EURISOL DS EUropean Isotope Separation On-Line Radioactive Ion Beam Facility
THE GOAL Producing an engineering oriented study of the EURISOL Facility and developing prototypes of the most critical parts of the facility itself.
“Starting point: EURISOL RTD Recommendations”
Design Study
THE MANAGEMENT BOARD
Graziano Fortuna: Project Leader
Yorick Blumfeld
Peter Butler Mats Lindroos
Management Support Team (core staff)
Technical Coordinator: John Cornell Scientific liaison Office: A. Andrighetto
M. Comunian …….
Administrative Office: R. Battistella V. Vandevoorde
…….
EURISOL DS EUropean Isotope EURISOL DS EUropean Isotope SeparationSeparation
On-Line Radioactive Ion Beam Facility On-Line Radioactive Ion Beam Facility
IDENTITY CARDIDENTITY CARD
EU CONTRIBUTION:EU CONTRIBUTION: ((k€)k€) 9161.99161.9 - FTE 113,25- FTE 113,25
TASKS:TASKS: 12 12 (FOUR TOPIC AREAS)
PARTICIPANTS:PARTICIPANTS: 21 21 GANIL (F), CNRS/IN2P3 (F), INFN-LNL (I), INFN (I), CERN (UE), UCL (B), CEA (F), NIPNE (RO), JYU (FI), LMU (G), FZJ (G), FI (LT), UW (PL), SAS (SK), U- LIVERPOOL (UK), GSI (G), USDC (E), CCLRC (UK), PSI (CH), IPUL (LV), SU MSL (SE) (15 countries involved)(15 countries involved)
PROJECT ESTIMATED TOTAL EFFORTS:PROJECT ESTIMATED TOTAL EFFORTS: ((k€)k€) 32.284,3 32.284,3 - FTE 490,45- FTE 490,45
Design Study
DURATION OF THE PROJECT:DURATION OF THE PROJECT: 48 MONTHS48 MONTHS
STARTING DATE:STARTING DATE: END OF JANUARY-BEGINNING OF FEBRUARY END OF JANUARY-BEGINNING OF FEBRUARY 20052005COORDINATING INSTITUTION:COORDINATING INSTITUTION: GANIL (F)GANIL (F)
CONTRIBUTORS: 21U-FRANKFURT (G), BUDKER (RU) ,VNIIFT (RU), PNPI (RU), ORNL (USA), ANL (USA), KAERI (SKR), TRIUMF (CA),
JAERI (JP), SOREQ (IL), U-MAINZ (G), VINCA (YU), KVI (NL), U-SURREY (UK), U-YORK (UK), U-PAISLEY (UK), U-UPPSALA (SE), NSCL (USA), FNAL (USA), INFN-LNS (I), HUG (CH)
(13 countries involved from Europe, Asia and North America)
TASKSAND RELATED FOUR TOPIC AREAS
• EURISOL DS Managemt (GANIL/INFN-LNL/CNRS-IN2P3/CERN)
• Targets and ion sources (Synergies with neutron spallation sources and neutrino facilities)
– Multi-MW target station : mercury converter (CERN) – Direct target : Several target-ion source prototypes (CERN) – Fission target : UCx target (INFN-LNL)
• Accelerators (Synergies with HIPPI (CARE))– Proton accelerator design: the driver (INFN-LNL): – Heavy ion accelerator design: the post accelerator (GANIL)– SC cavity development, prototypes and multipurpose cryomodule (CNRS-
IN2P3-IPNO)
• Physics, beams and safety (Synergies with EURONS)– Physics and instrumentation (U-LIVERPOOL)– Beam intensity calculations (GSI)– Safety and radioprotection (CEA)
• Beta-Beams Aspects (Synergies with BENE (CARE))– Beam preparation : breeders, 60 GHz ECR source (JYV) – Beta-beam aspects: conceptual design report of the Beta-Beam facility. It
includes preliminary studies on modifications of CERN accelerators in case the facility is sited at CERN
Design Study
3
2
3
1 1 1
2
1 1 1 1 1 1 1 1
0
1
2
3
4
France
Italy
Germ
any
Cern
(Eur)
Switzer
land
Spain
Unite
d Kin
gdom
Finla
ndLith
uania
Polan
dRom
ania
Latvi
aBel
gium
Slova
kia
Sweden
Country of Origin of Partecipanting I nstitutions
4
2
3 3
1 1 1 1 1 1 1 1 1
0
1
2
3
4
5
Country of origin of Contributing Institutions
4 4
10
1413
8
5
9
15
9 9
3
0
2
4
6
8
10
12
14
16M
anag
emen
t
Mul
ti M
W T
arge
t Sta
tion
Direct
Tar
get
Fiss
ion
Targ
et
Safet
y& R
adio
prot
ectio
n
Heavy
Ion
Acc
eler
ator
Des
ign
Proto
n Acc
eler
ator
Des
ign
SC Cav
ity D
evel
opm
ent
Beam
Pre
para
tion
Physi
cs a
nd In
stru
men
tatio
n
Beam
Inte
nsity
Cal
cula
tions
Beta
Beam
s A
spec
ts
Participants and Contributors per task
TASK LEADERS PER COUNTRY
3
33
1
11
France
I taly
Switzerland
Finland
United Kingdom
Germany
STEERING COMMITTEE
1 representative of each Participant+ Management Board and Chairs of NUPECC,
ESGARD, EURONS (all ex-officio)1 meeting/year
MANAGEMENT BOARD
Project Leader + 3 Members
MANAGEMENT SUPPORT TEAM
1. Administrative Office2. Scientific liaison Office3. Technical coordinator
COORDINATION BOARD
Management Board+ Task Leaders
+ Coordinators of HIPPI JRA and BENE Network (ex-officio)
2-3 Meetings/year
INTERNATIONAL ADVISORY PANEL
3 Members – 1 Meeting/year
ANNUAL PARTICIPANT MEETING
1 Meeting/year
Ta
sk 2
Ta
sk 3
Ta
sk 1
MANAGEMENT STRUCTUREDesign Study
Where have we got to?
Annex I to the contract and CPF Forms submitted to EC
on 30th September, 2004
The “magic words” most frequently used in Annex I:
1. Objectives2. Milestones3. Deliverables
Design Study
ANNEX I TO THE CONTRACT LIST OF CONTENTS
1. Project summary 2. *Project objectives3. List of participants4. Implementation plan for the full duration of the project 4.1 List of tasks 4.2 Implementation plan 4.3 *Description of tasks5. Consortium management activities 5.1 Organisational structure and overall project management 5.2 Potential impact and risks assessment 5.3 Plan for use and dissemination of knowledge6. Project resources and budget overview 6.1 Personnel effort for the full duration of the project 6.2 Description of other resources needed 6.3 Overall budget for the full duration of the project
* Significant reshaping of the related original test of the proposal
Design Study
TASK DESCRIPTION EXAMPLE
Design Study
Objectives
Due to drastically increased radioactive inventory compared to current worldwide RIB facilities, the following list of objectives has been identified that need research and development:
1. Calculation of radiation production and activation. 2. Methods for shielding against prompt radiation and for the containment of
activity. 3. Handling of targets and in particular the disposal of spent targets.4. Conformity of the proposed installation to the legislation.
The realization of this task is crucial for the Design Study of the new generation RIB facility in order to characterize the radioactive inventory, to identify the technical challenges, to characterize the safety approval procedures, to estimate the impact of safety and radioprotection issues on the final cost of the installation.
Start month 1 End month 46
Participant number* 7 1 5 8 10 11 12 13
Participant short name CEA GANIL CERN NIPNE LMU FZJ FI UW Total
Person-months 66.00 33.00 66.00 96.00 78.00 78.00 108.00 36.00 561.00
Task number 5 Task title Safety & Radioprotection
TASK DESCRIPTION EXAMPLEDesign Study
Description of work
The work includes:1. Radiation, activation, shielding & doses - characterization of radiation from primary beam components, target-converter, RNB production
target, beam dump, secondary beam lines; - activation estimates of accelerator components, target-converter, RNB production target, beam dump,
separator and ionizer, secondary beam lines, environment (building, air, soil, ground water); - characterization of radio-elements produced with respect to (2); - optimization of shielding against prompt radiation fields and activated structures; - dose rate calculations.2. Radioactivity control, safety & risks - study of dispersion of radio-elements, contamination, migration; - study of safety associated with oxidation of target materials; - study of containment of volatile radioactivity; - safety and risks associated with target preparation, handling, confinements and nuclear ventilation,
flow of radioactive materials, etc.; - prevention and limitation of personnel direct and indirect exposure: risk and failure scenarios; - prevention and limitation of waste production, radioactivity dispersion and rejections. 3. Decommissioning - storage and disposal of spent targets; - characterization of radioactive waste produced; - characterization of activated structures, their volumes, masses, specific activity, radio-elements; - guidelines of the decommissioning and dismantling strategy; - risk estimates.4. Conformity to legislation - study of the licensing and permission procedures; - guidelines on the technical options; - guidelines on implementation and execution conditions; - potential risk and delays estimates.
TASK DESCRIPTION EXAMPLE
Design Study
NO. Milestones and expected result of this task: Months due
M1 Radiation, activation, dose
M1.1 Validation of code 6
M1.2 Radiation & activation estimates 12
M1.3 Shielding guidelines 22
M2 Radioactivity control, safety and risk
M2.1 Dispersion of radioactivity 17
M2.2 Test of purification system 31
M2.3 Containment of radioactivity 17
M2.4 Activity transport in ground water 17
M2.5 Report 44
M3 Decommissioning issues
M3.1 Report 45
M4 Conformity to legislation
M4.1 Report 46
Deliverable number
Deliverables Dissemination level1
D1 Radiation, activation, doseShielding guidelines
PU
D2 Radioactivity control, safety and riskReport
PU
D3 Decommissioning issues Report
PU
D4 Conformity to legislation Report
PU
ANNEX I TO THE CONTRACTASSESSMENT OF RISKS
Design Study
Task Main deliverable Crucial milestones Type of risk Actions Consequences
2 Multi-MW liquid-Hg proton-to-neutron converter design
Decisions on draft design parameters (14 months)
Some challenging technical aspect(s) unsolved
(1)Further R&D(2)Use of high-Z solid converter
Staging of the target station construction, delay of full power operation (1-2 years)
4 Design and test of a sizable(few kg) UCx
target
Target design and integration on the n-converter (36 months)
Geometry and coupling to the converter and 1+ source not optimized
Need for further R&D Degradation of RIB intensity, delay in reaching expected final RIB intensities (1-2 years)
5 Evaluation of the facility impact (safety and radioprotection aspects) on the environment and on the maintenance and running procedures
Radiation and activation estimated (12 months)
Need to reconsider layout of the very “hot” parts of the facility
(1)Redesigning the “hot” parts of the facility(2)Reducing the beam power
(1)Increase of facility cost(2)Facility performance degradation (partially recovered in long term by optimizing overall efficiency)
7,8 Design and test of prototypes related to the SC low-energy part of the driver linac
Cold test of complete cryomodule(36 months)
Beam tests of cryomodule and cavities too time- consuming
(1)Need more time for tests and problem solving(2)Rely only on off-beam tests
Minor impact on construction planning of the facility
9 Charge Breeder: advanced performance in terms of high charge state and related efficiency
Report on charge
breeding R&D
(19 months)
132Sn25+ produced with poor efficiency (below 10%)
(1)Need for further R&D,(2)Use of stripping sections
Increase of post-accelerator cost and/or size (10-20%)
9 60-GHz pulsed ECR ion source
Intermediate report on
bunched efficiency
(24 months)
Source not reaching design
specifications
(1)Need for further R&D(2)Use different approach to meet bunching requirement
(1)Delay Beta Beam (1-2) years(2)Delay Beta Beam (3-4) years
The Beta-Beam conceptDesign Study
=10
Decay
RingISOL target & ion source
Proton driver linac
Linac
<150
ECR
Storage ring, synchrotrons and decay ring
EURISOL
=10
Decay
RingISOL target & ion source
Proton driver linac
Linac
<150
ECR
Storage ring, synchrotrons and decay ring
EURISOL
TOPICS OF MAJOR CONCERN FOR THE MANAGEMENT
The upper list regards topics already assessed in Eurisol RTD but they need to be fully explored in this design study
1. Layout of the facility2. Cost estimation of the facility (better then 20%)3. Site options (National Lab., Intergovernmental Institution, Less
favorite countries new Lab.4. Multi user capability5. Cost/benefit of the different technical solutions6. Comparison of CW and high duty cycle driver solution
1. Global coherence2. Synergies with EURONS, CARE (HYPPI), SPALLATION NEUTRON
SOURCES3. Dissemination of results4. EURISOL DS Web site5. Outreach activity
Design Study
NEXT STEPS
1. Signature of the contract (within the end of the year - Ganil /EC)
2. Signature of the Consortium Agreement (Participants)
3. Access to the contract by participants (Ganil- Participants)
4. Appointment of the Steering Committee Members by Contractors and election
of the Chair person (kick-off meeting)
5. Kick-off meeting date: 3/2/2004 Afternoon MB-CB meeting 4/2/2005 SC meeting
Design Study
6. Tentative dates of the 2005 official meeting
- End of May: MB and CB meeting - Mid September: MB and CB Meeting - 30th Nov-3rd Dec: Eurisol Ds week During the week the following meetings will take place:
a) MB and CB b) Annual participants meeting c) Steering Committee meeting
Aim of the Eurisol week:
Review and monitor the activities of the year, check the overall project planning, extend the discussion and the confrontation on the achieved results to all community, approve the general lines (technical, scientific and administrative matters) of the yearly reports, discuss and approve the activities planning for the incoming year taking into account the suggestion given by the community