21
Eskom’s Pilot National Eskom’s Pilot National Cogeneration Project Cogeneration Project Rob Higgo, Project Development Department Stuart van Zyl, Industry Association Resource Centre 16 October 2007 60 60 th th AMEU Convention AMEU Convention

Eskom’s Pilot National Cogeneration Project

  • Upload
    amish

  • View
    38

  • Download
    1

Embed Size (px)

DESCRIPTION

60 th AMEU Convention. Eskom’s Pilot National Cogeneration Project. Rob Higgo, Project Development Department Stuart van Zyl, Industry Association Resource Centre 16 October 2007. Contents. Background Strategic issues The need for a “pilot project” - PowerPoint PPT Presentation

Citation preview

Page 1: Eskom’s Pilot National Cogeneration Project

Eskom’s Pilot National Cogeneration Eskom’s Pilot National Cogeneration

ProjectProject

Rob Higgo, Project Development DepartmentStuart van Zyl, Industry Association Resource

Centre16 October 2007

6060thth AMEU Convention AMEU Convention

Page 2: Eskom’s Pilot National Cogeneration Project

2

Contents

• Background• Strategic issues• The need for a “pilot project”• Objectives & Principles of the pilot project• Eskom’s “Pilot Project” • What is Eskom Offering • Consideration of Connection & Billing Issues• Network considerations

Page 3: Eskom’s Pilot National Cogeneration Project

3

What is Co-generation?

• Co-generation: a source of electrical power that is a co-product, by-product, waste product or residual product of an underlying industrial process.– Type I: projects utilizing process energy which

would otherwise be underutilized or wasted (e.g. waste heat recovery).

– Type II: Primary fuel based generation projects which produce other usable energy in addition to electricity (e.g. Combined Heat and Power projects).

– Type III: Renewable fuel based projects where the renewable fuel source is a co-product of an industrial process (e.g. use of bagasse and/or forestry waste from the sugar and paper industries).

Page 4: Eskom’s Pilot National Cogeneration Project

4

The Eskom challenge

• During June 2006, Eskom’s Exco challenged the organisation to develop new cogeneration opportunities in South Africa– A target of 900MW1 was established, to be achieved within a 5 year

window, ending March 2011

• In so doing, Eskom would:– Support NERSA’s initiative to established a cogeneration

framework (guidelines) that will promote new cogeneration

– Pursue and actively procure cogeneration opportunities that make good business sense

• An Eskom cogeneration workgroup was established internally to support the initiative

• Eskom has worked jointly with the EIUG workgroup, NERSA and others in industry to meet its objectives

1) The target is not definitive, and actual cogeneration developed will be dependent on market response

Page 5: Eskom’s Pilot National Cogeneration Project

5

Strategic Considerations

• Cogeneration has potential to deliver capacity “quickly”• Cogeneration may provide electricity at lower cost than

conventional generation (not all Cogeneration is cheaper)• Cogeneration potentially reduces investment in networks

and supports distributed generation – Transmission cost savings

• Cogeneration may improve industrial efficiency and can be environmentally friendly e.g. Combined Heat and Power (CHP) – Deferred investment at (possible) lower cost– Overall efficiency gains

• Environmental benefits• Improved reliability and quality of supply• Employment / BEE opportunities

Eskom’s strategic considerations closely mirror those of the EIUG and Industry

Page 6: Eskom’s Pilot National Cogeneration Project

6

The need for an Eskom “pilot” project

• NERSA’s guidelines, regulations and implementation programme may take some time to conclude

• Window of opportunity exists between now and approximately 2012– Eskom’s first new base load power plants due to come on line

during 2012 to 2013• The initial “pilot” will allow both Eskom and NERSA an

opportunity to gauge the cogeneration market in SA– Quantity and size of the market offering– Cogeneration mix, location, profile– Pricing of cogeneration options being proposed– Timing of potential cogeneration projects

• Results from the “pilot” project will feed into the current NERSA guidelines and thinking

• Lessons learned will be carried forward into the long term model for SA

Page 7: Eskom’s Pilot National Cogeneration Project

7

Objectives & Key principles

• Develop the necessary tender documentation to attract new cogeneration

• Obtain NERSA support and approval for the process• Develop a standard contract for cogeneration developers which

is bankable (PPA)• Have a transparent evaluation process to evaluate tender

submissions• Implement the process in a timely fashion• Develop a ceiling price which will be approved by NERSA

beyond which contracts will not be offered

Page 8: Eskom’s Pilot National Cogeneration Project

8

Objectives & Key principles

• Transparency– Well defined and clearly understood process– Known implementation parameters– Equitable treatment across projects– Determination of qualifying projects

• Simplicity– Procedural simplicity for projects to achieve regulatory approval– Minimisation of transaction negotiations– Minimisation of transaction costs

Page 9: Eskom’s Pilot National Cogeneration Project

9

What is Eskom offering?

• An opportunity to attract and contract new cogeneration into the market

• Requirements:– new build or re-commissioned plant of nett capacity >1MW.– Must be co-generation not renewable generation that requires

renewable energy grants (i.e. must be cost effective as a stand alone co-generator)

• “Cheapest bids” from technically and commercially qualified bids win contract provided that they do not exceed the ceiling price set by Eskom’s avoided cost model – there are modifiers for siteing and timing (first on line)

advantages– Maximum 15 year contracts are offered

• A standard contract (PPA) was developed for the Cogeneration projects which include inter alia– Payment profiles aligned with energy needs: support TOU /

peaking periods; Winter vs. Summer etc.

Page 10: Eskom’s Pilot National Cogeneration Project

10

Progress to date

Activity Target date 1. Expression of interest – Pre qualified 125 projects for approximately 5000MW

29 June 2007*

2. Request for Tender(RFT) Approval to issue draft PPA to market 27 September 2007* Issue RFT and draft PPA to pre-qualified

bidders 4 October 2007*

Bidders clarification conference 7 November 2007 Updated draft PPA released to bidders November 2007

3. Bid submission 28 February 2008 4. Bid evaluation completed April 2008 5. Final recommendation on PPA’s to be offered April 2008 6. Approval to sign PPA’s obtained from Eskom Board

June 2008

7. Succesful bidders notified June 2008 * Activities completed

• Pilot project is essentially a tender process.

Page 11: Eskom’s Pilot National Cogeneration Project

11

Progress to date

• Summary of EOI’s received: Co-generator Types

Combination of Types, 16,

13%

Type III, 22, 18%

Type II, 42, 34%

Type I, 44, 35%

Waste Energy

Generation with 2ndary Process Energy

Renewable Energy

Page 12: Eskom’s Pilot National Cogeneration Project

12

0

5

10

15

20

25

30

35

40

Net Capacity (MW)

EO

I's R

ece

ived

Progress to date

• Summary of EOI’s received: Generator net output

Page 13: Eskom’s Pilot National Cogeneration Project

13

Contractual vs Physical Flow*

Eskom Wholesaler

Cogeneration Industrial Load

Eskom Generation

Eskom Tx Network

Retailer(Eskom Dx / Munic / RED)

Dx Network(Eskom Dx / Munic / RED)

Physical flow

PPA (Meter 2)

ESAb (Meter 1 + 2)

Contractual flow

Meter 2

Meter 1

ESAa (Meter 1’ + 2’)

* Within embedded generation networks

Page 14: Eskom’s Pilot National Cogeneration Project

14

Contractual vs Physical Flow*

Eskom Wholesaler

Cogeneration Industrial Load

Eskom Generation

Eskom Tx Network

Retailer(Eskom Dx / Munic / RED)

Dx Network(Eskom Dx / Munic / RED)

Physical flow

PPA (Meter 2)

ESAb (Meter 1 + 2)

Contractual flow

Meter 2

Meter 1

ESAa (Meter 1’ + 2’)

Eskom Wholesaler purchases Eskom energy generated at existing Eskom generation tariff

* Within embedded generation networks

Eskom Wholesaler “purchases” gross energy generated

at Meter 2 at cogen PPA tariff

Page 15: Eskom’s Pilot National Cogeneration Project

15

Contractual vs Physical Flow*

Eskom Wholesaler

Cogeneration Industrial Load

Eskom Generation

Eskom Tx Network

Retailer(Eskom Dx / Munic / RED)

Dx Network(Eskom Dx / Munic / RED)

Physical flow

PPA (Meter 2)

ESAb (Meter 1 + 2)

Contractual flow

Meter 2

Meter 1

ESAa (Meter 1’ + 2’)

* Within embedded generation networks

Eskom Wholesaler bills

for energy summating

Meters 1 and 2 at standard power sales tariff within

identified and ring fenced area

Page 16: Eskom’s Pilot National Cogeneration Project

16

Contractual vs Physical Flow*

Eskom Wholesaler

Cogeneration Industrial Load

Eskom Generation

Eskom Tx Network

Retailer(Eskom Dx / Munic / RED)

Dx Network(Eskom Dx / Munic / RED)

Physical flow

PPA (Meter 2)

ESAb (Meter 1 + 2)

Contractual flow

Meter 2

Meter 1

ESAa (Meter 1’ + 2’)

* Within embedded generation networks

Retailer similarly bills for energy

summating Meters 1 and 2 at standard power sales tariff within

identified and ring fenced area

Page 17: Eskom’s Pilot National Cogeneration Project

17

Connection & Billing Arrangements

• The “export” of energy may be physical or only a commercial arrangement (own use but paid for by Eskom)

• The commercial arrangement (PPA) will not impact the distributor’s revenue (no netting off of usage)– PPA will be with co-generator and ring-fenced contractually

from the usage by the end user (load)– Standard tariff paid by end user (load) for energy purchased

by consumer is that metered by the distributor plus energy generated by co-generator and sold to Eskom via the PPA

– No impact on sales and revenue

• Distributor to take into account technical factors arising from generator connection:– The associated costs payable by the generator– Physical export will increase technical complexity and

impact connection costs

Page 18: Eskom’s Pilot National Cogeneration Project

18

• Penetration levels of Embedded Generation are low: Experienced SA engineers are few.– Consultant(s) to be appointed to assist in evaluating

technical impact and provide designs where required– Includes skills transfer on network studies

• Embedded Generator connection policy is handled in the Grid and Distribution codes– Distribution Code approved by NERSA October 2007– Principle of open access to Embedded Generators– Each Distributor to develop interconnection standards

• Detailed technical guidelines lacking– Eskom interconnection standard– Planning guideline

Technical Considerations

Page 19: Eskom’s Pilot National Cogeneration Project

19

• Fault level contribution• Detection of Loss-of-Grid

– Difficult to detect in some instances– Guidelines given on when dedicated protection is

required• Network earthing and earth fault protection

– MV networks are resistively earthed at the source. Generator neutral to be left unearthed

• Protection and protection settings– Related to generator operating philosophy

• Isolation of system for safe working• Metering

– Installation near generator terminals

Technical factors to be considered

Page 20: Eskom’s Pilot National Cogeneration Project

20

• Eskom’s Pilot National Co-generation project seeks to connect 900MW of new-build generation by 2011.

• Effectively a tender process– Expression of interest netted 124 submissions, 5000MW.

• Power Purchase Agreements (PPAs) and Technical Standards presently under development.– Distribution Code is a second driver for interconnection

standards– Earthing, loss-of-grid protection some of the key technical

aspects

Conclusion

Page 21: Eskom’s Pilot National Cogeneration Project

ESKOMESKOMHoldings LtdHoldings Ltd

Thank YouThank You