This map shows the U.S. EPA's conceptual sampling plan for the Creese and Cook Tannery Superfund Site in Danvers. Field work to determine the extent of contamination on the east side of the Crane River is scheduled to begin in May and take four to six weeks.
Citation preview
CLINTON AVENUE
ENDICOTT STREET
WATE
RST
REET
HIGH STREET
HUTCHINSON DRIVE
PERR
Y STR
EET
NEEDHAM ROAD
YANKEE DIVISION HIGHWAY
CHEEVER STREET ME
RRILL
STRE
ET
HOOD TE
RRAC
E
PERR
Y DRIVE
PERRY TERRACE
HIGH STREE
T COURT
CRANERIVER
Notes: 1. Actual soil boring locations will be determined based on observations made during Study Area reconnaissance,geophysical investigation results, and field screening results for previous borings during the same sampling event. 2. Actual groundwater monitoring well locations will bedetermined based on observation made during Study Area reconnaissance, geophysical investigation results, and initial results of soil sampling program.
3. Only 60 soil borings are illustrated. Up to 15 more soilborings will be advanced based on field observations during the soil investigation.
4. Location of site features depicted hereon is approximate and given for illustrative purposes only.
LegendProposed MW Installation 0 75 150 300 CONCEPTUAL SAMPLING PLAN
CREESE & COOK TANNERY (FORMER)Proposed DPT Soil Boring FeetExisting MWs SUPERFUND SITE