Upload
philipyap
View
224
Download
0
Embed Size (px)
Citation preview
8/13/2019 Example2 Two Equal Spans Option2 Final
1/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 1
Details on following slides
Example 2 Option 2:
Bent columns on capped piles
Piles: 14" concrete-filled steel pipeAbutment
Abutment
Bent cap
Pile cap
8/13/2019 Example2 Two Equal Spans Option2 Final
2/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 2
4.0'
20.0'
8" slab deck
Ground level
4"
railing
6.25'
47.0'
8.25'
24.0'
4.0'
Assumed point of pile fixity
(idealized cantilever pile)
Top of column at mid-
height of bent cap
Top of piles at mid-
height of pile cap14.75' 12.75'
32.25'
BT-63 girder
30.25'
8/13/2019 Example2 Two Equal Spans Option2 Final
3/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 3
4.0'
5.0' 8.5'
2.0'
12.75'
13.0'
Assumed point of pile fixity
30"
Bent cap
Pile cap: 13' x 13' x 4'
14" concrete-filled
steel pipe
2.0'
2.0'
4.5'
4.5'
13.0'
6.5'
Extend the pile to the mid-
depth of the pile cap
8/13/2019 Example2 Two Equal Spans Option2 Final
4/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 4
X
ZX = 80.0'
Z = -6.083'Z = -6.25'
Z = -6.083'
Z = -32.25'
Z = -47.0'
Z = 0
Z = -6.25Z = -8.25'
24.0'
14.75
X=75.5
'
X=73.5
'
X=84.5
'
X=86.5
'
Roller bearing
(X = 0, X = 160')
Pinned bearing
Abutment
Bent
Extend the pile to the mid-
depth of the pile cap
8/13/2019 Example2 Two Equal Spans Option2 Final
5/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 5
2.0'
4.0'
8.5'
13.0'
15.0'
Y
Z
Y=0
Y=-2.0
Y=-4.0
Y=-8.5
Y=-13.0
Y=-15.0
Y=2.0
Y=4.0
Y=8.5
Y=13.0
Views toward X = 0
Units: feet
8/13/2019 Example2 Two Equal Spans Option2 Final
6/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 6
X
Z
Y
Bridg e Wizardcannot model the pile and pile cap.
These must be modeled (drawn) manually.
The pile cap is modeled as a 4.0' deep thick-plate
element(element boundaries and all plate nodes
are in one plane at the mid-depth of the plate).
The piles are frame sectionsthat must be defined
before they can be used.
X = 80, Y = 0, Z = 0
8/13/2019 Example2 Two Equal Spans Option2 Final
7/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 7
X
Z
Y
next 2 slides
Y
=
-8.5
'
8/13/2019 Example2 Two Equal Spans Option2 Final
8/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 8
View in +Xdirection
nodes
overlapping nodes
bent cap
pile
column
Z
column ( frame section)
bent cap ( frame section)
pile cap ( thick-shell
element )
pile ( frame section)
top of deckY
Z = - 32.25'
Z = - 8.25'
Z = 0
Z = - 47.0'
8/13/2019 Example2 Two Equal Spans Option2 Final
9/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 9
mid-depth of pile cap in
a plane at Z = - 32.25'
top of column at mid-depth of bent cap at
X = 80.0', Y = - 8.5', Z = - 8.25'
bottoms of all piles at depth Z = - 47.0'
X
Z
Y
nodes
overlapping nodes
column
pile
tops of piles in a plane at
cap mid-depth Z = - 32.25'
8/13/2019 Example2 Two Equal Spans Option2 Final
10/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 10
Open file CSI Bridge fileExample2-Two-Equal-Span-Option2.bdb
saved at the end of Option 1
8/13/2019 Example2 Two Equal Spans Option2 Final
11/178
8/13/2019 Example2 Two Equal Spans Option2 Final
12/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt12
For the rest of this example, the Bridge Wizard will not be used
Instead, the CSI command line tabs and sub-tabs in thescreen headings will be used. For example:
Command l ine tab
Sub-tabs
8/13/2019 Example2 Two Equal Spans Option2 Final
13/178
8/13/2019 Example2 Two Equal Spans Option2 Final
14/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 14
Recall that in Option 1 the Bentwas
named Bent_fixed_base
Bent_fixed_base
Fixedbase support
( all 6 d.o.f. )
8/13/2019 Example2 Two Equal Spans Option2 Final
15/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 15
For Option 2 a new Bentnamed Bent_free_basewill be created. The free
end of each column base will later be connected to the pile cap foundation.
Freebase support
( all 6 d.o.f. )
Bent_free_base
See next slide
8/13/2019 Example2 Two Equal Spans Option2 Final
16/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 16
The built-in Base Supportoptions provided by the
BridgeBent Column Dataform are only Pinnedor
Fixed ( the default option is Fixed, as show ).
In order to have a Free column base support it is
necessary to define and attach a new user-defined
FoundationSpringthat is freein all 6 d.o.f.
This FoundationSpringis a new Component. It
will be created in the following slides, and named
Column_base_spr ing.
Column_base_spr ing
( free in all 6 d.o.f. )
Bent_free_base
X
Z
Y
8/13/2019 Example2 Two Equal Spans Option2 Final
17/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 17
Components command line tab, Item Foundation Springssub-tab
8/13/2019 Example2 Two Equal Spans Option2 Final
18/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 18
Create a new Foundation Spring
8/13/2019 Example2 Two Equal Spans Option2 Final
19/178
8/13/2019 Example2 Two Equal Spans Option2 Final
20/178
8/13/2019 Example2 Two Equal Spans Option2 Final
21/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 21
Components command line tab, Item Bents sub-tab
8/13/2019 Example2 Two Equal Spans Option2 Final
22/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 22
Create a new Bentto be named Bent_free_base
( note that Bent_fixed_base already exists )
Symbol for fixed reaction at base
of column for Bent_fixed_base
8/13/2019 Example2 Two Equal Spans Option2 Final
23/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 23
The new Bent_free_base has been
created, but has not yet been assigned
to the bridge model ( to replace the
currently assigned Bent_free_base)
8/13/2019 Example2 Two Equal Spans Option2 Final
24/178
8/13/2019 Example2 Two Equal Spans Option2 Final
25/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 25
8/13/2019 Example2 Two Equal Spans Option2 Final
26/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 26
Updatemodel to complete replacing Bent_fixed_basewith Bent_free_base
8/13/2019 Example2 Two Equal Spans Option2 Final
27/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 27
No base reaction symbol is
shown at a reaction point that
is free ( Bent_free_base)
Revising the reaction condition at the base of the bent columns is complete.
8/13/2019 Example2 Two Equal Spans Option2 Final
28/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 28
Add a new Frame Sectionfor the 14"-diam concrete-filled steel pipe piles
Review existingMaterial Properties
Reinforcing steel
Structural steel ( default )
4 ksi concrete ( will be
used in piles )
The materials needed for the piles have already available ( no new materials are required )
8/13/2019 Example2 Two Equal Spans Option2 Final
29/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 29
Create a Frame Sectionfor the concrete-filled pipe pile
( reference: CSIBridge-EI-multiplier.ppt )
doutside= 14"tw = 3/8"
concrete core
steel pipe
CSI Bridge has no built-in Frame Sections of this type.
1. Start with a concretesection whose outside diameter is that of the pipe doutside.
douts ide = 14.0 in
2. Enter a Stiffness Multiplication Factor SMF = 2.297 to increase the EI of the
concretesection to that of the filled-pipe section
The program uses the following method to create a FrameSectionlike this one:
Concrete:
fc' = 4 ksi
Ec = 3708 ksi
Note that the steelproperties
are not entered ( they areneeded to compute the SMF )
8/13/2019 Example2 Two Equal Spans Option2 Final
30/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 30
8/13/2019 Example2 Two Equal Spans Option2 Final
31/178
8/13/2019 Example2 Two Equal Spans Option2 Final
32/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 32
Conc_fi l led_pipe_pi leis a fictitious 14"-diam concrete pile section whose stiffness has been
increased by a SMF = 2.297 so that it will act as a concrete-filled steel pipe pile section.
Complete creating Conc_fi l led_pipe_pi le
8/13/2019 Example2 Two Equal Spans Option2 Final
33/178
8/13/2019 Example2 Two Equal Spans Option2 Final
34/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 34
Verify units:
Kip, ft, F
Complete Pile_cap_platedefinition
8/13/2019 Example2 Two Equal Spans Option2 Final
35/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 35
Redefined bent:
Bent_free_base
New component definitions added:
Pile cap thick-plate elements:
Pile_cap_plate
Concrete-filled steel pipe piles:
Conc_fi l led_pipe_pile
X
Z
Z = -32.25'
24.0'Bent_free_base
"Free" bent column base defined by:
Column_base_spr ing(free in 6 d.o.f.)
Bridge is now ready for adding pile/cap foundation
8/13/2019 Example2 Two Equal Spans Option2 Final
36/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 36
Add the pile cap and piles to each column in the Bridge Model
The bent cap, bent columns and the piles have been defined as Frame Sections.
The pile cap finite elements have been defined as a thick plate Area Sections.
Piles: 14" concrete-filled steel pipe pile
Bent cap: 4.0' x 4.0' x 27.0'
( already in Bridge Model )
Pile cap: 13.0' x 13.0' x 4.0' thick plate element
Bent column: 30"-diam x 24.0'
( already in Bridge Model )
X
Z
Y
8/13/2019 Example2 Two Equal Spans Option2 Final
37/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 37
Z
Y
8.25'
Draw this pile/cap foundation first,
and then copy to other side
X
8/13/2019 Example2 Two Equal Spans Option2 Final
38/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 38
Z = - 32.25
Z = - 8.25
Z = 0
Z = - 47.0
Y
Z View in +Xdirection
( section thru X = 80)
Z = - 32.25
Z = - 47.0
X
Z
Z = - 8.25
Z = 0
View in +Ydirection
( section thruY = - 8.5)
8/13/2019 Example2 Two Equal Spans Option2 Final
39/178
8/13/2019 Example2 Two Equal Spans Option2 Final
40/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 40
nodes required to for pile cap area
nodes required to draw piles
nodes at ends of column
nodes that will be inserted when pile
cap is assembled from plate elements
X
Z
Y
Z = - 32.25
Z = - 8.25
Z = - 47.0
Nodes ( "joints" ) and grid lines
The grid lines will be used to draw
thick plate elementsthat make up
the pile cap, and the nine piles.
Nodes will be added by the program
as these components are drawn.
8/13/2019 Example2 Two Equal Spans Option2 Final
41/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 41
Z = - 32.25'
Z = - 8.25'
Z = - 47.0'
In order to draw piles and pile cap
grid lines will be required at:
X = 73.5 , 75.5 , 80.0 , 84.5 , 86.5
Y = -2.0 , -4.0 , -8.5 , -13.0 , -15.0
Z = -8.25 , -32.25 , - 47.0
8/13/2019 Example2 Two Equal Spans Option2 Final
42/178
8/13/2019 Example2 Two Equal Spans Option2 Final
43/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 43
Typical joint and label
8/13/2019 Example2 Two Equal Spans Option2 Final
44/178
8/13/2019 Example2 Two Equal Spans Option2 Final
45/178
8/13/2019 Example2 Two Equal Spans Option2 Final
46/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 46
Repeat Rubberband Zoom
to zoom in further
Region enclosed with RubberbandZoomexpanded to full view window
8/13/2019 Example2 Two Equal Spans Option2 Final
47/178
8/13/2019 Example2 Two Equal Spans Option2 Final
48/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 48
Uncheck
Turn off Joint Labels, but leave Jointsshowing
Rememberthese joints are
automatically created by CSI Bridge
anytime model is Updated
8/13/2019 Example2 Two Equal Spans Option2 Final
49/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 49
Right-click anywhere in
drawing window
Can be in any heading ( Homeshow here )
View default grid linescreated by CSI Brid ge
8/13/2019 Example2 Two Equal Spans Option2 Final
50/178
8/13/2019 Example2 Two Equal Spans Option2 Final
51/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 51
1. Delete the grid lines for X = 0, Y = 0 and Z = 0
2. Enter grid lines listed on Slide 38 ( be certain units are Kip, ft, F)
Enter
Double left-click on
each cell
8/13/2019 Example2 Two Equal Spans Option2 Final
52/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 52
8/13/2019 Example2 Two Equal Spans Option2 Final
53/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 53
Only the grid lines listed in the Define
Grid System Datatable are shown
8/13/2019 Example2 Two Equal Spans Option2 Final
54/178
8/13/2019 Example2 Two Equal Spans Option2 Final
55/178
8/13/2019 Example2 Two Equal Spans Option2 Final
56/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 56
View of XZplane ( in +Ydirection )
If the XZ view is chosen, then the user can
"step through" the XZ planes at
Y = -2.0 , -4.0 , -8.5 , -13.0 , and -15.0
These are the planes that have been created
by drawing the grid lines.
There must be grid lines at these Y locations
for the "step through" to be possible
X
Z
Y
8/13/2019 Example2 Two Equal Spans Option2 Final
57/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 57
Switch to a 2D view in the XZplane in the +Ydirection
View of XZplane
8/13/2019 Example2 Two Equal Spans Option2 Final
58/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 58
View of XZplane atY = -15
"X-Z Plane @ Y=-15"
X=0
X=80
X=160
X=86.5
X=73.5
X=73.5
X=84.5
Z = -8.25
Z = -32.25
Z = -47.0
Cursor location
Use arrows to "step up" or "step down" through Y planes
Grid lines
8/13/2019 Example2 Two Equal Spans Option2 Final
59/178
8/13/2019 Example2 Two Equal Spans Option2 Final
60/178
8/13/2019 Example2 Two Equal Spans Option2 Final
61/178
8/13/2019 Example2 Two Equal Spans Option2 Final
62/178
8/13/2019 Example2 Two Equal Spans Option2 Final
63/178
8/13/2019 Example2 Two Equal Spans Option2 Final
64/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 64
For a horizontalelement ( on that lies in the structure X-Yplane ) the plate element 1-2-3
local coordinates are oriented as shown:
U1
U2
U3
R3
R2
R1
1
3
2
X
Z
Y
8/13/2019 Example2 Two Equal Spans Option2 Final
65/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 65
Bent column
PilePile
Joint
Element
Pile cap corner
Pile-to-cap connection Column-to-pile-to-cap connection
The pile cap must be subdivided into enough
elements so that there is ajo in tat each location
where "something happens":
Pile cap corners
Pile-to-cap connections
Bent column-to-pile-to-cap connection
8/13/2019 Example2 Two Equal Spans Option2 Final
66/178
8/13/2019 Example2 Two Equal Spans Option2 Final
67/178
D il i XY l t Z 32 25
8/13/2019 Example2 Two Equal Spans Option2 Final
68/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 68
Draw pile cap in XYplane at Z = -32.25
Use Hometab Rubberband Zoomto enlarge figure
nodes at column bases
grid lines
8/13/2019 Example2 Two Equal Spans Option2 Final
69/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 69
Enlarged view of XYplane grid lines at Z = -32.25
Joint at column base
grid lines
8/13/2019 Example2 Two Equal Spans Option2 Final
70/178
8/13/2019 Example2 Two Equal Spans Option2 Final
71/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 71
Draw rectangular area
Select Area Section
Pile_cap_platethat
was defined earlier
Select Rectangular Areatab and select Area Section
8/13/2019 Example2 Two Equal Spans Option2 Final
72/178
8/13/2019 Example2 Two Equal Spans Option2 Final
73/178
8/13/2019 Example2 Two Equal Spans Option2 Final
74/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 74
Move(not drag) the
cursor to this Grid Point
and left-clickmouse
1
Line added to show element just drawn
Position cursor to draw element 2
8/13/2019 Example2 Two Equal Spans Option2 Final
75/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 75
Move(not drag) cursor
pointer to Grid Point
Left-clickmousethis will
show joints at the corners of
plate element 2just drawn
2 11 2
Lines added to show previously-drawn element
Dotted line appears as cursor is moved until Grid Point is reached
Draw the secondof 16 plate Areaelements
8/13/2019 Example2 Two Equal Spans Option2 Final
76/178
8/13/2019 Example2 Two Equal Spans Option2 Final
77/178
P iti t d l t 4
8/13/2019 Example2 Two Equal Spans Option2 Final
78/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 78
Move(not drag) the cursor to this
Grid Pointand left-clickmouse
Grid point
1 2 3
Position cursor to draw element 4
8/13/2019 Example2 Two Equal Spans Option2 Final
79/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 79
Grid point
Move(not drag) cursor
pointer to Grid Point
Left-clickmousethis will
show joints at the corners of
plate element 4just drawn
41 2 3 41 2 3
Dotted line appears as cursor is moved until Grid Point is reached
Dotted lines added to show
previously-drawn elements
Draw the fourthof 16 plate Areaelements
8/13/2019 Example2 Two Equal Spans Option2 Final
80/178
8/13/2019 Example2 Two Equal Spans Option2 Final
81/178
8/13/2019 Example2 Two Equal Spans Option2 Final
82/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 82
Second row of fourelementsthat make up the
pile cap plate. Againjoints
have been inserted at the
corners of each element at
the grid points.
Dotted lines added to show elements
1 2 3 4
5 6 7 8
Firstand second rows of elements are now drawn
Draw third row of 4 elements ( elements 912 of 16 )
8/13/2019 Example2 Two Equal Spans Option2 Final
83/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 83
Start
Left-click
Left-click
Left-click
Left-click End
( )
Fi t d d thi d f l t d
8/13/2019 Example2 Two Equal Spans Option2 Final
84/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 84
Third row of four elements
that make up the pile cap
plate.
Dotted lines added to show elements
1 2 3 4
5 6 7 8
9 10 11 12
First, second, and third rows of elements are now drawn
Draw fourth row of 4 elements ( elements 13 16 of 16 )
8/13/2019 Example2 Two Equal Spans Option2 Final
85/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 85
Start
Left-clickLeft-click Left-click
Left-click
End
Left-click
Draw fourth row of 4 elements ( elements 13 16 of 16 )
Drawing of Area elements that make up pile cap is complete
8/13/2019 Example2 Two Equal Spans Option2 Final
86/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 86
Drawing of Areaelements that make up pile cap is complete
Fourth row of four elementsthatmake up the pile cap plate.
Dotted lines added to show elements
1 2 3 4
5 6 7 8
9 10 11 12
13 14 15 16
8/13/2019 Example2 Two Equal Spans Option2 Final
87/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 87
Click arrow symbol to exit drawing mode Go to Homeand turn on Extrude View
Grayed area shows elements just drawn
8/13/2019 Example2 Two Equal Spans Option2 Final
88/178
8/13/2019 Example2 Two Equal Spans Option2 Final
89/178
Turn on Area Labels and Local Axes
8/13/2019 Example2 Two Equal Spans Option2 Final
90/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 90
Turn on Area Labelsand Local Axes
X
Z
Y
Turn onExtrude View
8/13/2019 Example2 Two Equal Spans Option2 Final
91/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 91
Z = - 32.25
4.0'
Z = - 32.25
In Display Options
check Extrude View
Labelsare not shown
in Extrude View
Use Set 3D Viewto switch to XZ View
8/13/2019 Example2 Two Equal Spans Option2 Final
92/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 92
XZ view
XZ l E t d Vi ( P ti t l d ff )
8/13/2019 Example2 Two Equal Spans Option2 Final
93/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 93
XZplane Extrude View( Perspectivetoggled off )
Base of column atmid-depth of pile cap
Z = -32.25
Perspectivetoggle
D th th il t Y 13 0
8/13/2019 Example2 Two Equal Spans Option2 Final
94/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 94
Draw the three piles at Y = -13.0
Z = - 32.25
Z = - 47.0
Switch to XZ View and step to plane at Y = -13
8/13/2019 Example2 Two Equal Spans Option2 Final
95/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 95
Switch to XZ Viewand step to plane atY 13
Here, do not use Moreto set view
Three piles will be draw
using these grid lines
Use Rubberband Zoom to expand the area where the piles will be drawn
8/13/2019 Example2 Two Equal Spans Option2 Final
96/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 96
Use Rubberband Zoomto expand the area where the piles will be drawn
8/13/2019 Example2 Two Equal Spans Option2 Final
97/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 97
Three piles will be draw using
these three grid lines
Mid-depth of pile cap
Z = -32.25
Tips of pilesZ = -47.0
Go to Advancedtab, which opens Drawoptions
8/13/2019 Example2 Two Equal Spans Option2 Final
98/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 98
, p p
Select Frame/Cable/Tendon
Select from list
Draw pile at X = 75 5
8/13/2019 Example2 Two Equal Spans Option2 Final
99/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 99
Draw pile at X = 75.5
Move pointer to grid point atX = 75.5, Y = -13.0, Z = -47.0
Left c l ickto begin drawing
8/13/2019 Example2 Two Equal Spans Option2 Final
100/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 100
Move pointer to grid point at
X = 75.5, Y = -13.0, Z = -32.25
Left cl ickto complete line
Right cl ick to "lift pencil"
Draw pile at X = 80 0
8/13/2019 Example2 Two Equal Spans Option2 Final
101/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 101
Draw pile at X = 80.0
Move pointer to grid point atX = 80.0, Y = -13.0, Z = -47.0
Left c l ickto begin drawing
8/13/2019 Example2 Two Equal Spans Option2 Final
102/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 102
Move pointer to grid point at
X = 80.0, Y = -13.0, Z = -32.25
Left c l ickto complete line
Right cl ick to "lift pencil"
Draw pile at X = 84.5
8/13/2019 Example2 Two Equal Spans Option2 Final
103/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 103
Move pointer to grid point at
X = 84.5, Y = -13.0, Z = -47.0
Left cl ickto begin drawing
8/13/2019 Example2 Two Equal Spans Option2 Final
104/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 104
Move pointer to grid point at
X = 84.5, Y = -13.0, Z = -32.25
Left cl ickto complete line
Right cl ick to "lift pencil"
The three piles at Y = -13.0 are complete
8/13/2019 Example2 Two Equal Spans Option2 Final
105/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 105
Exit drawing mode
At Hometab Refresh Windowto see the piles and nodes just drawn
8/13/2019 Example2 Two Equal Spans Option2 Final
106/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 106
What's missing?
There are no boundary
restraintsat the column bases(as shown, columns are free in
all d.o.f.)
Apply a fixedboundary restraint at the base of the column at X = 75.5
8/13/2019 Example2 Two Equal Spans Option2 Final
107/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 107
Pile
Right cl ickon joint Flashing red circle
8/13/2019 Example2 Two Equal Spans Option2 Final
108/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 108
Double left click
8/13/2019 Example2 Two Equal Spans Option2 Final
109/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 109
8/13/2019 Example2 Two Equal Spans Option2 Final
110/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 110
Restraint symbol
added at node
8/13/2019 Example2 Two Equal Spans Option2 Final
111/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 111
Repeat for these nodes ( one at a time )
See next page
8/13/2019 Example2 Two Equal Spans Option2 Final
112/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 112
Right clickjoint
Double left click
Piles with boundary restraints completed at Y = -13.0 are complete
8/13/2019 Example2 Two Equal Spans Option2 Final
113/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 113
Refresh drawing
8/13/2019 Example2 Two Equal Spans Option2 Final
114/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 114
Rubberband Zoomthis area
Piles, nodes and boundary restraints at Y = -13.0
8/13/2019 Example2 Two Equal Spans Option2 Final
115/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 115
Nodes at outer cornersof corner plate elements
8/13/2019 Example2 Two Equal Spans Option2 Final
116/178
8/13/2019 Example2 Two Equal Spans Option2 Final
117/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 117
8/13/2019 Example2 Two Equal Spans Option2 Final
118/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 118
Base of column and tops of
piles at mid-depth of pile cap
Z = -32.25
Tips of piles
Z = -47.0
Draw the three piles each at Y = -8.5 and Y = -4.0
8/13/2019 Example2 Two Equal Spans Option2 Final
119/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 119
Z = - 32.25
Z = - 47.0
Option 1: In XZViewmanually draw piles at Y = -8.5 and Y = -4.0
8/13/2019 Example2 Two Equal Spans Option2 Final
120/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 120
Y = -8.5
Y = -4.0
Step to Y = -8.5 and draw threepiles and add boundary restraints
as previously shown
Step to Y = -4.0 and repeat
Option 2: Replicatethe three piles and boundary restraints at Y = -13.0
8/13/2019 Example2 Two Equal Spans Option2 Final
121/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 121
to Y = -8.5 and Y = -4.0. This can be done in
1. Two steps: Replicate three piles at Y = -13.0 to Y = -8.5 in one step,
and then replicate the same piles atY = -13.0 to Y = -4.0
in a separate step
2. One step: Replicate three piles at Y = -13.0 to both Y = -8.5 and
Y = -4.0 in a single step.
The one-step replication is possible if spacings between the three lines of piles are the same.
Here, the spacings between Y = -13 andY = -8.5 and between Y = -85. and Y = -4.0 are
Y = +4.5 . Note thatY is positive because the "Y steps" will be from Y = -13.0 to
Y = -8.5 and then from Y = -8.5 to Y = -4.0.
The one-step replication will be use here.
Show only the footing/pile area
8/13/2019 Example2 Two Equal Spans Option2 Final
122/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 122
Rubberband Zoomthis area
Select: Three piles, six nodes (at ends of piles), and three boundary restraints
8/13/2019 Example2 Two Equal Spans Option2 Final
123/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 123
Do not include the
plate edge nodes
for replication
Use the following four steps
to make this selection
Selection Step 1
8/13/2019 Example2 Two Equal Spans Option2 Final
124/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 124
Hold leftbutton down
Let left
button up
Drag mouse from leftto right
Selected area
Plate corner node
Node at bottom of pile
Node at top of pileDrag mouse to include the pile,
plus the joints at the top and
bottom of the pile.
Note that the plate corner node
cannot be avoided. It will be
deselected in Step 4.
Selection Step 2 Selection Step 3
8/13/2019 Example2 Two Equal Spans Option2 Final
125/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 125
p Selection Step 3
Hold left
button down
Let left
button up
Drag mouse
Selected area
Node at top of pile
Node at bottom of pile
Drag mouse
Hold left
button down
Let left
button up
Selected area
Node at top
of pile
Node at bottom
of pile
Selection Step 4
8/13/2019 Example2 Two Equal Spans Option2 Final
126/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 126
Selection Step 4
Objects to be replicated
Left-click to deselect
the plate corner joint
Replicate3-pile selection Y = +4.5 twice in one step
8/13/2019 Example2 Two Equal Spans Option2 Final
127/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 127
Y = +4.5
Y = +4.5
Replicatecompletedview in Hometab, Rubberband Zoom
8/13/2019 Example2 Two Equal Spans Option2 Final
128/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 128
Rubberband Zoom
Two rows of
piles added
Perspective Extrude Viewof selected area
8/13/2019 Example2 Two Equal Spans Option2 Final
129/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 129
Open and select Extrude View
Switch to XZ View
8/13/2019 Example2 Two Equal Spans Option2 Final
130/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 130
XZ Extrude View ( Perspectiveturned off )
8/13/2019 Example2 Two Equal Spans Option2 Final
131/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 131
X
Z
Perspectivetoggle
Switch to YZ View
8/13/2019 Example2 Two Equal Spans Option2 Final
132/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 132
YZ Extrude View ( Perspectiveturned off )
8/13/2019 Example2 Two Equal Spans Option2 Final
133/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 133
Y
ZView towardX = 0
Pile rows added by Replicate
Perspectivetoggle
Z Z
Finish drawing the foundations
8/13/2019 Example2 Two Equal Spans Option2 Final
134/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 134
Y
Z
5.0 5.017.0
Y
Z
Y = +17.0
Replicate
Just completed
In Hometab:
Turn off Extrude View, select 3-dView, and Rubberband Zoomto get area shown
8/13/2019 Example2 Two Equal Spans Option2 Final
135/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 135
u o Extrude View , se ec 3 d View , a d Rubberband Zoom o ge a ea s o
Drag mouse from left to right to select pile cap and piles
8/13/2019 Example2 Two Equal Spans Option2 Final
136/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 136
Start selection
End selection
Be sure to include the
plate node at the farcorner of the pile cap.
Selected objects to Replicate
8/13/2019 Example2 Two Equal Spans Option2 Final
137/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 137
Selected objects: Pile cap
(16 finite elements) and
nine fixed-base piles
Replicateselected objects
8/13/2019 Example2 Two Equal Spans Option2 Final
138/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 138
8/13/2019 Example2 Two Equal Spans Option2 Final
139/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 139
Replicated objectsnote that grid
lines are not replicated or expanded
In Hometab, return to Perspective View
8/13/2019 Example2 Two Equal Spans Option2 Final
140/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 140
Switch to Perspective Extrude View
8/13/2019 Example2 Two Equal Spans Option2 Final
141/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 141
Switch toYZ Extrude View
8/13/2019 Example2 Two Equal Spans Option2 Final
142/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 142
YZ Extrude View
8/13/2019 Example2 Two Equal Spans Option2 Final
143/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 143
Y
Z
Grid lines
Perspectivetoggle
Y
Z
Perspectiveon Perspectiveoff
Grid lines
The grid linescan now be either deletedor hidden
Deletegrid lines .. a bad idea .DON'T DO IT
8/13/2019 Example2 Two Equal Spans Option2 Final
144/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 144
Delete all
Right click
anywhere in view
panel
Hidethe grid lines
8/13/2019 Example2 Two Equal Spans Option2 Final
145/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 145
Right click
anywhere in view
panel
The grid lines are still there, but are hidden.
They can be unhidden by the same procedure ( as will be done in Option 3 of this Exercise )
8/13/2019 Example2 Two Equal Spans Option2 Final
146/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 146
Foundation drawing completed and the grid has been hidden
8/13/2019 Example2 Two Equal Spans Option2 Final
147/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 147
Perspectiveon
Perspectivetoggle
Perspectiveoff
But.is the foundation part
of the Bridge Model?
In Hometab, Restore Full View( Perspective) and turn off Extrude View
8/13/2019 Example2 Two Equal Spans Option2 Final
148/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 148
In Bridgetab, Updatethe Bridge Modelto include the foundations
8/13/2019 Example2 Two Equal Spans Option2 Final
149/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 149
After the Bridge Modelhas been updated, switch to the Analysistab
and run an analysis for the DEADloads
8/13/2019 Example2 Two Equal Spans Option2 Final
150/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 150
8/13/2019 Example2 Two Equal Spans Option2 Final
151/178
In the Hometab, open the Deformed Shapebox
8/13/2019 Example2 Two Equal Spans Option2 Final
152/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 152
The deformed shape has been drawn using a
very small default Auto Scalingfactor
Choose a Scale Factorthat shows a reasonable deformed shape
8/13/2019 Example2 Two Equal Spans Option2 Final
153/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 153
The magnitude of the scale factor has no physical
significance it is just a relative number
8/13/2019 Example2 Two Equal Spans Option2 Final
154/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 154
Extrude Viewoff
Extrude Viewon
Displacements U1, U2, U3measured in structure X-Y-Zcoordinates
8/13/2019 Example2 Two Equal Spans Option2 Final
155/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 155
X (U1)
Z (U3)
Y (U2)
Deflected profile
8/13/2019 Example2 Two Equal Spans Option2 Final
156/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 156
Deflection reference line
Deflection at bent due to elastic shortening
of the bent columns and the piles
X (U1)
Z (U3)
XZplane
Selected vertical deflections
8/13/2019 Example2 Two Equal Spans Option2 Final
157/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 157
U3 = -0.2957 in
X (U1)
Z (U3)
Set units to inches
Move cursor to joint
U3 = -0.0593 in
Longitudinal ( M3) moment diagramEntire Bridge
8/13/2019 Example2 Two Equal Spans Option2 Final
158/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 158
X
Z
Y
1
2
3
Structure ("global")
coordinate system
Member coordinate system for
member laid out from X = 0 toX at the end of the bridge
3107 ft-k
4913 ft-k
Compare DEADload moment diagrams for two column base options
Option 2Option 1
8/13/2019 Example2 Two Equal Spans Option2 Final
159/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 159
Bent columns on pile foundations
( column extended to mid-depth
of pile cap )
3107 ft-k
4913 ft-k
Bent columns fixed at bases
4949 ft-k
2997 ft-k
Why are they different?
Vertical reactions at tips of piles
8/13/2019 Example2 Two Equal Spans Option2 Final
160/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 160
If necessary, use Display Options
to turn off viewing Restraints
8/13/2019 Example2 Two Equal Spans Option2 Final
161/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 161
Rubberband Zoomto
isolate this footing
Isolated view of pile footing reactions in Y region
8/13/2019 Example2 Two Equal Spans Option2 Final
162/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 162
Bentcolumn
Right-click on joint
In XZ plane view reactions at each Y position
8/13/2019 Example2 Two Equal Spans Option2 Final
163/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 163
Use arrows to select Y = - 4.0
( note that Y position is notshown
anywhere on the screennasty )
Rubberband Zoom
Vertical reactions atY = - 13.0 ft
8/13/2019 Example2 Two Equal Spans Option2 Final
164/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 164
X=75.5
X=80.0
X
=84.5
Y = - 13.0
Vertical reactions at Y = - 8.5 ft
8/13/2019 Example2 Two Equal Spans Option2 Final
165/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 165
X=75.5
X=80.0
X=
84.5
Y = - 8.5
Vertical reactions at Y = - 4.0 ft
8/13/2019 Example2 Two Equal Spans Option2 Final
166/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 166
X=75.5
X=80.0
X=
84.5
Y = - 4.0
Total upward vertical reactionper pile footing
8/13/2019 Example2 Two Equal Spans Option2 Final
167/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 167
52.47 + 55.05 + 52.39 = 159.9
52.47 + 55.05 + 52.39 = 159.9
55.09 + 65.87 + 55.01 = 176.0 495.8 kips
Axial forceat base of bent column
8/13/2019 Example2 Two Equal Spans Option2 Final
168/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 168
present view ( whatever it may be )
Display member axial force for Frame Members
8/13/2019 Example2 Two Equal Spans Option2 Final
169/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 169
Rubberband Zoom to improve resolution
8/13/2019 Example2 Two Equal Spans Option2 Final
170/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 170
Bent column appears when Y = - 8.5'
Select Y = - 8.5 ft
Note: Y position not shown!!
Rubberband zoom
Axial force near base of bent column ( approximately at top of pile cap )
8/13/2019 Example2 Two Equal Spans Option2 Final
171/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 171
Bent column appears when Y = - 8.5'
Axial compression near base of bent
column = - 372.0 (4 sig. figures)
Alternate viewXZ View ( Rubberband Zoom)
8/13/2019 Example2 Two Equal Spans Option2 Final
172/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 172
Bent column appears when Y = - 8.5'
Axial compression near base of bent
column = - 372.0 (4 sig. figures)
Select Y = - 8.5 ft in XZ view
Note: Y position not shown!!
Show member axial force diagrams
8/13/2019 Example2 Two Equal Spans Option2 Final
173/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 173
If necessary, use Display Options
to turn off viewing Restraints
Compression forces in piles and in bent column where it connects to
the plate element at the mid-depth of the pile cap
8/13/2019 Example2 Two Equal Spans Option2 Final
174/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 174
R = 52.47
(earlier slides)
Put cursoron joint
Rubberband Zoom
Use Advanced Assign More to clear display of currently-shown results
8/13/2019 Example2 Two Equal Spans Option2 Final
175/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 175
13.0' x 13.0'
concrete pile capWeight of concrete pile cap( disregard 2.0' steel pipe
Pile and cap weights
8/13/2019 Example2 Two Equal Spans Option2 Final
176/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 176
4.0'
12.75'
concrete pile cap
concrete filled 14"-diamsteel piles ( 9 total )
doutside= 14"
tw = 3/8"
concrete core
steel pipe
g p p ( g p p
length extensions into pile cap ):
13.0' x 13.0' x 4.0' x 0.15 k/ft3
= 101.4 kips
Weight per pile:
Core diameter = 13.25" / 12 in/ft = 1.102 ft
ft/ft9575.0ft/ft4
104.1 222
Core area per foot =
Core weight = 0.9575 ft2/f x 0.15 k/ft3 = 0.1436 k/ft
Pipe area per foot = ft/ft1115.0ft/)ft/in144(4
in)25.130.14( 222
222
Pipe weight = 0.1115 ft2/f x 0.495 k/ft3 = 0.0552 k/ft
Pile weight per foot = ( 0.1436 + 0.0552 ) k/ft = 0.1988 k/ft
Weight per pile = 0.1988 k/ft x 12.75 ft = 2.535 k/pile
Total pile weight = 2.535 k/pile x 9 piles = 22.8 kips
Check pile footing vertical equilibrium
Column force near top of pile cap = 372.0 kips
8/13/2019 Example2 Two Equal Spans Option2 Final
177/178
10/19/2011 Example2-Two-Equal-Spans-Option2-Final.ppt 177
Total reaction = 495.8 kips upward ( Slide 176 )
Total pile weight = 22.8 kips
Pile cap weight = 101.4 kips
496.2 kips downward
Close enough !!
(why not use 373.1 kipsSlide 176 ??)
Save your CSI Bridge .bdb file in twoversions:
8/13/2019 Example2 Two Equal Spans Option2 Final
178/178
Save as: Example2-Two-Equal-Span-Option2.bdb
This is the option just completed in which the two columns bases frame into
the pile cap in a pile-cap/piles foundation
Save as: Example2-Two-Equal-Span-Option3.bdb
This will be the starting point for the next option in which the columns bases
are connected to the pile caps by Joint Constra ints