Example2 Two Equal Spans Option2 Final

Embed Size (px)

Citation preview

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    1/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 1

    Details on following slides

    Example 2 Option 2:

    Bent columns on capped piles

    Piles: 14" concrete-filled steel pipeAbutment

    Abutment

    Bent cap

    Pile cap

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    2/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 2

    4.0'

    20.0'

    8" slab deck

    Ground level

    4"

    railing

    6.25'

    47.0'

    8.25'

    24.0'

    4.0'

    Assumed point of pile fixity

    (idealized cantilever pile)

    Top of column at mid-

    height of bent cap

    Top of piles at mid-

    height of pile cap14.75' 12.75'

    32.25'

    BT-63 girder

    30.25'

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    3/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 3

    4.0'

    5.0' 8.5'

    2.0'

    12.75'

    13.0'

    Assumed point of pile fixity

    30"

    Bent cap

    Pile cap: 13' x 13' x 4'

    14" concrete-filled

    steel pipe

    2.0'

    2.0'

    4.5'

    4.5'

    13.0'

    6.5'

    Extend the pile to the mid-

    depth of the pile cap

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    4/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 4

    X

    ZX = 80.0'

    Z = -6.083'Z = -6.25'

    Z = -6.083'

    Z = -32.25'

    Z = -47.0'

    Z = 0

    Z = -6.25Z = -8.25'

    24.0'

    14.75

    X=75.5

    '

    X=73.5

    '

    X=84.5

    '

    X=86.5

    '

    Roller bearing

    (X = 0, X = 160')

    Pinned bearing

    Abutment

    Bent

    Extend the pile to the mid-

    depth of the pile cap

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    5/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 5

    2.0'

    4.0'

    8.5'

    13.0'

    15.0'

    Y

    Z

    Y=0

    Y=-2.0

    Y=-4.0

    Y=-8.5

    Y=-13.0

    Y=-15.0

    Y=2.0

    Y=4.0

    Y=8.5

    Y=13.0

    Views toward X = 0

    Units: feet

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    6/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 6

    X

    Z

    Y

    Bridg e Wizardcannot model the pile and pile cap.

    These must be modeled (drawn) manually.

    The pile cap is modeled as a 4.0' deep thick-plate

    element(element boundaries and all plate nodes

    are in one plane at the mid-depth of the plate).

    The piles are frame sectionsthat must be defined

    before they can be used.

    X = 80, Y = 0, Z = 0

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    7/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 7

    X

    Z

    Y

    next 2 slides

    Y

    =

    -8.5

    '

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    8/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 8

    View in +Xdirection

    nodes

    overlapping nodes

    bent cap

    pile

    column

    Z

    column ( frame section)

    bent cap ( frame section)

    pile cap ( thick-shell

    element )

    pile ( frame section)

    top of deckY

    Z = - 32.25'

    Z = - 8.25'

    Z = 0

    Z = - 47.0'

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    9/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 9

    mid-depth of pile cap in

    a plane at Z = - 32.25'

    top of column at mid-depth of bent cap at

    X = 80.0', Y = - 8.5', Z = - 8.25'

    bottoms of all piles at depth Z = - 47.0'

    X

    Z

    Y

    nodes

    overlapping nodes

    column

    pile

    tops of piles in a plane at

    cap mid-depth Z = - 32.25'

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    10/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 10

    Open file CSI Bridge fileExample2-Two-Equal-Span-Option2.bdb

    saved at the end of Option 1

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    11/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    12/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt12

    For the rest of this example, the Bridge Wizard will not be used

    Instead, the CSI command line tabs and sub-tabs in thescreen headings will be used. For example:

    Command l ine tab

    Sub-tabs

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    13/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    14/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 14

    Recall that in Option 1 the Bentwas

    named Bent_fixed_base

    Bent_fixed_base

    Fixedbase support

    ( all 6 d.o.f. )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    15/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 15

    For Option 2 a new Bentnamed Bent_free_basewill be created. The free

    end of each column base will later be connected to the pile cap foundation.

    Freebase support

    ( all 6 d.o.f. )

    Bent_free_base

    See next slide

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    16/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 16

    The built-in Base Supportoptions provided by the

    BridgeBent Column Dataform are only Pinnedor

    Fixed ( the default option is Fixed, as show ).

    In order to have a Free column base support it is

    necessary to define and attach a new user-defined

    FoundationSpringthat is freein all 6 d.o.f.

    This FoundationSpringis a new Component. It

    will be created in the following slides, and named

    Column_base_spr ing.

    Column_base_spr ing

    ( free in all 6 d.o.f. )

    Bent_free_base

    X

    Z

    Y

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    17/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 17

    Components command line tab, Item Foundation Springssub-tab

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    18/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 18

    Create a new Foundation Spring

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    19/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    20/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    21/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 21

    Components command line tab, Item Bents sub-tab

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    22/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 22

    Create a new Bentto be named Bent_free_base

    ( note that Bent_fixed_base already exists )

    Symbol for fixed reaction at base

    of column for Bent_fixed_base

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    23/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 23

    The new Bent_free_base has been

    created, but has not yet been assigned

    to the bridge model ( to replace the

    currently assigned Bent_free_base)

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    24/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    25/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 25

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    26/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 26

    Updatemodel to complete replacing Bent_fixed_basewith Bent_free_base

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    27/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 27

    No base reaction symbol is

    shown at a reaction point that

    is free ( Bent_free_base)

    Revising the reaction condition at the base of the bent columns is complete.

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    28/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 28

    Add a new Frame Sectionfor the 14"-diam concrete-filled steel pipe piles

    Review existingMaterial Properties

    Reinforcing steel

    Structural steel ( default )

    4 ksi concrete ( will be

    used in piles )

    The materials needed for the piles have already available ( no new materials are required )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    29/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 29

    Create a Frame Sectionfor the concrete-filled pipe pile

    ( reference: CSIBridge-EI-multiplier.ppt )

    doutside= 14"tw = 3/8"

    concrete core

    steel pipe

    CSI Bridge has no built-in Frame Sections of this type.

    1. Start with a concretesection whose outside diameter is that of the pipe doutside.

    douts ide = 14.0 in

    2. Enter a Stiffness Multiplication Factor SMF = 2.297 to increase the EI of the

    concretesection to that of the filled-pipe section

    The program uses the following method to create a FrameSectionlike this one:

    Concrete:

    fc' = 4 ksi

    Ec = 3708 ksi

    Note that the steelproperties

    are not entered ( they areneeded to compute the SMF )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    30/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 30

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    31/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    32/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 32

    Conc_fi l led_pipe_pi leis a fictitious 14"-diam concrete pile section whose stiffness has been

    increased by a SMF = 2.297 so that it will act as a concrete-filled steel pipe pile section.

    Complete creating Conc_fi l led_pipe_pi le

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    33/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    34/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 34

    Verify units:

    Kip, ft, F

    Complete Pile_cap_platedefinition

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    35/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 35

    Redefined bent:

    Bent_free_base

    New component definitions added:

    Pile cap thick-plate elements:

    Pile_cap_plate

    Concrete-filled steel pipe piles:

    Conc_fi l led_pipe_pile

    X

    Z

    Z = -32.25'

    24.0'Bent_free_base

    "Free" bent column base defined by:

    Column_base_spr ing(free in 6 d.o.f.)

    Bridge is now ready for adding pile/cap foundation

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    36/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 36

    Add the pile cap and piles to each column in the Bridge Model

    The bent cap, bent columns and the piles have been defined as Frame Sections.

    The pile cap finite elements have been defined as a thick plate Area Sections.

    Piles: 14" concrete-filled steel pipe pile

    Bent cap: 4.0' x 4.0' x 27.0'

    ( already in Bridge Model )

    Pile cap: 13.0' x 13.0' x 4.0' thick plate element

    Bent column: 30"-diam x 24.0'

    ( already in Bridge Model )

    X

    Z

    Y

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    37/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 37

    Z

    Y

    8.25'

    Draw this pile/cap foundation first,

    and then copy to other side

    X

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    38/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 38

    Z = - 32.25

    Z = - 8.25

    Z = 0

    Z = - 47.0

    Y

    Z View in +Xdirection

    ( section thru X = 80)

    Z = - 32.25

    Z = - 47.0

    X

    Z

    Z = - 8.25

    Z = 0

    View in +Ydirection

    ( section thruY = - 8.5)

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    39/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    40/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 40

    nodes required to for pile cap area

    nodes required to draw piles

    nodes at ends of column

    nodes that will be inserted when pile

    cap is assembled from plate elements

    X

    Z

    Y

    Z = - 32.25

    Z = - 8.25

    Z = - 47.0

    Nodes ( "joints" ) and grid lines

    The grid lines will be used to draw

    thick plate elementsthat make up

    the pile cap, and the nine piles.

    Nodes will be added by the program

    as these components are drawn.

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    41/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 41

    Z = - 32.25'

    Z = - 8.25'

    Z = - 47.0'

    In order to draw piles and pile cap

    grid lines will be required at:

    X = 73.5 , 75.5 , 80.0 , 84.5 , 86.5

    Y = -2.0 , -4.0 , -8.5 , -13.0 , -15.0

    Z = -8.25 , -32.25 , - 47.0

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    42/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    43/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 43

    Typical joint and label

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    44/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    45/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    46/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 46

    Repeat Rubberband Zoom

    to zoom in further

    Region enclosed with RubberbandZoomexpanded to full view window

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    47/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    48/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 48

    Uncheck

    Turn off Joint Labels, but leave Jointsshowing

    Rememberthese joints are

    automatically created by CSI Bridge

    anytime model is Updated

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    49/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 49

    Right-click anywhere in

    drawing window

    Can be in any heading ( Homeshow here )

    View default grid linescreated by CSI Brid ge

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    50/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    51/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 51

    1. Delete the grid lines for X = 0, Y = 0 and Z = 0

    2. Enter grid lines listed on Slide 38 ( be certain units are Kip, ft, F)

    Enter

    Double left-click on

    each cell

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    52/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 52

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    53/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 53

    Only the grid lines listed in the Define

    Grid System Datatable are shown

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    54/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    55/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    56/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 56

    View of XZplane ( in +Ydirection )

    If the XZ view is chosen, then the user can

    "step through" the XZ planes at

    Y = -2.0 , -4.0 , -8.5 , -13.0 , and -15.0

    These are the planes that have been created

    by drawing the grid lines.

    There must be grid lines at these Y locations

    for the "step through" to be possible

    X

    Z

    Y

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    57/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 57

    Switch to a 2D view in the XZplane in the +Ydirection

    View of XZplane

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    58/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 58

    View of XZplane atY = -15

    "X-Z Plane @ Y=-15"

    X=0

    X=80

    X=160

    X=86.5

    X=73.5

    X=73.5

    X=84.5

    Z = -8.25

    Z = -32.25

    Z = -47.0

    Cursor location

    Use arrows to "step up" or "step down" through Y planes

    Grid lines

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    59/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    60/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    61/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    62/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    63/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    64/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 64

    For a horizontalelement ( on that lies in the structure X-Yplane ) the plate element 1-2-3

    local coordinates are oriented as shown:

    U1

    U2

    U3

    R3

    R2

    R1

    1

    3

    2

    X

    Z

    Y

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    65/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 65

    Bent column

    PilePile

    Joint

    Element

    Pile cap corner

    Pile-to-cap connection Column-to-pile-to-cap connection

    The pile cap must be subdivided into enough

    elements so that there is ajo in tat each location

    where "something happens":

    Pile cap corners

    Pile-to-cap connections

    Bent column-to-pile-to-cap connection

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    66/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    67/178

    D il i XY l t Z 32 25

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    68/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 68

    Draw pile cap in XYplane at Z = -32.25

    Use Hometab Rubberband Zoomto enlarge figure

    nodes at column bases

    grid lines

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    69/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 69

    Enlarged view of XYplane grid lines at Z = -32.25

    Joint at column base

    grid lines

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    70/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    71/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 71

    Draw rectangular area

    Select Area Section

    Pile_cap_platethat

    was defined earlier

    Select Rectangular Areatab and select Area Section

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    72/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    73/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    74/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 74

    Move(not drag) the

    cursor to this Grid Point

    and left-clickmouse

    1

    Line added to show element just drawn

    Position cursor to draw element 2

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    75/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 75

    Move(not drag) cursor

    pointer to Grid Point

    Left-clickmousethis will

    show joints at the corners of

    plate element 2just drawn

    2 11 2

    Lines added to show previously-drawn element

    Dotted line appears as cursor is moved until Grid Point is reached

    Draw the secondof 16 plate Areaelements

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    76/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    77/178

    P iti t d l t 4

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    78/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 78

    Move(not drag) the cursor to this

    Grid Pointand left-clickmouse

    Grid point

    1 2 3

    Position cursor to draw element 4

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    79/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 79

    Grid point

    Move(not drag) cursor

    pointer to Grid Point

    Left-clickmousethis will

    show joints at the corners of

    plate element 4just drawn

    41 2 3 41 2 3

    Dotted line appears as cursor is moved until Grid Point is reached

    Dotted lines added to show

    previously-drawn elements

    Draw the fourthof 16 plate Areaelements

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    80/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    81/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    82/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 82

    Second row of fourelementsthat make up the

    pile cap plate. Againjoints

    have been inserted at the

    corners of each element at

    the grid points.

    Dotted lines added to show elements

    1 2 3 4

    5 6 7 8

    Firstand second rows of elements are now drawn

    Draw third row of 4 elements ( elements 912 of 16 )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    83/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 83

    Start

    Left-click

    Left-click

    Left-click

    Left-click End

    ( )

    Fi t d d thi d f l t d

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    84/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 84

    Third row of four elements

    that make up the pile cap

    plate.

    Dotted lines added to show elements

    1 2 3 4

    5 6 7 8

    9 10 11 12

    First, second, and third rows of elements are now drawn

    Draw fourth row of 4 elements ( elements 13 16 of 16 )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    85/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 85

    Start

    Left-clickLeft-click Left-click

    Left-click

    End

    Left-click

    Draw fourth row of 4 elements ( elements 13 16 of 16 )

    Drawing of Area elements that make up pile cap is complete

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    86/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 86

    Drawing of Areaelements that make up pile cap is complete

    Fourth row of four elementsthatmake up the pile cap plate.

    Dotted lines added to show elements

    1 2 3 4

    5 6 7 8

    9 10 11 12

    13 14 15 16

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    87/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 87

    Click arrow symbol to exit drawing mode Go to Homeand turn on Extrude View

    Grayed area shows elements just drawn

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    88/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    89/178

    Turn on Area Labels and Local Axes

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    90/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 90

    Turn on Area Labelsand Local Axes

    X

    Z

    Y

    Turn onExtrude View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    91/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 91

    Z = - 32.25

    4.0'

    Z = - 32.25

    In Display Options

    check Extrude View

    Labelsare not shown

    in Extrude View

    Use Set 3D Viewto switch to XZ View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    92/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 92

    XZ view

    XZ l E t d Vi ( P ti t l d ff )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    93/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 93

    XZplane Extrude View( Perspectivetoggled off )

    Base of column atmid-depth of pile cap

    Z = -32.25

    Perspectivetoggle

    D th th il t Y 13 0

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    94/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 94

    Draw the three piles at Y = -13.0

    Z = - 32.25

    Z = - 47.0

    Switch to XZ View and step to plane at Y = -13

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    95/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 95

    Switch to XZ Viewand step to plane atY 13

    Here, do not use Moreto set view

    Three piles will be draw

    using these grid lines

    Use Rubberband Zoom to expand the area where the piles will be drawn

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    96/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 96

    Use Rubberband Zoomto expand the area where the piles will be drawn

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    97/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 97

    Three piles will be draw using

    these three grid lines

    Mid-depth of pile cap

    Z = -32.25

    Tips of pilesZ = -47.0

    Go to Advancedtab, which opens Drawoptions

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    98/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 98

    , p p

    Select Frame/Cable/Tendon

    Select from list

    Draw pile at X = 75 5

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    99/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 99

    Draw pile at X = 75.5

    Move pointer to grid point atX = 75.5, Y = -13.0, Z = -47.0

    Left c l ickto begin drawing

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    100/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 100

    Move pointer to grid point at

    X = 75.5, Y = -13.0, Z = -32.25

    Left cl ickto complete line

    Right cl ick to "lift pencil"

    Draw pile at X = 80 0

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    101/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 101

    Draw pile at X = 80.0

    Move pointer to grid point atX = 80.0, Y = -13.0, Z = -47.0

    Left c l ickto begin drawing

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    102/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 102

    Move pointer to grid point at

    X = 80.0, Y = -13.0, Z = -32.25

    Left c l ickto complete line

    Right cl ick to "lift pencil"

    Draw pile at X = 84.5

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    103/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 103

    Move pointer to grid point at

    X = 84.5, Y = -13.0, Z = -47.0

    Left cl ickto begin drawing

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    104/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 104

    Move pointer to grid point at

    X = 84.5, Y = -13.0, Z = -32.25

    Left cl ickto complete line

    Right cl ick to "lift pencil"

    The three piles at Y = -13.0 are complete

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    105/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 105

    Exit drawing mode

    At Hometab Refresh Windowto see the piles and nodes just drawn

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    106/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 106

    What's missing?

    There are no boundary

    restraintsat the column bases(as shown, columns are free in

    all d.o.f.)

    Apply a fixedboundary restraint at the base of the column at X = 75.5

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    107/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 107

    Pile

    Right cl ickon joint Flashing red circle

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    108/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 108

    Double left click

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    109/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 109

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    110/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 110

    Restraint symbol

    added at node

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    111/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 111

    Repeat for these nodes ( one at a time )

    See next page

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    112/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 112

    Right clickjoint

    Double left click

    Piles with boundary restraints completed at Y = -13.0 are complete

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    113/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 113

    Refresh drawing

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    114/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 114

    Rubberband Zoomthis area

    Piles, nodes and boundary restraints at Y = -13.0

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    115/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 115

    Nodes at outer cornersof corner plate elements

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    116/178

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    117/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 117

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    118/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 118

    Base of column and tops of

    piles at mid-depth of pile cap

    Z = -32.25

    Tips of piles

    Z = -47.0

    Draw the three piles each at Y = -8.5 and Y = -4.0

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    119/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 119

    Z = - 32.25

    Z = - 47.0

    Option 1: In XZViewmanually draw piles at Y = -8.5 and Y = -4.0

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    120/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 120

    Y = -8.5

    Y = -4.0

    Step to Y = -8.5 and draw threepiles and add boundary restraints

    as previously shown

    Step to Y = -4.0 and repeat

    Option 2: Replicatethe three piles and boundary restraints at Y = -13.0

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    121/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 121

    to Y = -8.5 and Y = -4.0. This can be done in

    1. Two steps: Replicate three piles at Y = -13.0 to Y = -8.5 in one step,

    and then replicate the same piles atY = -13.0 to Y = -4.0

    in a separate step

    2. One step: Replicate three piles at Y = -13.0 to both Y = -8.5 and

    Y = -4.0 in a single step.

    The one-step replication is possible if spacings between the three lines of piles are the same.

    Here, the spacings between Y = -13 andY = -8.5 and between Y = -85. and Y = -4.0 are

    Y = +4.5 . Note thatY is positive because the "Y steps" will be from Y = -13.0 to

    Y = -8.5 and then from Y = -8.5 to Y = -4.0.

    The one-step replication will be use here.

    Show only the footing/pile area

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    122/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 122

    Rubberband Zoomthis area

    Select: Three piles, six nodes (at ends of piles), and three boundary restraints

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    123/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 123

    Do not include the

    plate edge nodes

    for replication

    Use the following four steps

    to make this selection

    Selection Step 1

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    124/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 124

    Hold leftbutton down

    Let left

    button up

    Drag mouse from leftto right

    Selected area

    Plate corner node

    Node at bottom of pile

    Node at top of pileDrag mouse to include the pile,

    plus the joints at the top and

    bottom of the pile.

    Note that the plate corner node

    cannot be avoided. It will be

    deselected in Step 4.

    Selection Step 2 Selection Step 3

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    125/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 125

    p Selection Step 3

    Hold left

    button down

    Let left

    button up

    Drag mouse

    Selected area

    Node at top of pile

    Node at bottom of pile

    Drag mouse

    Hold left

    button down

    Let left

    button up

    Selected area

    Node at top

    of pile

    Node at bottom

    of pile

    Selection Step 4

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    126/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 126

    Selection Step 4

    Objects to be replicated

    Left-click to deselect

    the plate corner joint

    Replicate3-pile selection Y = +4.5 twice in one step

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    127/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 127

    Y = +4.5

    Y = +4.5

    Replicatecompletedview in Hometab, Rubberband Zoom

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    128/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 128

    Rubberband Zoom

    Two rows of

    piles added

    Perspective Extrude Viewof selected area

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    129/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 129

    Open and select Extrude View

    Switch to XZ View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    130/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 130

    XZ Extrude View ( Perspectiveturned off )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    131/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 131

    X

    Z

    Perspectivetoggle

    Switch to YZ View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    132/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 132

    YZ Extrude View ( Perspectiveturned off )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    133/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 133

    Y

    ZView towardX = 0

    Pile rows added by Replicate

    Perspectivetoggle

    Z Z

    Finish drawing the foundations

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    134/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 134

    Y

    Z

    5.0 5.017.0

    Y

    Z

    Y = +17.0

    Replicate

    Just completed

    In Hometab:

    Turn off Extrude View, select 3-dView, and Rubberband Zoomto get area shown

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    135/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 135

    u o Extrude View , se ec 3 d View , a d Rubberband Zoom o ge a ea s o

    Drag mouse from left to right to select pile cap and piles

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    136/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 136

    Start selection

    End selection

    Be sure to include the

    plate node at the farcorner of the pile cap.

    Selected objects to Replicate

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    137/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 137

    Selected objects: Pile cap

    (16 finite elements) and

    nine fixed-base piles

    Replicateselected objects

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    138/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 138

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    139/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 139

    Replicated objectsnote that grid

    lines are not replicated or expanded

    In Hometab, return to Perspective View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    140/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 140

    Switch to Perspective Extrude View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    141/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 141

    Switch toYZ Extrude View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    142/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 142

    YZ Extrude View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    143/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 143

    Y

    Z

    Grid lines

    Perspectivetoggle

    Y

    Z

    Perspectiveon Perspectiveoff

    Grid lines

    The grid linescan now be either deletedor hidden

    Deletegrid lines .. a bad idea .DON'T DO IT

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    144/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 144

    Delete all

    Right click

    anywhere in view

    panel

    Hidethe grid lines

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    145/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 145

    Right click

    anywhere in view

    panel

    The grid lines are still there, but are hidden.

    They can be unhidden by the same procedure ( as will be done in Option 3 of this Exercise )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    146/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 146

    Foundation drawing completed and the grid has been hidden

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    147/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 147

    Perspectiveon

    Perspectivetoggle

    Perspectiveoff

    But.is the foundation part

    of the Bridge Model?

    In Hometab, Restore Full View( Perspective) and turn off Extrude View

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    148/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 148

    In Bridgetab, Updatethe Bridge Modelto include the foundations

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    149/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 149

    After the Bridge Modelhas been updated, switch to the Analysistab

    and run an analysis for the DEADloads

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    150/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 150

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    151/178

    In the Hometab, open the Deformed Shapebox

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    152/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 152

    The deformed shape has been drawn using a

    very small default Auto Scalingfactor

    Choose a Scale Factorthat shows a reasonable deformed shape

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    153/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 153

    The magnitude of the scale factor has no physical

    significance it is just a relative number

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    154/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 154

    Extrude Viewoff

    Extrude Viewon

    Displacements U1, U2, U3measured in structure X-Y-Zcoordinates

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    155/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 155

    X (U1)

    Z (U3)

    Y (U2)

    Deflected profile

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    156/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 156

    Deflection reference line

    Deflection at bent due to elastic shortening

    of the bent columns and the piles

    X (U1)

    Z (U3)

    XZplane

    Selected vertical deflections

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    157/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 157

    U3 = -0.2957 in

    X (U1)

    Z (U3)

    Set units to inches

    Move cursor to joint

    U3 = -0.0593 in

    Longitudinal ( M3) moment diagramEntire Bridge

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    158/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 158

    X

    Z

    Y

    1

    2

    3

    Structure ("global")

    coordinate system

    Member coordinate system for

    member laid out from X = 0 toX at the end of the bridge

    3107 ft-k

    4913 ft-k

    Compare DEADload moment diagrams for two column base options

    Option 2Option 1

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    159/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 159

    Bent columns on pile foundations

    ( column extended to mid-depth

    of pile cap )

    3107 ft-k

    4913 ft-k

    Bent columns fixed at bases

    4949 ft-k

    2997 ft-k

    Why are they different?

    Vertical reactions at tips of piles

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    160/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 160

    If necessary, use Display Options

    to turn off viewing Restraints

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    161/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 161

    Rubberband Zoomto

    isolate this footing

    Isolated view of pile footing reactions in Y region

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    162/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 162

    Bentcolumn

    Right-click on joint

    In XZ plane view reactions at each Y position

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    163/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 163

    Use arrows to select Y = - 4.0

    ( note that Y position is notshown

    anywhere on the screennasty )

    Rubberband Zoom

    Vertical reactions atY = - 13.0 ft

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    164/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 164

    X=75.5

    X=80.0

    X

    =84.5

    Y = - 13.0

    Vertical reactions at Y = - 8.5 ft

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    165/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 165

    X=75.5

    X=80.0

    X=

    84.5

    Y = - 8.5

    Vertical reactions at Y = - 4.0 ft

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    166/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 166

    X=75.5

    X=80.0

    X=

    84.5

    Y = - 4.0

    Total upward vertical reactionper pile footing

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    167/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 167

    52.47 + 55.05 + 52.39 = 159.9

    52.47 + 55.05 + 52.39 = 159.9

    55.09 + 65.87 + 55.01 = 176.0 495.8 kips

    Axial forceat base of bent column

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    168/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 168

    present view ( whatever it may be )

    Display member axial force for Frame Members

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    169/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 169

    Rubberband Zoom to improve resolution

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    170/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 170

    Bent column appears when Y = - 8.5'

    Select Y = - 8.5 ft

    Note: Y position not shown!!

    Rubberband zoom

    Axial force near base of bent column ( approximately at top of pile cap )

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    171/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 171

    Bent column appears when Y = - 8.5'

    Axial compression near base of bent

    column = - 372.0 (4 sig. figures)

    Alternate viewXZ View ( Rubberband Zoom)

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    172/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 172

    Bent column appears when Y = - 8.5'

    Axial compression near base of bent

    column = - 372.0 (4 sig. figures)

    Select Y = - 8.5 ft in XZ view

    Note: Y position not shown!!

    Show member axial force diagrams

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    173/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 173

    If necessary, use Display Options

    to turn off viewing Restraints

    Compression forces in piles and in bent column where it connects to

    the plate element at the mid-depth of the pile cap

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    174/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 174

    R = 52.47

    (earlier slides)

    Put cursoron joint

    Rubberband Zoom

    Use Advanced Assign More to clear display of currently-shown results

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    175/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 175

    13.0' x 13.0'

    concrete pile capWeight of concrete pile cap( disregard 2.0' steel pipe

    Pile and cap weights

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    176/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 176

    4.0'

    12.75'

    concrete pile cap

    concrete filled 14"-diamsteel piles ( 9 total )

    doutside= 14"

    tw = 3/8"

    concrete core

    steel pipe

    g p p ( g p p

    length extensions into pile cap ):

    13.0' x 13.0' x 4.0' x 0.15 k/ft3

    = 101.4 kips

    Weight per pile:

    Core diameter = 13.25" / 12 in/ft = 1.102 ft

    ft/ft9575.0ft/ft4

    104.1 222

    Core area per foot =

    Core weight = 0.9575 ft2/f x 0.15 k/ft3 = 0.1436 k/ft

    Pipe area per foot = ft/ft1115.0ft/)ft/in144(4

    in)25.130.14( 222

    222

    Pipe weight = 0.1115 ft2/f x 0.495 k/ft3 = 0.0552 k/ft

    Pile weight per foot = ( 0.1436 + 0.0552 ) k/ft = 0.1988 k/ft

    Weight per pile = 0.1988 k/ft x 12.75 ft = 2.535 k/pile

    Total pile weight = 2.535 k/pile x 9 piles = 22.8 kips

    Check pile footing vertical equilibrium

    Column force near top of pile cap = 372.0 kips

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    177/178

    10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 177

    Total reaction = 495.8 kips upward ( Slide 176 )

    Total pile weight = 22.8 kips

    Pile cap weight = 101.4 kips

    496.2 kips downward

    Close enough !!

    (why not use 373.1 kipsSlide 176 ??)

    Save your CSI Bridge .bdb file in twoversions:

  • 8/13/2019 Example2 Two Equal Spans Option2 Final

    178/178

    Save as: Example2-Two-Equal-Span-Option2.bdb

    This is the option just completed in which the two columns bases frame into

    the pile cap in a pile-cap/piles foundation

    Save as: Example2-Two-Equal-Span-Option3.bdb

    This will be the starting point for the next option in which the columns bases

    are connected to the pile caps by Joint Constra ints