Expansion Joint & Bearing Installation Issues:
An Owner’s Perspective
AASHTO Subcommittee on Bridges & Structures2017 AASHTO SCOBS MeetingSpokane WA ~ June 2017
Ralph J. Dornsife P.E., S.E.Washington State Dept. of Transportation
Bridge & Structures OfficeOlympia Washington USA
Page 2
Joint / Bearing Case Studies
• I-5 SB Blakeslee Junction• I-5 SB BNSF / Dike Road O/C• I-5 Capitol Lake O/C• I-5 / SR 18 Triangle Project W-S Ramp• I-90 WB East Channel• Nalley Valley SW-Line N-W Ramp• SR 520 Floating Bridge Replacement
Page 3
I-5 Blakeslee Junction Bridge Strip Seal Joint Failure
Page 4
Support and Setting Details
Page 5
Installation Hardware
Page 6
Installation Hardware - Close-up
Page 7
Strip Seal Joint Failure
Page 8
I-5 BNSF / Dike Road O/C
Page 9
Installation Hardware
Page 10
Detached Elastomeric Seal
Page 11
I-5 Capitol Lake O/C Bridge
Page 12
Preformed Silicone Seal Replacement and Failure
Seal debonding
Page 13
Unarmored Silicone Strip Seal Installation Deficiencies
Page 14
I-5 / SR 18 Triangle Project Modular Expansion Joints
Page 17
MEJ Blockout Reinforcement
Page 18
Traffic Implications
Page 19
I-90 WB East Channel Bridge Failed MEJ Centerbeam Splices
Page 20
MEJ at Splice Location
Page 21
Damaged SS Slide Plate
Page 22
Nalley Valley SW-Line BridgeMisoriented Disk Bearings
Sliding DiskBearing
TransverseStop Bearing
Page 23
Disk Bearing Installation
Page 24
SR 520 Replacement Floating Bridge
Page 25
Elastomeric BearingsDamaged during Installation
Page 26
Gouged Elastomer Exposed Steel Shims
Page 27
Use of Installation Technician
• Acknowledgment of Role• Qualifications• Present at Critical Times
Page 28
Role of the Inspector
• Experience• Specialized Training (Just-in-Time)• Staff Retention
Page 29
Communication
• Backgrounds• Roles• Coordinating
Page 30
Installation Procedures
• Documentation– Shop Drawings– Written Procedures
• Review & Approval
Page 31
Modular Finger Joint System
Page 32
Installed Finger Joint System
Page 33
Design Considerations
• Inspection• Maintenance• Installation