OIL INDIA LIMITED
Expression of Interest (EOI)
EOI No: EOI/GM (E)/2013/1
“Consultancy Services” for feasibility study of various options andpreparation of medium term and long term plan for augmentation of electrical
power generation and distribution network capacity at Oil India Limited FHQ
Duliajan, PHQ Noonmati and Moran Field.
1. Oil India Limited is a premier National Oil Company having “ Navaratna”status under Ministry of Petroleum and Natural Gas, Govt. of India.
2. OIL intends to obtain “Consultancy Services” from interestedexperienced and capable parties/firms for augmentation of electricalpower generation and distribution network capacity at Oil India
Limited’s FHQDuliajan, PHQ Noonmati and Moran Fields.
3. Interested Parties / Consultancy Firms / Consortium of Parties meetingthe prequalification criteria are invited to submit their EOI ( in duplicate)
together with necessary documents to reach the following address on or
before ‘ 07 December,2013 (day) till 15.00 hrs. (IST).
Chief Engineer Electrical (Planning & Admin.)
Electrical Engineering Dept.
Oil India Limited, Duliajan, Pin – 786602
Dist: Dibrugarh, Assam (India)
4. For details on the above EOI (Details of Expression of Interest), pleaserefer to the OIL’s website: www.oil-india.com
5. OIL reserves the right to (a) accept or reject any/all EOIs submitted byparties and (b) cancel the process at any time without any liability and
assigning any reason thereof.
http://www.oil-india.com/http://www.oil-india.com/http://www.oil-india.com/http://www.oil-india.com/
8/13/2019 EOI_EOIGME20131
2/4
ANNEXURE-I
Prequalification Criteria and Scope of Work:
1. Prequalification Criteria:
1.1 The bidder shall be a consultancy firm providing Engineering andProject Management Consultancy (EPMC) services. The bidder shall haveexperience in successful execution & completion of EPMC jobsincorporating Front End Engineering Design (FEED), involving latest,appropriate and proven technology ; preparation of Engineering BidPackage; Project Management including preparation of specification,selection, procurement, installation and commissioning jobs in projects
for gas/diesel supplied power generation and distribution network only,during last 7 (seven) years in central Govt./State Govt./PSU/Pvt. LimitedCompany.
1.2 The experience of the Bidder for Engineering & Project ManagementConsultancy Services must be of their own and not with the support ofanother party/ parent company/ subsidiary/ partner firm/ group firm/ backupConsultant etc.
2. Scope of Work:
Consultancy services are required for feasibility study & to prepare short term,
medium term & long term plan for augmentation of electrical power generation and
distribution capacity, with latest/energy efficient technology and system, in Oil
India Limited at Duliajan and Moran, Assam.
A. Present load survey and future load forecasting:
This involves understanding of the present power supply system; Study of
present load condition; Future forecast of load demand; Measures (short term,
medium term & long term) to meet the deficit; Demand Side Management &
energy savings thereof; Strategy for power generation (including Distributed
Power Generation system) to meet the additional demand;
a. Recommendation of technology to be adopted while deciding generation
capacities (gas based) to meet the deficit in power demand:
This includes study of gas availability; Best suitable technology for power
generation (Gas Engines / Turbines / Any other); Cost benefit analysis of the
recommended technology; Distributed Power Generation system vs the present
power generation & distribution system & its advantages/disadvantages with cost-benefit analysis;
8/13/2019 EOI_EOIGME20131
3/4
B. Sizing and running configuration of alternators and prime movers:
This involves sizing of the prime-movers, alternators & other auxiliaries;
Availability of the recommended sizes of power generation units in the market &
the sources; Cost benefit analysis of various combinations of power generationunits based on their sizing; Cascade combination strategy based on sizing (plug-in
type); Redundancy; Recommend installed capacity with standby strategy;
i) Phasing-out plan of existing 2x14.45 MW Gas Turbines & its replacement strategy:
This shall include the possibility of replacing the existing 2x14.45 MW GT sets with
another 20 MW or cascade of smaller sets; Evaluation of phasing-out plan of
existing GTs based on the residual life after the internally planned & partly
implemented (rotors refurbished) / partly under implementation (control systems)strategy; Feasibility of buy-back strategy of replacement & the sources;
ii) Feasibility of hiring or procuring Gen-sets for meeting power needs, both in short
and medium terms:
This includes cost benefit study of procuring the recommended sizes of power
generating units vis a vis hiring the same on rental/Kwh basis (gas supply by OIL);
Plan for short-term & medium-term based on the recommendations;
iii) Feasibility of tapping power from State Power Utilities / Central Power Utilities:
Analyzing the feasibility of options available under open access for OIL India’s
respective facility in Duliajan & Moran; Analysis of the Open Access regulations
for the Assam state; Analyzing the issues that may arise, involved to Open
Access, etc; Case study of existing PSU/ Govt. customers availing Open Access
in the respective state and otherwise; Analyzing the load profile, tariff structure,
etc; Preparation of Savings model in case OIL India’s facility avails Open Access;
Cost-Benefit Analysis; Understanding the present power supply arrangements
with Central and State Utilities and the penalties , if any involved in closure of the
same;
iv) Siting of power generation units:
Identification of possible locations for setting up generating stations, considering
existing and future load points, facilities available and required to be developed at
these sites;
v) Distribution Network:
Recommendations on the present distribution network, and changes (technology /
configuration) to be made in view of future load growth and added generation;
Techno-Economic study of a grid system for Distributed Generation system shall
also be investigated.
8/13/2019 EOI_EOIGME20131
4/4
vi) Feasibility of generation & utilisation of Renewable Energy (RE):
Feasibility study for use of renewable energy in OILs premises (residential/field
installations) & the capacity; Applicability of Renewable Power purchase
Obligation (RPO) to Oil India Limited, and its solution (purchase of RenewableEnergy Certificates); Integrating renewable source of energy into gas based
generation;
vii) Any other points that may be required for augmentation of power generation and
distribution capacity:
This includes the future road-map for power generation strategy based on the
existing system vis a vis the recommendations of the report, taking into
consideration of future demand.