7
Erasmo Vellucci Via E. Montale, 9 – Porto Torres (SS) – ITALY Landline +39 0799104316 Telephone +39 3356161034 (Italy) Telephone +971 563101587 (UAE) Email – [email protected] Linkedin – Erasmo Vellucci Skipe – Eraves Current work residence Fares Tower, Street 7, Blg.30 – Fintas, Al Ahmadi – KUWAIT Landline +965 23906395 (Flat no.30) Telephone +965 60073928 (Kuwait) August 2016 Professional Profile Site Manager Senior Construction & Commissioning Manager Safety & Quality Manager Planning & Training Manager Languages – English, Italian & French Professional Experience Sewage Treatment Plants & Industrial Treatment Plants – 30 years Pumping Stations, Firefighting Systems & Booster Systems – 30 years Utilities for Power Plants & Refineries (Boilers, Turbines, Engines, Pumps, Cooling Systems, Compressors, Generators, HVAC) – 20 years Demineralization Plants (Reverse Osmosis, Resins, Desalination) – 20 years Civil Constructions (Villas & Buildings) – 15 years Solid Waste Treatments Plants (RDF and Compost Plant, Incinerator) – 10 years Marine Plants & Equipment (Oil Tankers & Cargo Ships) – 10 years Recovery competitiveness in Plants with delay in Construction & Commissioning . Checking & Consulting Design (Water Treatment Plants, Pumping Stations, Solid Waste Plants). Preparation and review of documents for Construction (Method Statements, Procedure, Manuals, P&ID, etc.) and Commissioning (Functional Description, Operation & Maintenance Manuals, Test Forms Equipment, Permit to Works, etc.). References SC Eptisa SRL – Bucharest – Romania (Mr. George Allan Black) Parsons International Limited – Abu Dhabi – UAE (Mr. Mark Thomas) Kharafi National C. LLC – Abu Dhabi – UAE (Mr. Laith Jarrar) Emit SpA – Milano – Italy (Mr. Luigi Pisante) Reference available on request Education 1

Erasmo Vellucci CV_2016August

Embed Size (px)

Citation preview

Page 1: Erasmo Vellucci CV_2016August

Erasmo Vellucci

Via E. Montale, 9 – Porto Torres (SS) – ITALY Landline +39 0799104316Telephone +39 3356161034 (Italy)Telephone +971 563101587 (UAE)Email – [email protected] – Erasmo VellucciSkipe – Eraves

Current work residence

Fares Tower, Street 7, Blg.30 – Fintas, Al Ahmadi – KUWAITLandline +965 23906395 (Flat no.30)Telephone +965 60073928 (Kuwait) August 2016

Professional Profile

Site ManagerSenior Construction & Commissioning ManagerSafety & Quality ManagerPlanning & Training ManagerLanguages – English, Italian & French

Professional Experience

Sewage Treatment Plants & Industrial Treatment Plants – 30 yearsPumping Stations, Firefighting Systems & Booster Systems – 30 yearsUtilities for Power Plants & Refineries (Boilers, Turbines, Engines, Pumps, Cooling Systems, Compressors, Generators, HVAC) – 20 years Demineralization Plants (Reverse Osmosis, Resins, Desalination) – 20 years Civil Constructions (Villas & Buildings) – 15 years Solid Waste Treatments Plants (RDF and Compost Plant, Incinerator) – 10 yearsMarine Plants & Equipment (Oil Tankers & Cargo Ships) – 10 years

Recovery competitiveness in Plants with delay in Construction & Commissioning.

Checking & Consulting Design (Water Treatment Plants, Pumping Stations, Solid Waste Plants).

Preparation and review of documents for Construction (Method Statements, Procedure, Manuals, P&ID, etc.) and Commissioning (Functional Description, Operation & Maintenance Manuals, Test Forms Equipment, Permit to Works, etc.).

References

SC Eptisa SRL – Bucharest – Romania (Mr. George Allan Black)

Parsons International Limited – Abu Dhabi – UAE (Mr. Mark Thomas)

Kharafi National C. LLC – Abu Dhabi – UAE (Mr. Laith Jarrar)

Emit SpA – Milano – Italy (Mr. Luigi Pisante)

Reference available on request Education

1

Page 2: Erasmo Vellucci CV_2016August

Marine Technical Diploma (June 1972)Italian Technical Institute Marine – Gaeta (LT) – Italy

Certificate Conductor of Steam Boilers (October 1979)Italian Technical Institute Marine – Gaeta (LT) – Italy

Degree Marine Engineer (June 1985)Italian Ministry of Merchant Marine – Rome – Italy

Certificate Health and Safety & Supervisor Construction Projects (June 1998)National Council of Geometers – Rome – Italy

Certificate Auditor of Quality Management Systems (February 2003)Italian Industrial Association – Certiquality Company – Milan – Italy

Certificate Fire Officer High Risk (December 2009)Command Firefighters – Crotone – Italy

Documents available on request

Personal Information

Nationality – Italian

Visa Status – Kuwait Residency Visa / UAE Residency Visa

Marital Status – Married

Work Experience – Last 16 years

1) January 2016 – Open

Position: Package Manager Company: La’ala Al Kuwait Real Estate Co. K.S.C. (Main Contractor).Location: Sabah Al Ahmad Sea City – Al Khiran – Kuwait.Customer: La’ala Al Kuwait Real Estate Co. K.S.C. / Subsidiary of KMGC (Khalid Yousuf Al-Marzouq & Sons Group of Companies) – Kuwait City.

Role & Responsibilities: Head of department of Construction, Commissioning, Planning and Quality (Material approval, Manuals, FDS, Test forms, etc.) of No.2 Sewage Treatment Plants (A1/A3-STP with capacity of 12,000 m3/day and A4/A5-STP with capacity of 46,320 m3/day) and No. 2 Pumping Stations.Verification design of STPs and PSs process and mechanical part.Management Subcontractors.

2) June 2014 – 31August 2015

Position: Site Manager & Mechanical ManagerCompany: EMIT SpA (Main Contractor).Location: Iasi / Podu I. / Targu F. / Harlau – Romania.Customer: APAVITAL – Iasi – Romania.

Role & Responsibilities: Contractor Representative of EMIT.Head of Construction, Rehabilitation, Commissioning, Planning and Quality (Material approval, Manuals, FDS, Test forms, etc.) of No.4 Sewage Treatment Plants (Iasi with

2

Page 3: Erasmo Vellucci CV_2016August

capacity of 710,000 m3/day, Podu I. with capacity of 6,300 m3/day, Targu F. with capacity of 12,100 m3/day and Harlau with capacity of 11,500 m3/day).Management Contractor Customer and Subcontractors.

3) September 2011 – May 2014

Position: Site Manager & Construction Manager of No.4 Projects in different cities of Governorate of Iasi.Company: EMIT SpA – Italy (Design & Technological Systems).Position: Commissioning ManagerCompany: KHARAFI NATIONAL – UAE (Main Contractor).Location: Saadiyat Island – Abu Dhabi – UAE.Customer: ADSSC / TDIC – Abu Dhabi – UAE.

Role & Responsibilities: Head of Construction Mechanical, Instruments, SCADA systems, Process, Planning and Quality (Material approval, Manuals, QCPs, etc.). Commissioning, Planning Manager (Testing, Performance test and End over) & Quality (FDS, Test Forms, Permit to Work etc.) of Sewage Treatment Plant (Saadiyat STP-2 of 38,000 m3/day) & Main Pumping Station.Management Subcontractors. 4) October 2009 – December 2011

Position: Site Manager & Construction Manager, Safety & Quality ManagerCompany: EMIT SpA, Italy (Main Contractor).Location: Tunis West – Tunis – Tunisia.Customer: ONAS, Tunis – Tunisia.

Role & Responsibilities: Head of Construction, Planning, Safety (Method of statements, etc.) & Quality (Material approval, Manuals, QCPs, etc.) of Sewage Treatment Plant & Biogas (Tunis West STP of 60,000 m3/day).Management Contractor Customer and Subcontractors.

5) January 2007 – September 2010

Position: Site Manager, Construction & Commissioning Manager, Safety & Quality Manager of No.4 Projects in different cities of south Italy.Company: EMIT SpA, Italy (Main Contractor / Partner).

1. Location: Scandale (CR) – Italy. Consortium: Alstom Power (Main Contractor) Techint C.M., Emit.Customer: Ergosud – Italy (E.On – Germany / A2A – Italy).Project: Waste Water Treatment Plants Zero Discharge (Pretreatment, Biological, Oils plants, Reverse Osmosis and EDI plant, Evaporator and Crystallization brine) & Utilities for Combined Cycle Power Plant with capacity of 2x400 MW.

2. Location: Lauria (PZ) – Italy.Customer: Municipality of Lauria – Italy.Project: Civil Solid Waste Recycling & Treatment Plant (RDF production and Composting plant with capacity of 20 Tons/day).

3. Location: Acerra (NA) – Italy.Customer: Sviluppo Italia Aree Produttive SpA, Acerra (Naples) – Italy.Project: Water Treatment Plant (Emergency Containment & Recovery of Ground water).

3

Page 4: Erasmo Vellucci CV_2016August

4. Location: Brindisi – Italy.Customer: Municipality of Brindisi – Italy.Project: Maintenance & Mothballing of Civil Solid Waste Recycling & Treatment Plant (RDF Production & Composting Plant) with capacity of 500 Tons/day.

Role & Responsibilities: Head of Construction, Planning, Safety (Method of statements, etc.) & Quality (Material approval, Manuals, QCPs, etc.).Commissioning, Planning Manager (Testing, Performance test and End over) Safety and Quality (FDS, Test Forms, Permit to Work, etc.).Management Contractor Customer and Subcontractors.

6) September 2001 – December 2006

Position: Construction & Commissioning Manager, Safety & Quality Manager of No. 21 Projects in north of Sardinia in Italy.Companies: VECOS Srl & EDENCOS Srl (Owner & Main Contractor) – Sardinia – Italy. Location: Sardinia Island – Italy.Customer: Private citizen & various company – Italy.

Role & Responsibilities: Head of Design, Construction, Planning, Safety, Quality & Commissioning of Villas, Buildings & Warehouses.Management Contractor Customer and Subcontractors.

7) April 2000 – August 2001

Position: Construction & Quality ManagerCompany: TTR Srl / FALK GROUP – Italy (Main Contractor).Location: Trezzo sull’Adda (MI) – Italy.Customer: Municipality of Trezzo sull’Adda (MI) – Italy.

Role & Responsibilities: Head of Construction, Planning & Quality (Material approval, Manuals, QCPs, etc.) of Incinerator Solid Waste with capacity of 550 Tons / day and electricity of 19 MGW/day.Management Contractor Customer and Subcontractors.

8) August 1999 – March 2000

Position: Construction & Quality Manager Company: SIMM Srl – Cagliari – Italy (Sub Contractor).Location: Porto Torres (SS) – Italy.Customer: Enichem, Porto Torres (SS) – Italy.

Role & Responsibilities: Head of Construction & Quality (Material approval, Manuals, QCPs, etc.) of Pipe Rack Phenol Plant.

Work Experience – 1999 ÷ 1973

9) December 1993 – July 1999

Position: Site Manager & Construction Manager, Safety & Quality ManagerConsortium: EMIT (Main Contractor) // Termokimik // Termomeccanica.Location: Porto Torres (SS) – Italy.Customer: ENEL SpA – Rome – Italy.

4

Page 5: Erasmo Vellucci CV_2016August

Role & Responsibilities: Head of the Consortium, Safety (Method of statements, Permit to Work, etc.) & Quality (Material approval, Manuals, QCPs, Test Forms, etc.) Manager of the Consortium,& Construction Manager of EMIT of Flue Gas Desulfurization Plant, Transport Coal Ash & TSD Plants for Power Plant with capacity of 2x320 MGW.Management Contractor Customer and Subcontractors EMIT.

10) December 1986 – November 1993

Position: Supervisor PlantsCompany: EMIT SpA – Milan – Italy with more than No.50 projects.Location: In different regions and cities in Italy.Customer: Various Municipality and Public Entity – Italy.

Role & Responsibilities: Supervisor of Construction, Planning, Safety, Quality & Commissioning of Civil and Industrial Waste Water Treatment Plants, Main Pumping Stations, Drinking Water Plants, Ballast Water Treatment Plant with Gas Inert System, Hydroelectric Plants, Solid Waste Treatment Plants.Management Contractor Subcontractors.

11) January 1986 – November 1986

Position: Supervisor PlantsCompany: Italimpianti IT – Genoa – Italy.Location: Chergoum el Aid & Sour el Ghoslane – Algeria.Customer: Government Entity – Algeria.

Role & Responsibilities: Supervisor of Revamping, Commissioning and Performance Tests of the Utilities Plants of the Factory Production Detergent.

12) March 1984 – April 1985

Position: Technical Manager of the ResortCompany: Valtur Vacanze – Rome – Italy.Location: Island of Gasfinolhu – Republic of Maldives.Customer: Valtur Vacanze – Rome – Italy.

Role & Responsibilities: Head of the Maintenance (Generators, Sewage Treatment Plant, Pumps, Water Softener, HVAC, Kitchen, Gardens, Boungalows, Laundry, Boats and Motorboats, etc.) of the Holiday Resort.Management Budget and Contractor Subcontractors.

13) October 1983 – February 1984

Position: Supervisor Plants Company: Tecnipetrol – Rome – Italy.Location: Kirkuk – Iraq.Customer: Government Entity – Iraq.

Role & Responsibilities: Supervisor of Pre-commissioning, Commissioning and Performance Tests of the Utilities of Gas Refinery & Sulfur system.

5

Page 6: Erasmo Vellucci CV_2016August

14) January 1973 – July 1983

Position: Career as Cadet Engineer to Chief Engineer Companies: Snam Armamento – Milan – Italy // Gulf Oil Company – USA // S.S.O.S. – Fiumicino (Rome) – Italy.Location: Navigation in the seas of the world.

Role & Responsibilities: Supervisor of Operation and Maintenance Plants of Oil Tankers and Cargo Ships.

6

Page 7: Erasmo Vellucci CV_2016August

14) January 1973 – July 1983

Position: Career as Cadet Engineer to Chief Engineer Companies: Snam Armamento – Milan – Italy // Gulf Oil Company – USA // S.S.O.S. – Fiumicino (Rome) – Italy.Location: Navigation in the seas of the world.

Role & Responsibilities: Supervisor of Operation and Maintenance Plants of Oil Tankers and Cargo Ships.