14
1/22/2020 1 1 COMMERCIAL ENERGY CODE BUILDING ENVELOPE 2015 IECC & ASHRAE 90.1 -2013 Presented by Southface: Laura Case Mike Barcik www.southface.org https://www.southface.org/resources/georgia-energy-code-resources/ https://earthcraft.org/ ABOUT SOUTHFACE Building a Regenerative Economy, Responsible Resource Use & Social Equity Through a Healthy Built Environment for All 1 2

Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

  • Upload
    others

  • View
    16

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

1

1

COMMERCIAL ENERGY CODEBUILDING ENVELOPE

2015 IECC & ASHRAE 90.1 -2013

Presented by Southface:

Laura Case Mike Barcik

www.southface.org

https://www.southface.org/resources/georgia-energy-code-resources/

https://earthcraft.org/

ABOUT SOUTHFACE

Building a Regenerative Economy, Responsible Resource Use & Social Equity Through a Healthy Built Environment for All

1

2

Page 2: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

2

LEARNING OBJECTIVES

• Learn more about the building envelope

• Learn about ducted vs. non-ducted return plenums

ESTABLISHING THE BUILDING ENVELOPE

3

4

Page 3: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

3

DESIGNING THE AIR BARRIER

• Air barrier components must be identified or noted in construction documents

• Joints, intersections, and penetrations of air barrier components (incl. lighting fixtures) detailed

• Air barrier must extend over all surfaces of building envelope at lowest floor, exterior walls, and ceiling or roof

• It must be designed to resist pressures changes from wind, stack effect, and mechanical ventilation

Acceptable air barrier materials/assemblies• 3/8” plywood & OSB• ½” XPS & poly-iso• ½” Gyp board• ½” Cement board• Built up, modified bit, &

adhered single-ply roof membranes

• ½” cement parge, stucco or gyp board

• Concrete• Sheet metal• 1” (1.5”) Closed cell foam• 4.5” Open cell foam• CMU walls –

painted/grouted• Sheet steel/aluminum

AIR BARRIER INSTALLATION

The following areas are to be wrapped, sealed, caulked, gasketed, or taped:

• Joints around fenestration and door frames (both manufactured and site-built)

• Junctions between walls and• Foundations

• Building corners

• Roofs or ceilings

• Penetrations for roofs, walls, and floors

• Building assemblies used as ducts or plenums

• Joints, seams, connections between planes, and other changes in continuous air barrier materials

5

6

Page 4: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

4

THE DATA

Southface’s research indicated that buildings without clearly defined envelopes were three times leakier than those with a well-defined envelope.

There was no apparent correlation between age, type of construction, location, etc.

0

0.1

0.2

0.3

0.4

0.5

0.6

0.7

0.8

ECLC Non-ECLCE

LR

Air Leakage Testing

RETURN PLENUMS

Ducted vs. non-ducted

7

8

Page 5: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

5

IMPACTS OF NON-DUCTED RETURN AIR PLENUMS

• Reduced HVAC system costs of about

10% to 20% of the total HVAC system

cost.

• Reduced efforts for coordination of

overhead utilities.

• Assumed reduced fan energy costs due

to lower pressure drop of the plenum

return system.Photo by Yuji Sakai

PROBLEMS OF NON-DUCTED RETURN AIR PLENUMS

What could possibly

go wrong here?

9

10

Page 6: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

6

PROBLEMS OF NON-DUCTED RETURN AIR PLENUMS

• Cavities above suspended

ceilings are used as equipment

tunnels and chases causing

major air leakage

• These areas are highly

(de)pressurized, which

exacerbates the air leakage

• They are often adjacent to

unconditioned spaces (storage,

plant, warehouse, etc.)

WATER, WATER EVERYWHERE

Roof leak or something else?

11

12

Page 7: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

7

PLENUM INSULATION

C403.2.9 Duct and plenum insulation and sealing

Supply and return air ducts and plenums shall be insulated with a minimum of R-6 insulation where located in unconditioned spaces and where located outside the building with a minimum of R-8.

Where located within a building envelope assembly, the duct or plenum shall be separated from the building exterior or unconditioned or exempt spaces by a minimum of R-8 insulation.

IAQ CHALLENGES

• Ceiling insulation

shall not be

installed on a

suspended ceiling

with removable

ceiling panels

© Fiberglass Awareness

13

14

Page 8: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

8

BUILDING ENVELOPE: ROOFS

▪ Unacceptable Design: Batts over suspended ceiling tiles

▪ Poor pressure boundary caused by tile grid, porous tiles, lighting vent holes

▪ Many thermal breaks due to ductwork, light fixtures, grid, and support wires

▪ Poor durability -maintenance disrupts batts, exposureto fiberglass dust

Note: Energy codes ban insulation on top of suspended ceiling(90.1 section 5.8.1.8 ; IECC section C402.2.2)

BUILDING ENVELOPE EXAMPLE: ROOFS

▪ Unacceptable Design: Batts over suspended ceiling tiles

15

16

Page 9: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

9

▪ Okay Design:Insulation above hard ceiling

▪ Example: taped gypsum; similar to residential construction

▪ Ductwork is inside but must limit and seal HVAC, plumbing, and electrical penetrations through pressure boundary

▪ Thermal bridging from metal roof trusses

BUILDING ENVELOPE EXAMPLE: ROOFS

▪ Very Good Design: Spray foam insulation against underside of roof deck

▪ Minimal thermal breaks and continuous pressure boundary

▪ HVAC equipment and ductwork located within conditioned space

▪ Good durability

▪ Retrofit option

BUILDING ENVELOPE EXAMPLE: ROOFS

17

18

Page 10: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

10

▪ Best Design: Rigid insulation above roof deck

▪ No thermal breaks and continuous pressure boundary

▪ HVAC equipment and ductwork located within conditioned space

▪ Good durability

BUILDING ENVELOPE EXAMPLE: ROOFS

HEALTH CARE FACILITIES

• The Facility Guidelines Institute standards were adopted in Georgia in 2018.

• Those standards require ducted returns in many healthcare-related facilities to reduce the spread of infections.

19

20

Page 11: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

11

CASE STUDIES

CASE STUDY #1

21

22

Page 12: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

12

CASE STUDY #2

CASE STUDY #3

• Where is the air barrier?

• Where is the return

plenum?

23

24

Page 13: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

13

CASE STUDY #3

CASE STUDY #3

25

26

Page 14: Establishing a clear Building Envelope · building envelope at lowest floor, exterior walls, and ceiling or roof • It must be designed to resist pressures changes from wind, stack

1/22/2020

14

CONCLUSIONS

27