45
IWWS8 Beijing April 2006 Eumetsat Status report Ken Holmlund Eumetsat [email protected]

Eumetsat Status report Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

  • Upload
    tyanne

  • View
    66

  • Download
    5

Embed Size (px)

DESCRIPTION

Eumetsat Status report Ken Holmlund Eumetsat [email protected]. GEO Spacecraft Status and Plans EUMETCast status Eumetsat Retransmission Service (EARS) Metop (EPS) Status Reprocessing activities. Introduction. Met-7 drift start Met-9 drift stop Met-9 start imaging - PowerPoint PPT Presentation

Citation preview

Page 1: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Eumetsat Status report Ken Holmlund

Eumetsat [email protected]

Page 2: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Introduction

• GEO Spacecraft Status and Plans• EUMETCast status • Eumetsat Retransmission Service (EARS) • Metop (EPS) Status• Reprocessing activities

Page 3: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Met-9Met-8

MSG-2 Comm

J J JF M A M A S O N D J J JF M A M A S O N D

3.4ºW

MSG-2

• Met-7 drift stop• Met-7 start imaging• Met-5 stop imaging

• Met-7 drift start• Met-9 drift stop • Met-9 start imaging• Met-8 stop imaging

6.5ºW

J A S O N D2006

Met-8

2007

Met-7

Met-7

9.5ºE

2005

58ºE63ºE

• Met-6 stop RSS• Met-6 drift start

Met-6

Met-6

Met-5 in a graveyard orbit

Met-5

• Met-5 re-orbiting• Met-6 drift stop

J J JF M A M A S O N D J J JF M A M A S O N DJ A S O N D

2006 20072005

• Met-9 drift start

Page 4: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

• Met-7 direct dissemination stops on 14 June 2006• Met-9 enters Operational Service at 0° on 1 Aug 2006• Met-8 stops dissemination on end September 2006• Met-7 starts the IODC mission early Dec 06• Met-5 stops imaging and supports the DCP mission in eclipse• Met-6 stops the RSS service on 31 Dec 2006• Met-5 is re-orbited in late April 07• If DCP testing on Met-8 is successful, Met-6 is relocated at 63°E

to support the DCP mission in eclipse• During the Met-7 drift users are likely to experience degraded

performances of RSS. A minor impact is expected on IODC data• Meteosat-8 Rapid Scanning is TBC, earliest expected Jan 2008

Page 5: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

MSG-2 Commissioning• On schedule• Image and Product Validation ongoing• Low-frequency modulated noise on 6.2 micron

channel– Induced in pre-amp or other onboard electronics– Possible corrective measures

• Redundant h/w• On ground processing

Page 6: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

6.2 micron striping (MSG-1 vs MSG-2)

Page 7: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Impact of change in non-linearity correction

Page 8: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Met-8/Met-9 AMV

Page 9: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

MSG Rapid Scanning

• Specification– 7 yrs lifetime – nominal scanning full disc– Rapid scanning possible– But not combined!

• Current lifetime tests– 1-4 years nominal +3 yrs RSS– 2-7 years RSS– Spindle life test 3 years nominal + 7 yrs RSS (TBC)– Ball Bearings extension test

Page 10: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EUMETCast Status Report

Page 11: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Activities and Events • Aug 2005: Ku-Band bandwidth increase by 3 Mbps (EPS

Global Data dissemination support)• Oct 2005: Operational dissemination of Land SAF products

(products of preceding trial dissemination phase)• Dec 2005: Signature of contract for EUMETCast South

America Service• Dec 2005: Start of operational dissemination of the OSI SAF

(KNMI) product “Surface Wind Vector”• Dec 2005 Start of test dissemination of ERS SCAT data (in

EARS, precursor to EARS ASCAT Service)• Jan 2006: Start of EUMETCast South America Service• Feb 2006: Start of trial dissemination of the new OSI SAF

(Norway) product “North Hemisphere Sea Ice”

Page 12: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EUMETCast Coverage of South America• South America remains the most significant area imaged to which

Met-8 data is not disseminated - particularly Brazil with the same viewing angles like Spain and Portugal

• MSG-2 LRIT data will be available to South America, but is not suitable for quantitative applications (only half-hourly, 5 out of 11 channels, no HRV, lossy compression)

• 57th Council meeting (summer 2005) endorsed setting up of the EUMETCast South America service:– Pilot service of 3 years – Corresponding ITT issued beginning of August 2005, contract

signed December 2005, start of service in January 2006, operational acceptance scheduled for March/April

Page 13: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EUMETCast South America Service• Service Provider: GlobeCast Spain

• Communication S/C: NSS-806, 40.5 o West, from NewSkies• C-Band, 2.1 Mbps Bandwidth• Turn around service (like C-Band Africa Service)• Turn around of (only) the High Rate SEVIRI images• Turn around reception in Madrid, up-link station near Paris

Users in Europe

Users in South America

HotBird 6 at13°E

4 MbpsKu-band

2 MbpsC or Ku-band

EUMETCastSouth America

uplink

EUMETCast Ku-band uplink in

Usingen, Germany

NSS-806 at 40.5 o W

Page 14: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EUMETCast America Service Coverage

Page 15: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EUMETCast America Service Europe Coverage

Page 16: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Turn Around Services on C-Band

Multi Service ChannelChannel 32.7 Mbps

High Rate SEVIRI(all 12 spectral channels)Channel 2

BandwidthServiceKu-Band Multicast Channel

C-Band Africa Service

2.048 MbpsHigh Rate SEVIRI(all 12 spectral channels)Channel 2

BandwidthServiceKu-Band Multicast Channel

C-Band America Service

Page 17: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EUMETCast Provided Services & EKUs – Jan 05 to Jan 06

0

200

400

600

800

1000

1200

1400

1600

1800

Jan-05 Feb-05 Mar-05 Apr-05 May-05 Jun-05 Jul-05 Aug-05 Sep-05 Oct-05 Nov-05 Dec-05 Jan-06

15-min SEVIRI Users

RSS Users

DWDSAT Users

DCP Users

HRI 0 Users

HRI IODC Users

MDD Nominal Users

BMD

No.of EKUs Issued (EUMETCastStations)

Page 18: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Pilot EARS-AVHRR ServiceEarly Access

Page 19: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Pilot EARS-AVHRR ServiceEarly Access (1/2)

• Purpose: To enable Users and Manufacturers to adapt Processing and Visualisation Systems to new products;

• User Registration started on 9 March – 113 registrations in first week;• Trial dissemination via EUMETCast of NOAA-17 and NOAA-18 received

at Maspalomas has started.• In line with Operational Service Specification in terms of:

– Product Formatting;– Filename Convention;– Compression Algorithm;– 1-minute Segmentation;– EUMETCast configuration details.

Page 20: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Pilot EARS-AVHRR ServiceEarly Access (2/2)

• Trial dissemination may be interrupted or modified without prior notice.

• Additional Stations to be added in the coming months– Tromsoe expected in April;– Kangerlussuaq and Lannion during May/June;– Svalbard to replace Tromsoe during Summer;– Athens Awaiting resolution of Radio Frequency

Interference Problem.

Page 21: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Pilot EARS-AVHRR ServiceTarget Regional Coverage

Svalbard

Kangerlussuaq

Maspalomas

LannionAthens

Page 22: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

MODIS Winds in NWP

Current Operational Users:

• European Centre for Medium-Range Weather Forecasts (ECMWF) - since Jan 2003.

• NASA Global Modeling and Assimilation Office (GMAO) - since 2003.

• Deutscher Wetterdienst (DWD) – since Nov 2003.

• Japan Meteorological Agency (JMA), Arctic only - since May 2004.

• Canadian Meteorological Centre (CMC) – since Sept 2004.

• US Navy, Fleet Numerical Meteorology and Oceanography Center (FNMOC) –since Oct 2004.

• UK Met Office – since Feb 2005.

• National Centers for Environmental Prediction (NCEP) and the Joint Center for Satellite Data Assimilation - since Nov 2005.

• NCAR Antarctic Mesoscale Model (AMPS)

Page 23: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

MODIS Polar Winds Real-Time Processing Delays - Frequency of Delays in Wind Retrievals

With an average delay of 3-5 hours, MODIS winds do not meet the 3-hr (or less) cutoff for early model runs.

Possible solution: Generate winds with direct broadcast data, either on- or off-site.

Processing times are for the middle image in a 3-orbit triplet. Actually processing time from image acquisition to availability of wind vectors is 100 minutes (1.67 hrs) less than shown.

Page 24: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

MODIS Data Acquisition Time

Bent-pipe

McMurdo

Page 25: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Tromsø, Norway

A polar winds system was installed at Tromsø, Norway, at the Kongsberg Satellite Services (Ksat) facility in February 2006. The MODIS data are currently acquired with the Integrated Program Office (IPO, the NPOESS people) antenna on Svalbard. At present, wind generation if from Terra only and is irregular due to antenna scheduling issues.

Page 26: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Tromsø Winds

As with McMurdo, the wind quality is essential the same as the bent-pipe winds. Processing time is 10-15 minutes longer, however, because the low-level processing system is different and images are larger.

Page 27: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EPS STATUS

EUM.EPS.SYS.TRN.06.002 EPS LORR Part 2 - Presentation by the Project Team

Page 28: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Project Team assessment - Status:• Full “Spring 2004“ implementation expected to be ready for launch.• System testing for the “Spring 2004” PPFs currently performed on GS-3,

together with other “Spring 2004” facilities such as DIF and QCF (for which appropriate versions are already available & in use).

• Migration to GS-2 is foreseen for April and subsequently to GS-1 (mid May).

PPF “Spring 2004” Status

Page 29: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Level 1 Processors Availability: • “Spring 2004” testing has been successful for L1 of ATOVS, IASI, ASCAT and GOME :

– ATOVS L1 PPF OSAT took place in March, some minor corrections need to be integrated

– IASI L1 PPF is available and final NC corrections available– ASCAT L1 PPF is completed and fully available.– GOME L1 PPF FAT took place in February. A corrected version is already under

validation • “Spring 2004” GRAS PPF OSAT target date mid April. Test version of PPF provides

good level 1 a products. Converging on Level 1b.Level 2 Processors availability:• “Spring 2004” ATOVS L2 not yet available - Target date for FAT is 24th April.• “Spring 2004” IASI L2 not yet available - Target date for completion is 26th July.

PPF “Spring 2004” Status

Page 30: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Processor evaluation in 3rd quarter 2006, OSAT 04/2006

12/2006ATOVS L207/2006IASI L2

Level 1 a products ok, Level 1b products being verified, POD being checked.

04/2006GRAS L1

04/2006IASI L1

04/2006GOME L1

03/2006ASCAT L1

NRT production verified with NOAA-18 data

03/2006ATOVS-AVHRR L1

CommentsImplementationProduct chain

PPF Implementation PlanTransition of the operational processing facilities to “Spring 2004”:

– Activity initiated in February 2006 and will extend over the year 2006

Page 31: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

First CGS(-2) output of ATOVS L1NOAA 18, 11/01/2006 13h41 – 15h27

UTC:

Ackermann, 2006

Page 32: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Overview of Planned HRPT Data Availability

• Exact timeline is currently being refined: as such the information provided here is indicative only. An updated timeline will be available before end-April.

• HRPT link to be switched on by Day 2 of Satellite In-Orbit Verification (SIOV) Phase (5 days after launch).

• Check-out of link will be finished by end of Week 1 of SIOV.• The current planning for the SIOV timeline is indicated on next

slide. Note that the blue bars indicate that the instrument is in its nominal measurement mode.

• Data will also be available intermittently during mode check-outs (red bars).

• Not shown is the data availability of the AVHRR Visible Channel: already available at end of Week 1 of SIOV (will be included).

Page 33: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Week WK1 WK2 WK3 WK4 WK5 WK6 WK7 WK8 WK9 WK10 WK11

SVM

NIU MPU

PLM

ASCAT

GRAS

MHS

COOLER SHUTTER

GOME2

ROUTINE DECONT + LFD

IASI

AVHRR 3

HIRS 4

AMSU A1

AMSU A2

SEM 2

B A

SARR

1

SARP 3

A-DCS

Days from 01 02 03 04 05 08 09 10 11 12 15 16 17 18 19 22 23 24 25 26 29 30 31 32 33 36 37 38 39 40 43 44 45 46 47 50 51 52 53 54 57 58 59 60 61 64 65 66 67 68 71 72 73 74

Start of SIOV

ICU Switch on (including NIU & MPU) Equipment switch on & modes check Cal/Val activity

Outgassing Performance verification

Page 34: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EPS Product Services CGS BASELINE PRODUCTS INCLUDE:

All level 1 Products from all NOAA & Metop sensors Selected Level 2 Products: Temperature/Moisture Profiles, Cloud

Products... New level 2 products to be implemented

Soil moisture (ASCAT) Polar winds (AVHRR) NDVI (AVHRR)

VARIETY OF SERVICES/LEVEL 2 PRODUCTS FROM 7 SAFs: Ocean & Sea Ice Support to nowcasting & VSRF (SW Packages) Ozone Monitoring GRAS Meteorology Climate Monitoring Land Surface Analysis NWP

Page 35: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EPS Product Formats AVHRR

Native only ATOVS

L1 & L2 BUFR ASCAT

L1 & L2 BUFR (L2 Satellite Application Facility) IASI

L1 & L2 in BUFR, Limited data set over GTS GRAS

L1 BUFR and native, L2 BUFR (SAF), GTS potentially limited

GOME-2 L1 native, L2 various (SAF)

Page 36: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

• Detailed planning for validation of the individual PPFs available (see schedule)

• Availability of verified (Geometry, Radiometry) products after launch:

Level 1 products• AVHRR: 2 months after launch• ATOVS: 4 months after launch• IASI L1 : 5 months after launch• ASCAT: 4 months after launch• GRAS : 2 months after launch

L2 products:• ATOVS : February 2007• IASI L2 : December 2006

Note 1: These dates are likely to be earlier, since we plan to provide products as soon as they are in reasonable bounds after instrument switch on (caveat: not declared operational)

Note 2: HRPT data will be available to Users as soon as instruments are switched on, however quality may be degraded

Plan for validating PPFs

Page 37: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Status of EPS-EUMETCast Convergence (EEC)

• Dissemination of EPS Global Data via EUMETCast• Replacement of baseline Near Real Time (NRT) system• Past activities:

– In 2004, related analysis, preliminary design, feasibility testing and planning performed in an OPS Project

– Approval by 56th Council Meeting in December 2004 of extension of EUMETCast from 2006 - 2008 to include EPS Global Data dissemination

– Implementation Project “EPS-EUMETCast Convergence” set up in January 2005

– Additional Bandwidth in Ku-Band:• 3 Mbps (permanent) from August 2005, additional to 4

Mbps for the existing/operational services)• 12 Mbps permanent/total from 1 April 2006 on

Page 38: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EEC Activities• Jan/Feb Final configuration and testing of a Reference

EUMETCast Terminal supporting the full 12 Mbps datastream, including full product reconstruction S/W

• Jan/Feb Delivery and installation of Reference EUMETCast Terminals to SSST (ESTEC), CLS Argos and IASITEC (CNES/Toulouse)

• Jan - April Implementation and testing of new releases of TelliCast

Server (up-link) and Client (EUMETCast Terminal) S/W => bandwidth management AR and bandwidth sharing

• Feb - June Dissemination of EPS Global Data originating from theEPS GS (V&V and Ops Scenarios Testing)

• July - … Dissemination of Live Metop EPS Global Data

Page 39: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

EPS Programme Team Assessment• The activities are on target to enter the final pre-launch phase. • No significant, single blocking point has been identified

affecting launch critical elements of the system.• However:

– The AMSU-A1 instrument has to be replaced– The Metop CFS SW must be patched to correct the PMC SW problem

found during SSVT– A new MCS version must be installed – Regression testing approach for latter elements must be

defined/finalised– A number of system evolutions need to be completed during rehearsals.

• The rehearsals themselves present quite a challenge in this environment.

• Current launch date 17 July 2006

Page 40: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Reprocessing• Support to various activities

– ECMWF ERA, JMA ERA, Surface albedo, etc• Latest: Roughly 10 years in 90’s• Including ADC and XADC!

– Available from the archive• New reprocessing environment under

development– 1 month/day or better possible– Full Meteosat archive (33 years) ~1 year

Page 41: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

Re-calibration (reprocessing)

Page 42: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

ADC and XADC processing

Page 43: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

ADC CMW Product(Blue = IR, Red = WV)

Page 44: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

ADC CMW Product(Blue = IR, Green=VIS, Red = WV)

Page 45: Eumetsat Status report   Ken Holmlund Eumetsat kenneth.holmlund@eumetsatt

IWWS8 Beijing April 2006

RMPEF-2

• 1 month of single satellite data in 1 day– Full Meteosat archive ~1 year

• Reprocessing of MSG MPEF products• Inclusion of new products