eShuttle ® EDC Process Paradigm Shifting Technology IHS Global Chlor-alkali, Vinyls and Polyurethanes Conference October 7, 2020

eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

1 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

eShuttle® EDC ProcessParadigm Shifting Technology

IHS Global Chlor-alkali, Vinyls and Polyurethanes Conference

October 7, 2020

Page 2: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

2 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 20202

Agenda» Introduction to Chemetry

» Overview of eShuttle® EDC Process

» Tour of EDC Demonstration Facility

» Impact of eShuttle® EDC Technology

» Introduction to eShuttle® PO Technology

Page 3: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

3 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

Introduction to Chemetry

Page 4: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

4 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 20204

Chemetry Overview» Funded by leading energy investors and US

Department of Energy

» World class laboratories and demonstration

facilities with 100,000+ R&D hours

» Strategic partnership with engineering and

technology licensing leader - TechnipFMC

» Patents: 60+ allowed and 30+ pending

» Technology proven at pilot scale and

partnerships for commercialization for EDC

» 3 MT/day EDC Demo Plant operational 2022

» Propylene Oxide technology currently being

validated at Chemetry Pilot Plant

2017 Kirkpatrick Honor

Award Recipient

2018 American Chemical Society

Green Chemistry Award

Page 5: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

5 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 20205

The Commodity Chemical Problem» HIGH ENERGY CONSUMPTION

– Accounting for > 600,000 MWh of electricity daily

» HIGH OPERATING COSTS

– Plants uneconomic in high energy price regions

» ENVIROMENTAL IMPACT

– Worldwide CO2 impact of >160 BTA

– International markets rely on mercury and asbestos

» HEALTH & SAFETY CONCERNS

– Numerous accidents involving chlorine gas

» NOT GOING AWAY

– >>$100BB industry producing essential chemicals used

in 41% of goods

Page 6: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

6 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 20206

The Solution - Chemetry’s eShuttle® Platform

Page 7: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

7 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 20207

Overview of eShuttle® EDC Process

®

Page 8: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

8 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 20208

eShuttle® Platform - Next Generation Technology✓ Reduces power consumption by 25-50%

1 Plant = CO2 Savings of 100,000 EV’s

✓ Intrinsically safer process

✓ Same products from same feedstocks

✓ Proven at pilot scale

✓ Key strategic partnerships in place

✓ Shut-down economics

Page 9: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

9 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 20209

eShuttle® EDC is Commercialization Ready

2012

Chemetry-TechnipFMCCommercial Agreement

2016

2018

2020

2014eShuttle® Process

Conception

Laboratory Validation

eShuttle® Pilot Plant Construction

eShuttle® EDC Demo Plant Agreement

eShuttle® Demo PlantConstruction

Cell scale-up and manufacture

Page 10: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

10 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202010

EChlor-Alkali = 3.0V EeShuttle™ = 2.4V

eShuttle® Process Simplified2NaCl + 2H2O + C2H4 → H2 + 2NaOH + C2H4Cl2

Cl-

CATHODE

-+

ANODE: Cu+ Cu2+ + e-

E˚ = 0.159 → 0.7VCATHODE: 2H2O + 2e- H2 + 2OH-

E˚ = -0.83V

Na+

NaCl

H2

OH-

NaOH

CATION

MEMBRANE

ANION

MEMBRANE

CuCl

CuCl2ANODE

Homogenous Catalysis Reactor

Ethylene

H2O

EDC

Page 11: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

11 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202011

eShuttle® EDC Process Proven at Pilot Scale

✓ Fully integrated and automated facility

✓ 36 months of operation achieving key performance metrics

Page 12: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

12 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

Demonstration Facility» Maceio, Alagoas State, Brazil

Map and photos courtesy of Braskem, SA

Page 13: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

13 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

Facilities Location

PONTAL DA

BARRA

TRAPICHE

MACEIÓ

MARECHAL

DEODORO

Page 14: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

14 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

Chloralkali Plant

Chlor-Alkali plant is located on the coast a few kilometers south of Maceio, 200

meters from the Mundau lagoon and 100 meters from the Atlantic Ocean.

Atlantic Ocean

Green Belt

Maceio city

Page 15: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

15 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

Demo Plant Location

Page 16: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

16 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202016

Overview of Demonstration Plant

Page 17: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

17 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202017

Electrolyzer

Page 18: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

18 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202018

Side View of Electrolyzer and Frame

Page 19: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

19 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202019

Top of Reactor Tower

Page 20: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

20 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202020

Project Timeline» Construction through Q4 2021

» Transport and assembly on site – Q1 2022

» Commissioning and operations – Q1 2022 through Q2 2023

» Site visits possible beginning in Q2 2022

Page 21: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

21 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

Impact of eShuttle® EDC Technology

Page 22: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

22 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202022

Mercury Cell Chloralkali Plants» Number of plants - 22

» Capacity - 1,570 KTA

» Power consumption - 5.4 million

MWh/yr

» Power savings - 2.3 million MWh/yr

» Cost reduction - $70 million/yr

» GHG reduction - 1.5 million MT

CO2/per year

Capacity and baseline cost data courtesy of IHS Markit

Page 23: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

23 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202023

Diaphragm Chloralkali Plants» Number of plants* - 34

» Capacity - 10,900 KTA

» Power consumption – 30.9 million

MWh/yr

» Power savings - 9.2 million MWh/yr

» Cost reduction - $267.8 million/yr

» GHG reduction - 6.1 million MT CO2/yr

* - Not including plants committed to PO production

Capacity and baseline cost data courtesy of IHS Markit

Page 24: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

24 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202024

Older* Membrane Chloralkali Plants» Number of plants - 95

» Capacity - 13,713 KTA

» Power consumption - 36.2 million

MWh/yr

» Power savings - 8.9 million MWh/yr

» Cost reduction - $354 million/yr

» GHG reduction - 5.9 million MT CO2/yr

* - Plants built before 2000

Capacity and baseline cost data courtesy of IHS Markit

Page 25: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

25 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202025

The Economic Value of eShuttle® EDC» Potential Savings for the average plant in each decile on the cost curve

$-

$2.00

$4.00

$6.00

$8.00

$10.00

$12.00

1 2 3 4 5 6 7 8 9 10

Mil

lio

n U

S$

pe

r ye

ar

Decile of Cost Curve

Annual Cost Savings for an average plant in each Decile

Annual Savings (25% savings) MM$ Annual Savings (30% savings) MM$ Annual Savings (40% savings) MM$

Page 26: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

26 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

Preview of the eShuttle® PO Process

Page 27: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

27 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202027

» Chemetry process reduces power, NaOH, and wastewater

requirements

– Chemetry process saves 45+ tonnes of water for every tonne of PO

– 60% less energy versus traditional PO process

» Ability to leverage EDC

development work and pilot facility

» Pilot facility designed, constructed,

and producing PO

» Clear economic advantage

and market demand

– $500+MM additional NPV per plant*

Second Product - eShuttle® PO Process

2016

Chemetry-TechnipFMCCommercial Agreement

20182019

2020

2017Laboratory Validation

Pilot Plant Construction

*Based on Industry Validated Assumptions

Process Optimization

Page 28: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

28 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202028

PO Process Overview: Process Loops

Overall Reaction is: C3H6 + ½ H2O + ¼ O2 → C3H6O + ½ H2

Page 29: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

29 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202029

PO Process Overview: Key Advantages

Conventional

eChem Cell

Chlorohydrin

Reactor

PO

Reactor

O H

Cl

2 NaCl

O

2 NaOH

Chemetry

eChem Cell

Chemetry

Bromohydrin

Reactor(s)

PO

Reactor

O

1 NaOH

H2O

1 CuBr2

1 CuBr

Conventional Chlorohydrin Process

Chemetry eShuttle® Process O2

Cl2

Power savings:

Lower voltage

from eShuttle™

Zero-Liquid Discharge

from high concentration

saponification

Power savings: with

oxybromination,

current cut in half

H2O

OH

Br

NaBr

Page 30: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

30 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 202030

eShuttle® Platform Summary» EDC Technology on path for commercialization

– Demonstration Plant in operation in 2022

– Reduced operating expense and inherently safer process

– Partners are in place for scale up and commercialization

» PO Process being optimized in Pilot Plant

– Lower Capital Costs and Operating Expense than current processes

– Zero Wastewater generation and lower GHG Generation

– Seeking Demonstration Partner

» Chemetry and the eShuttle® Platform are focused on reducing power

consumption and environmental impact of Commodity Chemicals

Page 31: eShuttle EDC Process · 14 IHS Global Chloralkali, Vinyls and Polyurethanes –October 7, 2020 Chloralkali Plant Chlor-Alkali plant is located on the coast a few kilometers south

31 IHS Global Chloralkali, Vinyls and Polyurethanes – October 7, 2020

Thank you!