Upload
reidar
View
58
Download
0
Embed Size (px)
DESCRIPTION
Example: MRP Schedule. LocoMopeds is a manufacturer of off-road mopeds. The following product structure diagram represents the bill of materials for its dual-carburetor Model 442 moped. MOPED. Level 0. ENGINE ASSEMBLY. GAS TANK. WHEEL ASSEMBLY (2). FRAME. Level 1. MOTOR. - PowerPoint PPT Presentation
Citation preview
1
Example: MRP Schedule
LocoMopeds is a manufacturer of off-road mopeds. The following product structure diagram represents the bill of materials for its dual-carburetor Model 442 moped.
MOPED
ENGINEASSEMBLY
MOTOR CARBURETOR(2)
GASTANK
WHEELASSEMBLY
(2)
HUB ASSEMBLY TIRE
FRAME
Level 0
Level 1
Level 2
2
Example: MRP Schedule
Bill of MaterialParent Component Level Compon.Code Code Code Description Req’d
442 0 #442 Moped442 EA 1 Engine Assem. 1
GT 1 Gas Tank 1WA 1 Wheel Assem. 2F 1 Frame 1
EA M 2 Motor 1C 2 Carburetor 2
WA HA 2 Hub Assem. 1T 2 Tire 1
3
Example: MRP Schedule
Inventory Status ReportItemCode
On-Hand
SafetyStock
LotSize
LeadTime
Sched. ReceiptsQnty. Week
442 500 200 LFL 1 -- --
EA 300 100 500 1 1000 10
GT 600 200 LFL 2 900 10
WA 500 400 500 1 2000 10
F 600 0 2000 3 2000 10
M 250 0 LFL 1 -- --C 150 100 2000+ 2 -- --
HA 100 0 LFL 1 2400 11
T 500 500 1000 3 3000,2000 11,12
4
Example: MRP Schedule
The company is currently planning production for weeks 10 through 16. Based on existing orders and demand forecasts, the master production schedule is as follows:
Master Production Schedule: #442 Moped
Determine the MRP schedule required to support the master production schedule for the Model 442 moped in weeks 10-16.
11
1300 800 1200 1400
10 1615141312
0 1000 0
WEEK
QUANTITY
5
Example: MRP Schedule
MRP Schedule for #442 Mopeds for Weeks 10 - 16, considering that:
Gross Requirements come from the moped MPS There is an On-Hand balance of 500 mopeds at the
end of week 9 There are no Scheduled Receipts for mopeds A lot-for-lot rule is used for ordering mopeds Safety stock of 200 mopeds is desired Lead time for mopeds is one week
6
Example: MRP Schedule
MRP Schedule for #442 Mopeds . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: 442 MOPED LT: 1 LOT SIZE: LFL SS: 200
0
10
1000 0
11 12 13
1300 800
1514
14001200
16WEEK
7
Example: MRP Schedule
MRP Schedule for #442 Mopeds . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: 442 MOPED LT: 1 LOT SIZE: LFL SS: 200
0
300
1000
10
1000
1000
300
1300
1300
0
0
11 12 13
1300
1200800
1200800
14001200
1300
1300
800
000 0
1400
800
15
1400
14
14001200
16WEEK
8
Example: MRP Schedule
MRP Schedule for Gas Tanks for Weeks 10 - 16, considering that:
Gross Requirements come from moped Planned-Order-Releases
There is an On-Hand balance of 600 gas tanks at the end of week 9
There is a Scheduled Receipt for 900 tanks in week 10
A lot-for-lot rule is used for ordering gas tanks Safety stock of 200 gas tanks is desired Lead time for gas tanks is two weeks
9
Example: MRP Schedule
MRP Schedule for Gas Tanks . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 600)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: GAS TANK LT: 2 LOT SIZE: LFL SS: 200
1000
900
10
0 1300
11 12 13
800 1200
1514
01400
16WEEK
10
Example: MRP Schedule
MRP Schedule for Gas Tanks . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 600)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: GAS TANK LT: 2 LOT SIZE: LFL SS: 200
1000
900
1300
1000
10
800
0
1200
300
1300
11 12 13
800
1200
1400
1200
1514
01400
16WEEK
300 000
1000
1000 800
800
1400
14001200
0
11
Example: MRP Schedule
MRP Schedule for Frames for Weeks 10 - 16, considering that:
Gross Requirements come from moped Planned-Order-Releases
There is an On-Hand balance of 600 frames at the end of week 9
There is a Scheduled Receipt for 2000 frames in week 10
The firm uses a Lot Size (multiple) of 2000 for ordering frames
No safety stock of frames is desired Lead time for frames is 3 weeks
12
Example: MRP Schedule
MRP Schedule for Frames . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: FRAME LT: 3 LOT SIZE: 2000 SS: 0
1000
2000
10
0 1300
11 12 13
800 1200
1514
01400
16WEEK
600
13
Example: MRP Schedule
MRP Schedule for Frames . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 600)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: FRAME LT: 3 LOT SIZE: 2000 SS: 0
1000
2000
1600
0
2000
10
1600
0
2000
1600
1300
11 12 13
800
2000
500
2000
300300 900
0
1200
1514
01400
16WEEK
0 0
1500
0 1100
14
Example: MRP Schedule
MRP Schedule for Engine Assemblies for Weeks 10 - 16, considering that:
Gross Requirements come from moped Planned-Order-Releases
There is an On-Hand balance of 300 engine assemblies at the end of week 9
There is a Scheduled Receipt for 1000 engine assemblies in week 10
The firm uses a Lot Size (multiple) of 500 for ordering engine assemblies
Safety Stock of 100 engine assemblies is desired Lead time for engine assemblies is 1 week
15
Example: MRP Schedule
MRP Schedule for Engine Assemblies . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 300)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: ENGINE ASSEM. LT: 1 LOT SIZE: 500 SS: 100
1000
1000
10
0
1300
11 12 13
800 1200
1514
01400
16WEEK
16
Example: MRP Schedule
MRP Schedule for Engine Assemblies . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 300)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: ENGINE ASSEM. LT: 1 LOT SIZE: 500 SS: 100
1000
1000
200
10
1500
200
0
500
1500
1100
200
1300
11 12 13
800
10001100
10001500
1000
400
500
1500
400100400 0
1200
1514
01400
16WEEK
17
Example: MRP Schedule
MRP Schedule for Motors for Weeks 10 - 16, considering that:
Gross Requirements come from engine assembly Planned-Order-Releases
There is an On-Hand balance of 250 motors at the end of week 9
There are no Scheduled Receipts for motors A lot-for-lot rule is used for ordering motors No Safety Stock of motors is desired Lead time for motors is 1 week
18
Example: MRP Schedule
MRP Schedule for Motors . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 250)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: MOTOR LT: 1 LOT SIZE: LFL SS: 0 10
1500
500
11 12 13
1500
1000
1514 16WEEK
19
Example: MRP Schedule
MRP Schedule for Motors . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 250)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: MOTOR LT: 1 LOT SIZE: LFL SS: 0
250
1250
10
1250
500
1250
250
1500
1500
500
500
0
500
11 12 13
1500
1000
1000
1500
1500
1000
000 0
1000
1514 16WEEK
20
Example: MRP Schedule
MRP Schedule for Carburetors for Weeks 10 - 16, considering that:
Gross Requirements come from engine assembly Planned-Order-Releases (times 2)
There is an On-Hand balance of 150 carburetors at the end of week 9
There are no Scheduled Receipts for carburetors A Lot Size of 200+ is used for ordering carburetors Safety Stock of 100 carburetors is desired Lead time for carburetors is 2 weeks
21
Example: MRP Schedule
MRP Schedule for Carburetors . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 150)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: CARBURETOR LT: 2 LOT SIZE: 2000+ SS: 100 10
3000 1000
11 12 13
3000 2000
1514 16WEEK
22
Example: MRP Schedule
MRP Schedule for Carburetors . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 150)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: CARBURETOR LT: 2 LOT SIZE: 2500+ SS: 100
50
2500
10
2500
3050
3000
3000
2500
2500
950
50
1000
11 12 13
3000
950
2500
1450
2500
155010501550 1550
2000
1514 16WEEK
23
Example: MRP Schedule
MRP Schedule for Wheel Assemblies for Weeks 10 - 16, considering that:
Gross Requirements come from moped Planned-Order-Releases (times 2)
There is an On-Hand balance of 500 wheel assemblies at the end of week 9
There is a Scheduled Receipt for 2000 wheel assemblies in week 10
A Lot Size (multiple) of 500 is used for ordering wheel assemblies
Safety Stock of 400 wheel assemblies is desired Lead time for wheel assemblies is 1 week
24
Example: MRP Schedule
MRP Schedule for Wheel Assemblies . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: WHEEL ASSEM. LT: 1 LOT SIZE: 500 SS: 400
2000
2000
10
0
2600
11 12 13
1600 2400
1514
02800
16WEEK
25
Example: MRP Schedule
MRP Schedule for Wheel Assemblies . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: WHEEL ASSEM. LT: 1 LOT SIZE: 500 SS: 400
2000
2000
2100
10
2500
100
0
2000
2500
2500
100
2600
11 12 13
1600
28002000
30002000
3000
1600
2000
2000
04000 200
2400
1514
02800
16WEEK
26
Example: MRP Schedule
MRP Schedule for Hub Assemblies for Weeks 10 - 16, considering that:
Gross Requirements come from wheel assembly Planned-Order-Releases
There is an On-Hand balance of 100 hub assemblies at the end of week 9
There is a Scheduled Receipt of 2400 hub assemblies in week 11
A lot-for-lot rule is used for ordering hub assemblies No Safety Stock of hub assemblies is desired Lead time for hub assemblies is 1 week
27
Example: MRP Schedule
MRP Schedule for Hub Assemblies . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 100)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: HUB ASSEM. LT: 1 LOT SIZE: LFL SS: 0
0
10
2400
2500
2000
11 12 13
2000
3000
1514
00
16WEEK
28
Example: MRP Schedule
MRP Schedule for Hub Assemblies . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 100)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: HUB ASSEM. LT: 1 LOT SIZE: LFL SS: 0
0
100
10
2000
2500
2400
2500
2000
2000
2000
0
2000
11 12 13
2000
3000
3000
2000
2000
3000
000 0
3000
1514
00
16WEEK
29
Example: MRP Schedule
MRP Schedule for Tires for Weeks 10 - 16, considering that:
Gross Requirements come from wheel assembly Planned-Order-Releases
There is an On-Hand balance of 500 tires at the end of week 9
There are Scheduled Receipts for 3000 and 2000 tires weeks 11 and 12, respectively
A Lot Size (multiple) of 1000 is used for ordering tires
Safety Stock of 500 tires is desired Lead time for tires is 3 weeks
30
Example: MRP Schedule
MRP Schedule for Tires . . . Initially
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: TIRE LT: 3 LOT SIZE: 1000 SS: 500
0
10
3000
2500 2000
2000
11 12 13
2000
3000
1514
00
16WEEK
31
Example: MRP Schedule
MRP Schedule for Tires . . . Completed
GROSS REQUIREMENTS
SCHEDULED RECEIPTS
AVAILABLE (ON-HAND = 500)
NET REQUIREMENTS
PLANNED ORDER RECEIPTS
PLANNED ORDER RELEASES
ITEM: TIRE LT: 3 LOT SIZE: 1000 SS: 500
0
0
2000
10
3000
3000
3000
2500
2500
2000
2000
11 12 13
2000
2500
3000
1500
2000
500 500500 500
3000
1514
00
16WEEK
32
Issues in MRP
Management Commitment User involvement Education and training Selection of S/W packages Data accuracy Realistic MPS Realistic lead times Maintaining accurate BOM files
33
Lot-Sizing in MRP
Lot-size is the quantity ordered/produced at one time Large lots are preferred because:
Changeovers cost less and capacity greater Annual cost of purchase orders less Price breaks and transportation breaks can be
utilized Small lots are preferred because:
Lower inventory carrying cost Reduced risk of obsolescence Shorter cycle time to produce customer order
34
Lot-Sizing Methods in MRP
Economic Order Quantity (EOQ) does not consider quantity discounts does not always provide the most economical
approach with lumpy demands Lot-for-Lot (LFL)
accommodates lumpy demand Period Order Quantity (POQ) Many others
35
Lot-Sizing Methods in MRP
The best lot-sizing method, resulting in least cost,
depends on cost and demand patterns
36
Lot-Sizing in MRP
Lot-size is the quantity ordered/produced at one time Large lots are preferred because:
Changeovers cost less and capacity greater Annual cost of purchase orders less Price breaks and transportation breaks can be
utilized Small lots are preferred because:
Lower inventory carrying cost Reduced risk of obsolescence Shorter cycle time to produce customer order
37
The best method, resulting in least cost,depends on cost and demand patterns.
Lot-Sizing Methods
Economic Order Quantity (EOQ) does not consider quantity discounts does not always provide the most economical
approach with lumpy demand Lot-for-Lot (LFL)
accommodates lumpy demand Period Order Quantity (POQ)
38
Evaluation of MRP
Most beneficial to process-focused systems that have long processing times and complex multistage production steps
Lead times must be reliable Must freeze MPS for some time before actual
production... certain demand Difficult to implement
39
Closed Loop MRP
Production PlanningMaster Production Scheduling
Material Requirements PlanningCapacity Requirements Planning
Realistic?
NoFeedback
Execute:Capacity PlansMaterial Plans
Yes
Feedback
40
Closed Loop MRP
Materials Management at Washburn Guitar, Inc.
41
Manufacturing Resource Planning (MRP II)
Goal: Plan and monitor all resources of a manufacturing firm (closed loop):
Manufacturing Marketing Finance EngineeringShop-floor control
Simulation capability of the manufacturing system
42
Enterprise Resource Planning (ERP)
ERP systems available today integrate manufacturing with other functional areas in an organization
ERP systems make it easier for management to obtain local information about performance of specific processes, bottlenecks resources, and products (or product groups), etc.
Class I ERP software packages (for large companies) include BAAN, SAP, and Oracle
43
MRP II System
MRP II System
44
MRP I to MRP II
MRP I simply exploded demand (MPS) into required materials
MRP II became Manufacturing Resource Planning which provides a closed-loop business management system
Financial management Shop floor control Operations management Simulation capability
45
Capacity Requirements Planning (CRP)
46
Capacity Requirements Planning (CRP)
Tests MPS for feasibility Utilizes routings to determine labor/machine loads If schedule feasible, recommends freezing If schedule overloads resources, points out processes
that are overscheduled
47
Load Schedules
Compares actual labor and machine hours against available hours
Offsets schedules between successive stages of production by lead times
Provides feasible MPS and economically loaded work centers
Promotes system operating efficiency ... lowers costs!
48
World-Class Practice
Lead times respond to conditions Product development as levels of product structure
tree Lead times that adjust to load MRP reports shared with customers and suppliers