Introductions
Project Update
Project Objectives
Discussion of Alternatives
Update on Project Schedule
Questions?
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 3/25
The NY office of FHWA has determinedthat the project is a reconstruction of theexisting Exit 4 interchange.
As a result of this determination, thealternatives have been modified toincorporate removal of existing ramps
The design team has completed the
traffic models for the alternatives basedon these modifications
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 4/25
Improve access between I-87 and the Albany InternationalAirport without precluding future, long-term I-87 mainlineimprovements, and without impacting I-87 mainlineoperations between Exit 2 and Exit 5
Improve access between I-87 and Wolf Road withoutprecluding future, long-term I-87 mainline improvements,and without impacting I-87 mainline operations betweenExit 2 and Exit 5
Improve intersection operating conditions in the existingExit 4 area and address safety concerns in the areas thatexceed the statewide average crash rate for similartransportation facilities
Eliminate the structural deficiencies associated with the I-87 northbound and southbound bridges over Albany-Shaker Road by providing bridges with a 75-yearminimum service life
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 5/25
The existing bridgesneed to be replaced.
They are the onlyremaining bridges on I-87 in Albany Countyfrom the original
construction of theinterstate FHWA has statedthat the bridges arepart of the I-87 Exit 3-4project so that theNEPA process can becompleted for theoverall project and thebridges can bedesigned for the largerproject
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 6/25
Improve system connectivity between theexisting pedestrian/bicycle facilities onWolf Road and the facilities constructed
as part of the Albany-Shaker/Watervliet-Shaker Road projects
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 7/25
Exit 4 Upgrades
SPUI Interchange
Diamond Interchange
Flyover Interchange
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 8/25
Construction $21.8 M
ROW $3.0 M Wetlands 1.1 acres Minimal traffic operationimprovements Little public support Doesn’t address safety concerns
Region proposes to dismiss
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 9/25
N
OldWolf
Road
I-87 Exit 4 SB Off-Ramp
Legend:
- Injury
- Property Damage Only
Accident Locations by Severity
January 2007 through February 2010
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 10/25
N
Legend:
- Injury
- Property Damage Only
Accident Locations by Severity
January 2007 through December 2009
O l d
W o l f R o
a d
I - 8 7
E x i t
4
S B
O n
- R a m p
Albany-Shaker Road
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 11/25
N
Wolf Road
Albany-ShakerRo
ad
Legend:
- Injury
- Property Damage Only
Accident Locations by Severity
January 2007 through December 2009
I-87 Exit 4
NB On-Ramp
I-87Exit
4
NBOff-Ramp
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 12/25
Construction $ 32.0 M ROW $ 9.0 M +/-
Wetland 2.3 acres 2 lane roundaboutswould not work due to thefact that 50,000 vpdexceeds the 45,000 vpdlimit
Safety concerns are notaddressedRegion proposes todismiss
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 13/25
Construction $ 42.0 M ROW $ 10.0 M Wetland 3.7 acres Realigns Wolf RoadNot able to beconstructed in phases Traffic operations are
good Safety concerns areaddressed Little public supportPublic safety concernswith the closer of Old Wolf
RD Region proposes todismiss
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 14/25
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 15/25
Construction $ 38.9M
ROW $ 17.0 M Wetland 3.2 acres Farmland 0.8acres Ann Lee PondPreserve 9.3 acres
Traffic operationsare good Safety concernsare addressed Concerns withrunway safety zone Has little publicsupport Region proposes todismiss
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 16/25
Construction $ 36.5 M
ROW $ 20.0 M Wetland 3.0 acres Farmland 5.1 acres Traffic operations aregood Safety concerns are
addressed Has public support Region proposes toprogress
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 17/25
Construction $ 26.3 M ROW $ 9.0 M Wetland 3.0 acres Farmland 7.7 acres Traffic operations aregood Safety concerns areaddressed Has the most publicsupport Region proposes toprogress
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 18/25
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 19/25
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 20/25
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 21/25
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 22/25
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 23/25
8/6/2019 Exit 4 Power Point
http://slidepdf.com/reader/full/exit-4-power-point 24/25
Draft Environmental Impact Statement Report forPublic Review November 2011
Record of Decision December 2012
Final Construction Documents for the Replacementof the I-87 Bridges over Albany Shaker Road June 2013
Bid Letting for Replacement of the I-87 Bridges overAlbany Shaker Road September 2013
Construction Duration Replacement of the I-87Bridges over Albany Shaker Road 2014 & 2015