Euclid Creek Tunnel
Community Update
December 18, 2012
euclidcreek.blogspot.com
The Communications Team
• Jim BunseyDeputy Director of Engineering & Construction
• Doug GabrielProgram Manager, Euclid Creek Tunnel
• Ryan SullivanSenior Construction Supervisor
• Bob AuberConstruction Manager
• Jenn EltingPublic Information Specialist
euclidcreek.blogspot.com
Current Communications
• Contractor Communications– Hard-copy letters
– McNally/Kiewit
• Euclid Creek Newsletter– Quarterly
• Construction Hotline– (216) 432-7157
– Multiple Sewer District projects
• E-mails from Doug Gabriel
euclidcreek.blogspot.com
Current Communications
• Euclid Creek Blog (euclidcreek.blogspot.com)
– Construction updates (Ryan) & articles of interest (Jenn)
• E-mail Newsletter
– Twice-monthly (Jenn)
• Collinwood Observer
– More Sewer District articles &Euclid Creek Tunnel updates
• Regular Meetings
– Third Tuesday of each month: 6 p.m.
euclidcreek.blogspot.com
Project Overview
euclidcreek.blogspot.com
Construction Updates
• East 156th Street utility relocation
– Work completed last week
• New sewer, Lakeshore BoulevardEast 150th Street to (east of) Collinwood Rec.
– Work complete: Sept 2013
• New sewer, St. Clair Ave. and Nottingham Rd.
– Work completed: Oct 2013
euclidcreek.blogspot.com
Shaft #1Construction Staging Site
• “Mackenzie” tunneled and lined 2800’
• Operating 24/7 with regularly-scheduled maintenance periods
euclidcreek.blogspot.com
Shaft #2Easterly Wastewater Treatment Plant
• 60 feet excavated
• Add’l 40 feet before bedrock
– Blasting last 100 feet
– Will not begin until 2013
euclidcreek.blogspot.com
Shaft #3Beulah Park
• Construction staging area
– Crews to site week of November 5
– Secant pile wall
• Contractors mobilize week of December 17
• Monday through Saturday
– Other activities
• 100 ton crane arrived today
• Add’l large equipment arriving on site later this week
euclidcreek.blogspot.com
Shaft #3Beulah Park
Within construction site looking north.
euclidcreek.blogspot.com
Shaft #3Beulah Park: Safety
Construction Entrance to be 4-Way Stop
euclidcreek.blogspot.com
Shaft #4Triangle Park
• Excavation work is complete at this site
• Currently installing rebar to reinforce shaft
• Fencing will remain throughout 2014
euclidcreek.blogspot.com
Shaft #4Triangle Park
• Work is complete at this site
• Fencing will remain throughout 2014
euclidcreek.blogspot.com
Shaft #5Nottingham & St. Clair
• Excavation nearing completion
– 175 feet excavated
– 25 more to go
euclidcreek.blogspot.com
Shaft #5Nottingham & St. Clair
• 175 feet excavated, 25 more to go
• No blasting at this site
euclidcreek.blogspot.com
euclidcreek.blogspot.com
Upcoming Construction Impacts
• AT&T UG Relocation at 3-5 (E 156th and Lakeshore) – work to begin Late Dec
• Structure 3-2 – excavation to begin late January
• Structure 5-4 – solider pile installation and excavation to begin mid January
euclidcreek.blogspot.com
Next Meeting
• Tuesday, January 15, 20136:00 p.m.Cleveland Public Library,Memorial-Nottingham Branch
• Save the Date!
– February 19
– March 19
– April 16