Upload
navam-nanthan
View
9
Download
0
Embed Size (px)
DESCRIPTION
Building Estimate sample
Citation preview
Page 1 of 9
Estimate for Construction of House
NO DESCRIPTION QUANTITYUNIT RATE AMOUNTA Earth Works
Site clearing 1.00 Item 5000.00 5000.00
14.00 Cube 1500.00 21000.00
Earth Filling & Compacting the Floor 17.00 Cube 2400.00 40800.0066,800.00
B Masonry Work
19.00 Cube 21000.00 399000.00
5'' Block work Casting and Placing 15.50 Sqrs 17500.00 271250.00
4'' Block work Casting and Placing 16.50 Sqrs 15500.00 255750.00926,000.00
C Concrete Work
7.00 Sqrs 8000.00 56000.00
4.00 Nos 5000.00 20000.00
48.00 L.ft 650.00 31200.00
25.00 L.ft 500.00 12500.00
6.25 Sqrs 55000.00 343750.00
Lintel 6''*4'' including R/F and F/W 340.00 L.ft 450.00 153000.00
Arch Lintel 6''*4'' including R/F and F/W 34.00 L.ft 500.00 17000.00
17.00 Sqrs 9000.00 153000.00786,450.00
D Carpentry and Joiner
17.50 Sqrs 22000.00 385000.00
1.00 Nos 36000.00 36000.00
Internal doors D2 Vempu 1.00 Nos 18500.00 18500.00
Internal doors D2 Muthurai 3.00 Nos 21500.00 64500.00
Door D3 Muthurai 4.00 Nos 19500.00 78000.00
Bath room door plastic 2.00 Nos 10000.00 20000.00
Window W1 6.00 Nos 29500.00 177000.00
Window W2 4.00 Nos 26500.00 106000.00
Fanlight 4.00 Nos 4000.00 16000.00
901,000.00
Excavation for wall foundation(2'*2') and Column Footing
Random Rubble Masonry in cement sand mortar 1:5 in foundation up to DPC Level
Lean concrete 1:3:6(1'') for Wall Foundation & Column Footing
Column Footing including 10mm tor bar & F/W as per details
Column Concreting including 4Nos 12mm tor bar & F/W and plastering
Beam concreting including R/F details in drawing and Formwork
4'' Slab concreting including R/F and Formwork
3'' Floor concrete 1:21/2:5 including ramping on front site
Under ceiling comprising of 4*2 joists and 2*2 bearers in class 1 timber including
Main Door with design D1 Muthurai (5''*4'') including Varnish Painting
Page 2 of 9
NO DESCRIPTION QUANTITYUNIT RATE AMOUNT
E Roof Work
Roof frame work 21.00 Sqrs 29500.00 619500.00
ridge tiling 110.00 L.ft 100.00 11000.00
9'' Valance board 172.00 L.ft 175.00 30100.00
Upvc gutter 172.00 L.ft 160.00 27520.00
Down pipe 96.00 L.ft 150.00 14400.00
702,520.00
F Plasterer
DPC 3.50 Sqrs 5500.00 19250.00
Plinth Plaster 2.25 Sqrs 4500.00 10125.00
Tiling 19.50 Sqrs 26000.00 507000.00
Plastering internal 48.50 Sqrs 3500.00 169750.00
Plastering external 15.50 Sqrs 3500.00 54250.00
sofit plastering 12.50 Sqrs 4200.00 52500.00
812,875.00
G Painting
External 15.50 Sqrs 2000.00 31000.00
Internal 48.50 Sqrs 2000.00 97000.00
Soffit 12.50 Sqrs 2000.00 25000.00
153,000.00
H Plumbing
Commode with necessary pipe lines 1.00 No 10500.00 10500.00
Squatting pan with necessary pipe lines 1.00 No 4000.00 4000.00
Wash basin with necessary pipe lines 1.00 No 5000.00 5000.00
Sink with necessary pipe lines 1.00 No 6000.00 6000.00
bib tap and showers 2.00 No 3000.00 6000.00
Pipe lines connected to existing pit 1.00 Item 20000.00 20000.00
51,500.00
J Electrical work
Fan with wiring 7.00 No 6000.00 42000.00
Tube light 10.00 No 2500.00 25000.00
Bulb 12.00 No 1500.00 18000.00
5 amp 6.00 No 1750.00 10500.00
15 amp 2.00 No 2250.00 4500.00
Main 1.00 No 15000.00 15000.00
115,000.00
K Miscellaneous
work top and chimney 1.00 Item 30000.00 30000.00
design work for Verandah 30.00 L.ft 250.00 7500.00
cement grill work for above verandah 55.00 L.ft 250.00 13750.00
Page 3 of 9
NO DESCRIPTION QUANTITYUNIT RATE AMOUNT
Construction of Boundary wall 200.00 L.ft 1550.00 310000.00
Construction of water tank 1.00 Item 250000.00 250000.00
Construction of soakage pit 1.00 Item 75000.00 75000.00
Landscaping 1.00 Item 50000.00 50000.00
736,250.00
A Earth Works 66,800.00
B Masonry Work 926,000.00
C Concrete Work 786,450.00
D Carpentry and Joiner 901,000.00
E Roof Work 702,520.00
F Plasterer 812,875.00
G Painting 153,000.00
H Plumbing 51,500.00
J Electrical work 115,000.00
K Miscellaneous 736,250.00
Total 5251395.00
Discount 1395.00
Grand total 5,250,000.00
Construction Programme
Se.no Work 1st Month 2nd Month 3rd Month 4th Month 5th Month 6th Month
1 Site Mobilization
2 Earth Works 0 62
3 Masonry Work 156 274
4 Concrete Work 32 84
5Carpentry and Joiner
188 112
6Roof Work
49 58
7Plasterer
185 180
8Painting
70 30
9Plumbing
14 14
10Electrical work
22 22
11Miscellaneous
130 260
Total Workers 846 1096 S 105, U 210 S 160, U 230 S 150, U 190 S 180, U 180 S 136, U 150 S 115, U 136
No.of workers Skill , UnSkill
Item Description
1 Progress each month % 12.50% 20.19% 25.00% 21.15% 14.42% 6.73%2 Cumulative Progress % 12.50% 32.69% 57.69% 78.85% 93.27% 100.00%3 Progress in rupees Rs 650,000.00 1,050,000.00 1,300,000.00 1,100,000.00 750,000.00 350,000.004 Cumulative Progress in rupees Rs 650,000.00 1,700,000.00 3,000,000.00 4,100,000.00 4,850,000.00 5,200,000.005 Preliminaries
Revenue:Payments 585,000.00 945,000.00 1,210,000.00 1,100,000.00 1,100,000.00 260,000.00Cumulative payments 585,000.00 1,530,000.00 2,740,000.00 3,840,000.00 4,940,000.00 5,200,000.00
6 Purchase of Materials1. cement 50,000.00 200,000.00 200,000.00 100,000.00 25,000.002. sand 10,000.00 30,000.00 30,000.00 30,000.00 20,000.003. Metal 10,000.00 50,000.00 75,000.00 40,000.004. Soil for earth filling 20,000.005. Rubbles 50,000.00 50,000.006. Shuttering materials 25,000.007. Steel 10,000.008. Roof Materials 20,000.00 200,000.009. Carpentary items 300,000.00 400,000.009. Plumbing Items 30,000.0010. Electrical Items 50,000.00 25,000.0011. tiles 150,000.00 150,000.0012. Paint 50,000.00Total Materials Monthly 155,000.00 370,000.00 805,000.00 720,000.00 275,000.00 75,000.00Cumulative materials 155,000.00 525,000.00 1,330,000.00 2,050,000.00 2,325,000.00 2,400,000.00Man Powera. Labour 115,500.00 126,500.00 104,500.00 99,000.00 82,500.00 74,800.00b. Mason 73,500.00c. Carpenter
End of 1st
Month
End of 2nd
Month
End of 3rd
Month
End of 4th
Month
End of 5th
Month
End of 6th
Month
End of 9th
Month
End of 18th
Month
d. Blacksmithe. Plumberf. Painterg. ElectricianTotal labour cost 189,000.00 126,500.00 104,500.00 99,000.00 82,500.00 74,800.00Cumulative labour cost 189,000.00 315,500.00 420,000.00 519,000.00 601,500.00 676,300.00Overheads 80,000.00 75,000.00 60,000.00 60,000.00 60,000.00 60,000.00Interest 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00 20,000.00Total expences 444,000.00 591,500.00 989,500.00 899,000.00 437,500.00 229,800.00Total Cumulative Expencess 444,000.00 1,035,500.00 2,025,000.00 2,924,000.00 3,361,500.00 3,591,300.00 3,591,300.00 3,591,300.00
1 444000 02 1035500 03 2025000 5850004 2924000 15300005 3361500 27400006 3591300 38400009 3591300 4940000
18 3591300 5200000
0 2 4 6 8 10 12 14 16 18 200
1000000
2000000
3000000
4000000
5000000
6000000
Column D
0 2 4 6 8 10 12 14 16 18 200
1000000
2000000
3000000
4000000
5000000
6000000
Column D
0 2 4 6 8 10 12 14 16 18 200
1000000
2000000
3000000
4000000
5000000
6000000
Column D
0 2 4 6 8 10 12 14 16 18 200
1000000
2000000
3000000
4000000
5000000
6000000
Column D