Exercise-4
ActivityID***
Description Duration Dependency*
(ies)
1 Decorate room(summary task / workpackage)
- -
2 Remove furnishings 1 SS 3, 4
3 Fetch paint 2 SS 2, 4**
4 Fetch wallpaper 3 SS 2, 3**
5 Strip walls 4 FS 2
6 Paint ceiling and woodwork 5 FS 3
7 Hang wallpaper 6 FS 4, FS 5
8 Replace furnishings 7 FS 6, FS 7
9 Tidy up, relax and brag about DIY skills 8 FS 8
Table is concerning a small decorating project:
produce a Gantt Chart;
produce a Network diagram, and Determine the minimum project duration
FS - Finish-to-Start: Activity can only start when predecessor has finishedregardless of resource availability
SS – Start-to-Start: Activity and its predecessor may start simultaneouslyif resource is available
SF – Start-to-Finish: Activity must finish before predecessor may start
FF – Finish-to-Finish: Activity must finish at the same time as its predecessor