Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
EXECUTIVE SUMMARY
OF
M/s. SUJITH INFRA (Mining of Road Metal & Gravel)
Managing Partner: Sri B. Subba Reddy 1, Thippavarapadu Village,
Gudur Mandal, Andhra Pradesh
Site Address
Lease Area: 6.321 Ha. Sy. No. 1
Bhuvanagiripalem (V), Ozili (M) S.P.S.R Nellore District, A.P
Production Capacity
Mining of Road Metal – 84600 M3/Annum Gravel – 9400 M3/Annum
Primary Baseline Data Collected: January’ 2019 to March’2019
Approved ToR Lr. No: SEIAA/AP/NLR/MIN/11/2018/734-2018 Dt: 19.02.2019
Sector: 01 – Mining of Minerals, Cat –B
PREPARED BY
H.O: Block-B, B-1, IDA, Autonagar -12, Vishakapatnam
Ph: 0891-2755528, Fax: 0891-2755529, E-mail: [email protected] Ph: 9440338628
QCI NABET & NABL Accredited & Recognized by MOE&F, New Delhi.
MAY’ 2019
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
1
1.0 INTRODUCTION
M/s Sujith Infra, Managing Partner B.Subba Reddy filed an application on 12.02.2018
for Road Metal & Gravel over an extent of 6.321 Ha., in Sy.No.1, of Bhuvanagiripalem
Village, Ozili Mandal, SPSR Nellore District, Andhra Pradesh
The Assistant Director of Mines & Geology, Nellore has recommended for quarry lease
over an extent of 6.321 Ha. Vide Lr.No.783/Q/2018 dt.27.08.2018. The DDM&G,
Guntur decided in principle to grant quarry lease for Road Metal & Gravel over an extent
of 6.321 Ha. in Sy.No.1, of Bhuvanagiripalem Village, Ozili Mandal, SPSR Nellore
District, Andhra Pradesh State in favor of M/s Sujith Infra, Managing Partner Sri B.
Subba Reddy for a period of 10 years Vide Notice No. 3393/Q5/2018, dated 01.09.2018.
The Mining plan approved vide Letter No: 4364/MP/RM/NLR/2018, dated: 03.10.2018.
The proposed Project M/s. Sujith Infra extends over an area of 6.321 Ha. As per the latest
National Green Tribunal (NGT) New Delhi issued orders in O.A. No. 186 of 2016 dated
13.9.2018 & in E.A. No. 55/2018 of O.A. No. 520/2016 dated 11.12.2018 & Office
Memorandum F. No. L-11011/175/2018-IA-II (M) dated: 12.12.2018 that projects with
individual area or cluster area of mine leases from 5 to 25 Hectares falls under category
B2 at par with category B1, attracts Public Hearing and necessitates obtaining the
Environmental Clearance from State Environmental Impact Assessment Authority
(SEIAA).
Presentation for TOR has been made before the SEAC committee and the TOR order
issued by SEIAA, Govt. of Andhra Pradesh vide Lr. No.
SEIAA/AP/NLR/MIN/11/2018/734-2018, Dt.19.02.2019 with production of Road Metal-
84600 m3/Annum & Gravel-9400 m3/Annum. As per the TOR baseline data has been
prepared for one season i.e., non-monsoon season. The study area consists of the core
zone (lease area) and the buffer zone comprising area within 10 km radius from the mine
area.
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
2
In order to fulfill the further necessary requirements for obtaining the Environmental
Clearance for this mining activity, the proponent has initiated steps to carryout required
Environmental Impact Assessment (EIA) study in and around the proposed mine lease
area.
This assessment is performed to identify the likely Environmental Impacts and based on
the findings; an effective Environmental Management Plan is in place as per the EIA
Notification 2006 general guidelines and the approved TOR issued by APSEIAA.
The standards set by the Central Pollution Control Board (CPCB) and the State Pollution
Control Board (SPCB) will be met and adhered to.
This study covers an area surrounding the project site with a radial distance of 10 km
from the proposed mining lease area. The baseline monitoring was carried out during the
Period of January’2019 to March’2019.
1.1 SALIENT FEATURES OF THE PROJECT SITE
The mine lease area falls under the Topo sheet No. 57 N/16 bearing following details:
Topo sheet No. : 57 N/16
Latitude : 14°02'13.89"N to 14°02'07.60"E
Longitude : 79°49'18.19"E to 79°49'25.40"E
Details about Project site:
Name of the project M/s. Sujith Infra
Extent 6.321 Ha.,
Capacity Road Metal – 84600 m3/Annum
Gravel – 9400 m3/Annum
Location of the project District & State S.P.S.R Nellore & A.P.
Mandal Ozili
Village Bhuvanagiripalem
Latitude 14°02'13.89"N to 14°02'07.60"N
Longitude 79°49'18.19"E to 79°49'25.40"E
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
3
General climatic conditions
Maximum Temperature 45°C
Minimum Temperature 14°C
Annual average rain fall 1042 mm
Relative Humidity 64-79%
General location details
Nearest Habitation Bhuvanagiripalem Village at a distance of 1.85 kms
Nearest city Ozili at a distance of 9.00 kms
District headquarters Nellore at 48.15 kms
Nearest railway station Odur Railway station is at a distance of 5.1 km
Nearest Airport Tirupati Airport at 52.90 kms
Archaeological/Historically
important site
None within 10 km radius
Infrastructure Facilities Hospitals and schools are present in Ozili Mandal
Sanctuaries/National parks None within 10 km radius
Nearest RF/PF Proposed quarry lease area is 72.04 meters away from the
nearest boundary of Bhuvanagiripadu Reserve Forest.
Kondagunta R.F – 5.23 kms
Gudur R.F - 6.53 kms.
Vedicherla R.F – 6.86 kms
Vendodu R.F – 3.90 kms
Jayampu R.F – 6.48 kms
Virlagunapudi R.F - 5.28 kms
Saguturu R.F – 4.94 kms
Rudrapalem R.F – 8.91 kms
Oduru R.F – 6.00 kms
Nearest Water Bodies Canal at a distance of 1.89 kms from mine area
Water body at NE side near Mekanur village at a distance
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
4
of 3.99 kms
Water body at NW side near Ayyavaripalem village at a distance of 2.19 kms
Waterbody at a distance of 3.74 km at NW side
Waterbody SE side at a distance of 2.39 kms
Water body SE side near Pedda Pariya village at a distance of 4.49 kms
Water body SW side at a distance of 4.66 kms near veerlagunapadu village
Jayampu Lake – 8.14 kms
Jayampu Lake 2 – 7.05 kms
Mamidi Kaluva-7.70 kms
Engineers Well – 7.71 kms
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
5
TOPO MAP AROUND 10 KM RADIUS
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
6
1.2 DETAILS OF PRODUCTION
YEAR WISE PRODUCTION FOR ENSUING FIVE YEARS PERIOD
A total of 362455 m3 is being excavated out of which 90% recovery 326210 m3 is the
Road Metal & 10 % recovery 36246 m3 is Gravel and there will be no generation of
waste as the mineral excavated is of 100% economical value.
YEAR WISE & SECTIONAL WISE PRODUCTION OF ROAD METAL & GRAVEL
Year Name of
Section
SECTIONAL Saleable Road
Metal Recovery
@ 90%
Saleable Gravel
Recovery
@ 10%
Area in
Sq. M
Influence
in M
In-situ Mass
Cbm
1st A-A' 500 188 94000 84600 9400
2nd A-A' 410 177 72570 65313 7257
3rd A-A' 360 192 69120 62208 6912
4th A-A' 325 185 60125 54113 6013
5th A-A' 340 196 66640 59976 6664
Grand Total 362455 326210 36246
Annual Average 72491 65242 7249
Mineable Reserves:
The deposit was estimated through Cross-Sectional Method. The reserves are estimated
through one Cross Section A-A' which is drawn at appropriate distance to estimate the
reserves. The proved reserves were taken up to a depth RL 70 m i.e from hillock outcrop
Portion and further 10 meters has taken as Probable Reserves and 10 m as Possible Reserves
The mineable reserves are computed after deducting the quantities of material that should be
left out for 7.5 m buffer zone and for safety of the mine that is to maintain 650 final pit lines
but here the reserves indicated are inclusive of material that will be locked up in final pit, and
in safety zone as required under Regulation 111 of MMR-1961.
Total Mineable reserves -- 543960 M3
The average production per year
Road Metal -- 65242 M3
Gravel -- 7249 M3
Anticipated life of the mine -- 7.50 say 8.0 years
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
7
1.3 MINING PROCESS
The mining operations will be carried out by opencast method of mining. Road metal
is medium hard and gravel will be excavated by excavators directly. Drilling will be
carried out with the help of Wagon Drill machine. The excavated mineral is processed
through the crusher unit, which is within the proposed mine area to obtain required
size of rock as per market demand.
The operations in mine area will involve drilling, blasting, excavation by excavators,
crushing through crusher and directly loaded into the tipper/tractors for transportation.
The excavation will be carried out with bench height 4 to 6 m and width 5 to 12 m
minimum. Haul roads gradient will be 1:16. In this plan period it is proposed to
excavate Road Metal & Gravel of about 326210 m3 and 36246 m3 respectively for five
years.
1.4 EXTENT OF MECHANIZATION
Road metal is medium hard and gravel will be excavated by excavators directly.
Drilling and blasting are mandatory for excavation of road metal. The operations
involve drilling, blasting & excavation by excavators and directly load into the
Tippers/Tractors
1.5 PROPOSED MANPOWER
By this project many people will be benefited for their livelihood and get employment
in this remote area.
Employment Details Employment Details
S. No. Category No’s.
1 Mines Manager 1
2 Mine Mate 1
3. Time Keeper 1
4. Excavator Operators 3
5. Truck/Tractor Drivers 8
6. Helpers 2
7. Semi Skilled Workers 17
Total 33
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
8
1.6 WATER SUPPLY
A total of approximately 11.0 KLD of fresh water is required for the proposed project
activity which will be met through water tankers. Out of the total quantity, 1.5 KLD
will be utilized for domestic purpose and 3.0 KLD for Green belt development, 2.5
KLD for wet drilling. Remaining 4.0 KLD of water is required for dust suppression.
1.7 BASELINE DATA
The study area covers an area of 10km radius around the proposed mining site. The
study includes detailed characterization of various Environmental components such as
Air, Water, noise, Land and Socio-Economic within the study area.
OBJECTIVES OF STUDY AREA
To assess the existing base line data of Air, Water, Noise, Land and Socio-economic
environment.
To evaluate the beneficial and adverse impacts of the proposed activity.
To prepare an Environmental Management Plan (EMP) detailing control technologies
and measures to be adopted for minimizing the impacts and improving the
Environmental Quality.
To predict the incremental levels of pollutants in the study area due to the proposed
mining activity.
To prepare post mining programme for monitoring and regulating Environmental
parameters.
1.7.1 ENVIRONMENTAL SETTINGS:
Air Environment:
To know the existing ambient air quality, Eight sampling stations with in Core and
buffer zone were identified and monitored for pollutants like, Particulate Matter – 10
(PM10), Particulate Matter – 2.5 (PM2.5), SO2, NOx and Free Silica. For this sampling
calibrated through samplers of PM2.5 & PM10 dust samplers.
The Ambient air quality measured at mine site and surrounding stations with in the
study zone showed the following maximum and minimum concentrations of the
pollutants-
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
9
It may be seen that all the parameters i.e., PM 10, PM 2.5, SO2 and NOx are well within
the range of 24 hr average of National Ambient Air Quality Standards. Silica was also
monitored at all locations during the study period and was found to be Below
Detectable limit.
1.7.2 Noise Pollution:
The Ambient noise levels monitored within the study zone show a minimum and
maximum values of 35.0 dB (A) at location N2 and 55.3 dB (A) at location N8.
1.7.3 Water Environment:
Ground water samples are collected from eight locations and surface water from four
locations. All these samples are free from colour and pollutants.
Summary of Ground water:
During the study period, the pH of the groundwater was found varying between 7.1
and 7.5. The pH values for all the samples collected in the study area during study
period were found to be within the acceptable limits.
The TDS of all the samples were below the permissible limit of 2000 mg/l.
The Chloride levels in the groundwater samples collected in the study area were
ranging from 254– 331 mg/l
In the groundwater samples collected from the study area, the hardness was found to
be varying from 217 mg/l to 279 mg/l.
In the groundwater samples of study area the fluoride values were found to be within
a range of 0.28 mg/l to 0.53 mg/l.
All the heavy metals in all samples were found to be below the permissible limits.
Summary of surface water:
pH of the surface water collected was neutral with pH ranging from 7.2 -7.4
TDS was found to be 317 mg/l to 336 mg/l. The tolerance limit of 1,500 mg/l as per
IS:2296
Total hardness was found to be 165 mg/l to 191 mg/l
Presence of Nitrate was recorded as 2.1 mg/l to 2.8 mg/l
DO was observed as 5.8 mg/l to 6.6 mg/l
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
10
Total coliform in water was 690 MPN/100ml to 730 MPN/100ml The likely source of
bacteriological contamination was due to the proximity to residential area
All the heavy metals were found to be within below detectable limits.
1.7.4 LAND ENVIRONMENT:
Soil survey was carried out at 5 locations to assess the soil characteristics which
include both physical and chemical details.
Land Use Pattern:
The project covers a total ML area of 6.321 Ha., of Govt.Waste Land. During the
ensuing scheme period and area of 2.674 Ha., of land will be mined out, where as a
total of 2.674 Ha., of land will be degraded till the end of the scheme period.
The remaining area shall be put to use in the future basing on the demand for Road
Metal & Gravel.
1.7.5 FLORA & FAUNA:
No endangered species are found in the study area. No schedule – I species are found
within 10km radius from the proposed project site.
1.7.6 SOCIO-ECONOMIC ENVIRONMENT:
The operation of the proposed mining activity could result in elevation of living
standards of the people in nearby villages as it will generate work for the unemployed
and further will result in the upliftment of their socio-economic status. The
Management of M/s. Sujith Infra has proposed to give preference to local people for
recruitment of personal for mining operation. Therefore the impact on socio-economic
Environment could be beneficial.
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
11
1.8 RECLAMATION & REHABILITATION
The total mine lease area is about 6.321 Ha., During the ensuring scheme period an
area of 2.674 Ha., of land will be mined out. After Removal of mineral the benches
below the surface level the top benches will be applied top soil and develop grass and
plantation. An area of 0.5 Ha is proposed for green belt along the mine lease boundary
in 7.5m barrier zone.
1.9 PROJECT SCHEDULE AND COST ESTIMATES
The project cost is 490.0 Lakhs and the EMP budget is 41.0 Lakhs.
1.10 ENVIRONMENT MANAGEMENT PLAN
The Environment Management Plan envisaged for this mining activity is described
hereunder with a strong commitment to follow best environmental practices to reduce
the negative implication to make this project a sustainable development endeavor.
Environment Management Plan (EMP) is required to ensure sustainable development
in the study area of the proposed Mine Lease Area.
Air Environment:
Mitigation measures proposed to maintain the air quality are as follows:
Regular water sprinkling to suppress the dust on haul roads, service roads and
mining face by truck mounted water tankers.
Grading of haul roads, service roads time to time, to remove the accumulated dusty
material will be done.
Development of Green belt all around Plant and along mining area boundary.
Periodical monitoring of air quality to take steps to control the pollutants.
Noise Environment
There will be intermittent noise levels due to vehicular movement and trucks loading.
However the impact of noise on the surrounding area is likely to be minimal and
appropriate mitigation measures will be adopted accordingly.
Control Measures
The Management Plan for controlling noise pollution is envisaged as follows.
Selection of suitable machinery and equipment,
Proper mounting of equipment,
Providing noise insulation/padding wherever practicable and
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
12
Machinery will be fitted with properly designed noise acoustic silencers.
Proper maintenance and periodic lubrication of noise generating parts of the
machines.
Provision of thick plantation in and around the mine is planned in order to reduce
the noise and prevent it from reaching to surrounding habitation area.
Water Environment
There will not be any waste water generation except domestic waste water, therefore
no post waste water monitoring required.
Water Pollution Management
In anticipation of seasonal streams and run-off in the core zone, channels and
bunds would be constructed and maintained to avoid any erosion and contamination.
The mine pit water collected due to rains will be utilized for water spraying on the
haul roads and for watering plantation.
This water will be harvested for utilization in plantation watering, spraying on the
haulage roads and mineral and waste dumps.
1.11 SOCIO-ECONOMIC ENVIRONMENT AND SAFETY
The company management shall give preference to local people through both direct
and indirect employment.
It will provide ample opportunity to the locals to up-lift their living standards by
organizing events that propagate mutual benefits to all, such as health camps,
awareness campaigns, donations to poorer sections of society and downtrodden.
Educational needs of the region will be improved by encouraging the workers to
allow their children to attend schools.
Sufficient funds shall be allocated for these and other emergency needs.
Adequate supply of potable water to the workers will be made during the working
hrs.
The mines department will supervise the safe working of the contractor and their
employees. The working personnel will be provided with face masks, ear plugs,
safety helmets and goggles in order to reduce health hazards.
M/s. SUJITH INFRA – 6.321 Ha., EXECUTIVE SUMMARY
13
The proponent will provide all necessary provisions stipulated under the Mines Act.
In addition a Safety committee will be formed and manned by equal participants from
Management and Workers.
Personnel Protection Equipment (PPE) will be issued to each worker. Other safety
equipments shall be used according to the nature of job involved.
1.12 ENVIRONMENTAL MONITORING
Regular monitoring of various Environmental parameters shall be carried out to
ascertain the following points,
Status of air, noise, water, land pollution within the mining activity and in its
vicinity;
Generate data for predictive or corrective purpose in respect of environmental; and
To assess and monitor Environmental impacts periodically.
1.13 SAFETY AND ENVIRONMENT
The management firmly believes in the concept of safety and environmentally
sustainable growth. The authorities and staff are very much concern in
Environmental issues.
The management is going to develop scientifically designed green belt around the
premises to mitigate air and noise pollution impacts on the surroundings.
The management proposed to monitor ambient air as per APPCB guidelines.
All the employees will be provided with personnel protective equipment
The management will provide safety training to all employees periodically and
regularly.
1.14 CONCLUSION
The management of M/s. Sujith Infra is committed to meet all stringent norms and
to safe guard environment.