Estimating Duration

Embed Size (px)

Citation preview

  • 8/2/2019 Estimating Duration

    1/27

    Estimating Duration

  • 8/2/2019 Estimating Duration

    2/27

    Estimating Duration

    The duration of a project is the elapsed time in

    business working days

    It does not include weekends, holidays, orother non-working days

    Work effort is labor required to complete an

    activity

    That labor can be consecutive or non-

    consecutive hours

  • 8/2/2019 Estimating Duration

    3/27

    Resource Loading Vs Activity Duration

    Resource loading means that number of persons assigned to a task

    The duration of an activity is influenced by the amount of resources

    scheduled to work on it

    We say influenced because there is not necessarily a direct linear

    relationship between the amount of resource assigned to an activity andits duration

    There are diminishing returns for adding more resources

    There is a maximum loading of resources on a task to minimize the

    activity duration, and that by adding another resource you will actually

    begin to increase the duration You have reached the crashpoint of the activity. The crashpoint is that

    point where adding more resources will increase activity duration

  • 8/2/2019 Estimating Duration

    4/27

    Variation in Activity Duration

    Activity duration is a random variable because we cannot know exactly

    how long it will take

    One of your goals in estimating activity duration is to define the activity to

    a level of granularity so that your estimates have a narrow variance

    There are several causes of variation in the actual activity duration-

    Varying skill levels

    Unexpected events

    Efficiency of work time

    Mistakes and misunderstandings

    Common cause variation (the reality is that durations will vary for no reasonother than the statistical variation that arises because the duration is in fact a

    random variable )

  • 8/2/2019 Estimating Duration

    5/27

    Methods of estimating Activity Duration

    In consulting practice six techniques are found

    to be quite suitable for initial planning

    estimates as follows

    Similarity to other activities

    Historical data

    Expert advice

    Delphi technique

    Three-point technique

    Wide-band Delphi technique

  • 8/2/2019 Estimating Duration

    6/27

    Extrapolating Based on Similarity to

    Other Activities

    Some of the activities in your WBS may be

    similar to activities completed in other

    projects

    Recollections of those activities and their

    duration can be used to estimate the present

    activitys duration

  • 8/2/2019 Estimating Duration

    7/27

    Studying Historical Data

    Every good project management methodology

    contains a project notebook that records the

    estimated and actual activity duration

    This historical record can be used on other projects

    The recorded data becomes your knowledge base for

    estimating activity duration

    This technique differs from the previous technique in

    that it uses a record, rather than depending onmemory

  • 8/2/2019 Estimating Duration

    8/27

    Seeking Expert Advice

    When the project involves a breakthrough

    technology or a technology that is being used

    for the first time in the organization, there

    may not be any local experience or even

    professionals skilled in the technology within

    the organization

    In these cases, you will have to appeal tooutside authorities

  • 8/2/2019 Estimating Duration

    9/27

    Applying the Delphi Technique

    The Delphi technique can produce good estimates in the absence of expert advice

    This is a group technique that extracts and summarizes the knowledge of the

    group to arrive at an estimate

    After the group is briefed on the project and the nature of the activity, each

    individual in the group is asked to make his or her best guess of the activity

    duration

    The results are tabulated and presented to the group

    Those participants whose estimates fall in the outer quartiles are asked to share

    the reason for their guess

    After listening to the arguments, each group member is asked to guess again

    The results are presented as a histogram labeled Second Pass, and again the outer

    quartile estimates are defended

    A third guess is made, and the histogram plotted is labeled Third Pass

    Final adjustments are allowed. The average of the third guess is used as the

    groups estimate

  • 8/2/2019 Estimating Duration

    10/27

    Applying the Three-Point Technique

    Activity duration is a random variable

    If it were possible to repeat the activity several times under

    identical circumstances, duration times would vary

    That variation may be tightly grouped around a central value,

    or it might be widely dispersed In any given instance of the activity, you would not know at

    which extreme the duration would likely fall, but you could

    make probabilistic statements about their likelihood in any

    case The three-point technique gives us a framework for doing just

    that

  • 8/2/2019 Estimating Duration

    11/27

    Applying the Three-Point Technique

    To use the method, you need three estimates of activity duration:

    Optimistic Time: It is defined as the shortest duration one has had or might expect to

    experience given that everything happens as expected.

    Pessimistic Time: It is that duration that would be experienced (or has been

    experienced) if everything that could go wrong did go wrong, yet the activity wascompleted.

    Most likely Time: It is that time usually experienced

    For this method you are calling on the collective memory of professionals

    who have worked on similar activities but for which there is no recorded

    history

  • 8/2/2019 Estimating Duration

    12/27

    Applying the Wide-Band Delphi

    Technique

    The combination of the Delphi and the three-point methods

    results in the wide-band Delphi technique

    This technique involves a panel, as in the Delphi technique

    I

    n place of a single estimate, the panel members are asked, ateach iteration, to give their optimistic, pessimistic, and most

    likely estimates for the duration of the chosen activity

    The results are compiled, and any extreme estimates are

    removed

    Averages are computed for each of the three estimates, and

    the averages are used as the optimistic, pessimistic, and most

    likely estimates of activity duration

  • 8/2/2019 Estimating Duration

    13/27

    Estimation Precision

    Early estimates of activity duration will not be as

    good as later estimates

    Estimates will always be subject to the vagaries of

    nature and other unforeseen events We can only hope that we have gained some

    knowledge through the project to improve our

    estimates

    In top-down project planning model, we start outwith roughly right estimates, with the intention of

    improving the precision of these estimates later in

    the project

  • 8/2/2019 Estimating Duration

    14/27

    Estimating the Resource Requirements

    The importance of resources varies from project to project

    The six estimation techniques used earlier can be used to

    estimate the resource requirements also, for any project

    Types of resources include the following- People

    Facilities

    Equipment

    Money

    Materials

  • 8/2/2019 Estimating Duration

    15/27

    People as Resources

    People are the most difficult type of resource

    to schedule because we plan the project by

    specifying the types of skills we need, when

    we need them, and in what amounts

    There are a few tools you can use to help you

    schedule people

  • 8/2/2019 Estimating Duration

    16/27

    People as Resources-Skill Matrices

    The two matrices are used to assign staff to activities The assignment could be based on activity characteristics such

    as risk, business value, criticality, or skill development

    This process involves gathering inventory data for two

    inventories- An inventory of the demand for skills needed to perform the tasks

    associated with specific activities. This is represented as a matrix

    whose rows are the activities and whose columns are the skills. These

    are both current and long-term needs

    An inventory of the current skills among the professional staff. This is represented as a

    matrix whose rows identify the staff and whose columns are the skills

    The columns of both matrices define the same set of skills. This gives us a way to link the

    two matrices and assign staff to activities

  • 8/2/2019 Estimating Duration

    17/27

    People as Resources-Skill Matrices

  • 8/2/2019 Estimating Duration

    18/27

    People as Resources-Skill Matrices

    Skill Categories-This part of the skill matrix is

    developed by looking at each activity that the unit

    must perform and describing the skills needed to

    perform the activity Skill Levels- Skills must be qualified with a statement

    of how much of the skill the person possesses.

    Various methods are available, and companies often

    develop their own skill-level system

  • 8/2/2019 Estimating Duration

    19/27

    Resource Breakdown Structure

    The Resource Breakdown Structure is used to assist

    in not only resource estimation but also cost

    estimation

    TheR

    esource Breakdown Structure is determined bythe job families, which are defined by the human

    resource department

    That definition is simply put into this hierarchical

    framework and used as the basis for identifying thepositions and levels that are needed to staff the

    project and from that constructing the staffing

    budget

  • 8/2/2019 Estimating Duration

    20/27

    Resource Breakdown Structure

  • 8/2/2019 Estimating Duration

    21/27

    Estimating Duration as a Function of

    Resource Availability

    Three variables influence the duration estimate of an activity, and all ofthem influence each other. They are as follows-

    The duration itself

    The total amount of work, as in person hours/days, that will be done on theactivity by a resource

    The per cent per day of his or her time that the resource can devote toworking on it

    Many project management software products today allow you to enterany two of these three variables and calculate the third for you

    There is no one right way; its a matter of what works best and is mostconsistent with the way you mentally approach estimating

  • 8/2/2019 Estimating Duration

    22/27

    Estimating Duration as a Function of

    Resource Availability

    There are four ways to approach the calculation of

    duration, total effort, and per cent/day

    Remember that two of them are specified and the

    third is calculated

    The methods are listed here and described in the

    units that follow-

    Assign as a total work and constant per cent/day

    Assign as a duration and total work effort

    Assign as a duration and per cent/day

    Assign as a profile

  • 8/2/2019 Estimating Duration

    23/27

    Assign as a TotalWork and a Constant Per

    cent/Day

    If we know that the total head down, focused work effort

    required to do the activity is 40 hours but that the resource

    can devote only 50 per cent of his or her typical day to doing

    project activity work, then the resulting duration is going to

    be 80 hours, or 10 business days

    The formula is simply this-40 hours/0.50 = 80 hours

    The duration becomes a calculated value based on the per

    cent per day and the work

    This method is the one that most software products use as

    their default method

  • 8/2/2019 Estimating Duration

    24/27

    Assign as a Duration and TotalWork

    Effort

    Alternatively, you could use your or someone elses

    experience and estimate the duration based on

    history

    Then the total work could be averaged over thatduration, yielding the per cent per day value. Using

    the same values as above, the formula would look

    like this-5 person days/10 days = 0.5

    Here again were making the assumption of an eight-

    hour day. In this case, the per cent is calculated

  • 8/2/2019 Estimating Duration

    25/27

    Assign as a Duration and Per cent/Day

    The third method is to estimate the duration

    as previously described and assign the per

    cent per day

    This method will calculate the total work

    effort. The formula works like this-10 days

    0.50 = 5 person days

    Of the three methods, this is the least used

  • 8/2/2019 Estimating Duration

    26/27

    Assign as a Profile

    The three duration estimating and resource

    assignment methods discussed here all presume that

    the resource is going to work at about the same per

    cent per day for each day of the activity

    There will be cases where the person cannot work at

    a constant rate because of other commitments

    In such cases, the duration is estimated first and then

    the work is assigned at different per cents over the40-hour window

  • 8/2/2019 Estimating Duration

    27/27

    Estimating Cost

    Now after that we have estimated activity duration

    and resource requirements, we know the resources

    that will be required and the number of hours or

    volume of resources needed These are the data we need to establish the cost of

    the project. Unit cost data can be applied to the

    amount of resource required to estimate cost