTK

UTE Andasol 3Legal Framework

Financing UTE OPEMASOL

AS3 KWBtlg. GmbH

O&M

Page 4: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Solar Field Heat Storage Power BlockSteam

Heat Steam Power

Plant Overview

Page 5: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Project Phases

Basic Engineering

Detailed Engineering

Procurement

Construction

Pre-Commissioning

Commissioning Start-Up

Overall MC/ RFC

RFSU PAC

MC: Mechanical Completion

RFC: Ready for Commissioning

PAC: Provisional Acceptance Certificate

Page 6: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

From Pre-Commissioning to Hot Commissioning

Pre-Commissioning

Walkdown

Preparation TOP

TOP Sign. Constr. Mang.

TOP Sign. Comm. Mang.

Cold Commissioning

TOP: Turn Over Package *

TOP Sign. Owner / Direct. Fac.

Notifying Body Certificate

Approval by Eng. Chamber

Approval Authority

Hot Commissioning

* Handover protocoll from construction to commissioning

Page 7: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Turn Over Packages

Page 8: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Example TOP Status Summary

Page 9: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

System Breakdown Structure for Solar Field Commissioning

Graph Courtesy of Flagsol GmbH

Page 10: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Example: Hydro-testing of the 152 SF loops

Page 11: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Overlap between Mechanical Completion and Commissioning

Graph Courtesy of Flagsol GmbH

Page 12: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Example: Progress Curves

Page 13: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

TES Commissioning: Salt Melting Process

Salt Handling Station

Salt Melting in Furnace

Buffer Tank with Pump

Pumping toCold Tank

Cold Salt Tank

Page 14: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

TES Commissioning: Temporary Salt Storage Tanks

Buffer for 5.000t Salt BigBags1 tent 30m x 60m1 tent 30m x 70m

Tent for Salt Handling Equipment1 tent 25m x 10m

During melting continuous salt supply.

Page 15: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Temporary Salt Storage Tents

Page 16: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

TES Commissioning: Unloading of salt bags

Page 17: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Salt Handling Equipment

Two parallel lines with working stations for:• Big Bag Transportation• Big Bag Crushing and Opening• Salt Transportation on Conveyor Belts• Salt Milling to desired grain size• Dosing Station to Salt Furnace• Air Filter on working stations

Page 18: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Salt Handling Equipment

Page 19: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Salt Handling Equipment

Page 20: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Crushing of Salt

Page 21: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Salt of the crushing process

Page 22: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Gas fired Furnace with Stack• 20t/h Melting capacity• 5,4MW thermal capacity• 12 Burners• Ca. 570 Nm³/h Gas Consumption• Ca. 28t weight ; 70 t weight filled with salt

TES Commissioning: Melting Furnace

Page 23: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

TES Commissioning: Melting Furnace

Page 24: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Buffer Tank• 8,8m³• Internals for Salt impurity separation• Carbon Steel• Heat traced• Trays for drainage of tank and furnace

SM Pump• 14,3 m³/h; 7,5kW• Vertical suspended Pump to transmit salt to Cold Salt Tank

I&C for control of process (L, P, T) located on Buffer Tank

TES Commissioning: Buffer Tank

Page 25: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Pipeline• Carbon Steel• 8“ Line • Fully heat traced• Inlet to Salt Tank with Vent Hole

TES Commissioning: Connection Line to Cold Salt Tank

Page 26: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

• 1 Operation Manager available 24hours

• 3 Operation Teams working in 12h shifts– 2 Operators

– 1 Shift Responsable.

– 2 Drivers for Forklift

– 4 Workers

• 1 Shift for Salt Unloading 8.00h – 20.00h– 3 Driver

– 1 Worker

• UTE Commissionning Personnel

TES Commissioning: Personal for Salt Melting

Page 27: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Commissioning Milestone: Steamblow

Page 28: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Video2013 06 12 SonnenkolloquiumK öln Vers 2 .3GP

Commissioning Milestone: Steamblow

Page 29: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Commissioning Milestone: 1st synchronization

Page 30: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

Further milestones

• 10 day “Dispatchability Test”

• PAC Performance Test

• Commercial Operation– Interim Performance Test

– Final Performance Test

Page 31: Experience from the commissioning of Andasol 3 · 2013. 6. 19. · Mang. TOP Sign. Comm. Mang. Cold Commissioning TOP: Turn Over Package * TOP Sign. Owner / Direct. Fac. Notifying

September 2011 | 31Andasol III