Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Eskom UCGStrategic Intent
Presented at :
FFF & IEA-CCC Conference,
“Underground Coal Gasification - going forward”,
13th to 14th July 2011, Johannesburg, South Africa.
Chris GrossDr Mark Van der Riet
EPPEI, Technology DivisionEskom Holdings SOC LtdSouth Africa
2012/02/28 2
Content
1. Context
2. Eskom’s UCG Strategic Drivers
3. Majuba Coalfield, South Africa
4. Eskom UCG Program
5. Environmental Impacts
6. Risk Status
7. UCG Performance
8. Conclusions
Context
2012/02/28 4
Context
• Coal is one of South Africa’s largest primary energy resources.
• Eskom presently generates 88% of its electricity from coal.
• This predominance will decrease, with the introduction of alternative energy carriers to mitigate the impact of the continued usage of coal (refer to IRP 2010).
• Coal will however remain a dominant, albeit reducing primary energy carrier for the foreseeable future in RSA.
• Eskom has therefore run a comprehensive Clean Coal Technology research and development program for several decades, to explore, identify and demonstrate solutions for continued coal usage.
• Underground Coal Gasification (UCG) is one of the advanced clean coal technology options being demonstrated by Eskom
2012/02/28 5
Context - Eskom Primary Energy
2009/10 : 246,566 GWh Net
2012/02/28 6
Context - Policy Adjusted IRP 2010
Policy Adjusted IRP Capacity – 2010 to 2030
IRP Section 7.4 “Research into Underground Coal Gasification (UCG) should have a priority in the research agenda as there is a potential for this option to be used in place of natural gas.”
MW % MW % MW %
Coal 41071 45.9 16383 29.0 6250 14.7
OCGT 7330 8.2 4930 8.7 3910 9.2
CCGT 2370 2.6 2370 4.2 2370 5.6
Pumped Storage 2912 3.3 1332 2.4 0 0.0
Nuclear 11400 12.7 9600 17.0 9600 22.6
Hydro 4759 5.3 2659 4.7 2609 6.1
Wind 9200 10.3 9200 16.3 8400 19.7
CSP 1200 1.3 1200 2.1 1000 2.4
PV 8400 9.4 8400 14.9 8400 19.7
Other 890 1.0 465 0.8 0 0.0
Total 89532 56539 42539
Total capacity Capacity added (including
committed) from 2010 to
2030
New (uncommitted) capacity
options from 2010 to 2030
Existing 2010 capacity = 43,895 MW (including non-Eskom generators)Less decommissioning capacity (-10,902 MW up to 2030) = 32,993 MW by 2030
There is a clear intent to start moving South Africa away from coal in the next two decades
Eskom’s UCGStrategic Drivers
2012/02/28 8
Eskom’s UCG Strategic Drivers
1. Security of supply
2. Clean energy
3. Flexibility
4. Utilize Unminable Coal
5. Lower cost option
Lower C02
Emissions
Modularity, lead time
Competitive R/MWh
Potentially 350GWe
Baseload option
Better utilisation than conventional
mining
2012/02/28 9
RSA Unminable Coal Resources
Three quarters of South Africa’s coal resources are currently regarded as unminable. UCG is ideally suited to extracting such coals. UCG
is therefore a strategic energy option for the country’s future.
Map Source :
S Walker, Major Coalfields of the World,
IEA CCC/32, June 2000
UCG enables the effective extraction and use of previously unminable RSA coal resources
Majuba Coalfield,South Africa
2012/02/28 11
Majuba Colliery at closure : 1993
2012/02/28 12
Why choose Majuba for UCG ?
• Majuba coal field was found to be unminable by conventional means due to dolorite intrusions, heat affected coal and seam displacements
• Coal seam 280-300 metres deep
• Eskom owned the Mineral Rights
• Land used for cattle farming, and Eskom owns the farm land
• Study showed that gas could be co-fired with coal at Majuba power station giving a direct use for the gas.
• Study also showed that gas could be used as a fuel for a modern, high efficiency IGCC power station.
Dolorite intrusions
Majuba 4100MW power station
Eskom UCG Program
2012/02/28 14
Majuba UCG
2012/02/28 15
Eskom UCG Development Plan
2002
Scoping Study
2003
Pre-feasibility
Study
2005
Site
Characterisation
20th January 2007
Commissioned
5000 Nm3/h pilot plant
on Majuba coalfield
Done
To do
Current
28th October 2010
Commissioned
15000 Nm3/h co-firing into
Majuba power station
U2Comm
U3Comm
U4Comm
U5Comm
U6Comm
Commission
U1Comm
Apr 2009 Dec 2011 Sep 2015Mar 2015 Mar 2020 Sep 2022
ConstructionDesign
ConstructionDesign
Demonstration Plant
2100MW 1st Proof-of-Concept Plant
Provisional Future Dates
2012/02/28 16
UCG Project Progress
• UCG technology scan - April 2001
• Scoping study highlighted potential at Majuba colliery - Nov 2002
• Pre-feasibility study confirmed Majuba potential - Dec 2003
• Site characterisation study confirmed the potential - July 2005
• Commissioned a 3-5000 Nm3/h pilot plant - 20 Jan 2007
• First electricity generated from UCG gas at Majuba - 31 May 2007
Eskom flarestack – 20 Jan 2007
100 kW converted diesel gensetEskom has licenced UCG technology fromErgo Exergy Technologies Inc. (Canada)
2012/02/28 17
UCG Project Progress
Co-firing :
• Commissioned new co-firing gas treatment plant – Jun 2010
• Commissioned new 7km x 600mm NB pipeline to Majubapower station – Jun 2010
• Gas co-fired into Majuba U4 - 28 Oct 2010
UCG-OCGT demo plant :
• Design study underway for a demonstration plant comprising 250,000 Nm3/h gas production and a 100 – 140 MW gas turbine plant 15,000 Nm3/h gas
treatment plant
Gas Pipeline to Majuba
power station
© Eskom
2012/02/28 18
UCG Phased Development
This figure explains UCG modularity, and the technology roll-out
Pilot Demo 1st Proof-of-Concept Plant
5-15,000 Nm3/h
250,000 Nm3/h
3,800,000 Nm3/h
100-140 MW OCGT Approx 250-350 MW CCGT per unit X multiple units = approx. 2100 MW
+ +
Environmental Impacts
2012/02/28 20
Environmental Impacts : Water
• Baseline water sampling performed of aquifers, including coal seam
• Water from surrounding aquifers monitored from shallow and deep boreholes, in concentric rings surrounding the process
• UCG is monitored extensively with piezometers (for measuring pressure & temperature)
• No UCG contamination evident
2012/02/28 21
Environmental Impacts : Air
• Baseline air quality tests done prior to UCG
• Permanent meteorological station on the UCG site monitors wind speed/direction, ambient temperature, barometric pressure
• Eskom’s continuous ambient emission monitoring stations monitor meteorological parameters, SO2, NO2, O3, PM10 etc.
• Additional comprehensive audit completed for : meteorological parameters, CO, CO2, SO2, H2S, NO, NO2, BTX, NH3, PM10 , PM2.5etc.
• Permanent monitoring site to be established
• UCG-IGCC promises a reduction in greenhouse gas emissions, compared to conventional power stations
2012/02/28 22
Environmental Impacts : Land
• Comprehensive plan in place with management and rehabilitation procedures. Regular audits done.
• Baseline flora & fauna survey and soil tests done prior to UCG starting up
• Majuba site shows natural vegetation re-establishes rapidly after drilling disruption
• Surface impact minimal post-gasification
• Subsidence is being monitored at Majuba using devices for conventional underground monitoring. The potential strata collapse has also been modelled.
• No subsidence observed yet.
Risk Status
2012/02/28 24
Risk Status – Feb 2011
Risk Rank Mitigation
Environmental HighMonitoring, design,engagement
Permitting &Licences
High Engagement
Cost Creep &Financial
Medium Project management
Resources &Skills
Medium Recruitment & training
ScheduleCreep
Medium Project management
UCG Performance
2012/02/28 26
Coal Seams
Majuba Seam Detail
Details in another Eskom presentation
2012/02/28 27
Eskom’s UCG Production Data
Operating Data - 20 Jan 2007 to 20 Jan 2011 :
• Total coal consumed/gasified = 34 663 tons
• Total gas produced = 131 719 400 m3
• A representative CV of the gas was 4.2 MJ/Nm3
• The average efficiency is 72 % (coal @ 20 GJ/ton)
• Current gas production rate = 11500 m3/hr (6768 cfm)
• Average well exit temperature = 168 ºC (344 ºF)
• Maximum well exit temp (normally temporary) = 430 ºC (806ºF)
• Average water consumption = 0.58 litre per kg of coal.
2012/02/28 28
UCG Gas Composition Range
• Gas composition varies with the lifetime of the production well, and between production wells.
• Gas composition depends on the operating parameters such as P and flow, and also on the design of the underground gasifier.
• Incorrect gasifier design or operation can result in the gasifier running in combustion mode.
• The final volume of gas is a blended average from several production wells.
UCG Gas - major components only
Composition (% by vol)
Hydrogen H2 15 - 19
Oxygen O2 0.2
Water Vapour H2O 5
Atm. Nitrogen N2 47 - 55
Carbon Monoxide CO 7 - 12
Carbon Dioxide CO2 17 - 19
Methane CH4 3 - 5
Calorific Value LHV MJ/Nm3 3.5 - 5.1
Conclusions
2012/02/28 30
Conclusions
• UCG is a promising clean coal option which allows the effective extraction and use of previously unminable RSA coal resources
• UCG has a role to play in the reduction of greenhouse gases and has possible potential for carbon capture and storage
• The Eskom UCG pilot has been operating reliably since Jan 2007 – 53 months and counting !!
• No environmental concerns have been noted to date
• Eskom has embarked on the phased research, development and demonstration of the technology, culminating in the 1st Proof-of-Concept Plant comprising approximately 2100 MW
2012/02/28 31
THANK YOU
Eskom UCG website URL :
http://www.eskom.co.za/c/14/underground-coal-gasification/