Environmental Monitoring Report Annual Report December 2011
IND: North Karnataka Urban Sector Investment Program Tranche 2 – Dharwad Subproject Prepared by Wilbur Smith Associates for the Karnataka Urban Infrastructure Development and Finance Corporation, Government of Karnataka and the Asian Development Bank.
NORTH KARNATAKA URBAN SECTOR NORTH KARNATAKA URBAN SECTOR
INVESTMENT PROGRAMMEINVESTMENT PROGRAMME
(ADB ASSISTED)(ADB ASSISTED)
Compliance Report
on
Environmental
Management Plan
December 2011
Prepared by
Wilbur Smith Associates Private Limited
Program Consultant – Package 1
Hubli
Package I – Dharwad(Bijapur, Davanagere, Gadag-Betageri, Haveri, Hubli-Dharwad & Ranebennur)
Karnataka Urban Infrastructure Development and Finance Corporation, Government of Karnataka
North Karnataka Urban Sector Investment Program (NKUSIP)
Package I – Dharwad
Compliance Report on
Environmental Management Plan
(Bijapur, Davanagere, Gadag-
Betageri, Haveri, Hubli-Dharwad &
Ranebennur
December 2011
Prepared by
Wilbur Smith Associates,
Program Consultant - Package I,
I.T Park, Hubli
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-1
Contents 1. EMP for Haveri Town ................................................................................................................................... 3
1.1. Introduction – Haveri Town .................................................................................................................... 3
1.2. Permissions/Consents/Clearances/Approvals: ......................................................................................... 3
1.3. Field Visits & Training Conducted ......................................................................................................... 3
1.4. Compliance to EMP ................................................................................................................................ 3
1.5. Redress of Grievances ............................................................................................................................. 4
1.6. Labour Registration ................................................................................................................................. 4
1.7. Summary and Conclusions ...................................................................................................................... 4
2. EMP for Ranebennur Town ......................................................................................................................... 6
2.1 Introduction – Ranebennur Town ............................................................................................................ 6
2.2 Permissions/Consents/Clearances/Approvals: ......................................................................................... 6
2.3 Field Visits & Training Conducted ......................................................................................................... 6
2.4 Compliance to EMP ................................................................................................................................ 6
2.5 Redress of Grievances : ........................................................................................................................... 7
2.6 Summary and Conclusions ...................................................................................................................... 7
3 EMP for Bijapur .............................................................................................................................................. 9
3.1 Introduction – Bijapur Town ................................................................................................................... 9
3.2 Permissions/Consents/Clearances/Approvals: ......................................................................................... 9
3.3 Field Visits & Training Conducted ......................................................................................................... 9
3.4 Compliance to EMP .............................................................................................................................. 10
3.5 Redress of Grievances ........................................................................................................................... 10
3.6 Labour Registration ............................................................................................................................... 10
3.7 Summary and Conclusions .................................................................................................................... 10
4 EMP for Hubli-Dharwad .............................................................................................................................. 12
4.1 Introduction – Hubli - Dharwad ............................................................................................................ 12
4.2 Permissions/Consents/Clearances/Approvals: ....................................................................................... 12
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-2
4.3 Field Visits & Training Conducted ....................................................................................................... 12
4.4 Compliance to EMP .............................................................................................................................. 13
4.5 Redress of Grievances ........................................................................................................................... 13
4.6 Labour Registration ............................................................................................................................... 13
4.7 Summary and Conclusions .................................................................................................................... 13
5 Monitoring Sheets (Received on 05.01.2012) ............................................................................................. 16
6 Status of Clearances/Approvals ...................................................................................................................... 25
7 Display of Executive Summary of IEE, in Kannada ........................................................................................ 31
7 Display of Executive Summary of IEE, in Kannada ........................................................................................ 31
8 Labour Registration ...................................................................................................................................... 32
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-3
1. EMP for Haveri Town
1.1. Introduction – Haveri Town
The components taken up for Haveri are detailed in the following Table.
Package Sub Project Physical
Completion (%)
Date of
Award
Date of
Completion
Date of Extensions if any
01 HVR 01 Water Supply
96.5 19.12.2009 18.06.2011 Earlier extensions of
17.12.2011 (With LD) expired.
01HVR 02 Sewerage System,
Urban Drain &
STP
59.9
50
15
19.12.2009 18.06.2011 05.02.2012 (Without LD)
June 2012 (With LD)
The Initial Environmental Examination (IEE) Report was approved by ADB in the year 2009. The status of
Environmental Management Plan (EMP) for the month of December 2011 are presented in the following sections.
1.2. Permissions/Consents/Clearances/Approvals:
Particulars Sub
Project
KSPCB Railways PWD KPTCL /
HESCOM
Forest Minor
Irrigation
Irrigation*
Consent/Clearances/
Permissions/Approval
Status (Obtained – √
Not Obtained X)
Water
Supply
NA √ √ √ √ √ NA
UGD &
STP
√ X √ √ NA NA NA
Note: For details refer Monthly Progress Review Meeting Dec 2011.; NA-Not Applicable; * for drawal for water from reservoir for demand of year 2041/2044
1.3. Field Visits & Training Conducted
Field
Visit
Date Sites Visited Persons Met Remarks
30 Dec.
2011
0IHVR02: Sewer pipes laying at
PB Road near Mythri Hotel,
MG Road, Basaveswaranagar (C
Block), Akkipete, Railway
Station Road, STP
1. V.N.Hadimani, AEE, NKUSIP Cell, Haveri
2. Mr, P. Hanumantha Naik, AE, NKUSIP Cell
3. Mr. Shyam Pujari, CSS, PC
4. Mr. Sampath, Mr. Veeranna , Mr. Mahesh ,
Mr. Somasekhar, of Gautham Jahnavi Constructions
5. Mr. Ramesh, RE, PC
01 HVR 01: Ashwini Nagar 1. Mr. Irshad , Site Engineer, Sai Sudhir Infrastructure
2. Mr.Subodh, RE, PC
Training
Date Location Nature of Training Participants
3 Nov.
2011
DC office Road,
Hosa Nagara
JP Circle
On the job training on
the importance of Safety
of workers and safety of
public was held
8 Participants. Detailed list provided in November
2011 EMP Report
16 Jun
2011
Conference Hall,
RO, Hubli Orientation Program for
Implementing Agency
and Executing Agency
43 participants attended. Detailed list see Annexure
3 of August EMP Report
13 July,
2011
NKUSIP Cell,
Haveri Orientation Program for
Contractors and
Supervisory staff
8 participants. viz
Detailed list see Annexure 3 of August EMP Report
1.4. Compliance to EMP
Particulars Sub Project Complied Compliance to EMP
Design/Location/
Preconstruction
Stage Monitoring
Sewerage System.
Urban drain & STP √ Details on EMP page 55 of Initial Environmental Report, March
2009, is made part of Contractor Agreement Page No. 81 & 82
Water Supply
√ Details on EMP page 57 of Initial Environmental Report, March
2009, is made part of Contractor Agreement Page No.76 & 77
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-4
Construction
Stage Monitoring
Sewerage System &
STP √ Contractor complying with EMP. Also see Annexure 2
Water Supply
√ Contractor complying with EMP. Also see Annexure 1
Occupational
Health Risks and
Safety Plan for
Workers
Sewerage System &
STP √ Contractor complying with EMP. Also see Annexure 2 and
photographs Attachment 1
Water Supply
√
Complied. Please Refer Monitoring Format (Annexure 1)
The photographs enclosed as Attachment 1.
1.5. Redress of Grievances
Sub Project Registers Maintained No. of Grievances received
in the month
Action Taken
Sewerage System & STP √
16 Nos. Attended all 16 nos. of
complaints received
Water Supply √ Nil
1.6. Labour Registration
Informed the Contractors. The license is yet to be received from both the contractors.
1.7. Summary and Conclusions
EMP monitoring being done daily (see Annexure 1& 2) on the critical issues and following improvements/
positive developments are observed.
Sl Details Compliance Status
1 Display of IEE Executive Summary in Kannada on Notice Board of NKUSIP
Cell office and CMC office
Complied on 16.08.2011. The same
exist in the Notice Board
2 KSPCB’s CFE Condition (V.7), the ULB shall furnish point-wise compliance to
the conditions within 30 days to KSPCB
Complied on 15.10.2011
3 Dust control measures are being done Complied
2.
However, the following issues need to be addressed.
Sl Issues/Deviations Compliance Status Corrective Actions to be taken
1 As per the KSPCB’s CFE
Condition (I.3), the ULB
shall maintain 500 mts buffer
zone around STP area (I.7).
Yet to be complied. Informed ULB to initiate a letter to Town Planning
department for earmarking no development zone
around the STP site.
2 The name of contact person
along with the phone number
to be included in the project
information board.
Yet to be complied. Informed Contractor to provide the Contact person
name & Phone number in Project information Board.
3 Safety measures, Helmets,
Gum boots, First Aid Kits,
barricading etc. needs to be
provided
First Aid kits &
Helmets not available
at Site, insufficient
barricades and Caution
boards for sewerage
package
Informed Contractor to provide stronger barricades
and caution board
Informed Contractor to insist the workers to use the
safety measures
Informed CSS and AEE to monitor the critical
parameters regularly & avoid discrepancy
4. Labour License Not complied for both
the packages
Informed Contractor and AEE to provide the same
5 Road restoration Yet to be complied. Informed Contractor to clear the excess soil and
restore the roads
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-5
Attachment 1: Haveri Photographs
PACKAGE – 01 HVR 02
LOCATION : Basaveshwara Nagar (C Blk)
DATE : 12.12.2011
LOCATION : Akkipet Road
DATE : 02.12.2011
Safety Measures for Excavation of Manhole
Dust control measures
LOCATION : P.B. Road (Near Maitri Hotel)
DATE : 22.12.2011
Safety Measures provided during laying of
Sewer lines
Caution Board provided during execution of
Sewer lines
PACKAGE – 01 HVR 01 – Interconnection work for Water supply at Ashwini Nagar
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-6
2. EMP for Ranebennur Town
2.1 Introduction – Ranebennur Town
The components taken up for Ranebennur are detailed in the following Table.
Package Sub Project Physical
Completion (%)
Date of
Award
Date of
Completion
Date of Extensions
if any
02 RNR02 Sewerage System & STP 45 % 23.06.2010 22.12.2011 To be finalized
The Initial Environmental Examination (IEE) Report was approved by ADB in the year 2009. The status of
Environmental Management Plan (EMP) for the month of December 2011 are presented in the following
sections.
2.2 Permissions/Consents/Clearances/Approvals:
Particulars Sub
Project
KSPCB Railways PWD KPTCL /
HESCOM
Forest Minor
Irrigation
Irrigation*
Consent/Clearances/
Permissions/Approval
Status (Obtained – √
Not Obtained X)
UGD &
STP
√ √ √ √ NA NA NA
Note: For details refer Monthly Progress Review Meeting Dec 2011.; NA-Not Applicable; * for drawal for water from reservoir for demand of year 2041/2044
2.3 Field Visits & Training Conducted
Field
Visit
Date Sites Visited Persons Met Remarks
30 Dec
2011
Sewer pipes laying at,
Doddakere lake,
Umashankara Nagar
Gowrishankara Nagar
Rajeshwari Nagar
Vidyanagar
1. Mr. G.N. Kundapur, AEE, NKUSIP Cell, Ranebennur
2. Mr.Prabhudev Mundasad, AE, NKUSIP Cell
3. Mr.Rajesh Kukarni, AE, NKUSIP Cell
4. Mr. Uppar, Construction Supervision Specialist, PC
5. Mr. Kashinath, RE, PC
6. Mr. Sriman Narayana, Project Manager, Mr. Sudhir
Reddy, Mr. Srinivasa Reddy, Mr. Harish, Mr. Rehman,
Mr. Girish, Site Engineer of Ramky Enviro Engineers
No barricades are
provided except at
Doddakere lake.
No safety measures
for workers
No first aid facility
made.
Train
ing
Date Location Nature of Training Participants
3 Nov.
2011
STP, Mrutyunjaya
Nagar, UMashankar
Nagar
On the job training on the importance of Safety of
workers and safety of public was held
4 Participants. Details
given in November
EMP Report
16 Jun
2011
Conference Hall, RO,
Hubli Orientation Program for Implementing Agency and
Executing Agency
43 participants
attended. Detailed list
see Annexure 3 of
August EMP Report
14th
July,
2011
NKUSIP Cell,
Ranebennur Orientation Program for Contractors and Supervisory
staff included Environmental issues related urban
infrastructure Investment Programs during construction,
Implementation of mitigation measures , Monitoring of
implementation
6 participants. viz
Detailed list see
Annexure 3 of August
EMP Report
2.4 Compliance to EMP
Particulars Sub Project Complied Compliance to EMP
Design/Location/
Preconstruction
Stage Monitoring
Sewerage System.
& STP
√
Details on EMP page 49 of Initial Environmental Report, October
2009, is made part of Contractor Agreement Page No. 41 & 42
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-7
Construction Stage
Monitoring
Sewerage System
& STP √
Contractor complying with EMP. Also see Annexure 3
Occupational Health
Risks and Safety Plan
for Workers
Sewerage System
& STP
√
Contractor complying with EMP. Also see Annexure 3 and
photographs Attachment 2
2.5 Redress of Grievances :
Sub Project Registers Maintained No. of Grievances received
in the month
Action Taken
Sewerage System
& STP √
4 Nos. Attended 3 nos of complaints and one is under
progress. Informed AEE, NKUSIP Cell, to
follow up the compliances
2.6 Summary and Conclusions
EMP monitoring being done daily (see Annexure 3) on the critical issues and following improvements/
positive developments are observed.
Sl Details Compliance Status
1 Display of IEE Executive Summary in Kannada on Notice Board of NKUSIP
Cell office and CMC office
Complied on 22.08.2011. The same
exist in the Notice Board
2 KSPCB’s CFE Condition (V.7), the ULB shall furnish point-wise compliance to
the conditions within 30 days to KSPCB
Complied on 04.10.2011
3 Letter to Town Planning department informing the KSPCB’s CFE Condition (I.3),
for maintaining 500 mts buffer zone around the sewage treatment plant area.
Complied on 03.10.2011
4
Removing of excess soil near Devaragudda and STP road
Complied by removing most of the
excess soil near Devaragudda.
5 Documentation mechanism of grievances is evolved and entered in the
Grievances register(opened on 23.05.2011) and being maintained
Complied
However, the following issues need to be addressed.
Sl Issues/Deviations Compliance Status Corrective Actions to be taken
1 As part of safety, Helmets, Gum boots, and
First Aid Kits are required at work sites
Helmets provided
No Gum boots
First Aid Kits does not
exist in all the sites.
Informed Contractor to provide First Aid
Box, Gum Boots, and Helmets to the
workers and also to insist them to wear.
2 The name of contact person along with the
phone number to be included in the project
information board.
Not complied AEE of NKUSIP Cell, Ranebennur
informed that the Contact person Mr.
Nagaraj of Ramky and his number as
9060494758 shall be indicated.
3 Safety measures, barricading etc. needs to be
strengthened
In order to avoid drain blockages, removing
of left out excavated material to be cleared on
urgent basis
Not complied
Not complied
No barricades are provided except at
Doddakere lake.
No safety measures for workers
No first aid facility made.
Informed Contractor to provide stronger
barricades (Wooden/Steel) at various work
sites in city and STP.
Informed Contractor to remove left out
stones and soil deposits at few locations
near Devaragudda road, STP road.
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-8
Attachment 2: Ranebennur Photographs
Location : Haranagiri Road near Doddakere
Date : 30.12.2011
Location : Medleri Road
Date : 21.12.2011
Excavation for laying sewer line
Road Restoration Work
Location : Umashankara Nagar
Date : 29.12.2011
Location : Gourishankara Nagar
Date : 19.12.2011
Road Restoration Work
Road Restoration Work
Location : Devara Gudda Road
DATE : 14.12. 2011
Drain Cleaning activity in progress
Drain Cleaning activity in progress
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-9
3 EMP for Bijapur
3.1 Introduction – Bijapur Town
The components taken up for Bijapur are detailed in the following Table.
Package Sub Project Physical
Completion (%)
Date of
Award
Date of
Completion
02 BJR02 Sewerage System (District 1A) 3 01.02.2011 31.07.2012
02BJR02A Sewerage System (District 2A) with STP 15 01.02.2011 31.07.2012
02BJR02B Sewerage System (District 1B, 2A,2C, 2D& 3A) 5 20.04.2011 19.10.2012
The Initial Environmental Examination (IEE) Report was approved by ADB in the year 2009. The status of
Environmental Management Plan (EMP) for the month of December 2011 are presented in the following sections.
3.2 Permissions/Consents/Clearances/Approvals:
Particulars Sub
Project
KSPCB Railways NH PWD KPTCL /
HESCOM
Forest Minor
Irrigation
Irrigation*
Consent/Clearances/
Permissions/Approval
Status (Obtained – √
Not Obtained X)
UGD &
STP
√ X √ √ X NA NA NA
Note: For details refer Monthly Progress Review Meeting December 2011.; NA-Not Applicable; * for drawal for water from reservoir for demand of year 2041/2044
3.3 Field Visits & Training Conducted
Field
Visit
Date Sites Visited Persons Met Remarks
31 Dec.
2011
Sewer pipes laying at MG
Road,
Golgumbuz Road
Outfall Sewer near STP.
(02)
Mr. I.A. Dhundasi, AEE, & Mr. K.S. Hallur,
AE of NKUSIP Cell, and Mr. R.P. Shirur,
CSS, PC, Mr. Kulkarni, Project Manager and
Site Engineer Mr.Praveen, of Ramky
Infrastructures JV APR Projects P Ltd.,
Hyderabad
In MG Road, and Golgumbuz Road,
the contractor has not provided
Caution Board and First Aid Kit.
Helmets are being used
STP Lagoons, Staff quarters,
STP Wet well at Indi road
Sewer pipe laying at
Sanskruthi Colony Shek
colony, Near Kidney
Foundation, Wetwell at
Tapal layout (02A)
Mr. Pawar, AEE, & Mr. A.S.Patil, AE,
NKUSIP, and Mr. R.P. Shirur, CSS, PC &
Mr. R.B Patil, RE, PC
Mr. Sachin Rathod , Site Incharge, &
Mukund Supervisor Ramky Infrastructures
JV APR Projects P Ltd., Hyderabad
Trenches closed in Sanskruti colony
but excess soil to be cleared off.
No barricades are provided
Helmets were provided at STP but no
first aid kits at all sites
Laying of Sewer pipeline in
Kulkarni layout and Sindagi
road and construction of
Wet well & DG Room at
Bannur Layout, (02B)
Mr. Pawar, AEE & Mr. N.D. Ustad, AE and
Mr. R.P. Shirur, CSS, PC & Mr. M.A.
Managuli, RE, PC
Mr. Santhosh, Site Engineer of Patil
Constructions, Pune
No dust control measures, excess soil to
be removed, and no barricades are
provided at Sindagi road and Kulkarni
layout..
No first Aid kit and Helmets provided
Train
ing
Date Location Nature of Training Participants
04 Nov.
2011
Golgumbuz Road On the job training on the importance of
Safety of workers and safety of public
was held
8 participants : Mr. Bala Reddy, PM &
Site Engineer Mr.Tahir, Mr.
Shivanand, Umesh and Venkatesh
Supervisors of Ramky Infra., CSS, RE
& AE, NKUSIP Cell, Bijapur
17 July,
2011
NKUSIP Cell, Bijapur Orientation Program for Contractors and
Supervisory staff
11 participants. Detailed list see
Annexure 3 of August EMP Report
16 Jun
2011
Conference Hall, RO,
Bijapur Orientation Program for Implementing
Agency and Executing Agency covering
various topics;
43 participants attended. Detailed list
see Annexure 3 of August EMP Report
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-10
3.4 Compliance to EMP
Particulars Sub Project Complied Compliance to EMP
Design/Location/
Preconstruction Stage
Monitoring
Sewerage System.
& STP √
Details on EMP page 55 of Initial Environmental Report,
October 2009, is made part of Contractor Agreement, viz.,
Page No. 30-31 (02 BJR 02) Page No. 31-32 (02 BJR 02A)
Page No.29-30 (02 BJR 02B)
Construction Stage
Monitoring
Sewerage System √
Contractor complying with EMP. Also see Annexure 4, 5& 6
Occupational Health Risks
and Safety Plan for Workers
Sewerage System
& STP √ Contractor complying with EMP. Also see Annexure 4, 5 &
6 and photographs Attachment 3
3.5 Redress of Grievances
Sub Project Registers Maintained No. of Grievances
received in the month
Action Taken
Sewerage System & STP √ 02 BJR 02A - 9 Nos. All the 8 Nos of Grievances are complied &
one to be complied shortly
3.6 Labour Registration
The Labour license is obtained (Form VI) for two packages 02 BJR 02 AND 02 BJR 02A (Annexure 3 of EMP
Report , October 2011). The package No. 02 BJR 02B is yet to be received.
3.7 Summary and Conclusions
EMP monitoring being done daily (see Annexure 4, 5 & 6) on the critical issues and following improvements/
positive developments are observed.
Sl Details Compliance Status
1 Display of IEE Executive Summary in Kannada on Notice Board of NKUSIP
Cell office and CMC office
Complied on 22.08.2011
2 KSPCB’s CFE Condition (V.7), the ULB shall furnish point-wise compliance to
the conditions within 30 days to KSPCB
Complied on 15.07.2011
3 Letter to Town Planning department informing the KSPCB’s CFE Condition (I.3),
for maintaining 50- 100 mts buffer zone around the sewage treatment plant area.
Complied on 08.11.2011
4 Documentation mechanism of grievances is evolved and entered in the
Grievances register and being maintained
Complied from November 2011
4
However, the following issues need to be addressed.
Sl Issues/Deviations Compliance Status Corrective Actions to be taken
1 Safety measures,
barricading etc. needs
to be strengthened
Except STP site, first aid kits
are not provided in all three
packages
Helmets are used in 02 BJR02A
In sufficient helmets &
barricades in all the packages
Informed Contractor to provide First Aid kits in each
vehicle,.
The existing Caution boards are not sufficient and therefore
to increase the number of caution boards and barricades
To shift excavated surplus soil to authorized designated soil
dump yard
2 Sewer Trenches were
kept for longer period
without back filling
Manholes are not
provided with Covers
Yet to comply Trenches closed in Sanskruti colony but excess soil to be
cleared off.
Informed Contractor to backfill the various trenches and
also to provide the Manhole cover
3. Labour License Not complied for 02 BJR 02B Informed Contractor and EE to provide the same
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-11
Attachment 3 – Bijapur Photographs
02BJR02
LOCATION : Golgumbuz Road
DATE : 14-12-2011
LOCATION : Stadium Road
DATE : 22-12-2011
Dust Control measure
Workers wearing Helmets - Sewerage works
02 BJR02A
LOCATION : Shekh Colony
DATE : 02-12-2011
LOCATION : Shakti Nagar
DATE : 20-12-2011
No Safety Measures provided
No Barricades provided
02BJR02B
LOCATION : Tappal Layout
DATE : 28.12.2011
LOCATION : Kulkarni Layout
DATE : 01.12.2011
Helmets being used during concrete work for
DG Room
No Safety measures
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-12
4 EMP for Hubli-Dharwad
4.1 Introduction – Hubli - Dharwad
The components taken up for Hubli are detailed in the following Table.
Package Sub Project Physical Completion
(%)
Date of
Award
Date of Completion
02 HUB02 Sewer Trunk Main (Zone 2) 9 10.03.2011 09.09.2012
02 HUB 02A Sewer Trunk Main (Zone 1 & 3) 9 10.03.2011 09.09.2012
02 HUB 02B STP Turnkey Design phase 16.03.2011 02.05.2013
The Initial Environmental Examination (IEE) Report was approved by ADB in the year 2009. The status of
Environmental Management Plan (EMP) for the month of December 2011 are presented in the following
sections.
4.2 Permissions/Consents/Clearances/Approvals:
Particulars Sub
Project
KSPCB Railways NH PWD KPTCL /
HESCOM
Forest Minor
Irrigation
Irrigation*
Consent/Clearances/
Permissions/Approval
Status (Obtained – √
Not Obtained X)
UGD &
STP
√ X X √ √ NA NA NA
Note: For details refer Monthly Progress Review Meeting Dec 2011.; NA-Not Applicable; * for drawal for water from reservoir for demand of year 2041/2044
4.3 Field Visits & Training Conducted
Field
Visit
Date Sites Visited Persons Met Remarks
29 Dec.
2011
02 HUB 02
Sewer pipes laying at
SM Krishna Nagar,
Channapet,
Torvihakkal,
• Mr. R.A. Honna Kasturi, AEE, NKUSIP
Cell, Hubli
• Mr. S. Hariharan, Construction Supervision
Specialist, PC
• Mr.M.H. Pochetti, AE, NKUSIP Cell
• Malatesh N. Guden, Project Manager, Mr.
Ankush, Site Engineer, Mr.Samer Desai,
Mr. Sushanth, Mr. Umesh Desai of Eagle
Construction Co., Kolhapur
• Mr. S. B. Hadimani, RE, PC
Excess soil on roads to
be removed.
Drains filled up with
soil to be cleaned.
No water sprinkling
done. No first aid
facility at site
Helmets are provided.
02 HUB 02A
Vanivilas Circle,
Hunkal Bypass
road, Akshaya
colony road Chetana
college,
Tolankere lake
Heggeri road
• Mr. S L. Patil, AEE, NKUSIP Cell, Hubli
• Mr. S. Hariharan, Construction Supervision
Specialist, PC
• Mr.M.S. Hiremutt, AE, NKUSIP Cell
• Mr. Nagaraj Mahantashettar, Project
Manager, Sunil, Kiran Kumar, Sanjay C
hougule Site Engineer, Eagle Construction
Co., Kolhapur
• Mr. Ramesh Badiger, RE, PC
Helmets & First aid
facility exist.
No barricades near
Akshaya colony and
Tolankere lake
02 HUB 02B
STP, Gabbur • Mr. S L. Patil, AEE, NKUSIP Cell, Hubli
• Mr. S. Hariharan, Construction Supervision
Specialist, PC & Mr. Prabhakara, RE, PC
• Mr.Anil Kumar, AE, NKUSIP Cell
• Mr. B. Sarkar, Project Manager, Mr. V.R.
Prasad, Mr. P. Mukherji, Mr. Sitaram, Site
Engineer of SN Enviro- Tech Pvt. Ltd..,
Delhi
No first aid facility
No barricades and
buffaloes movement is
seen inside the site.
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-13
Date Location Nature of Training Participants
Train
ing
29 Dec.
2011
STP Site, Gabbur On the job training on the
importance of Safety aspects
was held
7 Participants : Mr. B. Sarkar, Project Manager,
Mr. V.R. Prasad, Mr. P. Mukherji, Mr. Sitaram,
Site Engineer of SN Enviro- Tech Pvt. Ltd..,
Delhi. Mr. S. Hariharan, Construction
Supervision Specialist, PC & Mr. Prabhakara,
RE, PC and Mr. M.H. Pochetti, AE, NKUSIP
5 Nov.
2011
Torvihakkal, KK
Nala, Devangpet
Nala,Vanivlas circle
On the job training on the
importance of Safety of
workers and safety of public
was held
9 Participants :Ashpak, Raju Manwani, Nitesh,
Sunil, Kiran Kumar, Sanjay Chougule of Eagle
Constr. Prabhakara & Ramesh Badiger RE, PC,
M.H. Pochetti, AE, NKUSIP
16 Jun
2011
Conference Hall, RO,
Hubli Orientation Program for
Implementing Agency & EA
43 participants attended. Detailed list see
Annexure 3 of August EMP Report
4.4 Compliance to EMP
Particulars Sub Project Complied Compliance to EMP
Design/Location/
Preconstruction Stage
Monitoring
Sewerage System.
& STP √
Details on EMP page 46 of Initial Environmental Report, October
2009, is made part of Contractor Agreement, viz.,
Page No. 43-44 (02 HUB 02), Page No. 46-47 (02 HUB 02A)
Page No.417-418 (02 HUB 02B)
Construction Stage
Monitoring
Sewerage System √
Contractor complying with EMP. Also see Annexure 7, 8, & 9
Occupational Health
Risks and Safety Plan
for Workers
Sewerage System
& STP √
Contractor complying with EMP. Also see Annexure 7, 8 & 9 and
photographs Attachment 4.
4.5 Redress of Grievances
Sub Project Registers Maintained No. of Grievances received
in the month
Action Taken
02 HUB02 √ 2 Attended all the four complaints
02 HUB 02A 2
4.6 Labour Registration
The Contractors have submitted the licenses and the same is detailed out under
4.7 Summary and Conclusions
EMP monitoring being done daily (see Annexure 7, 8 & 9) on the critical issues and following improvements/
positive developments are observed.
Sl Details Compliance Status
1 Display of IEE Executive Summary in Kannada on Notice Board of
NKUSIP Cell office and CMC office
Complied on 18.08.2011
2 KSPCB’s CFE Condition (V.7), the ULB shall furnish point-wise
compliance to the conditions within 30 days to KSPCB
Complied on 04.06.2011
3 As per the KSPCB’s CFE Condition (3), there shall not be any
complaints against the Corporation from surrounding public, and vide
I.8, the City Corporation shall take measure to develop green belt in the
periphery.
EE, NKUSIP Cell vide their letter dated
24.10.2011 had submitted an application to
Commissioner, HDUDA for earmarking 500
m as Buffer zone around STP.
4 Documentation mechanism of grievances by opening the Grievances
register
Complied
5 Labour License Complied for all three packages
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-14
However, the following issues need to be addressed.
Sl Issues/Deviations Compliance Status Corrective Actions to be taken
1 02 HUB 02: The excess soil on roads to be
removed and leveled to avoid accidents at
S.M. Krishna Nagar
The drains filled up with soil at Channapet near
Channa Basaveshwara Park to be cleaned.
No water sprinkling done for Dobhighat road..
Yet to be complied. Informed Mr. Malatesh N. Guden, Project
Manager, Mr. Ankush, Site Engineer,
Mr.Samer Desai, Mr. Sushanth, Mr. Umesh
Desai of Eagle Construction Co., Kolhapur
to comply the same
2 02 HUB 02A: No barricades near Akshaya
colony and Tolankere lake
Yet to be complied. Informed Mr. Nagaraj Mahantashettar,
Project Manager, Sunil, Kiran Kumar,
Sanjay C hougule Site Engineer, Eagle
Construction Co., Kolhapur to comply the
same
3 02 HUB 02B: Compound wall under
construction and no caution board and no barricades to stop buffaloes movement inside the
site.
Yet to be complied. Informed Mr. B. Sarkar, Project Manager,
Mr. V.R. Prasad, Mr. P. Mukherji, Mr.
Sitaram, Site Engineer of SN Enviro- Tech
Pvt. Ltd.., Delhi to comply the same.
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-15
Attachment 4
PACKAGE – 02 HUB 02
LOCATION : Kamaripet Road
DATE : 17.12.2011
LOCATION : Channapet Road
DATE : 16.12.2011
LOCATION : Aravind Nagar Road
near Channa Basaveswara Park
DATE : 27.12.2011
Dust suppression by watering Workers wearing Helmets
Barricading
PACKAGE – 02 HUB 02A
LOCATION : Devangpet Nalla
DATE : 19.12.2011
LOCATION : Vani vilas Road (Hosur)
DATE : 22.12.2011
LOCATION : Vani vilas Road (Hosur)
DATE : 22.12.2011
Workers wearing Helmets
Barricades and Direction Board
Road cleaning & removal of
excavated Soil materials
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-16
5 Monitoring Sheets (Received on 05.01.2012)
Annexure 1 Daily Monitoring Sheet – Haveri Water Supply
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-17
Annexure 2
Daily Monitoring Sheet – Sewerage System, Haveri
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-18
Annexure 3 – Daily Monitoring Sheet
Ranebennur Sewerage System
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-19
Annexure 4 - Daily Monitoring Sheet – Sewerage System, Bijapur (02 BJR 02)
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-20
Annexure 5 - Daily Monitoring Sheet – Sewerage System, with STP - Bijapur (02 BJR 02A)
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-21
Annexure 6 - Daily Monitoring Sheet – Sewerage System, Bijapur (02 BJR 02B)
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-22
Annexure 7 - Daily Monitoring Sheet – Sewerage System, Zone 2 Hubli (02 HUB 02)
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-23
Annexure 8 - Daily Monitoring Sheet – 02 HUB 02A - Sewerage System - (Zone 1&3), Hubli
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-24
Annexure 9 -
Daily Monitoring Sheet – 02 HUB 02B - STP, Hubli
Design Phase – Turnkey Package
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-25
6 Status of Clearances/Approvals
6.1. NH clearances received for Bijapur
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-28
6.2 Davanagere Permissions/Consents/Clearances/Approvals – Water Supply
Sl Line Departments Consent/Clearances/
Permissions/Approval
Status
(Obtained – √
Not Obtained X)
Remarks
1 KSPCB NA NA
2 National Highway (NH) X Awaited - Copy enclosed in November
2011 report
3 Panchayath Raj X Awaited - Copy enclosed in November
2011 report
4 APMC, Harihar √ Copy enclosed in November 2011 report
5 PWD X Awaited
6 Irrigation √ Copy enclosed in November 2011 report
7 Minor Irrigation √ Copy enclosed in November 2011 report
8 KPTCL / ESCOM X
9 Forest NA
Note: For details refer Monthly Progress Review Meeting Dec 2011.; NA-Not Applicable; * for drawal for water from reservoir for demand of year
2041/2044
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-29
6.3 Status of Clearances/Approvals – Gadag - Betageri
Sl Line Departments Consent/Clearances/
Permissions/Approval
Status
(Obtained – √
Not Obtained X)
Remarks
1 KSPCB NA NA
2 National Highway (NH) X Permission accorded for 3.4 kms on
NH-63 on 30 Nov 2011 by Chief
Engineer, NH, Bangalore
3 State Highway (SH) X Permission from KSHIP is required to lay
pipe line from Advi Somapur to Mundargi
4 PWD X Awaited Permission from PWD,
Mundargi Sub Division
5 Irrigation √ Approval for withdrawl of 50 MLD water
issued vide Government Order dated
29.01.2011
Approval has been given for Hammigi
barrage site - extent of 0.35 acre for
construction of Intake & Jackwell
6 Minor Irrigation NA
7 KPTCL / HESCOM √ Approval awaited
8 Forest
Note: For details refer Monthly Progress Review Meeting Dec. 2011.; NA-Not Applicable; * for drawal for water from reservoir for demand of year
2041/2044
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-31
7 Display of Executive Summary of IEE, in Kannada
Provided in November 2011 EMP Report
Report on Environmental Management Plan (EMP) – December 2011
KUIDFC WSAPL-32
8 Labour Registration
The status of submission of Labour Licenses and its validity are presented below;
Town Submission Status License Period Reference
Ranebennur 02RNR02 - Submitted 01.04.2011 - 31.03.2012 EMP Report of October 2011.
Bijapur 02BJR02 - Submitted
02BJR02A - Submitted
02BJR02B – Not Submitted
01.04.2011 - 31.03.2012
01.04.2011-31.03.2012
Nil
EMP Report of October 2011.
EMP Report of October 2011
Nil
Hubli 02HUB02 - Submitted
02HUB02A - Submitted
02HUB02B- Submitted
14.03.2011-13.03.2012
14.03.2011-13.03.2012
31.05.2011-02.05.2013
Enclosed in this Report
Enclosed in this Report
Enclosed in this Report
Haveri 01HVR01 – Not Submitted
01HVR02 – Not Submitted
Nil
Nil
Nil
Nil