17
EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and developing prototypes of the most critical parts of the facility itself. “Starting point: EURISOL RTD Recommendations” Design Study THE MANAGEMENT BOARD Graziano Fortuna: Project Leader Yorick Blumfeld Peter Butler Mats Lindroos Management Support Team (core staff) Technical Coordinator: John Cornell Scientific liaison Office: A. Andrighetto M. Comunian ……. Administrative Office: R. Battistella V. Vandevoorde …….

EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

Embed Size (px)

Citation preview

Page 1: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility

THE GOAL Producing an engineering oriented study of the EURISOL Facility and developing prototypes of the most critical parts of the facility itself.

“Starting point: EURISOL RTD Recommendations”

Design Study

THE MANAGEMENT BOARD

Graziano Fortuna: Project Leader

Yorick Blumfeld

Peter Butler Mats Lindroos

Management Support Team (core staff)

Technical Coordinator: John Cornell Scientific liaison Office: A. Andrighetto

M. Comunian …….

Administrative Office: R. Battistella V. Vandevoorde

…….

Page 2: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

EURISOL DS EUropean Isotope EURISOL DS EUropean Isotope SeparationSeparation

On-Line Radioactive Ion Beam Facility On-Line Radioactive Ion Beam Facility

IDENTITY CARDIDENTITY CARD

EU CONTRIBUTION:EU CONTRIBUTION: ((k€)k€) 9161.99161.9 - FTE 113,25- FTE 113,25

TASKS:TASKS: 12 12 (FOUR TOPIC AREAS)

PARTICIPANTS:PARTICIPANTS: 21 21 GANIL (F), CNRS/IN2P3 (F), INFN-LNL (I), INFN (I), CERN (UE), UCL (B), CEA (F), NIPNE (RO), JYU (FI), LMU (G), FZJ (G), FI (LT), UW (PL), SAS (SK), U- LIVERPOOL (UK), GSI (G), USDC (E), CCLRC (UK), PSI (CH), IPUL (LV), SU MSL (SE) (15 countries involved)(15 countries involved)

PROJECT ESTIMATED TOTAL EFFORTS:PROJECT ESTIMATED TOTAL EFFORTS: ((k€)k€) 32.284,3 32.284,3 - FTE 490,45- FTE 490,45

Design Study

DURATION OF THE PROJECT:DURATION OF THE PROJECT: 48 MONTHS48 MONTHS

STARTING DATE:STARTING DATE: END OF JANUARY-BEGINNING OF FEBRUARY END OF JANUARY-BEGINNING OF FEBRUARY 20052005COORDINATING INSTITUTION:COORDINATING INSTITUTION: GANIL (F)GANIL (F)

CONTRIBUTORS: 21U-FRANKFURT (G), BUDKER (RU) ,VNIIFT (RU), PNPI (RU), ORNL (USA), ANL (USA), KAERI (SKR), TRIUMF (CA),

JAERI (JP), SOREQ (IL), U-MAINZ (G), VINCA (YU), KVI (NL), U-SURREY (UK), U-YORK (UK), U-PAISLEY (UK), U-UPPSALA (SE), NSCL (USA), FNAL (USA), INFN-LNS (I), HUG (CH)

(13 countries involved from Europe, Asia and North America)

Page 3: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

TASKSAND RELATED FOUR TOPIC AREAS

• EURISOL DS Managemt (GANIL/INFN-LNL/CNRS-IN2P3/CERN)

• Targets and ion sources (Synergies with neutron spallation sources and neutrino facilities)

– Multi-MW target station : mercury converter (CERN) – Direct target : Several target-ion source prototypes (CERN) – Fission target : UCx target (INFN-LNL)

• Accelerators (Synergies with HIPPI (CARE))– Proton accelerator design: the driver (INFN-LNL): – Heavy ion accelerator design: the post accelerator (GANIL)– SC cavity development, prototypes and multipurpose cryomodule (CNRS-

IN2P3-IPNO)

• Physics, beams and safety (Synergies with EURONS)– Physics and instrumentation (U-LIVERPOOL)– Beam intensity calculations (GSI)– Safety and radioprotection (CEA)

• Beta-Beams Aspects (Synergies with BENE (CARE))– Beam preparation : breeders, 60 GHz ECR source (JYV) – Beta-beam aspects: conceptual design report of the Beta-Beam facility. It

includes preliminary studies on modifications of CERN accelerators in case the facility is sited at CERN

Design Study

Page 4: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

3

2

3

1 1 1

2

1 1 1 1 1 1 1 1

0

1

2

3

4

France

Italy

Germ

any

Cern

(Eur)

Switzer

land

Spain

Unite

d Kin

gdom

Finla

ndLith

uania

Polan

dRom

ania

Latvi

aBel

gium

Slova

kia

Sweden

Country of Origin of Partecipanting I nstitutions

Page 5: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

4

2

3 3

1 1 1 1 1 1 1 1 1

0

1

2

3

4

5

Country of origin of Contributing Institutions

Page 6: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

4 4

10

1413

8

5

9

15

9 9

3

0

2

4

6

8

10

12

14

16M

anag

emen

t

Mul

ti M

W T

arge

t Sta

tion

Direct

Tar

get

Fiss

ion

Targ

et

Safet

y& R

adio

prot

ectio

n

Heavy

Ion

Acc

eler

ator

Des

ign

Proto

n Acc

eler

ator

Des

ign

SC Cav

ity D

evel

opm

ent

Beam

Pre

para

tion

Physi

cs a

nd In

stru

men

tatio

n

Beam

Inte

nsity

Cal

cula

tions

Beta

Beam

s A

spec

ts

Participants and Contributors per task

Page 7: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

TASK LEADERS PER COUNTRY

3

33

1

11

France

I taly

Switzerland

Finland

United Kingdom

Germany

Page 8: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

STEERING COMMITTEE

1 representative of each Participant+ Management Board and Chairs of NUPECC,

ESGARD, EURONS (all ex-officio)1 meeting/year

MANAGEMENT BOARD

Project Leader + 3 Members

MANAGEMENT SUPPORT TEAM

1. Administrative Office2. Scientific liaison Office3. Technical coordinator

COORDINATION BOARD

Management Board+ Task Leaders

+ Coordinators of HIPPI JRA and BENE Network (ex-officio)

2-3 Meetings/year

INTERNATIONAL ADVISORY PANEL

3 Members – 1 Meeting/year

ANNUAL PARTICIPANT MEETING

1 Meeting/year

Ta

sk 2

Ta

sk 3

Ta

sk 1

MANAGEMENT STRUCTUREDesign Study

Page 9: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

Where have we got to?

Annex I to the contract and CPF Forms submitted to EC

on 30th September, 2004

The “magic words” most frequently used in Annex I:

1. Objectives2. Milestones3. Deliverables

Design Study

Page 10: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

ANNEX I TO THE CONTRACT LIST OF CONTENTS

1. Project summary 2. *Project objectives3. List of participants4. Implementation plan for the full duration of the project 4.1 List of tasks 4.2 Implementation plan 4.3 *Description of tasks5. Consortium management activities 5.1 Organisational structure and overall project management 5.2 Potential impact and risks assessment 5.3 Plan for use and dissemination of knowledge6. Project resources and budget overview 6.1 Personnel effort for the full duration of the project 6.2 Description of other resources needed 6.3 Overall budget for the full duration of the project

* Significant reshaping of the related original test of the proposal

Design Study

Page 11: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

TASK DESCRIPTION EXAMPLE

Design Study

Objectives

Due to drastically increased radioactive inventory compared to current worldwide RIB facilities, the following list of objectives has been identified that need research and development:

1. Calculation of radiation production and activation. 2. Methods for shielding against prompt radiation and for the containment of

activity. 3. Handling of targets and in particular the disposal of spent targets.4. Conformity of the proposed installation to the legislation.

The realization of this task is crucial for the Design Study of the new generation RIB facility in order to characterize the radioactive inventory, to identify the technical challenges, to characterize the safety approval procedures, to estimate the impact of safety and radioprotection issues on the final cost of the installation.

Start month 1 End month 46

Participant number* 7 1 5 8 10 11 12 13

Participant short name CEA GANIL CERN NIPNE LMU FZJ FI UW Total

Person-months 66.00 33.00 66.00 96.00 78.00 78.00 108.00 36.00 561.00

Task number 5 Task title Safety & Radioprotection

Page 12: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

TASK DESCRIPTION EXAMPLEDesign Study

Description of work

The work includes:1. Radiation, activation, shielding & doses - characterization of radiation from primary beam components, target-converter, RNB production

target, beam dump, secondary beam lines; - activation estimates of accelerator components, target-converter, RNB production target, beam dump,

separator and ionizer, secondary beam lines, environment (building, air, soil, ground water); - characterization of radio-elements produced with respect to (2); - optimization of shielding against prompt radiation fields and activated structures; - dose rate calculations.2. Radioactivity control, safety & risks - study of dispersion of radio-elements, contamination, migration; - study of safety associated with oxidation of target materials; - study of containment of volatile radioactivity; - safety and risks associated with target preparation, handling, confinements and nuclear ventilation,

flow of radioactive materials, etc.; - prevention and limitation of personnel direct and indirect exposure: risk and failure scenarios; - prevention and limitation of waste production, radioactivity dispersion and rejections. 3. Decommissioning - storage and disposal of spent targets; - characterization of radioactive waste produced; - characterization of activated structures, their volumes, masses, specific activity, radio-elements; - guidelines of the decommissioning and dismantling strategy; - risk estimates.4. Conformity to legislation - study of the licensing and permission procedures; - guidelines on the technical options; - guidelines on implementation and execution conditions; - potential risk and delays estimates.

Page 13: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

TASK DESCRIPTION EXAMPLE

Design Study

NO. Milestones and expected result of this task: Months due

M1 Radiation, activation, dose

M1.1 Validation of code 6

M1.2 Radiation & activation estimates 12

M1.3 Shielding guidelines 22

M2 Radioactivity control, safety and risk

M2.1 Dispersion of radioactivity 17

M2.2 Test of purification system 31

M2.3 Containment of radioactivity 17

M2.4 Activity transport in ground water 17

M2.5 Report 44

M3 Decommissioning issues

M3.1 Report 45

M4 Conformity to legislation

M4.1 Report 46

Deliverable number

Deliverables Dissemination level1

D1 Radiation, activation, doseShielding guidelines

PU

D2 Radioactivity control, safety and riskReport

PU

D3 Decommissioning issues Report

PU

D4 Conformity to legislation Report

PU

Page 14: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

ANNEX I TO THE CONTRACTASSESSMENT OF RISKS

Design Study

Task Main deliverable Crucial milestones Type of risk Actions Consequences

2 Multi-MW liquid-Hg proton-to-neutron converter design

Decisions on draft design parameters (14 months)

Some challenging technical aspect(s) unsolved

(1)Further R&D(2)Use of high-Z solid converter

Staging of the target station construction, delay of full power operation (1-2 years)

4 Design and test of a sizable(few kg) UCx

target

Target design and integration on the n-converter (36 months)

Geometry and coupling to the converter and 1+ source not optimized

Need for further R&D Degradation of RIB intensity, delay in reaching expected final RIB intensities (1-2 years)

5 Evaluation of the facility impact (safety and radioprotection aspects) on the environment and on the maintenance and running procedures

Radiation and activation estimated (12 months)

Need to reconsider layout of the very “hot” parts of the facility

(1)Redesigning the “hot” parts of the facility(2)Reducing the beam power

(1)Increase of facility cost(2)Facility performance degradation (partially recovered in long term by optimizing overall efficiency)

7,8 Design and test of prototypes related to the SC low-energy part of the driver linac

Cold test of complete cryomodule(36 months)

Beam tests of cryomodule and cavities too time- consuming

(1)Need more time for tests and problem solving(2)Rely only on off-beam tests

Minor impact on construction planning of the facility

9 Charge Breeder: advanced performance in terms of high charge state and related efficiency

Report on charge

breeding R&D

(19 months)

132Sn25+ produced with poor efficiency (below 10%)

(1)Need for further R&D,(2)Use of stripping sections

Increase of post-accelerator cost and/or size (10-20%)

9 60-GHz pulsed ECR ion source

Intermediate report on

bunched efficiency

(24 months)

Source not reaching design

specifications

(1)Need for further R&D(2)Use different approach to meet bunching requirement

(1)Delay Beta Beam (1-2) years(2)Delay Beta Beam (3-4) years

Page 15: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

The Beta-Beam conceptDesign Study

=10

Decay

RingISOL target & ion source

Proton driver linac

Linac

<150

ECR

Storage ring, synchrotrons and decay ring

EURISOL

=10

Decay

RingISOL target & ion source

Proton driver linac

Linac

<150

ECR

Storage ring, synchrotrons and decay ring

EURISOL

Page 16: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

TOPICS OF MAJOR CONCERN FOR THE MANAGEMENT

The upper list regards topics already assessed in Eurisol RTD but they need to be fully explored in this design study

1. Layout of the facility2. Cost estimation of the facility (better then 20%)3. Site options (National Lab., Intergovernmental Institution, Less

favorite countries new Lab.4. Multi user capability5. Cost/benefit of the different technical solutions6. Comparison of CW and high duty cycle driver solution

1. Global coherence2. Synergies with EURONS, CARE (HYPPI), SPALLATION NEUTRON

SOURCES3. Dissemination of results4. EURISOL DS Web site5. Outreach activity

Design Study

Page 17: EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility THE GOAL Producing an engineering oriented study of the EURISOL Facility and

NEXT STEPS

1. Signature of the contract (within the end of the year - Ganil /EC)

2. Signature of the Consortium Agreement (Participants)

3. Access to the contract by participants (Ganil- Participants)

4. Appointment of the Steering Committee Members by Contractors and election

of the Chair person (kick-off meeting)

5. Kick-off meeting date: 3/2/2004 Afternoon MB-CB meeting 4/2/2005 SC meeting

Design Study

6. Tentative dates of the 2005 official meeting

- End of May: MB and CB meeting - Mid September: MB and CB Meeting - 30th Nov-3rd Dec: Eurisol Ds week During the week the following meetings will take place:

a) MB and CB b) Annual participants meeting c) Steering Committee meeting

Aim of the Eurisol week:

Review and monitor the activities of the year, check the overall project planning, extend the discussion and the confrontation on the achieved results to all community, approve the general lines (technical, scientific and administrative matters) of the yearly reports, discuss and approve the activities planning for the incoming year taking into account the suggestion given by the community