Upload
others
View
84
Download
2
Embed Size (px)
Citation preview
EXPANSION OF JSW STEEL
16 MTPA to 18 MTPA
PRE-FEASIBILITY REPORT
JSW STEEL LIMITED, VIJAYANAGAR WORKS
AT
TORANAGALLU, DISTRICT BELLARY, KARNATAKA June 2018 Project Proponent
EXPANSION OF JSW STEEL
16 MTPA to 18 MTPA
PRE-FEASIBILITY REPORT
JSW STEEL LIMITED, VIJAYANAGAR WORKS
AT
TORANAGALLU, DISTRICT BELLARY, KARNATAKA June 2018 Project Proponent
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
1
CONTENTS
Sl.No. DESCRIPTION PAGE NO.
1. 2. 3.
4. 5 6. 7. 8. 9.
Executive Summary
Introduction of the Project
Project description Site Analysis Planning Brief Proposed Infrastructure Rehabilitation & Resettlement Implementation schedule & cost estimate Analysis of proposal
1-1 – 1-3
2-1 – 2-8
3-1 – 3-25
4-1 – 4-5 5-1 – 5-3 6-1 – 6-8 7-1 8-1 – 8-4 9-1
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2
List of Figures
Figure no. Details
Fig 3.1 Location of proposed facil ities in the expansion project Fig 3.2 Plant lay out showing the location of proposed facilities Fig 3.3 Process flow for manufacture of finished steel products Fig 4.1 Road and Railway connectivity Fig 6.1&2 Location of proposed expansion of crude steel capacity
List of Tables
Table no.
Details
1.1 New and proposed changes in facilities proposed 1.2 Proposed changes in existing facilities 1.3 List of facilities at 18 MTPA 2.1 India – Steel consumption scenario (Million Tons) 2.2 Major market segments - 2030
2.3 Major market segments - 2030 3.1 Changes/Additional facilities in the proposed project 3.2 Optimization of facilities at 16.0 MTPA stage 3.3 Design basis of Pellet Plants 3.4 Typical analysis of raw materials for pellet production 3.5 Design basis of Blast Furnace 3.6 Typical raw material analysis (Dry basis) 6.1 List of species of plants/shrubs in and around JSWSL 8.1 Cost estimates : 18.0 MTPA expansion of crude steel at Vijayanagar 8.2 Cost estimates : Environmental control measures at 18.0 MTPA
List of Annexures
Annexure no. Details
Annexure 1 Environment clearance for expansion from 10 MTPA to 16 MTPA, Dated : 01.10.2015
Annexure 2 Amendment for Environment clearance for expansion from 10 MTPA to 16 MTPA, Dated : 09.06.2016
Annexure 3 Amendment for Environment clearance for expansion from 10 MTPA to 16 MTPA, Dated : 22.01.2018
Annexure 4 Amendment for Environment clearance for expansion from 10 MTPA to 16 MTPA, Dated : 29.05.2018
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
1-1
1 EXECUTIVE SUMMARY
1.1 INTRODUCTION
JSW Steel ltd, formerly known as Jindal Vijayanagar Steel ltd. (JVSL), is
the flag ship company of OP Jindal group of industries. This integrated steel
plant at Toranagallu is the most modern, technologically efficient, eco-friendly
and the largest integrated steel plant in India.
JSW Steel ltd now intends to enhance the steel manufacturing capacity
approved by MoEF&CC from 16.0 MTPA to 18.0 MTPA and produce a wide
variety of steel products to meet the requirements of the customers. The
expansion facilities will be built within the existing integrated steel plant
complex. With this expansion, JSW Steel will be in a stronger position to supply
a wide variety of steel products to the consumers in south and central India. The
product mix that will be offered by JSWSL will then include semis like billets and
blooms, flat products, long products, wire rods, re bars, light & heavy sections,
and value added cold rolled and coated products.
Over the years, JSWSL has grown from a crude steel capacity of 1.2 MTPA in
1999 to 10 MTPA by 2011. Currently, JSWSL is implementing its expansion plan
of enhancing crude steel capacity from 10 MTPA to 16 MTPA approved by
MoEF&CC vide environment clearance J-11011/489/2009 lA-II(I) dated 01st
October 2015 and subsequent amendments in 9 th June 2016 and 29 th May 2018
(Annexure-1 and Anneure-2). Some of the facil ities which were originally
belonging to JSWSL were developed as new entities with respective core
expertise and the environment clearance was transferred to these companies
vide amendment dated 28th Feb 2018 (Annexure-3).
The original proposal of expansion of crude steel capacity at Vijayanagar from
10 MTPA to 16 MTPA, primarily involved in setting up of two 3.0 MTPA Blast
furnaces like the existing BF 3&4 units which were set up during the expansion
of the steel plant from 4.0 MTPA to 10.0 MTPA.
JSW Steel, Vijayanagar currently has an installed capacity of 12 MTPA crude
steel. During 2017-18, the crude steel production was 11.4 MTPA. As a part of
its expansion program to enhance the capacity to 16 MTPA, JSW Steel is in the
process of setting up additional facilities which will take the crude steel capacity
to 13 MTPA by Dec 2019.
However, with the upgradation of BF-1 and planned upgradation of BF-3 to
country’s largest blast furnace of 5560 m3 BF, the capacity of crude steel is
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
1 EXECUTIVE SUMMARY (cont’d)
1-2
being enhanced from 10 MTPA to 13 MTPA. JSW Steel is currently in the
process of installing a similar Blast furnace of 5560 M3 capacity in India at
Dolvi.
Keeping in view of the advantages of larger blast furnaces and JSW Steel’s own
expertise developed over the years in operating large blast furnaces, it is
proposed to install a large blast furnace of 5560 m3 in place of 4100 m3 blast
furnace proposed in the original project of expansion of capacity from 10 MTPA
to 16 MTPA. With this major change together with optimization of existing and
proposed facilities, the capacity of crude steel is being enhanced from 16 MTPA
to 18 MTPA.
In the proposed expansion, new steel finishing facilities (BRM, WRM and Cold
Rolling complex) and changes in the capacity and configuration of some
production facilities (BF, BOF, EAF, HSM) is being proposed.
The details are given in Table 1-1.
Table 1-1 NEW AND PROPOSED CHANGES IN FACILITIES PROPOSED
Production Facility
1 Pellet Plant-3 of 6.8 MTPA (in place of Sinter Plants 6) & SP-5 of 2.3
MT in place of 1.75 MTPA)
2 Blast Furnace-5 of 5500 m3 volume (in place of 4019 m3)
3 SMS-4 Larger size 350 T BOFs (from 2X200t to 2X350t)
3 Zero Power Furnace (in place of 1.2 MTPA EAF)
4 Hot Strip Mill-3 (enhancement from 3.6 to 5.0 MTPA)
5 Bar & Rod Mill-2(New)
6 Wire Rod Mill -2(New)
7 Cold Rolling Mill -3 of 2.3 MTPA capacity(New)
8 Larger capacity Lime and Dolo Calcining plants (from 8X300tpd to
4X600 tpd) (changes in configuration)
9 Oxygen Plants(new) – 3 nos
10 New ash pond for gypsum(FGD) and bottom ash
Over the years, there have been several changes in the quality of raw
materials, improvements in operational practices and efficient management of
resources by way of efficient use of energy, water and wastes. This has resulted
in necessities to modify some of the existing facil ities by relocation,
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
1 EXECUTIVE SUMMARY (cont’d)
1-3
reconciliation of capacities of production facilities and re configuration with ot
any change in overall capacity of steel making. The details are given in Table 1-
2.
Table 1-2 PROPOSED CHANGES IN EXISTING FACILITIES
Facility Remarks
1 Shifting of OBP-1(dry process) to OBP-2(wet Process)
No change in
overall capacity
There are no changes in all other facilities both existing or those planned under
the 16 MTPA expansion and yet to be executed.
With the above, the list of facilities at 18 MTPA will be as follows and is
presented in Table 1-3.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
1-1
List of facilities as existing now after amendments and those proposed in the expansion to 18 MTPA
Sl
no
Name of the
Unit
Facilities at various stages of expansion in MTPA Total Capacity
(at 16 MTPA)
Facilities
Proposed
(at 18 MTPA)
Total Capacity
( at 18 MTPA) 4 -MTPA
4-10 -
MTPA
10-16 -
MTPA
At 16
MTPA
1 Ore beneficiation
Plant - product
OBP-1
1 X 4.5
OBP-2
1X 2.5 ,
1X 5.0 &
1 X 7.5,
Nil
1 X 4.5
1X 2.5
1X 5.0
1 X 7.5
19.5
OBP-1 facilities to be
Relocated
to OBP-2
19.5
2 Pellet Plants PP1- 1- 5.0 PP-2- 5.0 Nil PP 1 & 2
2 X 5 .0 10
PP-3
6.8 16.8
3 Sinter Plants SP1 SP 2 -2.3
SP 3- 7.5
SP4 -2.3
SP5 -1.75
SP6 -5.75
SP1-6
3X 2.3
2 X 5.75
1 X 1.75
20.15
SP-5: 2.3
SP-6: deferred in lieu
of PP-3
14.95
4 Coke Oven – NR
CO 1 &2
2 X0.64
1.28
Nil
Dismantling of
Existing NR
Coke Oven
0 0 No addition 0
5 Coke Oven –
Recovery type Nil Coke 3 - 1.5 CO 1&2 -1.5
CO 1-5
2X1.5
1X2.0
1X3.0
8.0 No addition 8.0
6 Hot metal –Corex Corex 1 & 2
2X0.8 Nil Nil
Corex 1- 2
2 X 0.8 1.6 No addition 1.6
7 Hot metal-Blast
Furnace
BF-1-2.5
BF-2-2.17
BF 3 & 4
2 X 3.0
BF-3- 4.4
BF-5- 3.0
BF 1 -5
1X 2.5
1X 2.17
1X4.4
2X 3.0
15.07 BF-5 of 3.0 MTPA to
be built as 4.5 MTPA 16.57
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
1 EXECUTIVE SUMMARY (cont’d)
1-2
Sl
no
Name of the
Unit
Facilities at various stages of expansion in MTPA Total Capacity
(at 16 MTPA)
Facilities
Proposed
(at 18 MTPA)
Total Capacity
( at 18 MTPA) 4 -MTPA 4-10 -
MTPA
10-16 -
MTPA
At 16
MTPA
8 Pig Casting
Machines (TPD) 1200 7200 3600 12000 12000 MGP-5000 tpd 17000
9 Crude steel - BOF,
EAF & auxiliaries
SMS1
3.80
SMS2
6.0
SMS2 -6.4 SMS 3 & 4-
5.6
2X200T BOF
+2X1.2 EAF
SMS1-4 1X3.8
1X6.4
1X3.0
1X2.6
15.8
SMS-3: In place of 1
EAF, 1 ZPF is considered
SMS-4 will be changed
from 2 x 200T to 2 x
350T & will operate at
4.8 mtpa
18
10 Lime Kiln (TPD) LCP-1
4x300
LCP-2
4X300
,4X600
LCP-3
4 x 600
LCP 1- 4
8 X 300
8 X 600
7200 No addition 7200
11 Slab Caster 3.2 6.4 SMS-3-1 X1.6
SMS-4-1X3.6
Slab Caster 1-
4
14.8
14.8
SMS-4 slab caster
changed from 1 x 3.6
mtpa to 2 x 2.5 mtpa
16.2
12 Billet caster Nil SMS-2
1.5
SMS-3
3.0 4.5 4.5 4.5
13 HSM HSM 1
1X4.0
HSM-2
1X5.2
HSM-3
1X3.6
HSM1-3
12.8 12.8
HSM-3 upgraded to
5.0 14.2
14 Plate Mill Nil Nil Nil Nil Nil No addition Nil
15 Pipe Mill Nil 0.4 Nil 1X 0.4 0.4 No addition 0.4
16 Wire rod mill Nil WRM-1
1x0.6
WRM-2
1.2
WRM 1-2
1X0.6, 1X1.2 1.8 No addition 1.8
17 Rebar & Section
mill Nil
BRM-1
1X1.0 Nil
BRM-1
1.0 1
New BRM-2 of 1.2
MTPA 2.2
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
1 EXECUTIVE SUMMARY (cont’d)
1-3
Sl
no
Name of the
Unit
Facilities at various stages of expansion in MTPA Total Capacity
(at 16 MTPA)
Facilities
Proposed
(at 18 MTPA)
Total Capacity
( at 18 MTPA) 4 -MTPA
4-10 -
MTPA
10-16 -
MTPA
At 16
MTPA
18 Cold Rolling Mill
Complex
CRM-1- 1.8
CRM-2-2.3 Nil
CRM1&2
4.1 4.1 CRM-3 of 2.3 MTPA 6.4
19 Galvanizing Lines Nil Nil
CGL-1-
4X0.25
CGL-2-
2X0.45 -
CGL 1&2
4X0.25
2X0.45
1.9 No addition 1.9
20 Color Coating Line Nil- 0.5 Nil 0.5 0.5 No addition 0.5
21
Power Plant and
process steam
boilers in MW
CPP 1X100 CPP-2
1X130
all gas
CPP 3 &4
2X300
gas+coal
CPP5-1X660
coal
CPP 1-5
1X100, 1X130,
2X300,1X660
1490 No addition 1490
22 Incinerator (kg/hr) Nil 2 X 250kg/h 250kg/h 2 X 250kg/h 1000kg/h No addition 1000kg/h
23 Slag Grinding and
mixing unit CP-1
1X 0.2 Nil
CP-2 1X2.0
CP-1&2
1X0.2 1X2.0
2.2 No addition 2.2
24 Oxygen Plant (Out
sourced)
1x2500
TPD=2500
TPD
2x1800
TPD +
1X900 TPD
2X1800 TPD
1 X 2500 TPD
10600 TPD 1 x 2060(TP)
2 x 2200 14860 TPD 4 X1800 TPD
1 X 900 TPD
25 Township (nos) 2 Units 2 Units 2 units 6 units 6 units 1 unit 7 units
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2-1
2 - INTRODUCTION OF THE PROJECT
2.1 IDENTIFICATION OF THE PROJECT & PROJECT PROPONENT
India is the 3rd largest producer of crude steel globally with a total crude Steel
Production of over 102 Mt in 2017-18. Indian economy is rapidly growing with
special focus on infrastructure and construction, promoting further growth of
steel industry
JSW Group is a $ 12 bil lion leading conglomerate , with presence across India,
USA, South America & Africa, the JSW Group is a part of the O.P. Jindal Group
with strong footprints across core economic sectors , namely Steel, Energy,
Infrastructure, Cement, Ventures and Sports.
JSW Steel currently has a capacity of about 18 MTPA steel in its three steel
plants located at Vijayanagar(Karnataka), Dolvi(Maharashtra) and Salem (Tamil
nadu). JSW is also planning to enhance its capacity by scaling up existing
plants and planning on install ing new projects to produce 40 MTPA. Globally,
JSW owns a steel plant, plate and pipe mill in the US, and mining assets in the
US, Chile and Mozambique. JSW have integrated cutting-edge technology,
innovation, R&D with sustainability and community initiatives in their journey of
development.
JSW Steel, Vijayanagar currently has an installed capacity of 12 MTPA crude
steel. During 2017-18, the crude steel production was 11.4 MTPA. As a part of
its expansion program to enhance the capacity to 16 MTPA, JSW Steel is in the
process of setting up additional facilities which will take the crude steel capacity
to 13 MTPA by Dec 2019.
The original proposal of expansion of crude steel capacity at Vijayanagar
from 10 MTPA to 16 MTPA, primarily involved in setting up of two 3.0 MTPA
Blast furnaces like the existing BF 3&4 units which were set up during the
expansion of the steel plant from 4.0 MTPA to 10.0 MTPA.
However, with the upgradation of BF-1 and planned upgradation of BF-3 to
country’s largest blast furnace of 5560 m3 BF, the capacity of crude steel is
being enhanced from 10 MTPA to 13 MTPA. JSW Steel is currently in the
process of installing a similar Blast furnace of 5560 M3 capacity in India at
Dolvi. Keeping in view of the advantages of larger blast furnaces and JSW
Steel’s own expertise developed over the years in operating large blast
furnaces, it is proposed to install a large blast furnace of 5560 m3 in place of
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2 - Introduction of the Project (cont’d)
2-2
4100 m3 blast furnace proposed in the original project of expansion of capacity
from 10 MTPA to 16 MTPA. With this major change together with optimization of
existing and proposed facil ities, the capacity of crude steel is being enhanced
from 16 MTPA to 18 MTPA.
2.2 Brief Description of the Nature of the Project
The brief profile of the expansion project is as follows:
Hot Metal 18.17 MTPA
Crude Steel 18.00 MTPA
Saleable products
Hot Rolled Coils/Plates 14.20 MTPA
Cold rolled products 6.40 MTPA
(Cold rolled annealed & galvanized coil,
color coated coil. Tinplate coil, Silicon
steel)
Long Products (Bar, Wire Rod,) 4.00 MTPA
The proposed production of crude steel and subsequent rolling would be
accomplished via Blast Furnace (BF)-Basic Oxygen Furnace (BOF)-Caster
route, followed by hot, cold rolling.
The project falls under category A, Section 3 (a) of EIA Notification
September 2006 and amendment thereof vide Notification No. S.O 3067 (E)
dated 1st December 2009.
2.3 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY
In 2017-18, production of crude steel was about 102.2 MTPA in the country with
a growth of approximately 5.5% over 2016-17. India’s per capita steel
consumption is 61 kg, much lower than the global average of 208 kg. India’s
consumption of finished steel products has grown by
3.4 per cent in 2017-18 compared with 2016-17. With some of the measures
taken by the Government, India has become a net exporter of steel products.
Indian economy is rapidly growing with key focus on infrastructure and
construction sector. Several initiatives mainly, affordable housing, expansion of
railway networks, development of domestic shipbuilding industry, opening of
defense sector for private participation, and the anticipated growth in the
automobile sector, are expected to create significant demand for steel in the
country.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2 - Introduction of the Project (cont’d)
2-3
Major factors which carry the potential of raising the per capita steel
consumption in the country are listed below:
Infrastructure improvement initiatives, such as ‘Smart Cities project’,
'Housing for All by 2022', ‘Atal Mission for Rejuvenation and Urban
Transformation (AMRUT)’,
Manufacturing growth driven by Make-in-India initiative,
Encouraging use of Made in India steel for various projects and
levying of anti-dumping duties on certain steel products from Brazil,
Russia, China, Korea, Japan and Indonesia.
National Mineral Development Corporation expected to increase the
iron ore production favoring steel production
Emergence of the rural market for steel buoyed by projects like
MGNREGS, development of ‘Rurban Clusters’ under the Shyama
Prasad Mukherjee Rurban Mission, Pradhan Mantri Gram Sadak
Yojana, among others.
As per the National steel policy (NSP) 2017, in order to achieve expected
demand of 300 MT and per capita consumption of 160 kg of finished steel by
2030-31, steel demand would need to grow at a CAGR of around 7-7.5 per cent
during the period against a CAGR of 3.5 per cent-4 per cent over the last 5
years. This would mean that capacity additions planned by most of the major
steel players need to come on stream in next few years.
As per NSP 2017, it is aimed to domestically produce value added steel -
products with focus on exploiting the existing iron ore deposits. These factors
would emphasize on the need for the installation of the proposed projects.
2.3 DEMAND-SUPPLY GAP, IMPORTS VS. INDIGENOUS PRODUCTION,
EXPORT POSSIBILITY & DOMESTIC/EXPORT MARKETS
The total consumption of steel is estimated at 81.52 MT in FY16. Driven by
rising infrastructure development, growing demand for automotives and lower
per capita consumption compared to international average, steel consumption is
expected to reach 104 MT by the end of 2017. The consumption of steel during
FY17 (Q1) was estimated at 61.54 MT. World Steel Association (WSA) has
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2 - Introduction of the Project (cont’d)
2-4
projected a growth of Indian steel consumption of 7.1% at 94.91 MT in 2018,
one of the highest growing among the global steel producers.
The projected demand and capacity of finished steel products is as follows:
Overall Steel, MTPA 2025-26 2030-31
Demand 140.0 185.0
Capacity
Current 125.0
Required 185.0 245.0
Deficit 60.0 120.0
Though the country has been traditionally a net importer of steel products all these years, the total export of finished steel increased by 16.7 per cent to 9.621 million tonnes (MT) in 2017-18, as against exports of 8.242 MT finished steel during 2016-17.
The projected demand of consumption of steel products is given below in
Table 2-1
TABLE 2-1 - INDIA - STEEL CONSUMPTION SCENARIO (MILLION TONS)
Item Actual Forecast
2016-17 2020-21 2025-26 2030-31
Crude Steel
Capacity 122 140 185 245
Crude Steel
Production 91 110 150 195
Finished
Steel
Production
80 105 140 185
Domestic
Demand
84 95 125 165
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2 - Introduction of the Project (cont’d)
2-5
Item Actual Forecast
2016-17 2020-21 2025-26 2030-31
Exports 8 10 15 20
The National Steel Policy (NSP) 2017 aims to increase export of steel
and reduce import to nil by 2030. As of March 2017, the capacity utilization of
steel producers is set to increase with strong export demand and signs of revival
in domestic sales.
Steel products find application in multifaceted sectors mainly dominated by
areas of infrastructure & transport. Among the many drivers of demand, the
following are having maximum influence in triggering consumption of finished
steel products like Bars & Rods, Structural and Plates:
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2 - Introduction of the Project (cont’d)
2-6
Product/Category Application
Bars & Rods
Infrastructure - House Building
Fasteners & Wires
Bright Bars
Structural Infrastructure - High rises
Industrial Construction
Plates
Infrastructure – Bridges
Railways - Wagons, Coaches, Tankers
Industrial Construction
Defence Production
Energy - Boilers, Pressure Vessels, Penstocks
HR Products
Tube making industry
Railways - Wagon & Coach
Automobiles
Industrial Machinery
CR Products
White goods - Refrigerators, Air-conditioners
Automobiles
Silos & Containers
Precision Tubes
Furniture
Galvanized,Coated,
Tin Plate, Silicon
Steel (NGO)
Automobiles
Consumer durables
Food Industries
Electrical Appliances & machine
Construction
Packaging & Furniture
The NSP 2017 provides an overview of the segmental composition of the
projected Indian market for the year 2030-31 with quantitative estimates of the
likely demand and their associated growth rates adopted for the study. A
summary of the leading segments of the domestic market is furnished in the
Table 2-2 and Table 2-3 below.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2 - Introduction of the Project (cont’d)
2-7
TABLE 2-2 - MAJOR MARKET SEGMENTS - 2030
Market Segments Demand
(Million Tons) % Share
Infrastructure
(Project Construction) 90 39%
Construction
(Real Estate & Buildings) 45 20%
Engineering & Fabrication 43 19%
Energy 11 5%
Automotive 10 4%
Sub-total
(Major Segments) 199 87%
Other Segments
(Railways, Ship Building,
Defence, Gas Pipelines,
Packaging etc.)
31 13%
Total 230 100%
TABLE 2-3 - MAJOR MARKET SEGMENTS - 2030
Market Segments Annual Growth (%)
Infrastructure (Project Construction) 16%
Oil & Gas Pipelines 11.3%
Defense 9.8%
Automotive 9.7%
2.4 EMPLOYMENT GENERATION DUE TO THE PROJECT
In the construction & operation phases of the proposed project, both
direct & indirect deployment of local work force would be facilitated. The nature
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
2 - Introduction of the Project (cont’d)
2-8
of employment opportunities would involve contractual & casual labor work for
semiskilled & unskilled local skilled staff and direct employment for skilled
locals.
It is estimated that there would be a requirement of around 1200-1500
casual and contract workers, during the phase of construction. Subsequently in
the operation phase, approximately 1200 employees would be directly
employed.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3-1
3 - PROJECT DESCRIPTION
3.1. TYPE OF PROJECT INCLUDING INTERLINKED PROJECT
The proposed project is a brown field expansion project involving the
expansion of crude steel capacity of the integrated steel plant of JSW steel at
Vijayanagar from 16 MTPA to 18 MTPA, within the existing land area available
with JSW Steel. The increase in capacity is being planned by installation of large
capacity Blast furnace and improvement in productivity in some of the existing
manufacturing facilities, with consequent reduction in overall pollution.
3.2. LOCATION
JSW Steel, Vijayanagar is located at Toranagallu, Sandur Taluk, Ballari
district in the state of Karnataka. The existing integrated steel plant of JSW Steel
limited is situated between 15o 10' - 15o 12' N latitude and 76o 38' - 76o 40'E
longitude. The steel plant is located at 29 km from Bellary, 33 km from Hospet
and about 340 km from Bangalore by road. Nearest railway station to the steel
plant is Toranagallu. Broad gauge railway lines between Guntakal and Hubli are
passing through this station. The eastern port of Chennai is 460 km and western
port of Goa is 430 km. A glimpse of the location of the steel plant; lay out of the
plant; photograph of existing plant; location of proposed facil ities in the
expansion project is shown in Fig. 3-1.
3.3. DETAILS OF ALTERNATE SITES CONSIDERED AND THE BASIS OF
SELECTING THE PROPOSED SITE
The expansion of crude steel capacity is being planned by upgrading
capacity of existing blast furnaces during their campaign repair and installation
of a 4.5 MTPA large capacity blast furnace in place of a smaller furnace of 3.0
MTPA. This is a brownfield expansion, within the available land area and utilizing
existing infrastructure. Alternative site was not examined.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-2
FIG. 3-1 - SITE LOCATION MAP
Pla
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-3
3.4. SIZE OR MAGNITUDE OF OPERATION
The proposed project after its completion will facilitate in production of
18.0 MTPA of crude steel along with value added long and flat steel products to
meet the increasing demand of the customers and country`s infrastructure
development. The proposed facil ities wil l be set up in an area of about 450 acres
within the existing steel plant complex.
3.4 LAYOUT
The plant lay out showing the location of the proposed facilities is shown
in Fig-3.2
Fig-3-2 Location of Project site and surrounding 10 km area
3.5. PROJECT DESCRIPTION WITH PROCESS DETAILS
The basis of earlier expansion of crude steel capacity from 10 MTPA to
16.0 MTPA was based on the premise of installing two Blast Furnaces each of
3.0 MTPA. However, the first 3.0 MTPA expansion from 10 MTPA to 13 MTPA
has been realized by augmenting the capacity of BF-1 and BF-3 during their
respective campaign repairs. The BF-1 capacity has been enhanced from 0.9
MTPA to 2.5 MTPA and BF-3 from 3.0 MTPA to 4.5 MTPA by installing the
Country`s largest Blast furnace of 5560 m3, expected to be commissioned by
Dec 2019. JSWSL is also in the process of setting up a similar capacity Blast
furnace at its Dolvi unit, the first such furnace in India.
Considering the advantages of large capacity Blast furnaces, in terms of higher
productivity, energy efficiency and environment friendliness, it is now proposed
to install a 4.5 MTPA Blast furnace in lieu of BF-5 of 3.0 MTPA proposed at the
16 MTPA stage of expansion. This will lead to enhancing the capacity from 13
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-4
MTPA to 17.5 MTPA (in place of 13 MTPA to 16.0 MTPA as proposed earlier).
Further, due to optimization in some of the existing Blast furnaces due to
changes in iron ore quality, the overall hot metal production including from two
Corex units works out to 18.17 Mtpa. Accordingly, it is proposed to enhance the
crude steel production to 18.0 MTPA, as against the 16.0 Mtpa planned earlier.
The proposed production of crude steel and subsequent rolling would be
accomplished via Blast Furnace (BF)-Basic Oxygen Furnace (BOF)/Zero power
furnace(ZPF)-Caster route, followed by hot & cold roll ing for production of flat &
long products. The highlights of the proposed expansion are:
a. Installation of the largest blast furnace of the country to produce
4.5 MTPA of hot metal (in place of a smaller capacity Blast furnace
of 3.0 MTPA proposed in the 16 MTPA expansion)
b. Installation of Zero Power furnace(ZPF), for manufacturing steel
from hot metal & DRI, without use of electrical energy (in place of
Electrical Arc Furnace.)
c. Augment the capacity of BOF from 200 T capacity to 350 T capacity
d. optimization in some of the existing BF units due to changes in iron
ore quality.
e. Installation of 5.0 MTPA HSM in place of 3.6 MTPA unit an new 2.3
MTPA CRM-3
The flowsheet of manufacturing steel is shown in Fig-3.3.(See last page)
The changes or additional facil ities proposed in the expansion and
optimization being carried out in the 16 MTPA units in the propose project to
produce 18 MTPA of crude steel and associated finished products are given in
Table 3-1. and Table 3-2. However, there are no changes in the overall
capacities of following units as proposed in the 16 MTPA stage even at 18.0
MTPA stage.
1. Ore Beneficiation plant : 19.5 MTPA
2. Coke ovens : 8.0 MTPA
3. DRI(Gas based) : 1.2 MTPA
4. Lime Kilns : 7200 tpd
5. Water allocation : 72 MGD
6. Thermal Power Plant : 1490 MW
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-5
TABLE 3-1 – CHANGES / ADDITIONAL FACILITIES IN THE PROPOSED
PROJECT
Facility Capacity,
MTPA
1 Pellet Plant-3, in place of Sinter Plants 6 of 5.75 MTPA) 6.8
2 Sinter Plant of 2.3 MTPA in place of SP-5 of 1.75 MTPA
Additional
0.55 MTPA
3 Blast Furnace-5 of 5500 m3 volume (in place of 4019 m3)
Additional
1.5 MTPA
3 SMS-4 Larger size BOFs(2X200t to 2X350t)
Additional
2.2 MTPA
4 Zero Power Furnace(in place of 1.2 MTPA EAF)
No change in
capacity
5 Hot Strip Mill-3 (enhancement from 3.6 to 5.0 MTPA)
Additional
1.4 MTPA
6 Bar & Rod Mill-2(New) 1.0
7 Wire Rod Mill -2(New) 1.2
8 Cold Rolling Mill-3 (New) 2.3
9 Oxygen Plant(New)
1 x 2060 tpd
2X2200 tpd
10 Ash Pond for Gypsum (FGD) and bottom ash 1 unit
TABLE 3-2 – OPTIMISATION OF FACILITIES AT 16.0 MTPA STAGE
Facility Remarks
1 Relocation of OBP-1 to near OBP-2
No change in
overall capacity
2 Shif ting of OBP-1(dry process) to OBP-2(wet Process)
No change in
overall capacity
3 Larger capacity Lime and Dolo Calcining plants (from
8X300tpd to 4X600 tpd)
No change in
overall capacity
The production facilities would be adequately supported by necessary
modifications if required in the auxiliary facil ities such as raw materials unloading
and storage, proportioning of raw materials, electric power receiving and
distribution stations, various utili ty facilities, water treatment and distribution
system, etc.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-6
The following write-up gives the details of the additional/modified process
units which are being proposed in the 18.0 MTPA expansion.
3.5.1 Ore Beneficiation Plant: There are two Ore beneficiation plants existing
with a capacity to produce 19.5 MTPA of iron ore concentrate. The OBP-1, which
was installed during the 4.0 MTPA stage of steelmaking was based on dry
grinding of iron ore in three ball mills to produce green pellets. In view of heavy
dust pollution during grinding, all the new beneficiation units installed in the
OBP-2 area were based on wet grinding. The slurry after grinding is thickened
and filtered in special filters to produce pellet feed for the pellet plant.
The OBP-1 unit with dry grinding is planned to be shifted to OBP-2 area with
wet grinding. The iron ore concentrate slurry is pumped to PP-1, where the slurry
is f iltered and used for pellet production. The proposal is to shift the unit to OBP-
2 area. There is no change in the overall capacity of the OBP units, which is 19.5
Mt of beneficiated product.
3.5.2 Pellet Plant
The blast furnace burden will comprise of 42.5% sinter. 37.5% pellet and
20% C-Ore. Pellet is also required for production of DRI in the gas based DRI
plant and as feed material in Corex 1&2. Currently the existing PP-1&2 have an
installed capacity each of 5.0 MTPA and are producing pellets at a rate of 4.0
MTPA each. To meet the total requirement of pellets at 18.0 MTPA stage, it is
envisaged that one pellet plant of 6.8 MTPA capacity would be installed. Pellet
requirement for DR plant, Corex and blast furnaces would be met from these
three pellet plants. The new large capacity pellet plant is being built in lieu
of Sinter Plants 5 & 6, to reduce pollution from sintering process.
Design basis: The design basis considered for pellet plant is given in
Table 3-3.
TABLE 3-3 - DESIGN BASIS OF PELLET PLANTS
Item Value
Number of units, Nos. 1
Gross pellet unit, MTPA 6.8
Screening, % - at BF stock house 10
Operating days/year 350
Grate area4(w) X 204(L) M2 816
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-7
No of Balling discs for green pellet/dia 14Nos /
7.5M Dia
Fuel Used/CV Mixed Gas
1850
Kcal/Nm3
Hood exhaust volume m3/h 28,00,000
Wind box exhaust volume m3/h 13,00,000
The typical analyses of input raw materials (dry basis) for pellet
production are given in Table 3-4.
TABLE 3-4 - TYPICAL ANALYSIS OF RAW MATERIALS FOR PELLET
PRODUCTION
Fe SiO2 Al2O3 CaO MgO LOI
% % % % % %
Iron ore
concentrate
>62 4.0 3.2 1.75 0.6 4
Limestone 0.2 2.5 0.51 49.8 2.8 43.80
Dolomite 1.38 1.67 0.35 32.84 17.72 44.86
Lime - 0.64 0.25 95.00 1.54 3.00
Flue dust 43.13 5.66 3.68 9.44 1.42 16.48
Coke breeze 0.40 7.10 4.26 0.80 0.60 82.84
The indicative chemical analysis of pellet produced would be as follows:
Fe, % .. >62%
CaO/SiO2 ratio .. 0.35%
Al2O3, % .. 3.2
MgO, % .. 0.60
The envisaged physical and metallurgical properties of sinter would be as
follows:
Size range .. 6 - 19 mm Compressive strength .. 250 kg/pellet Tumbling index
+6.3 mm .. 92% -500 micron .. 6%
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-8
The pellet plant would comprise following facilities:
- Slurry storage and filtration units
- Storage and handling of iron ore and return fines
- Storage, handling and preparation of coal, dolomite and bentonite
- Proportioning and mixing
- Balling for production of green pellets
- Induration and cooling
- Product screening
- Product pellet storage
- Auxiliary facilities laboratory etc.
- Process and Plant de-dusting system
- Cranes, hoists and elevator
- Plant electrics
- Instrumentation and Level- 1
- Plant communication system
- Utility system
- Air-conditioning and ventilation system
- Fire fighting system
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-9
3.5.3 Blast Furnace
The requirement of hot metal for Steel Melt Shop at 18.0 MTPA would be
around 18.17 MTPA. The hot metal will be met from the following units:
- Corex1&2 : 1.6 MTPA (installed in inception of the plant)
- BF-1 : 2.5 MTPA (Upgraded during campaign repair)
- BF-2 : 2.17 MTPA (Installed at 4 MTPA stage)
- BF-3 : 4.4 Mtpa (To be upgraded in 2019 from 4019 m3
to 5360 m3)
- BF-4 : 3.0 MTPA
- BF-5 : 4.5 MTPA (Planned to install in l ieu of 3.0 MTPA unit)
The blast furnace BF-3 and the new BF-5 (in lieu of small BF of 4019 m3)
would incorporate all the modern technological features. The design basis of
blast furnace is given in Table 3-8.
TABLE 3-5 - DESIGN BASIS OF BLAST FURANCE
Item BF-5 at 16
MTPA
BF-5 at 18
MTPA
No. of furnaces 1 1
Volume, cu m (approx.) 4019 5,360 (U.V)
Operating days 350 350
Burden:
Sinter, % 80 42.9
Pellet, % 10 37.6
Ore, % 10 19.5
O2 enrichment, % 8 8
Coke rate (including nut), Kg/thm 332 360
Coal rate, Kg/thm 200 220
Slag rate, Kg/thm 340 400
Coke ash, % 11.8 11
Si in metal, % 0.56 0.4 to 0.7
Capacity of TRT in MW 12 27
No of cast houses 4 4
Blowers (2W+1SB) m3/min 6600 9000
Slag granulation capacity in ton per min 6 8
Design of dust catcher Cyclone Cyclone
Cast House FE system (2 ns) each 900000 1200000
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-10
Stock House De-dusting system m3/h 7,56,000 15,05,000
The major raw materials for blast furnace comprise iron ore, sinter, pellet,
additives and coke from the Coke dry quenching unit. Pulverized coal would be
injected through tuyeres as auxiliary fuel in blast furnace. The typical analysis of
raw materials envisaged is given in Table 3-9.
TABLE 3-6 - TYPICAL RAW MATERIALS ANALYSIS (DRY BASIS)
Fe SiO2 Al2O3 CaO MgO
% % % % %
Sinter 53- 53.8 5.5-5.8 3.1-3.3 11.5-12.5 2.1-2.2
Pellet 61.5-62.5
4-4.5 3.0-3.3 1.3-1.7 0.4-0.6
Sized ore 62.0-63 3-4.0 3.0-3.8 0.4-0.6 0.3-0.6
Quartzite 0.5-1.5 94-96 0.5-1.5 0.2-0.3 0.2-0.3
Limestone 1-2 6-8 1-2 40-48 1.5-2.5
Dolomite 0.8-1.5 8-10 1-2 27-29 17-20
The plant comprises following facilities:
- BF proper
- Cast house
- Slag granulation plant
- Hot blast stoves
- Gas cleaning plant
- Stock house and charging system
- Hot metal handling system
- Cranes and hoists
- Coal dust injection system
- Hot metal granulation and ladle repair shop
- Stock house & Cast house de-dusting system
- Air blowing system
- Plant electrics
- Instrumentation, automation and control system
- Communication system
- Water system
- Utility system
- Fire fighting system
- Air conditioning and ventilation system
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-11
The granulated BF slag would be used for manufacture of cement by JSW
Cement.
The profile of the 3.0 MTPA and 4.5MTPA Blast furnaces are given below
Profile of BF-5 (3.0 MTPA) Profile of BF-5 (4.5 MTPA)
3.5.4 STEEL MELT SHOP
Currently, JSW Steel has three Steel melt Shops.
SMS-1: The shop had 3 BOF converters of 130 T capacity, which has been
upgraded by modifications in lining design to produce 132 T per heat, thus
producing 4.0 MTPA of liquid steel.
SMS-2: The shop had 4 BOF converters of 175 T, which has been upgraded by
volume enhancement to 180 T per heat, thus producing 6.4 MTPA of liquid steel.
SMS-3: The shop has one EAF of capacity 150 T to produce 1.2 MTPA of liquid
steel. EAF utilizes DRI and hot metal to produce liquid steel. There is a provision
for another similar EAF at the 16 MTPA stage and is yet to be constructed.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-12
To handle the additional quantity of hot metal due to enhancement of capacity of
BF-5, the following changes are proposed at 18 MTPA stage.
SMS -1 & 2: No change
SMS-3 : The EAF-2, which is yet to be installed is proposed to be changed to
Zero Power Furnace(ZPF). This is like EAF but utilizes a larger portion of hot
metal and less DRI. The electrodes are dispensed away and the energy for steel
making is provided by oxygen injection. This unit has capability to produce 1.5
MTPA of l iquid steel from each shop. The details of EAF, currently operational
and the proposed ZPF is given below in Table 3.
Sl.No Descriptions UOM EAF ZPF
1 Heat Size Ton 160 160
2 HM Input % 42 80-85
3 DRI Input % 52 15-20
4 Tapping Temperature deg.cen 1610 1630
5 Metallic Charge t/heat T 203 181
6 Hot Metal t/heat T 85 148
7 Hot Metal t/day T 2250 4,744
8 Coolant (gas based DRI) t/heat T 106 33
9 Coolant (gas based cold DRI) t/day T 2650 1,041
10 Electrical Energy Consumption kWh/tls 275 0
11 Oxygen Consumption Nm3/tls 42 60
12 Electrode Consumption kg/tls 1.07 0
13 Burnt Lime & Dolo Lime kg/tls 88 100
14 Slag kg/tls 320 163
15 Oxygen Blowing min 37.4 37
16 Production time/EAF Day/Year No of Days 320 320
17 Yearly Production/EAF Mtliq/year MTPA 1.5 1.5
18 Type of Lance SIS3.0 SIS 4.0
19 No of Lance No 4 5
20 Total oxygen blowing capacity Nm^3/Hr 12000 20000
21 Tap to Tap time Mins 52 50
22 Primary & Secondary FE System m3/h 25,00,000 28,00,000
SMS-4: In the 16 MTPA stage expansion, this shop was designed to have 2X200
T BOF Converters to produce 2.6 MTPA of liquid steel. With the necessity to
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-13
handle additional hot metal, the size of the BOF Converters has been enhanced
from 200T to 350 T. The 350 T BOF can feed liquid steel to slab caster for higher
productivity.
The technical details of 200 T BOF as proposed earlier at 16.0 MTPA and 350 T
BOF as proposed now at 18 MTPA is given in Table 3-
SMS-4 (at 16.0 MTPA)
SMS-4 (at 18.0 MTPA)
1 No. of converters installed 2X200 2X350
2 Converter operation, days/year 330 330
3
Liquid steel production per day, tons Considering converter availability and utilization, No. of converters operating
10400 18200
4 Liquid steel production per day per operating converter, tons
5200 9100
5 Average tap-to-tap time(min). 50 50
6 No. of heats/day/converter 26 26
7 Liquid steel required per heat, tons
200 350
8 Selected heat size, tons liquid steel
200 350
9 Type of ladle for hot metal transport
Torpedo Torpedo
12 GCP wet or dry Wet GCP Dry GCP
13 Capacity of GCP 300,000Am3/hr 500,000Am3/Hr
14 Secondary FE system, volume 50,00,000 Am3/hr 55,00,000 Am3/hr
15 Gas holders nos and capacity (one)
50000m3 100000m3
16 No of boosters & capacity 2w+1 stand by 3w+1 stand by
Casters 4 2
17 Slab caster; capacity & size
two 1600 mm casters
two 2200 mm twin slab caster
Slab Caster details
19 Heat size, tcs 200 T 350 T
20
Reference slab size for calculation
1200-2200, 800-1600
900-1650
21 Reference casting speed, m/min. .8-2.2 1-2.4meter /min
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-14
22 Throughput, tons/min. 4.5T/Min per strand 9Tons
23 Average casting time, min. 55min 50 min
24 No. of heats in sequence 6 heats to 75 heats
3 heats to 40 heats
25 Preparation time, min. 90min 90 min
3.5.5 Lime Calcining Plant
At 16.0 MTPA production stage of crude steel, it was envisaged that eight
lime Calcining plant and dolomite calcining plant of
300 TPD would be installed to produced calcined lime and dolo, sufficient to
cater to the demand of calcined lime/dolo of the steel melt shops. However,
considering the advantages of 600 tpd kilns, the configuration will be changed
from 8X300 tpd to 4X600 tpd. It may be noted that the 600 tpd TSR kilns of
Cimprogetti was installed for the first time in the world. Over the years, the
technology has been perfected by JSW Steel.
3.5.6 Rolling Mills
The following mills would be installed with production capacities as
follows:
Mills No. and capacity
Hot Strip Mill (HSM-3) 1 x 5.0 MTPA in l ieu of earlier 3.6 MTPA
Rebar mill (BRM-2) 1 x 1.2 MTPA (New)
Wire rod mill (WRM-2) 1 x 1.2 MTPA (New)
Cold Rolling Mill(CRM-3) 1 x 2.3 MTPA (New)
Hot Strip Mill (HSM): Each hot strip mill would be designed for a
production of 5,000,000 tons/year of HR coils.
Input: Cast slab would be used as input for the hot strip mill.
Width, mm .. 800-2200
Thickness, mm .. 230
Length, mm .. 11,000
Unit weight (max), kg .. 40,000
Finished product: The HR coil size would be as follows:
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-15
Width, mm .. 800-2050
Thickness, mm .. 1.2 – 25.0
Coil weight (max), ton .. 40
Mill yield, % .. 98
Each hot strip mill would comprise of the following facilities:
- Walking beam type reheating furnaces
- Primary hydraulic descaler
- One (1) 2-Hi roughing stand with attached edger
- One (1) 4-Hi roughing stand with attached edger
- Crop shear
- Secondary hydraulic descaler
- Seven(7) 4-Hi finishing stands
- Run-out roller table
- Laminar cooling system
- Down coilers
- Walking beam coil conveyor system
Double Side Trimming Shear
• Slitting shear
• Dividing Shear
• Cold Plate Leveller
• Pile transfer
• Heat treatment facilities
Rebar Mill(RBM): The rebar mill would be designed for production of
1,200,000 tons/year.
Input: Continuously cast billets of following size would be used as input to
the rebar mill:
Section, mm .. 150 x 150
Length, mm .. 12000
Finished product: Output from rebar mill would be as follows:
Size .. 8-40 mm dia. rebars
Cut to length .. 6-12 m
Mill yield, % .. 97
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-16
The mill would comprise of the following major facilities:
- Billet Charging grids
- Walking beam type reheating furnace
- Roughing train and intermediate train
- Shears
- No twist blocks
- Water boxes and troughs
- Cooling beds with high speed entry equipment
- Cold shear
- Chain transfer
- Bundle strapping machines
- Bundle unloading stations
Wire Rod Mill(WRM): The Wire rod mill (WRM) would be designed for
production of 1,200,000 tons/year.
Input: Continuously cast billets of following size would be used as input
to the WRM:
Section, mm .. 150 x 150
Length, mm .. 12000
Finished product:
Size .. 5.5-20 mm dia
Mill yield, % .. 97
The mill would comprise of the following major facilities:
- Charging grids
- Walking beam type reheating furnace
- Descaler
- Single strand high speed roughing mill
- Double strand intermediate mill train
- Shears
- Pre-finishing mills
- Wire rod blocks
- Reducing and sizing blocks
- Water boxes and troughs
- Laying heads and pinch rolls
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-17
- Air cooling conveyors
- Reform station with ring distribution
- Coil conveyor
Cold Rolling Complex: an identical cold rolling mill complex like CRM-2
would be installed to produce cold rolled annealed, galvanized coils. The
complex would comprise of the following process units:
3.5.7 Cement Grinding Unit
The additional granulated slag generation will be about 0.8 MTPA. JSW
Cement has surplus capacity at their Vijayanagar Plant to consume this amount
of slag for Portland slag cement making. The clinker required to produce cement
would be procured from outside the plant.
3.5.8 Captive Power Plant
JSW Steel has following facilities for a total generation of 936 MW.
- Captive thermal power plants:
CPP-1 : 100MW,
CPP-2 : 130 MW
CPP-3&4 : 600 MW
CPP-5 : 660 MW (to be installed later)
TRTs of BF1,3&4: 30 MW
CDQ : 76 MW
Further the following power generating units are being installed
CDQ : 98 MW (CDQ of Coke 5&6(rebuilt battery of Coke1&2)
TRT : 42 MW (27 MW from BF-5 & 15 MW incremental of BF-4)
Total : 1076 MW Gross. Net 975 MW
The electrical power requirement at 18 MTPA stage has been worked out to be
1412 MW. The balance electrical power will be met from JSWEL which has an
installed capacity of 860 MW. To have stability of the system, the power system
will be connected to the grid and in case of any shortage, it wil l be drawn from
the grid. JSWSL has an approval for a CPP-5 of 660 MW thermal power plant at
16 MTPA stage of expansion. This facility wil l be set up later.
3.6 RAW MATERIALS
Sources of Raw Materials
The probable sources of major raw materials (indigenous/imported) for
meeting the production requirements are given below.
Major Raw Materials Mode of transport
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-18
Iron ore fines/lumps/CLO Rail/Road/ Pipe conveyor
Coking coal Sea/Rail/Road
PCI coal Sea/Rail/Road
Limestone(SMS grade) Sea/Rail/Road
Fluxes Rail/Road
Other additives Sea/Rail/Road
The plant would produce both long and flat products, which would have
potential for sale in national as well as international markets.
The estimated annual requirements of major raw materials at 18.0 Mtpa is
presented below.
Sl.
No. Major Raw materials
Estimated
Quantity, tons
1 Coking Coal 8,340,000
2 Iron ore (Lump) 7,310,000
3 Iron ore fines (Medium grade) 24, 100,000
4 Iron ore fines(High grade) 1,500,000
5 PCI coal 3,320,000
6 Limestone 6,350,000
7 Dolomite 3,500,000
8 Steam coal 1,500,000
9 Bentonite 150,000
10 Quartzite 370,000
11 Pet Coke for Coke ovens 900,000
3.7 RESOURCE OPTIMIZATION/RECYCLE & REUSE ENVISAGED IN THE
PROJECT
The plant has been designed with state-of-art technology for optimum
consumption of energy & other resources. By product fuel gases would be
reused within the plant as in-plant fuel and also to produce power in the CPP.
Corex gas/Coke oven gas would be used as reductant to produce DRI. In
addition, adopting a compact layout for the Plant would enable to optimise the
utilisation of land, which is another critical resource. By utilising the fines and
scrap generated during the process within the plant for the production process,
usage of raw materials is optimised. Water consumption would also be optimised
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-19
by treatment of water to the extent possible and recycle of treated water as
make-up in the network. Solid byproducts would be reused to the extent feasible.
BF slag and fly ash would be used to produce cement in captive cement
manufacturing unit.
3.8 AVAILABILITY OF WATER AND POWER
Water
JSW Steel receives the make-up water from two sources, viz Tunga
Bhadra Dam (32 MGD through pipeline of 35 KM) and Alamatti dam (40 MGD
through a pipeline of 178 Km). This allocation of a total of 3,30,000 m3/day was
obtained during the expansion of the steel plant from 4.0 MTPA to 10.0 MTPA. In
the expansion of capacity from 10MTPA to 16 MTPA, no additional allocation
was sought.
The total water requirement at 18 MTPA will be as under:
Steel plant : 1,44,000 m3/d
Captive power plant & JSWEL : 93,000 m3/d
Township : 24,000 m3/d
Losses & Evaporation : 40,000 m3/d
Total for JSWSL complex : 3,01,000 m3/d
The recovery of water from the existing seven RO Plants is 22,000 m3/d.
Further, additional 8400 m3/d of RO permeate will be recovered from the ZLD
plant of Coke-5 and a centralized RO plant.
JSWSL has established a Total water management approach, as a result the
water is extensively used by cascading from one process to another, ensuring
zero discharge plant. The existing water allocation of 3,30,000 m3/d is sufficient
to meet the requirements of the expansion up to 18.0 MTPA stage.
3.9 Power
The estimated power requirements of various plant units including utilities
and auxiliary facilities for the Plant at 18.0 Mtpa works out 1412 MW. The
available power from captive and from JSWEL is 1735 MW. Thus, there is
adequate availability of power for the steel plant operations at 18 MTPA stage.
DG sets of adequate capacities are proposed for the plant units as well as
CPP auxil iaries to cater to the requirement of safe shutdown and safety of
personnel during total black-out condition when power supplies to plant network
from both the sources viz. grid and CPP have failed.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-20
3.10 WASTE GENERATION AND MANAGEMENT
3.10.1 Wastewater generation & Management
Currently, the integrated steel plant complex of JSW Steel, at Vijayanagar
is a Zero Liquid Discharge plant, the only steel plant of this in the world. This has
been achieved through the following measures
- Technologies which conserve water
- Recycle of > 95% treated water back into the process after treatment
using specialty chemicals.
- Cascaded use of water where blow down from one unit is used as
make up in another unit
- Reuse of treated sewage as industrial make up
- Recover good quality water by installing RO Plants. Till now 7 RO
plants are in operation recovering 21,000 m3 of water per day.
- ZLD Plants with a combination of RO plant with evaporator for 100%
recovery of water.
- Use of high TDS water in quenching applications.
It is estimated that about 1000 m3/h of waste water and blow down water will be
generated in the proposed expansion to 18 MTPA stage. This wastewa ter will be
treated in the following units:
- A 300 m3/h ZLD Plant at Coke ovens to treat treated waste water from
BOD Plant to achieve zero liquid discharge.
- Two RO Plants to recover RO permeate, each of 500 m3/h, one near
OBP and another near SMS-4. The RO rejects will be used in slag
quenching and dust suppression in RMHS.
It is proposed to have ZLD at 18 MTPA stage of the plant, preventing any
pollution of the receiving environment.
3.10.2 Solid Waste Management
The estimated generation of major solid wastes at 18 MTPA stage is
tabulated below:
Solid wastes Expected
generatio
n at 18
MTPA
Management Scheme
MTPA
BF Slag 7.2 Granulation in Slag granulation plant of
BFs and used in cement manufacturing
in JSW cement plant. About 3% of the
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-21
BF slag would be air cooled and used
for construction sector after processing
to different sizes.
Steelmaking
Slag (*)
3.6 Recovery of metallics for in-plant use.
Balance utilized as construction
aggregate, after processing.
Dusts and
sludge(**)
1.70 Reuse in Agglomeration or steel
making area.
Fly Ash 0.50 Currently used in cement making. Will
be continued.
(*)Measures planned for steel slag: There are three types of steel slag
generated in the steel making processes. a. Hot metal treatment slag with high
Sulphur and metallics, b. Converter slag/EAF slag during steel making and c.
ladle furnace slag. One of the major problem with steel slag usage till recently
was mixing of all types of slag, rendering no utilization.
JSWSL has initiated measures to separately dump and treat the slag for their
gainful utilization. HMDS slag is treated for removal of metallics and the
nonmetall ic portion containing lime is used in sinter plant. The ladle furnace slag
is separately treated and is proposed to be briquetted for recycling a portion in
steel making as ladle additive. The balance portion is used in cement making as
a raw material. JSWSL is currently installing these plants both at
Dolvi and at Vijayanagar.
The steel making slag from BOF contains free lime and needs to be treated for
its removal. Such a process is called weathering. Traditionally natural
weathering takes 2-3 years, where as accelerated weathering takes 3-4 months.
JSWSL has developed a technology of steam aging in large pits wherein the
process of weathering is completed in 10 days. The product meets the
specification for aggregates. Further to avoid making large pits and to wait for 10
days, JSWSL is introducing a new technology called steam box type which can
weather steel slag within 10-12 hours within the slag bay itself. Such facilities
are being installed at Vijayanagar and at Dolvi at an estimated cost of Rs 200 cr.
The SMS-4 proposed in the expansion will also have this technology
(**) Dust and sludge:
Following technologies have been developed and implemented at Vijayanagar
for recycling of dust and sludge.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-22
Mill scale briquetting: A mill scale briquetting plant of 800 tpd has been set up
to recycle iron bearing sludge and dust like DRI, ARP fines, mill scales etc to
high strength briquettes using molasses as the binder. BOF converters. Thus the
recycle skips two processing stages and has huge economic benefits. The
additional volume of such dust generated in the proposed expansion processed
in this facility.
Micro pellet plant: A micro pellet plant of 0.6 mtpa has been set up to process
dust and sludge of medium iron and lime values by converting them to micro
pellets. The micro pellet in sinter plants, which otherwise could not handle such
micro fines due to problem of permeability and high dust emissions.
The process involves mixing all dust and sludge to bring in homogeneity and a
moisture level of about 12%. The mixture is granulated in a high intensity
gyratory type mixer. The micro pellets are cured and used in sintering process.
This unit is being expanded to enhance the capacity to treat the dust and sludge
generated in the proposed expansion to 18.0 MTPA
Waste to wealth plant: A waste to wealth plant of 1500 tpd has been set up to
process dust and sludge of low iron and carbon values by beneficiation. The
concentrate is used in pellet plant, and the low value is sent to existing slime
pond. Such dusts cannot be handled in micro pellet plant as they tend to lower
the Fe values in sintering. It is proposed to install a similar unit to process the
dust and sludge generated in the proposed expansion.
Besides the above, there would be other solid wastes like refractory and plant
debris etc. generated from the proposed steel plant. While some of these can be
recycled in the process, others would be disposed off in environmentally friendly
manner. The hazardous wastes like oily wastes, chrome sludge from CRM, salts
from ZLD unit shall be disposed through authorized re-processors or landfilled.
With these measures, it is proposed to utilize all dust and sludge for recycling.
3.10.3 Air Pollution
Various process operations would generate particulate dusts, volatile
organic carbons (VOCs), oxides of sulphur and nitrogen and carbon dioxide to
the environment. The emission would be from the stacks as well as there would
be fugitive emission of dusts from open & closed areas.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-23
Fugitive dust emissions generating from the handling and stockpiling of
raw material in open stockyards would be controlled by water sprinkling at
regular intervals. All closed zone working areas such as raw materials handling
zone, conveyor transfer points, dust generation points at screen would be
provided with dust extraction (DE) systems/dry fogging (DF) at several emission
points to control the fugitive dust emissions. DE system shall consist of suction
hood followed by bag filter / ESP, ducts, extraction fans and stack of appropriate
height.
Coke oven: Emissions from coke ovens would mainly result from coal
charging and coke pushing. Fugitive emissions may result from various
leakages from oven doors, charging lids, ascension pipe (AP) covers etc.
Charging emissions would be controlled by High Pressure Liquor Aspiration
(HPLA) injection in goose neck during charging. Coking emissions would be
controlled by efficient sealing of oven doors, water sealing arrangement of AP
cap etc. Land based fume extraction system would be adopted for charging and
pushing emission control. The hot coke would be quenched by coke dry
quenching (CDQ) with recovery of sensible heat for steam generation.
The raw coke oven gas (COG) would be cleaned in by-product recovery
plant with recovery of tar, ammonia and sulphur to make it suitable for use as
plant fuel and as reductant in the DR plant.
Sinter plant: The conventional air pollution systems like DE systems of
sinter stock house based on electrostatic precipitator (ESP) and waste flue gas
cleaning by ESP would be considered. The particulate dust emission from the
product sinter screening units would be controlled by DE systems complete with
duct, fabric filters and stack of adequate height.
Pellet Plant: Emissions from Pellet Plant would be from Induration Process,
which are controlled by installation of Bag Filter / ESP with adequate height of
chimneys.
Blast furnace: In addition to cleaning of BF gas in wet gas cleaning plant
(GCP), which is a process requirement, the main sources of air pollution would be
stock house and cast house. The BF stock house would be provided with DE
systems complete with dust extraction hoods, ESP/ Bag Filter, ID fan and stack of
adequate height. Similarly, the cast house would have separate fume collection
system during tapping of hot metal and slag, would be equipped with FE systems
along with bag filter/ESP for separation of particulates before venting through a
stack of appropriate height.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-24
Heat recovery from stove waste gas shall be installed for preheating of BF
Gas and combustion air for stoves.
Lime/dolomite Calcining Plant: The emissions arising due the fuel burning
in l ime calcining plant would be collected and taken through a bag filter to separate
out the lime/dolo fines. The lime/dolo fines thus collected would be recycled to the
sinter plant. The kilns in the calcining plant and other dust generation areas would
be provided with separate DE systems, complete with bag filters and stack of
adequate height to clean the particulates.
BOF: Besides BOF gas cleaning, which is basically a process necessity,
secondary emissions would be generated mainly from charging and tapping
operations. The secondary emissions of the steelmelt shop would be controlled by
providing dry ESP.
Ladle Furnace: The primary emissions of LF would be collected by fume
extraction (FE) devices. Dust laden fumes would be indirectly cooled and cleaned
through a bag filter for separation of particulates and the clean gas would be vented
into the atmosphere through a tall stack of adequate height. The secondary
emissions would be controlled through canopy hood extraction, which would be
integrated with the main system to clean the fugitive emissions during charging and
tapping operations. The gas cleaning system would be complete with water cooled
duct, fume and gas cooler, bag house, ID fan and stack of appropriate height.
Caster Area: The water required for cooling the hot cast slabs and bil lets
would generate hot fumes comprising mainly water vapour, hot waste water and
suspended particulates. The slab casting area would be provided with adequate
ventilation in order to have the water vapour properly dispersed.
Rolling Mills: Burning of the by-product fuel gases in reheating furnace
would give rise to the emissions of particulates, SO2 and NOx. NOx emissions
would be controlled by optimizing the excess air supply and proper burner design.
In addition, fume extraction (FE) system would be installed. The flue gas, which is
clean, would be vented through a stack of adequate height after heat recovery.
Cement Grinding Unit: The cement grinding unit would comprise of
raw material storage, handling and feeding facilities, mill system and finished
product storage, handling and packing facilities. The main sources of air
pollution would be fugitive dust emissions from the raw material & product
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-25
handling units, dust emission from the mill exit dust laden gas and SO2 & NOx
emission from the hot air generator. The raw material and product handling
facilities would be equipped with dust extraction systems comprising of bag
filters. The mill exit gas containing particulate matter wil l be passed through a
bag filter to capture dust.
Captive Power Plant: The surplus by-product fuels gases and steam
coal would be burnt in the boilers for generation of power. The flue gas thus
generated from the boiler would be vented through stack of appropriate height.
ESPs would be provided to capture the fly ash generated by the coal fired
burners. Power would also be generated from CDQ, TRT and process steam
from sinter cooler.
Highlights of air pollution: the following are the highlights being planned
in the proposed expansion:
a. Emission standards in line with EU standards
b. Design limit for dust emission from bag filters -< 10 mg/nm3
c. Additional high-performance bag filters in all sinter plants, with
emission limit of < 10 mg/nm3
d. High efficiency ESPs in pellet plant to limit dust to < 10 mg/nm3
e. Switching over to highly polluting sinter plants (SP-5 & 6) to pellet
plant.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production PRE-FEASIBILITY REPORT
3-1
List of facilities as existing now after amendments and those proposed in the expansion to 18 MTPA
Sl no Name of the
Unit
Facilities at various stages of expansion in MTPA Total Capacity
(at 16 MTPA)
Facilities
Proposed
(at 18 MTPA)
Total Capacity
( at 18 MTPA) 4 -MTPA
4-10 -
MTPA
10-16 -
MTPA
At 16
MTPA
1 Ore beneficiation
Plant - product
OBP-1
1 X 4.5
OBP-2
1X 2.5 ,
1X 5.0 &
1 X 7.5,
Nil
1 X 4.5
1X 2.5
1X 5.0
1 X 7.5
19.5
OBP-1 facilities to be
Relocated
to OBP-2
19.5
2 Pellet Plants PP1- 1- 5.0 PP-2- 5.0 Nil PP 1 & 2
2 X 5 .0 10
PP-3
6.8 16.8
3 Sinter Plants SP1 SP 2 -2.3
SP 3- 7.5
SP4 -2.3 SP5 -1.75
SP6 -5.75
SP1-6 3X 2.3
2 X 5.75
1 X 1.75
20.15 SP-5: 2.3
SP-6: deferred in lieu
of PP-3
14.95
4 Coke Oven – NR
CO 1 &2
2 X0.64
1.28
Nil
Dismantling
of Existing
NR Coke
Oven
0 0 No addition 0
5 Coke Oven –
Recovery type Nil Coke 3 - 1.5 CO 1&2 -1.5
CO 1-5
2X1.5
1X2.0
1X3.0
8.0 No addition 8.0
6 Hot metal –Corex Corex 1 & 2
2X0.8 Nil Nil
Corex 1- 2
2 X 0.8 1.6 No addition 1.6
7 Hot metal-Blast
Furnace
BF-1-2.5
BF-2-2.17
BF 3 & 4
2 X 3.0
BF-3- 4.4
BF-5- 3.0
BF 1 -5
1X 2.5
1X 2.17
1X4.4
2X 3.0
15.07 BF-5 of 3.0 MTPA to
be built as 4.5 MTPA 16.57
8 Pig Casting
Machines (TPD) 1200 7200 3600 12000 12000 MGP-5000 tpd 17000
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-2
List of facilities as existing now after amendments and those proposed in the expansion to 18 MTPA
Sl
no
Name of the
Unit
Facilities at various stages of expansion in MTPA Total Capacity
(at 16 MTPA)
Facilities
Proposed
(at 18 MTPA)
Total Capacity
( at 18 MTPA) 4 -MTPA
4-10 -
MTPA
10-16 -
MTPA
At 16
MTPA
9
Crude steel -
BOF, EAF & auxiliaries
SMS1 3.80
SMS2 6.0
SMS2 -6.4
SMS 3 & 4-
5.6 2X200T BOF
+2X1.2 EAF
SMS1-4
1X3.8
1X6.4 1X3.0
1X2.6
15.8
SMS-3: In place of 1
EAF, 1 ZPF is
considered
SMS-4 will be changed from 2 x
200T to 2 x 350T &
will operate at 4.8
mtpa
18
10 Lime Kiln (TPD) LCP-1 4x300
LCP-2 4X300
,4X600
LCP-3 4 x 600
LCP 1- 4 8 X 300
8 X 600
7200 No addition 7200
11 Slab Caster 3.2 6.4
SMS-3-1
X1.6
SMS-4-
1X3.6
Slab Caster
1-4
14.8
14.8
SMS-4 slab caster
changed from 1 x 3.6
mtpa to 2 x 2.5 mtpa
16.2
12 Billet caster Nil SMS-2
1.5
SMS-3
3.0 4.5 4.5 4.5
13 HSM HSM 1
1X4.0
HSM-2
1X5.2
HSM-3
1X3.6
HSM1-3
12.8 12.8
HSM-3 upgraded to
5.0 14.2
14 Plate Mill Nil Nil Nil Nil Nil No addition Nil
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-3
List of facilities as existing now after amendments and those proposed in the expansion to 18 MTPA
Sl
no
Name of the
Unit
Facilities at various stages of expansion in MTPA Total Capacity
(at 16 MTPA)
Facilities
Proposed
(at 18 MTPA)
Total Capacity
( at 18 MTPA) 4 -MTPA
4-10 -
MTPA
10-16 -
MTPA
At 16
MTPA
15 Pipe Mill Nil 0.4 Nil 1X 0.4 0.4 No addition 0.4
16 Wire rod mill Nil WRM-1
1x0.6
WRM-2
1.2
WRM 1-2
1X0.6,
1X1.2
1.8 No addition 1.8
17 Rebar & Section
mill Nil
BRM-1
1X1.0 Nil
BRM-1
1.0 1
New BRM-2 of 1.2
MTPA 2.2
18 Cold Rolling Mill
Complex
CRM-1-
1.8
CRM-2-2.3
Nil CRM1&2
4.1 4.1 CRM-3 of 2.3 MTPA 6.4
19 Galvanizing Lines Nil Nil
CGL-1-
4X0.25
CGL-2-
2X0.45 -
CGL 1&2
4X0.25
2X0.45
1.9 No addition 1.9
20 Color Coating
Line Nil- 0.5 Nil 0.5 0.5 No addition 0.5
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-4
List of facilities as existing now after amendments and those proposed in the expansion to 18 MTPA
Sl
no
Name of the
Unit
Facilities at various stages of expansion in MTPA Total Capacity
(at 16 MTPA)
Facilities
Proposed
(at 18 MTPA)
Total Capacity
( at 18 MTPA) 4 -MTPA
4-10 -
MTPA
10-16 -
MTPA
At 16
MTPA
21
Power Plant and
process steam
boilers in MW
CPP 1X100
CPP-2
1X130
all gas
CPP 3 &4
2X300
gas+coal
CPP5-1X660
coal
CPP 1-5
1X100,
1X130,
2X300,1X660
1490 No addition 1490
22 Incinerator
(kg/hr) Nil
2 X
250kg/h 250kg/h 2 X 250kg/h 1000kg/h No addition 1000kg/h
23 Slag Grinding and
mixing unit
CP-1
1X 0.2 Nil
CP-2
1X2.0
CP-1&2
1X0.2
1X2.0
2.2 No addition 2.2
24 Oxygen Plant
(Out sourced)
1x2500
TPD=2500
TPD
2x1800 TPD +
1X900
TPD
2X1800 TPD
1 X 2500
TPD
10600 TPD 1 x 2060(TP)
2 x 2200 14860 TPD 4 X1800 TPD
1 X 900
TPD
25 Township (nos) 2 Units 2 Units 2 units 6 units 6 units 1 unit 7 units
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production PRE-FEASIBILITY REPORT
3 - Project Description (cont’d)
3-5
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
4-1
4 - SITE ANALYSIS
4.1 CONNECTIVITY
Road Connectivity
The site is at 29 km from Bellary, 33 km from Hospet and about 340 km
from Bangalore by road. The site is well connected by roads, including State
and National highways and to the mining area of Sandur.
Rail Linkage
Nearest railway station to the steel plant is Toranagallu. Broad gauge
railway lines between Guntakal and Hubli are passing through this station.
Airport
JSW Steel has an airport adjacent to the steel works with connectivity to
nearby cities of Hyderabad and Bengaluru.
Sea Port
The eastern port of Chennai is 460 km and western port of Goa is 430 km.
Mumbai is about 740 km on the North West.
Location map of the site is shown as Fig. 4-1
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
4 - Site Analysis (cont’d)
4-2
FIG. 4-1 - ROAD AND RAILWAY CONNECTIVITY
4.2 LAND FORM, LAND USE AND LAND OWNERSHIP
The proposed site for setting up of the brownfield project is located within
the jurisdiction of Toranagallu village of Sandur taluk in the district of Ballari in
Karnataka. The existing integrated steel plant is situated between 15o 10' - 15o
12' N latitude and 76o 38' - 76o 40'E longitude
The land is industrial land area and is currently in the ownership of JSW
Steel, after the expiry of the lease by Government of Karnataka. The total land
area is about 7640 acres and the proposed expansion is located over an area of
about 450 acres within the overall plant area, utilizing the existing infrastructure
and util ities.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
4 - Site Analysis (cont’d)
4-3
4.3 TOPOGRAPHY: The topography of the study area is gently sloping from
south to north. The area is in a valley surrounded by small mountain ranges.
The highest elevation of the existing steel plant and the proposed expansion site
is 500m while the lowest is 430m above msl. The site is drained by Narihalla on
the western side and Kaniganahalla on the eastern side. Narihalla and
Kaniganahalla drain into Daroji tank which is the only noteworthy tank in Sandur
taluk with a capacity of 788.28 mcft (22.3million cubic meter) located about 5km
north of the proposed site. Daroji tank also receives water from Tungabhadra
high level canal. Important rivers of Bellary district are Tungabhadra and its
tributaries namely hegari and chikka Hagari, which flow outside the study area.
River Tungabhadra flows on the north side of Toranagallu at a distance about 25
km. The flow of Tungabhadra river and Narihalla nallah is regulated by
respective reservoir authorities and the flow is very less during dry season. The
natural nallah, Kaniganahalla is also dry during the dry seasons.
4.4 EXISTING LAND USE
The present land use is industrial area housing the integrated steel plant
of JSW Steel.
4.5 SOIL
The top layer of the site is characterised by recent sand, murram, with
rectangular pebbles of banded hematite and black cotton soil. This combination
of topsoil ranges from 0 to 1.5 m, below 1.5 m the weathered schist formation is
encountered upto depth of 8m. Beyond 8m the formations are found to be
fractured. The basement/fresh rock occurs beyond 10 m. The general profile
observed in the study area is as follows.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
4 - Site Analysis (cont’d)
4-4
The above soil profiles was observed from the well and nallah cuttings which
are located in the valley portion of the study area. The recent formation of
murram and black cotton soil are observed to the depth of 0.5m to 1.0m. It
appears that the fractured rock starts immediately and extends to the depth of
1.5m and the fresh rock strata 2 m below the ground level. From the
geotechnical map it is evident that three seismic zones have been identified at
Bellary district. There are three lineaments are also identified. All the lineaments
are occurring at Zone II of seismic activities. The existing plant is located in
seismic Zone II and without any lineament. From the map it also can be seen
that the plant is located on pediplain plateau residual hill with structural hill
ranges. The basement has crystalline, granite, charnockite .
4.6 HYDROLOGY
The entire study area forms a part of Tungabhadra basin, downstream
catchments. The study area is mainly drained by Kaniga nala and Nari nala and
finally these two nala became tributaries to Daroji kere. The overflow of Daroji
kere meets Tungabhadra at 25 Km towards North. Hagari and Chikka hagari are
other tributaries to Tungabhadra which are not falling in the study area. There
are 15 minor and 2 major tanks are in Santur taluk. Daroji is one major tank with
1790 acres of command area with maximum water holding capacity of 788.28
Mcft located at 5 km in the north. Another one is man made exclusively meant
for plant feed water located at south of the plant. High level lined Tungabhadra
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
4 - Site Analysis (cont’d)
4-5
irrigation canal is passing at about 8 km north of the plant site. The let out water
from Tungabhadra dam to Andhra Pradesh flows in this canal for 8 to 9 months
in a year with an average height of water column ranging from 2 to 3 meter. This
water head influences the groundwater in the down gradient and near the canal
to some extent till the groundwater head gets matched with running water head.
Nevertheless, this canal water is not used for any industrial purpose and it is
unaffected by proposed activities. Hence further detailed study about the canal
is not detailed in this report.
4.7 CLIMATIC CONDITIONS
The climate of the area is interior arid zone and the total rainfall ranges
from 331 to 626.7 mm. (Year 1998 to 2005). More than 80% of the rainfall
received during the months of July to September from South West monsoon and
the balance is equated in North East monsoon. The study region is
characterized by hot and dry summer with temperature raising above 47 0 C
during the month of May.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
5-1
5 - PLANNING BRIEF
5.1 PLANNING CONCEPT
The proposed brown field expansion project would be sited near
Toranagallu, Sandur taluk, Ballari district. The total land area of the proposed
project would be about 450 acres within the overall land area available with JSW
Steel.
5.2 POPULATION
The JSW Steel limited comes under the Sandur taluk an iron ore mining
area, has a population of 2,22,782 with nearly 80% residing in the rural area as
per 2011 Census. Due to relatively less rainfall and irrigation facilities there has
been a shift of employment from agriculture to industrial. This has also been
triggered by the setting up of the large steel plant in the taluk, besides Sandur
being the iron ore area for mining activities. This trend is continuing with new
opportunities of employment and business due to the setting up of the steel
plant. The proposed project will keep this momentum going.
The proposed project as per applicable regulations would employ local
workers. However due to foreseen employment opportunities in the proposed
project and increase in ancillary economic activities, growth in migrant
population is anticipated during construction stages.
5.3 LAND USE PLANNING
The total area for steel plant would be about 7742.06 acres, consisting of
tentatively the following:
Built up facilities in terms of buildings, shops, yards etc :
Roads & railway corridors
Drainage channels
Water bodies
Green Cover
Others:
The total greenbelt, of about 2208 acres constitute nearly 30% of the
overall plant area. Further an area of 228 acres is being covered with water
bodies. Further it is intended to carry out plantation on another 500 acres of
land adjoining the steel plant belonging to the forest and defense departments.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
5 - Planning Brief (cont’d)
5-2
The layout would also house canteen, administrative buildings, workshops,
laboratories, railway tracks, stores, in-plant roads, etc.
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND
The following infrastructure development in the area is being carried out to
support the growth of the steel plant and for its sustainable operation.
A network of seven Pipe conveyors of 86 Km from the mine iron areas to
the steel plant site is under construction at an estimate of Rs 1200 cr by
JSW Steel to reduce the number of trucks operating for transporting iron
ore. This is being carried out to reduce the fugitive emissions and as a
compliance to one of the condition of the earlier EC.
Setting up of a raw water pond over 600 acres’ area for storing water to
meet the requirements of the steel plants during the dry months for
stable operations.
4- lane National highway is under construction by NHAI connecting
Hospet to Gooty. This will lessen the fugitive emission during road
movement and assist in dispatch of steel products by Road.
A Daroji railway link for providing another outlet connection for the
Ballari side (to the east side of the plant) to move the raw material and
steel products.
Provision of safe potable water facilities in surrounding vil lages is being
implemented by JSW Steel along with other Government agencies.
seasons
Provision of safe piped potable water facilities to Sandur is being
executed by Government agencies.
A by pass along the road along Vaddu is planned to facilitate smooth
movement of traffic to avoid my railway cross overs currently existing in
the JSW land
Under the Karnataka Mining Environment Restoration Corporation a SPV
appointed by the Honorable Supreme court, several infrastructure
development works is being taken up in Sandur taluk, at an estimated
cost of over Rs 10,000 Cr in the next few years. These include:
Drinking water facilities
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
5 - Planning Brief (cont’d)
5-3
Provision of medical facilities in the project influence area with
special emphasis on primary health care through private Mobile
Health Units, Government Public Health Centers and medical camps
Industrial and Vocational training to local youth groups (both girls
& boys) for diversification of skills and enhancement of livelihood
Provision of social infrastructure like that of community toilets,
playgrounds, community halls with basic amenities
JSW STEEL Limited 18.0 MTPA CRUDE STEEL PRODUCTION
PRE-FEASIBILITY REPORT
Fig 6-1&2 : Location of proposed expansion of crude steel capacity
6 - PROPOSED INFRASTRUCTURE
6.1 Industrial Area (Processing Area)
The existing integrated steel plant of JSW Steel l imited is situated between
15o 10' - 15o 12' N latitude and 76o 38' - 76o 40'E longitude, near Toranagallu
village of Bellary district in the state of Karnataka. The site is located at 32 km
from Bellary, 33 km from Hospet and about 340 km from Bangalore by road.
Nearest railway station to the steel plant is Toranagallu. Broad gauge railway
lines between Guntakal and Hubli are passing through this station. The eastern
port of Chennai is 460 km and western port of Goa is 430 km. Mumbai is about
740 km on the North West. Location map is shown as Fig. 6-1
National Highway (NH) 67 connecting Ballari and Hubli is situated at the
northern part of the proposed project site. State Highway (SH) 40 connecting
Toranagallu & Sandur is located along the western side of the site and the road
connecting Antapur to NH-67 is on the eastern site of the plant site. The SER
line connecting Vijayawada to Hubli is situated on the northern side of the site.
The production facilities in the proposed expansion to 18 Mtpa will be located
within the existing plant area which is highlighted in Fig 6-2
6.2 RESIDENTIAL AREA
JSW Steel currently has at present five satellite townships (Vidyanagar,
VV nagar, Shankar hill town, Lake view) located along the periphery of the steel
plant with about 6200 dwellings. Another township Hill View township with 2600
dwellings is under construction. All these residential areas have amenities like
roads, electricity, drinking water, underground drainage, sewage treatment,
parks & gardens, security etc. Besides, due to the existence of the steel plant,
the surrounding villages have also been developed and are capable of handling
additional population as needed. Other amenities such as school, community
center, guest house, health center, hospital, shopping complex, post office,
bank, park, playground etc has also been provided in these townships.
Further, a township to accommodate 3500 construction workers is proposed to
take care of the housing needs of migrant population during construction
activities. The accommodation for the additional manpower for the proposed
expansion will be accommodated in these existing facilities. There will be no
temporary construction for accommodating the workers employed during
construction.
JSW STEEL Limited 18.0 MTPA CRUDE STEEL PRODUCTION
PRE-FEASIBILITY REPORT
6 - Proposed Infrastructure (Cont’d)
6-2
The electrical power and treated water is provided from the existing steel plant.
Treated water is being supplied from the drinking water treatment plant
located within the steel plant.
6.3 GREENBELT
The steel plant is surrounded by lush greenery which besides arresting
pollution has helped in providing a serene environment for the surrounding
population. A total area of about 2500 acres has been developed both inside
and surrounding the steel plant area. Unpaved areas, if any, within the plant
boundary is also provided with grass/tree cover. The greenery development
beyond the “own area” is being carried out on the barren areas surrounding the
steel plant with the help of the local forest department.
The list of species of trees planted in and around JSWSL is given in Table- 6-1
6.4 PROPOSED SOCIAL INFRASTRUCTURE
JSW Steel over the years, though its CSR activities has provided support for the
overall socio-economic development the surrounding areas. It is estimated that
about two lakh population in the surrounding areas have been directly benefited
by JSW infrastructure development activities. To develop these infrastructure,
JSW has already invested around 120 crores. These include:
Rural Social Infrastructure including clean water, decent housing,
environmental sanitation, personal hygiene and adequate nutrition,
Coordination between multiple funding streams and agencies supporting the
surrounding areas.
Basic education to promote quality, dignity, self-respect, with a sense of
belonging as well as political integration.
Formal and informal education to promote rural productivity
Set up OP Jindal Centre, a multi-functional educational campus which
provides Vocational Training, Distance Education, Tamanna special school,
Rajiv Gandhi Institute of Steel Technology, Safety training center, Textile
training center, Sanitary Napkin production unit.
Model schools have been built in Vaddu, Bhujanganagar& Toranagallu. These
model schools each having 20 classrooms to kindle the spirit of education
among the children
Constructed 42 model School Toilets as a part of 'Swachh Bharat'
Two rural BPO center where local women are employed
In association with Akshaya Patra foundation, a midday meal scheme
benefitting about 30,000 children in 432 schools in the surrounding villages.
Developed parks in several vil lages and towns.
Built an Interpretation center at Daroji wildlife sanctuary.
JSW STEEL Limited 18.0 MTPA CRUDE STEEL PRODUCTION
PRE-FEASIBILITY REPORT
6 - Proposed Infrastructure (Cont’d)
6-3
Restoration of temples in and around Hampi.
Set up Jindal Sanjeevani Hospital, a multi-specialty hospital etc
It is intended to continue and expand these activities for the overall development
of the area.
6.5 CONNECTIVITY
JSW steel is well connected to other parts of the country by Road and Rail.
Toranagallu is now connected by air from Hyderabad and Bangalore.
6.6 DRINKING WATER MANAGEMENT AND SEWAGE SYSTEM
Over the years, JSW has built necessary infrastructure for providing drinking
water to the residents in the township and to surrounding villages. Currently,
about 15,000 m3/d of drinking water is being supplied to the steel plant and
township. This will be augmented to 20,000 m3/d in the proposed expansion.
The treated wastewater is being used for plantation and industrial purposes.
Further, Karnataka Government is proposing to provide drinking water to Sandur
taluk by laying a separate pipeline from the HLC canal. The work is in progress
and is expected to be completed by Dec 2019.
6.7 INDUSTRIAL WASTE MANAGEMENT
In the process of steel mal process and non-process wastes and effluents are
generated. These are discussed in detail in Chapter-3.
6.8 SOLID WASTE MANAGEMENT
The major solid wastes produced in the steel manufacture are blast furnace
slag, steel slag dust & sludge among others. The solid waste management has
been discussed in detail in Chapter-3.
6.9 POWER REQUIREMENT AND SUPPLY/SOURCE
JSW Steel has set up four captive power plants with a capacity to generate 830
MW of electricity. Besides about 110 MW of electrical power is being generated
from waste energy sources. Electrical power is also being imported from
JSWEL, a Group company which has an installed capacity of 860 MW.
The power requirement of the steel plant and township will be met from these
sources. There is no proposal to install any power plant under the proposed
expansion. The details of power requirement at 18 Mtpa is explained in detail in
Chapter-3
TABLE 6-1: LIST OF SPECIES OF PLANTS/SHRUBS PLANTED IN AND
AROUND JSWSL
JSW STEEL Limited 18.0 MTPA CRUDE STEEL PRODUCTION
PRE-FEASIBILITY REPORT
6 - Proposed Infrastructure (Cont’d)
6-4
JSW STEEL Limited 18.0 MTPA CRUDE STEEL PRODUCTION
PRE-FEASIBILITY REPORT
6 - Proposed Infrastructure (Cont’d)
6-5
JSW STEEL Limited 18.0 MTPA CRUDE STEEL PRODUCTION
PRE-FEASIBILITY REPORT
6 - Proposed Infrastructure (Cont’d)
6-6
JSW STEEL Limited 18.0 MTPA CRUDE STEEL PRODUCTION
PRE-FEASIBILITY REPORT
6 - Proposed Infrastructure (Cont’d)
6-7
JSW STEEL Limited 18.0 MTPA CRUDE STEEL PRODUCTION PRE-FEASIBILITY REPORT
Fig 6-1&2 : Location of proposed expansion of crude steel capacity
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
7-1
7-REHABILITATION & RESETTLEMENT
The proposed project is a brown field project with all the proposed facilities
coming up with in the existing land area of the existing integrated steel plant
complex.
The project entails use of existing water allocation, power generation
facilities with zero l iquid discharge. Further, all the solid wastes are proposed to
be recycle or sold.
In view of this, there are no R & R issues.
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
8-1
8 - IMPLEMENTATION SCHEDULE & COST ESTIMATE
8.1 IMPLEMENTATION SCHEDULE
The proposed project of installation of the 18 Mtpa steel plant is an
extension of the earlier proposed expansion of capacity from 10 MTPA to 16
MTPA. The expansion of crude steel capacity to 18 MTPA is expected to be
completed by March 2022, with commissioning of various plant facilities of the
project is shown in the form of a bar chart in Fig.8-1 which is attached.
It is envisaged that the project would be completed within a period of 44
months from the date of receipt of Environmental Clearance (EC) . It is
considered that construction work at site for various plant facilities of the project
would commence after Grant of EC from MoEFCC & CFE from KSPCB, and
also, completion of major engineering works .
8.2 CAPITAL COST ESTIMATE
The estimated capital cost for the plant & equipment worked out for all
the facilities are presented in Table 8-1. The expansion from 10 Mtpa to 16 Mtpa
was originally estimated at Rs 16000 Cr. Considering the changes in
configuration of the facilities, the proposed expansion from 13 Mtpa to 18 Mtpa
is expected to cost Rs 19621 Cr, out of which Rs 1055 Cr will be spent for
implementation for environment monitoring & control facilities as given in Table
8-2
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
8 - Implementation Schedule & Cost estimate (Cont’d)
8-2
TABLE 8-1 :COST ESTIMATES : 18.0 MTPA EXPANSION OF CRUDE STEEL AT VIJAYANAGAR
Sl. No.
Unit Total in Rs Crore
1 Blast Furnace No.5 1895
2 Pellet Plant No.3 (including Filtration facilities)
1212
3 Steel Melting Shop No. 3 & 4 2953
4 Hot Strip Mill No.3 2846
5 Cold Rolling mill 3 4800
6 Raw Material handling augmentation 470
7 Utility & Services 133
8 Energy management & MSDS. 594
9 Logistics 202
10 Daroji rail linkage 182
11 Infrastructure (including dismantling CO 1&2), Road and bridges.
145
12 Design, Engineering & Consultancy services for 18.0 MTPA
47
13 Salaries & Admin 1% 24
Basic Project Cost 15503
Taxes 7% 1085
Contingency 5% 775
Core Project Cost 17363
IDC 8 % 1389
Margin Money 5% 868
Total Project Cost 19621
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
8 - Implementation Schedule & Cost estimate (Cont’d)
8-3
TABLE 8-2 COST ESTIMATES : ENVIRONMENTAL CONTROL MEASURES AT 18.0 MTPA
Major Environment Control Facilities Total in Rs Crore
1. Dry GCP for higher capacity BOF converters 80
2. Enhanced capacity of earlier proposed environmental control facilities
280
3. Flue gas desulphurisation for CPP 3&4 350
4. Additional bag filter for ESPs of Sinter Plant 245
5. Environment control monitoring 20
6. Steel slag- Steam box technology in SMS-4 80
Total 1055
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
8 - Implementation Schedule & Cost estimate (Cont’d)
8-4
JSW STEEL LIMITED 18.0 MTPA Crude Steel Production
PRE-FEASIBILITY REPORT
9-1
9 - ANALYSIS OF PROPOSAL
9.1 FINANCIAL BENEFITS OF THE PROJECT
The financial benefits accrued from the project would improve the
profitability of the promoter company, but also strengthen the economy of the
state due to revenues from taxes and duties derived from sale of value added
products. Installation additional facilities in terms of state-of-art steel plant
with captive power plant, add huge impetus to the growing economy of the
state and the country.
9.2 SOCIAL BENEFITS
The proposed brown field expansion in a relatively backward part of the
state of Karnataka would help in
- Further enhance local direct and indirect employment opportunities
in the project influence area
- promote the development of ancillary industries, medium-small scale
trade & commercial establishments, local entrepreneurship and
diversification in skill set
- generate local income, boost the local purchasing power and promote
an increase in land prices & rent
- contribute to the local economy and the state revenue
The peripheral development activities that would be undertaken by the
proposed project will focus on vulnerable communities in the project influence
area. The project would bring forward an overall socio-economic development
with emphasis in the areas of employment, education, training, health and
infrastructure.