46
Coastal Cities Control Pollution Project Environmental Management Plan 1 COASTAL CITIES POLLUTION CONTROL PROJECT Loan 7226/HR Environmental Management Plan Waste Water Treatment Plant and Sewerage System Vodice – Srima - Tribunj Zagreb, May 2008. E1933 v2 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

  • Upload
    buidiep

  • View
    215

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

1

COASTAL CITIES POLLUTION CONTROL PROJECT

Loan 7226/HR

Environmental Management Plan

Waste Water Treatment Plant and Sewerage System Vodice – Srima - Tribunj

Zagreb, May 2008.

E1933v2

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Page 2: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

2

C o n t e n t s Chapter 1. Introduction .....................................................................................................3 Chapter 2. Project description, purpose and envir onmental impact ...........................6 2.1. Project description and objectives ....................................................................6

2.2. Input data and facility sizing …………………………...………………................ 6 2.3. Environmental impact .......................................................................................9 2.3.1. Particular importance of discharging of treated water into ground ...................9 2.3.2. Existing data about measurements and sea water quality ............................12 2.3.3. Environmental impact and prevention measures ...........................................15 Chapter 3. Institutional framework ................................................................................19 Chapter 4. Environmental impact mitigation plan .......................................................20 Chapter 5. Monitoring plan .............................................................................................21 Chapter 6. Proposal for cooperation with the publ ic ...................................................22 Chapter 7. Appendices ...................................................................................................23 7.1. General layout 7.2. Plan of avoiding adverse environmental impact (Mitigation plan) 7.3. Monitoring plan 7.4. List of laws and bye-laws relevant to environmental protection in the Republic of Croatia

Page 3: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

3

CHAPTER 1. INTRODUCTION

The International Bank for Reconstruction and Development (IBRD) offered a loan to the Republic of Croatia for financing of the improvement of sewerage systems and wastewater treatment for settlements along the Adriatic coast and islands, i.e. financial support for the realization of the Program called the Costal Cities Water Pollution Control Project.

The Program is of a regional character and shall be realized on the coastal area with a high potential for tourism, important for the economic development of the Republic of Croatia, and it is planned to be realized on the principle of active participation of local authorities in cooperation with competent government agencies.

The International Bank for Reconstruction and Development (IBRD) and the Government of the Republic of Croatia have concluded a Loan Agreement (Loan no. APL 7226 HR) on July 2, 2004, in Zadar.

The Project Agreement was signed in Zadar on the same day between the International Bank for Reconstruction and Development (IBRD) and Hrvatske vode, by which Hrvatske vode have taken over the obligation towards the International Bank for Reconstruction and Development for the implementation of the Project.

The Program shall be carried out by Hrvatske vode PIU, named Hrvatske vode Jadranski project.

Implementation of the Program is planned in three stages, and the first stage of the Program shall be implemented in the period of four years (from 2005 to 2008). The total estimated cost of realization of the Program is ca € 280 million, and the value of the first stage is ca € 80 million. Value of the second stage is planed in ca € 120 million.

The primary objectives of the Program are protection of seawater quality, creating conditions for a safe economic development in accordance with the objectives of environmental protection and protection and improvement of the achieved level of environmental protection.

The basic developmental objective of the Program is to improve the quality of coastal water in the Croatian Adriatic and meet EU standards regarding the quality of environment in local communities.

Consistent with the scope and objectives identified above, the Program has three components: 0. Coastal Environmental Infrastructure component 1. Institutional Strengthening and Program Management Component to finance equipment,

technical assistance 2. Strengthening of the Coastal Waters Monitoring Network to finance equipment, civil

works and technical assistance

The key elements of the first and second phase of the Program are:

) Expansion of the sewerage network, adequate treatment and disposal of sanitary wastewater;

) Improvement of operation and management in municipal water and sewerage companies;

) Reform of financial and control instruments for wastewater disposal infrastructure.

Page 4: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

4

Eleven subprojects are realized in first phase of implementation of the Program on the coastal area, The subprojects proposed for financing in Phase II of implementation of the Program are related to the 35 cities on the coastal area.

The World Bank appraises each project proposed for financing on the basis of social procedures and environment protection procedures, so-called ˝Safeguard Policies˝.

Contents of the Environmental Impacts Studies are defined considering Safeguard Policies of the Coastal Cities Water Pollution Control Project, by Ordinance on Environment Impact Assessment (Uredba o procjeni uljecaja zahvata na okoliš, NN 64/08), Operation manual – Environmental Framework and the corresponding feature of World Bank procedures.

Environmental Assessment has to be done in combination with EMP. According to the general definition, EMP may be described as a set of measures for elimination, avoiding or reducing adverse environmental and social impact of certain interventions in environment during construction, operation or removal. Interventions in environment are permanent or temporary human activities that may disturb ecologic stability or biodiversity, or cause any other adverse impact. This plan should define certain activities in order to implement preventive and protective measures, and to establish the system of monitoring of environmentally relevant parameters.

Page 5: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

5

THE PROJECT

In connection with the Vodice-Srima-Tribunj sewerage system and waste water treatment plant, the following procedures were followed, in accordance with the Croatian law:

• Preparing of the Environmental Impact Study, according to Croatian regulations, • Procedure of acceptance of the Study – including public hearing • Issuing of corresponding decisions or permits of the Ministry of Environmental Protection,

Physical Planning and Construction

In accordance with environmental legislation, there is an obligation of assessment of environmental impact for interventions defined by the Ordinance on Assessment of Environmental Impact (OG No 64/08). The scientific basis for assessment of environmental impact is the Environmental Impact Study, which has to be worked out for eight types of interventions into the environment: construction of facilities for transport, power, water supply, industry, sports, waste water treatment, structural complexes (commercial centers), and mining.

The study of environmental impact of the sewerage system and waste water treatment in Vodice was made and issued in 2004. The procedure of study acceptance was conducted in accordance with Croatian regulations.

Also, in 2007, the Executive Summary had been prepared by Institut građevinarstva Hrvatske dd, Poslovni centar Split, according to Procedure C (see Operation Manual – Vol. III - Safeguard Policies).

This Environment Management Plan has been worked out in accordance with environmental policies of the World Bank, the document Operation Manual – Volume III – Safeguards Policies of the Coastal Cities Control Pollution Project, and with the legislation of the Republic of Croatia, and it completes the documentation related to assessment of environmental impact of the sewerage and waste water treatment system in Vodice.

Following the reviewing of the existing documentation by the World Bank, it has been agreed that Hrvatske vode will prepare the EMP according to the Bank’s procedures.

Page 6: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

6

CHAPTER 2. PROJECT DESCRIPTION, OBJECTIVES AND ENV IRONMENTAL IMPACT 2.1. Project description and objectives

Construction of the public separate-type sewerage system is planned in the area Srima - Vodice - Tribunj. Trunk sewer, extending along the coast, will collect wastewater by gravity and transport it to the local pumping stations where wastewater will be pumped to the wastewater treatment plant in the area of Mrzanac. Treated effluent will be discharged from the wastewater treatment plant via long submarine outfall that will be situated southwest of the straight between Lukovnik and Logorun islands into the Kaprijski channel.

Basic sewerage network comprises eight local pumping stations with the appurtenant rising mains (3,2 km total length) and gravity main sewers (6,5 km total length). Apart from main sewers, secondary network will also be constructed. About 35.000 p.e. will be connected to the system; thus primary treatment is required for effluent discharged into the Kaprijski channel (less sensitive area). Necessary space shall also be reserved at the WWTP site for potential extension to the secondary treatment.

The Šibenik-Knin County Council has adopted the project concept elaborated in the study „Water Protection Study in the Šibenik-Knin County“ (Hidroprojekt-ING, 2000), based on the Preliminary design (Hidroprojekt-ing, 1997.g.) for the area Srima - Vodice - Tribunj, with the planned separate-type common public sewerage system. Central wastewater treatment plant is planned in the Mrzanac area. Submarine outfall with the diffuser will be situated southwest of the strait between the islands Lukovnik and Logorun into the Kaprijski channel.

1.1. Input data and facility sizing

Wastewater quantities and characteristics

Planned number of public sewerage system users at the end of the design period: Summer Winter Population 8.850 PE 8.850 PE Hotel guests 8.750 PE 4.000 PE Tourists in private and 17.750 PE 3.000 PE other accommodation Total 35.350 PE 15.850 PE

Wastewater quantities have been estimated at 80% of daily consumption; thus average daily wastewater quantity shall be Q = 3.650 m3/day and Q = 8.120 m3/day in winter and summer, respectively.

Wastewater load estimated based on ATV 131 guidelines.

Table: Wastewater load Indicator Winter Summer BOD-5 (mg O2/l) 260 263 COD (mg O2/l) 521 525 SS (mg/l) 304 306 Nuk (mg N/l) 48 48 Puk (mg P/l) 11 11

Page 7: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

7

In the area of interest, apart from population and tourist, Oil Mill – Tribunj is another source of pollution. According to the Water permit, Oil Mill - Tribunj is obliged to treat wastewater before discharge into the public sewerage system, all in compliance with the Regulations on Limit Values of Parameters, Dangerous and Other Substances in Wastewater (OG No. 40/99, 6/01).

Sizing of sewerage system components

Mains can be divided to gravity mains and rising mains. Gravity mains:

• ø 300 mm 2,0 km • ø 400 mm 1,0 km • ø 500 mm 2,5 km • ø 600 mm 1,0 km

Rising mains: • ø 300 mm 1,9 km • ø 400 mm 0,6 km • ø 500 mm 0,7 km

There are 8 pumping stations, situated at the trunk sewer alignment along the coast.

Wastewater treatment plant Required area for WWTP construction phase I. (primary treatment) is 0,20 hectares. Area for primary (I) and secondary (II) treatment is estimated at 0,50 ha. Rectangular area of 50 x 100 m should be foreseen.

Two treatment lines are foreseen. Primary treatment will comprise the following. • floating matter removal • suspended solids reduction • reduction of oils i.e. organic matter portion.

Basic components of primary (I) treatment WWTP are the following: • automatic coarse screens, • automatic fine screen, • grit-grease removal

The following components shall be added to expand the WWTP to secondary (II) treatment (optional):

• biological tank • secondary settling tank • sludge thickener • mechanical sludge dewatering

Submarine outfall Submarine outfall with the diffuser is planned, in the length of 1900m. In fact, the waste waters planned to be discharged into the sea will first be treated to a certain treatment stage and only then discharged in a carefully selected location.

One of the objectives in the waste water discharge is to endeavor to make the discharge to the water column under the pycnocline.

Page 8: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

8

If this objective can be achieved, then the probability of waste waters reaching the sea surface will be small. It has been found out, however, that during summer cyclonic changes the complete homogenization of water column can take place in the southern shallower parts of the Channel. In such conditions, waste waters could come up to the sea surface and be taken by wind-driven surface currents to the nearby shore in a relatively short period of time.

The outlet location, the conditions of waste water discharge and the treatment stage have been determined taking into account the following:

a) The area to be protected by applying the existing standards for the sea quality. b) The outlet end must be located in a predetermined area. c) The initial dilution requiring the outlet opening to be as far as possible from the

protected area. d) The use of the diffuser enabling to increase initial dilution, i.e. with the openings

of Ø 10-15 cm. e) The dilution at the boundary of the 250-300 m wide sea body of minimum

100.000 with the initial dilution, the secondary dilution (circulations) and bacteria decay (T90 of 2,5 h).

f) The circulation velocity toward the shore of 10 cm/s. g) The flow rate in the outlet to be about 1 m/s, and in the diffuser 2 m/s.

Figure1. Route of performed hydrographic measurements and geological investigation

Page 9: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

9

2.3. Environmental impact 2.3.1. Particular importance of discharging of trea ted water into see – Kaprijski Channel

Water protection is implemented by prescribing the quality of water defined in regulations referring to: - the water recipient, - discharged wastewaters.

Regulations referring to the water recipient govern the purpose and method of water usage (National Water Protection Plan NN 8/99 and Regulation on Classification of Waters NN 77/98). Criteria for maximum allowed concentrations of wastewater are determined based on scientific researches, as well as laboratory and «in situ» monitoring of indirect and direct impact of hazardous and toxic substances on human organism.

Allowed concentrations have been selected so as not to disturb the natural representation of species of organisms and their development stages, at the same time enabling the preservation of all existing natural characteristics of water courses and the sea.

Regulations referring to discharged wastewaters:

- Regulations on Boundary Values of Parameters of Hazardous and Other Substances in Wastewaters (NN 40/99) determine the allowed concentrations of individual toxic and hazardous substances in wastewater after the treatment process of such waters.

- Regulations on Modifications and Amendments of Regulations on Boundary Values of Parameters of Hazardous and Other Substances in Wastewaters (NN 06/01) refers to wastewater discharge into the sea and, among amendments, in Article 3 the document expands Article 4, Paragraph 1 for Items e) and f), as follows:

e) the sea, with wastewater discharge via a marine outfall into «less sensitive areas» (an area with good exchange of water mass not susceptible to eutrophication or oxygen reduction or having low probability to become such due to wastewater discharge from public drainage systems),

SIZE OF PLANT TREATMENT DEGREE under 10.000 EP appropriate

10.000 to 50.000 EP First (I) over 50.000 EP first (I) + second (II)

f) the sea, with wastewater discharge via a marine outfall into «sensitive areas» (an area with poor exchange of water mass susceptible to eutrophication or having high probability to become such due to wastewater discharge from public drainage systems),

SIZE OF PLANT TREATMENT DEGREE under 10.000 EP first (I)

10.000 to 50.000 EP first (I) + second (II) over 50.000 EP first (I) + second (II) + third (III)

⇒ in case the sensitivity of the Kaprijski Channel changes (increases).

Page 10: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

10

The above Regulations determine the treatment degree for the WWTP Vodice – First degree Wastewater Treatment Plant since the Kaprijski Channel is a «less sensitive area».

The application of these Regulations ensures the monitoring of the discharge of waste substances by each individual contaminator, as well as the control of operation of the wastewater treatment plant.

Both previously described aspects of water protection are interrelated, i.e. the concentration of waste substances in wastewater prior to the discharge into the recipient shall directly impact the concentration of pollutants in the recipient. Consequently, efficient implementation of water protection requires the control of the allowed concentration of pollutants in wastewater, enhanced by the control of maximum allowed values of hazardous and toxic substances in the water recipient.

These Regulations and Decrees define the requirements on the allowed concentration of hazardous and toxic substances in discharged wastewaters and the water recipient, i.e. their application represents only the basis of an integral program of control and preservation (or upgrading) of the quality of the coastal sea with the final goal to ensure and upgrade the natural environment in which we live.

The required wastewater treatment degree at the Vodice-Srima-Tribunj Riviera - Wastewater Tr eatment Plant Vodice According to the sensitivity of the recipient (the Vrgada Channel sea) and the size of the plant for individual phases of construction, and the National Water Protection Plan (NN 8/99), the required treatment degree is: PHASE I (N = 22.000 PE) For: Plant size of 10.000÷50.000 EP Recipient category: «less sensitive sea»

Treatment degree: First (I) treatment degree with the provision of a marine outfall

In the next development phase of the BIOGRAD n/r “KUMENAT” WTP, at this location the following shall be constructed: PHASE II (N = 44.000 EP) For: Plant size of < 50.000 EP Recipient category: «less sensitive sea» Treatment degree:

First (I) treatment degree with the provision of a marine outfall

The boundary values of parameters of wastewater discharged into a natural recipient from a wastewater treatment plant after a given treatment degree are specified by the Regulations on Boundary Values of Parameters of Hazardous and Other Substances in Wastewaters (NN 40/99) and the Regulations on the Modifications and Amendments of the Regulations on the Boundary Values of Parameters of Hazardous and Other Substances in Wastewaters (NN 06/01), as follows:

TREATMENT DEGREE PARAMETERS BOUNDARY VALUE

I Total suspended matter 120 – 150 mg/l

Page 11: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

11

Treatment efficiency (%):

"first (I) degree" of treatment PHASES

I and II Boundary

value Upon

treatment Treatment,

%

Minimum reduction of

inflow loading, % BPK5 271 mg/l → 21o mg/l 20% ≥ 20% KPK 525 mg/l → - - - - R.T. 300 mg/l → 150 mg/l 150 mg/l 50% ≥ 50% b.c. 108/100 ml → - - - -

Submarine outlet The use of the long submarine outfall with an adequate treatment level is rational, having in view the proved self-cleaning capacity of the sea as a recipient, i.e. its power to reduce the bacteriological pollution that is difficult to eliminate by various technical and technological processes. The natural properties of the sea water offer the possibility for the sea as a recipient to participate, under certain discharge conditions, in further degradation of organic matters without any danger for the ecological stability of the marine environment at the discharge site. That is noticeable especially with smaller drainage systems.

To design the submarine outfall and to define its exact position, it is necessary first to make a hydrographic study containing all data on the sea bottom geology, prevailing winds and local currents at the foreseen location. Based on the data from the hydrographic study, and taking into account the sea water categorization in the zone of effluent impact and in the area outside the circle with a radius of 300 m around the outfall diffusors (the National Water Protection Plan requires the sea water outside the radius of 300 m around the outfall difussors to be of category II) as well as the forbidden zone of 300 m from the coast-line for sports and recreation, the exact length and position of the submarine outfalls and their related diffusors will be determined.

A diffuser is recommended in order to achieve required dilution even for small settlements. Guidelines for diffuser design are given hereinafter (UNEP, 1995): - diameter of diffuser orifices shall not be under 10 to 15 cm, - recommended distance between diffuser orifices shall be equal to one forth of the sea

depth - discharge velocity from diffuser orifices shall be about 2 m/s.

Wastewater treatment plant of the planned 44.000 PE (22.000 PE – Phase I) capacity and ”first degree” will be constructed, complete with the submarine outfall for effluent discharge into „less sensitive area“.

In compliance with the adopted wastewater quantities, Conceptual Design foresees construction of submarine outfall of about 1.900 m total length. Assumed diameter of HDPE pipes will be Ø 500 mm.

Submarine outfall direction and length have been defined in the Hydrographic Study “The results of research works at the submarine outfall alignment of the Vodice-Srima-Tribunj public sewerage system” («Rezultati istraživačkih radova trase podmorskog ispusta otpadnih voda sustava javne odvodnje naselja Primošten») HHI, August, 2003.

Page 12: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

12

2.3.2. Existing data about measurements and sea water quality

0. Bathing water quality standards in the marine en vironment of Vodice

The data on bathing water quality (data from EIA) in the area of the Town of Vodice i.e. Srima, Vodice and Tribunj settlements are given. Sampling and testing has been carried out according to the Regulation on Bathing Water Quality Standards (OG No. 33/96) during 2001 and 2002 bathing seasons.

Table 1. Bathing water quality in the area of the Town of Vodice in 2001.

Code Gauging station Sampling No. Assessment Cate-gory

3066 Srima, settlement 10 sea suitable for bathing 2 3067 Srima, Lovetovo 10 sea suitable for bathing 2 3068 Vodice, "Imperial" hotel 10 sea suitable for bathing 2

3069 Vodice, "Olimpija" hotel 10 sea under temporary pollution impact

3

3070 Vodice, Hangar 10 sea under temporary pollution impact 3

3071 Vodice, Odmaralište (holiday resort) 10 sea under temporary

pollution impact 3

3072 Vodice, "Punta" hotel 10 sea suitable for bathing 2

3073 Vodice, Plava plaža (Blue beach)

10 sea suitable for bathing 2

3074 Tribunj, Zamalin 10 sea suitable for bathing 2 3075 Tribunj, Sovlja 10 sea suitable for bathing 2

In addition follows water quality in the area of the Town of Vodice in 2007., disclosed on the MEPPPC’s web site.

Table 2. Bathing water quality in the area of the Town of Vodice in 2001.

Code Gauging station Sampling No. Assessment Cate-gory

3066 Srima, settlement 9 sea suitable for bathing 2 3067 Srima, Lovetovo 9 sea suitable for bathing 2 3068 Vodice, "Imperial" hotel 9 sea suitable for bathing 2 3069 Vodice, "Olimpija" hotel 9 sea suitable for bathing 2 3070 Vodice, Hangar 9 sea suitable for bathing 2

3071 Vodice, Odmaralište (holiday resort)

9 sea suitable for bathing 2

3072 Vodice, "Punta" hotel 9 sea suitable for bathing 2

3073 Vodice, Plava plaža (Blue beach)

9 sea suitable for bathing 2

3074 Tribunj, Zamalin 9 sea suitable for bathing 2 3075 Tribunj, Sovlja 9 sea suitable for bathing 2

Page 13: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

13

2. Oceanographic data

Figure 2. Map of Oceanographic measurements (OC) and See currents measurements (ASS) in the area of the submarine outfall

Oceanographic measurements carried out to determine oceanographic characteristics of the marine environment of Srima - Tribunj – Vodice sewerage system outfall comprised measurements of sea currents at two gauging stations, measurements of vertical profiles of temperature, salinity and density at 10 stations as well as seawater sampling at 3 stations, in order to determine nutrient concentrations, pH-values and dissolved oxygen (% of saturation). The study also analyzed the data on sea levels registered at the Zadar-Gaženica mareographic station, which is being representative for the researched area, the data on visual observation from ships (database of HHI - Croatian Hydrographic Institute) as well as measurements of surface waves generated by wind in the broader marine environment of the outfall. Measurements were carried out in the period from September 11th 2001 to October 10th 2001. Thermohaline characteristics Vertical temperature profiles point to homogeneity to about 15 m depth. Developed thermocline has been observed in the layer between 15 and 23 m. At the stations situated east, thermocline is even more pronounced and starts at about 18 m depth. Under the thermocline, temperature gradually decreases to the seabed. Seawater temperature in the layer by the thermocline ranges between 19,5 and 19,7oC. Temperature is constant to the thermocline (which is situated between 15 and 23 m depth), then it decreases and ranges from 15,4 and 15,7oC close to the seabed. In the surface layer salinity ranges from 37,9 and 38,1‰ and increases towards the seabed to be about 38,4‰. Seawater density, which depends on the sea temperature, salinity and depth (pressure) has similar vertical distribution as seawater temperature, except near the surface where somewhat

Page 14: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

14

smaller salinity causes lower density. Seawater density ranges between 1.027,1 and 1.027,2 kg/m3 in surface layer and about 1.028,5 kg/m3 in bottom layer. Sea currents In the broader area of Vodice, average daily oscillation of sea level (average amplitudes of the tides) is 26 cm. At the station ASS-1, maximum measured current velocities were 31 cm/s in the surface layer (3 m) and 19 cm/s in the bottom layer (46 m). Average current velocities were 5,5 cm/s (3 m) and 2,6 cm/s (46 m). The resulting direction of surface currents was NW , while S was the resulting direction of bottom currents. Stability factors in the surface and bottom layers were 21,7% and 35,4%, respectively, which points to great variability of sea current directions, in particular in surface layer. At the station ASS-2, maximum measured current velocities were 37 cm/s in the surface layer (3 m) and 13 cm/s in the bottom layer (58 m). Average current velocities were 9,1 cm/s (3 m) and 2,3 cm/s (58 m). The resulting direction of surface currents was NW, while WSW was the resulting direction of bottom currents. Stability factor in the surface layer is relatively high (59,8%), and lower in the bottom layer (38,1%). It points to relatively stable sea current direction in surface layer and less stable one in bottom layer. As can be concluded from the current rose, about 23% of the surface current field and about 8% of the bottom current field were directed onshore. In fall-winter period of the year (November-March), the most frequent are the waves generated from SE direction, with the usual heights from 0,5 to 1,5 m, although maximum wave height up to 3,5 m were recorded in the broader marine environment of the Srima - Tribunj - Vodice sewerage system outfall. Frequent are also waves generated from NE direction with the maximum height up to 2,5 m. Nutrient concentrations The highest nitrite concentrations were recorded at the station ASS-2 at 50 m depth (0,197 mmol/m3). Maximum nitrate concentrations (0,401 mmol/m3) were also registered at the same gauging station. The highest orthosilicone concentration (0,752 mmol/m3) was recorded at 50 m depth as well as the ammonia (0,706 mmol/m3) on the surface at the station ASS-1. The highest orthophosphate concentration (0,036 mmol/m3) has been registered at the surface of the station OC-1. The minimum dissolved oxygen (% of saturation) (90,76%) has been registered on the surface at the station OC-1. The maximum dissolved oxygen (% of saturation) (97,44%) has been registered at 20 m depth at the station ASS-1. Recorded pH values ranged from 8,25 to 8,27. Eutrophication level assessment Nutrient concentrations, dissolved oxygen (% of saturation) and pH-value, and their vertical distributions recorded at the stations OC-1, ASS-1 and ASS-2 were within the limit values recorded at open sea (Zore - Armanda, et al, 1991). Thus, it all points that there was no eutrophication caused by antropogeneous activities at the researched location.

Page 15: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

15

2.3.3. Environmental impact and prevention measures Potential adverse environmental impacts may occur:

• during construction, • during system operation, • due to accidents and failure in operation.

0. Environmental impacts during construction Noise

During construction works, noise will be emitted by construction machinery, vehicles for transport of material and equipment, plants, manpower transport vehicles etc. Noise level can exceed allowable limits on and outside the construction site, permanently or periodically.

Air pollution

Airborne particles carried by wind as a consequence of dusting, caused by earth and other works at the construction site.

Loose material carried by wind from transport vehicles and exhaust gases from construction machinery.

Soil pollution

Disposal of surplus excavated earth material on surfaces not intended nor prepared as landfill. Oil and lubricant spill from construction machinery and vehicles. Washing and transport of loose material scattered over carriageway by precipitation.

Seawater pollution

Excavation of the outfall trench could cause seawater pollution by increased turbidity and transport of fine particles by sea currents and their settling outside the project impact area.

Impact on flora and fauna

During construction of facilities and installations, parts of the existing habitat will be damaged, which will adversely impact the organisms settling within the WWTP site.

Submarine works will destroy parts of benthos communities and disturb the nutrition of pelagic communities.

Impact on existing facilities

During construction, possible are damages to municipal utilities (water supply, power supply…).

Impact on traffic

During laying of sewerage system mains along and/or under the existing asphalt roads, traffic will be disturbed.

Page 16: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

16

0. Impacts during system operation Flora and fauna

Flora and fauna of the existing terrestrial habitat will change. Some of green surfaces will be replaced by solid surfaces. Due to changes in habitat conditions, some species will desert the existing habitats.

Changes in benthos communities are possible in the diffuser vicinity.

Odors

Evaporation or vaporization of odorous gases and vapors (ammonia, amine, hydrogen sulfide, merkaptans, hydrocarbons, organic acids...) generated due to organic and inorganic matter degradation, is expected at the following sewerage system facilities: raw wastewater pumping stations, coarse screens, grit-grease removal, waste collection tanks.

Noise

High level noise can be generated at the following public sewerage system facilities: pumping station, blower unit

Decline in land value

Since wastewater treatment plant is situated far enough from the residential area, there should be no large scale decline in the adjacent land value. However, inadequate visual appearance of the facility as well as irregular maintenance would significantly impact the landscape.

Wastewater infiltration

Wastewater infiltration into soil and/or seawater can occur at the mains and tank joints due to cracking or hardstandings at solids load points.

Wastewater infiltration into the sea could occur at submarine outfall cracks i.e. pipeline damages.

Insect breeding

Insect breeding is possible in warm periods of the year at still waters, tanks, wastewater puddles and plashes, work areas or green areas.

Impact on the use of coast

Sea pollution could impact the coast, thus making it unsuitable for planned use (recreation, sports) including residential and hotel development.

Impact on the sea use

Coastal sea could be polluted and therefore unsuitable for bathing, water sports. Human health could also be endangered.

Page 17: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

17

Impacts due to waste disposal

Disposal of wastes produced at the wastewater treatment plant could cause unwanted environmental impacts such as odors and insect breeding, and could also endanger life of people and animals

0. Environmental accident impacts

Force majeure (major earthquake, ravages of war) could cause damages to public sewerage system facilities. It would result in uncontrolled release of untreated wastewater into coastal sea thus deteriorating seawater quality to the present state or even more polluted. Due to “outage” of system facilities, there could be a decrease in system operation efficiency and thus short-term increase in coastal sea pollution. Submarine outfall damages are also possible resulting in uncontrolled wastewater spill in unwanted locations. If submarine outfall is to be constructed of high-density polyethylene (HDPE) pipes, occasional pipeline lifting from seabed and floating is possible. In respect to materials and construction technology, small-scale fires can be generated due to break in power lines or electrical machines. Gases released from wastewater surfaces can corrode unprotected metal parts, thus causing disturbances in operation and environmental accident.

Law on Physical Development and Construction - Zakon o prostornom planiranju i gradnji, NN 76/07, in the part regulating site organization (Articles 252 through 254), requires the following mandatory measures:

- the site shall be delimited to prevent uncontrolled access,

- the site shall be marked by the sign plate containing the name or firm of the investor, the designer, the contractor and the supervising engineer, name and type of the structure, the name of the agency that has issued the construction permit, classification code, registration number, date of issuing and expiration of the construction permit, as well as the note on cultural property, if the structure is entered in the Register of Cultural Property of the Republic of Croatia,

- parts of the site extending over larger areas (e.g. roads, railways, ducts, etc.) shall be fenced, or marked by special signs,

- in case of temporary occupation of public roads for the purpose of construction, the investor or the contractor shall obtain the corresponding permits from relevant agencies; preliminary works may be carried out on surrounding land only if the investor has obtained the permission from the land owner for carrying out of such preliminary works,

- temporary structures erected for the purposes of the site, equipment, unused material and waste shall be removed from the site, and the site shall be returned to previous condition,

- on site, necessary measures shall be taken and implemented for protection of air from pollution, protection from noise, soil and ground water protection, safety at work, and protection of public health.

Besides this, the construction materials and installed equipment must be selected, installed and maintained so that their chemical, physical and other influences during use do not result in hazards, obstacles, injuries or damage, and must be handled in accordance with technical standards.

Page 18: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

18

Taking into consideration the above remarks, it may be assumed that in the construction phase of the facilities there will be some small and short environmental impacts. Such impacts are usual in interventions in municipal infrastructure, involving various field works. In this sense, the following forms of environmental impact may be foreseen during construction: - minor traffic problems, - increased air pollution by dust particles, - increased soil erosion and spreading on roads (during rainfall), - increased noise level, - additional production of waste material.

In connection with traffic problems, in addition to the safety aspect, one may expect increased local air pollution due to increased emission of exhaust gases of motor vehicles, as well as local pollution by noise.

During earthmoving works, in particular during the dry season, locally increased concentration of dust is probable. Construction machines (vehicles) can bring sediment (soil or sand) from site to roads. Sediment can also get to roads during rain.

The waste produced during construction mainly consists of construction waste and municipal waste, managed in accordance with the Waste Act, which, inter alia, implies separating of packing material from municipal waste, and regular transport of waste to the landfill.

During operation of the facilities, in proper handling conditions, no particular adverse environmental impacts are expected. Namely, during operation, waste (in the form of sediment or sludge) is produced only in the retention basin, but it is, together with waste water, forwarded towards the treatment plant, and in the treatment plant. There is a potential risk, in case of accidental damage of parts of the sewerage network, of infiltration of ground water into the sewerage network, or of exfiltration of waste water into the underground. However, as a prevention measure, the user of the facility must regularly check the impermeability of the sewerage network (in the frame of his regular annual control and maintenance plans) and, if necessary, repair the damaged parts.

Other, mainly minor environmental impacts, both at the treatment plant and in the sewerage network, are mainly related to improper operation and/or accidental events. The annexes, in table form, give the possible environmental impacts, including planned mitigation measures.

On a long term, however, positive effects of construction of project facilities may be expected, reflected in higher numbers of population connected to sanitary sewerage, thus preventing environment pollution, in particular pollution of ground water and see water.

As the Project will be implemented within already existing areas, any cultural issues are not foreseen, but the civil work contracts for all infrastructure investments will include requirements that the contractor is obliged to look for chance finds and stop the construction work and alert Ministry of Culture in case of chance finds.

Page 19: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

19

CHAPTER 3. INSTITUTIONAL FRAMEWORK

The supervision over implementation of the Environment Management Plan will be provided by the Hrvatske vode PIU, named Hrvatske vode Jadranski project. Hrvatske vode Jadranski project will implement the entire Coastal Cities Control Pollution Project and supervise adherence to the environment protection measures during the period of designing, construction and operation of the project, and ensure implementation of environment protection measures and measures for mitigation of environmental impacts as provided by the environment management plan. Hrvatske vode rely on the experience from previous projects financed by the World Bank, such as the Coastal Cities Pollution Control Project, Phase I and other similar projects in the Republic of Croatia. Hrvatske vode Jadranski project shall submit to the Bank regular Project Management Report, which shall also include observations made during inspection of construction sites, as well as remarks regarding environment protection measures. Hrvatske vode Jadranski project shall assist the municipalities in preparing of tender documents for procurement of goods and equipment. Also, having sufficient expertise in the field of environment protection, Hrvatske vode Jadranski project will provide advice to the municipalities, the supervising engineer and/or site manager, and to the utility manager. One person in Hrvatske vode PIU, named Hrvatske vode Jadranski project will be in charge for the coordination of environmental issues.

Along with Hrvatske vode Jadranski project, participating in the Plan monitoring will be the supervising engineer representing the investor, and the site manager or utility manager representing the user. They shall, within their regular activities, monitor the implementation of environmental impact mitigation measures, as required, or at least on a quarterly basis inform Hrvatske vode Jadranski project and persons in charge of the project in the municipality. Hrvatske vode Jadranski project shall analyze all documentation and include the results in regular reports (Project Management Report) to the World Bank quarterly.

The supervision engineer and/or site manager will make sure that all workers are introduced to EMP mitigation measures and that EMP is visibly accessible at site.

The environment protection inspectors of the Ministry of Environment Protection, Physical Planning and Construction shall, together with the professionals in environment protection of the Ministry of Agriculture, Forestry and Water Management exercise supervision through unannounced field visits during construction and operation of sub-projects within the Inland Waters Project, inspecting the conditions of construction, environment protection and water quality.

Page 20: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

20

CHAPTER 4. ENVIRONMENTAL IMPACT MITIGATION PLAN The Mitigation Plan i based on - Croatian laws - regulatory framework - available level of project documentation - Environmental impact assessment study - Decision of Ministry of Environmental and Physical Planning on EIA - Experience in implementation of good engineering praxis The contractor and the investor shall be responsible for implementation of the plan of environmental impact mitigation. Implementation of these measures should be regulated by the contract on construction, including sanctions for failing to apply the measures. The investor shall supervise implementation of the measures stipulated by the plan. It is recommended to include the contractor’s obligations into the terms of reference to make them a part of the contract. The plan of mitigation of environmental impact is given in the Appendix in table form, and includes all stipulated requirements from Decision of Ministry of Environmental and Physical Planning and good environmental practice.

Page 21: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

21

CHAPTER 5. MONITORING PLAN The obligations with respect to monitoring are defined by the Decision of the Ministry of Environmental Protection and Physical Planning, Class: UPI/I 351-02/02-06/0020, Urbroj: 531-05/4-STZ-04-9-01-8 dated April, 02, 2004. Additional monitoring program will be defined in the Building Inspection Certificate and the Water-Rights Permit. Pursuant to the provisions of the Water Act and the respective by-laws, Hrvatske vode, an institution relevant for water management operations, shall define, in the Water-Right Permit, the monitoring to be performed by the utility company on a regular basis so that it could, among other things, collect the water protection rate (polluter pays principle). In addition, the utility company shall be obliged to transmit the results of such monitoring regularly to the Environmental Emission Register at the Ministry of Environmental Protection, Physical Planning and Construction. The Monitoring Plan is given in the attached table.

Page 22: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

22

CHAPTER 6 COOPERATION WITH THE PUBLIC

The proposed project was already announced to the public through public presentation of Environmental Impact Study on several occasions in year 2004 on a special consultation with local authorities of the City of Vodice and stakeholders as announced in Slobodna dalmacija, dated February 06, 2004, inviting comments and concerns from local population of the proposed project. As confirmed by the official correspondence from the officials of Šibensko-kninska županija (Šibenik County), no critical concerns or complaints have been raised by the population concerned.

This EMP will be available to public on HVJP's web site, from July 09. 2008. for comments, questions and suggestions. All received comments will be attached to this document.

Page 23: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

23

CHAPTER 7. APPENDICES 7.1. General layout 7.2. Table 1: Plan of avoiding adverse environmental impacts 7.3. Table 2: Monitoring plan 7.4. List of laws and bye-laws relevant to environmental protection in the Republic of Croatia

Page 24: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

24

Page 25: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

25

Annex No 7.2: PLAN OF AVOIDING ADVERSE ENVIRONMENTA L IMPACT (MITIGATION PLAN)

Stage Impact Remediation measures Additional costs Responsibilit y Implementation Supervision Construction Traffic disturbance In order to avoid bigger traffic disturbances, works have to be done in

time with minimum traffic. In regard of traffic safety, there is a legal obligation to mark the part of the road where the works have to be done, with equivalent traffic signs, and that the traffic participants are secured with fences. If because of the works alternating by-passing of the vehicles has to be done, it should be done with temporary traffic lights. Before such action special permission has to be provided by the local authorities and police should be informed (Law on traffic safety OG No105/04)

Costs included in the costs of work

Contractor Police, Supervising engineer,

Construction Air pollution (increased dust concentration)

Surfaces where ground works will be performed should previously be sprinkled with water in order to prevent high air pollution with dust or the vehicle speed on the site has to be reduced. Machines and vehicles used during construction must be under constant supervision regarding the quantity and quality of exhaust fumes, and meet the permissible values.

Costs included in the costs of work

Contractor Environmental Protection Inspector, Supervising engineer

Construction Silt run-off/erosion and sedimentation It is necessary to prevent sediment or silt run-off. Sediment should never be rinsed off the site; instead it must be cleaned up in a manner that does not allow it to reach a storm drain or a waterway. Equipment tires must be rinsed before leaving the site if necessary to avoid tracking sediment into the roadway or off the site.

Costs included in the costs of work

Contractor Supervising engineer,

Construction Noise pollution Since the works will be performed in inhabited areas, and in order to prevent high noise pollution measures according to the current legislation (Law on noise protection, OG No 20/03 and Regulation on Highest Allowed Noise Level in Areas where Humans Work and Dwell OG 145/04) appropriate measures should be taken. Contractor is obligated to compile Noise protection report. Regarding the highest allowed noise levels during the day, night works should be avoided so that night silence and satisfying conditions for rest and work should be achieved. It is allowed to use only construction machines, transportation vehicles and equipment in compliance with the set technical regulations which refer to the maximum allowed noise level which they produce.

Costs included in the costs of work

Contractor Sanitary inspection and labour (work safety) inspection, Supervising engineer

Page 26: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

26

Stage Impact Remediation measures Additional costs Responsibilit y

Implementation Supervision Construction Soil and water pollution by waste Waste which will appear at the construction site should be disposed in

compliance law (Law on waste, OG No. 178/04, 158/05, 111/06 and 60/08). Temporary disposal of waste on the site must be done as provided by the Law on Waste. Drainage system of all working and transport areas should be planned.

Costs included in the costs of work

Contractor Environmental Protection Inspector Water management inspection, Supervising engineer

Construction Disposal of surplus excavated material Surplus excavated material shall be disposed of by the Contractor in places as specified by the Decision of Town Government only. Temporary disposal of waste on the site must be done as provided by the Law on Waste, and the locations must be shown in the site plan. In transport of surplus excavated material, trucks shall be loaded to the limit preventing material dropping out during transport. If necessary, silty material shall be sprayed with water before leaving the building site on trucks, to avoid dust creation during transport or reduce the speed of the vehicles.

Costs to be borne by the Investor.

Investor Contractor

Environmental Protection Inspector, Labour inspection , Supervising engineer

Construction Environment During construction, all trees and plants that need not necessarily be cut in order to build facilities shall be protected obligatorily. Make the landscaping design. Before the beginning of exploitation, all area shall be planted with autochthonous species (according to the landscaping design).

Costs included in the price of construction

Contractor Environmental Protection Inspector Construction inspection, Supervising engineer

Construction Installation protection During the execution of the works, in particular during excavation, the Contractor shall protect existing installations and buildings against possible damage. In case of breaking any utility installation, including the house services, the Contractor shall be obliged to repair it, within the shortest time possible, as instructed and under supervision of the relevant utility service.

Costs included in the price of construction

Contractor Relevant utility service, Supervising engineer

Service Odours PUMPING STATIONS: In order to protect the environment against unpleasant odours, the Pumping Station shall be constructed as a closed building. Covers on all openings shall be sealed, preventing gas evacuation to the environment. Ventilation of the pump tank and valve chamber is permitted, provided the vent is placed minimum 3.0 m high from the land around the covers on the manholes to the Pumping Station. WASTE WATER TREATMENT PLANT: To protect the environment against unpleasant odours, the following components of the Plant shall be constructed as closed buildings: - inlet structure, screens, sand-trap,

Costs included in the price of construction

Contractor during construction or Investor during services

Environmental Protection Inspector, Sanitary Inspector; Site manager

Page 27: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

27

Stage Impact Remediation measures Additional costs Responsibilit y Implementation Supervision

- facility for receiving septic tank water, - return and excess sludge pumping stations, - sludge thickeners, - sludge dewatering unit, - stabilized sludge tanks. In the closed rooms underpressure shall be maintained, and polluted air shall be cleaned (biofilters) before its evacuation into the environment. According to the Ordinance on Recommendable and Limit Values of Air Quality (Official Gazette 133/05), the following tested air values (24 hours) shall not be exceeded at the Plant site boundary line: ammonia 70 µg/m* hydrogen-sulphide µg/m3 mercaptans 1 µg/m3

COLLECTORS: At all sewer route breaks and gradient changes, the manholes of working chamber size, with the ground plan dimensions of no less than 1.0x1.0 m and minimum 1.8 m high, shall be installed. No installation of step irons made of concrete steel shall be allowed. The covers placed on the inspection manholes shall be in accordance with the traffic load of the existing or planned road. In case ventilation valves are used on the pressure pipelines, they shall be placed in the manholes that by their size will enable maintenance of such valves and the replacement of individual parts.

Service/Construction Noise PUMPING STATIONS: In order to ensure protection against noise, all electro-mechanical equipment shall be placed in closed buildings. The buildings shall be constructed in the way that the noise level at P.S. location does not exceed 55 dBA by day and 45 dBA by night, namely does not exceed the as-found values according to Article 5, of the Regulations on Maximum Permissible Noise Levels in Rooms where People Work and Live (Official Gazette no. 145/04). WASTE WATER TREATMENT PLANT: To ensure protection against noise, all machines producing higher noise shall be installed in closed building. During the design work, noise level tests shall be carried out and, if necessary, installation of additional materials for protection against noise shall be foreseen. During the day period, the permissible equivalent noise level may be 65 dB (A). In the period from 8.00 a.m. to 6.00 p.m. exceeding of the equivalent noise level by additional 5 dB (A) is permissible, according to the Regulations on Maximum Permissible Noise Levels in Rooms where People Work and Live (Official Gazette no. 145/04, Art. 17). During use at the border of the plant location, depending on the zone, Article 5 of the above-mentioned Regulations shall apply.

Costs included in the price of construction

Contractor or Investor

Sanitary inspection, Labour inspection, Site manager

Page 28: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

28

Stage Impact Remediation measures Additional costs Responsibilit y Implementation Supervision Service Waters It is necessary to ensure good drainage of all working and traffic

surfaces by maintaining adequate slopes and catchwater manholes. PUMPING STATIONS: No wastewater overflowing from the Pumping Station tank into the environment is permitted. To prevent such overflowing in case of the pump failure, the Pumping Station shall be constructed and maintained in the following conditions: - next to the operating pump a stand-by pump having the same

characteristics shall be installed, which will automatically start pumping when the waste water level in the pump tank rises;

- for the case water level continues to rise, an alarm system connected to the control service shall be foreseen;

- once the control service receives the alarm, it shall remedy the defect in the Pumping Station within 30 min, using a portable diesel alternator, a spare pump, or other auxiliary equipment that always must be available for emergency interventions.

WASTE WATER TREATMENT PLANT: The construction of the Waste Water Treatment Plant in phases is permitted provided the processes of each phase make a technological entity and meet the requirements of the Regulations on Limit Values of Indices of Hazardous and Other Substances in Waste Water (Official Gazette 40/99, 6/01, 14/01). At the Plant outlet, in the first phase the limit values of waste material concentrations shall not exceed the following:

LEVEL OF TREATMENT PARAMETER BOUNDERIES

VALUE

I.

Total dispersed matter

concentration 150 mg/l

The waste materials from the screens and the sand-trap shall be collected in closed tanks and transported daily to the non-dangerous (solid) waste disposal site. Non-dangerous (solid) waste disposal sites have to be constructed in accordance with the Ordinance on the methods and conditions for the waste disposal, categories and operational requirements for waste disposal sites (OG No. 117/07).

Sand from the screens sand grease will be washed and transported to the a non-dangerous (solid) waste disposal site in accordance with the Ordinance on the methods and conditions for the waste disposal, categories and operational requirements for waste disposal sites (OG No. 117/07).

Costs included in the price of construction

Contractor or Investor

Environmental Protection Inspector; Water management inspection, Site manager

Page 29: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

29

Stage Impact Remediation measures Additional costs Responsibilit y Implementation Supervision

SUBMARINE OUTLET:

Vodice-Tribunj-Srima sewerage system wastewater shall be discharged after treatment at the WWTP by submarine outfall of 1900 m in length.

During system operation, seawater shall satisfy Category II standards i.e. values for Sea 1 given in Tables 1 and 2 of the Ordinance on Dangerous Substances in Freshwater and Coastal Sea Water (OG No. 78/98) at 300 m distance from the outfall. Microbiological parameters shall comply with the requirements set forth in the Directive on Bathing Water Quality Standards (OG No.33/96) at the protected zone boundary (200 m offshore distance).

During sewerage system operation, at maximum wastewater loads, the maximum allowable concentration of Total Coliforms can be exceeded over a short period (few hours). However short-term exceeding will not impact the quality of High Quality Sea at nearby beaches. The coastal – protected zone will be endangered if the following conditions are satisfied:

� sea density homogenization along the vertical, induced by wind-wave climate;

� sea currents directed onshore.

Having in mind summer stratification the plume moves under the depth of thermocline (15-25 m), so there is very small possibility that it comes to the surface. COLLECTORS: When using sludge outlets on the pressure pipelines, a special chamber for wastewater discharge shall be foreseen, which will be emptied by an auxiliary (portable) pump.

Service Waste materials and sludge The problem of sludge disposal shall be solved by the Investor with the Town of Vodice. The waste materials from the screens and the sand-trap shall be collected in closed tanks and transported daily to the a non-dangerous (solid) waste disposal site. Non-dangerous (solid) waste disposal sites have to be constructed in accordance with the Ordinance on the methods and conditions for the waste disposal, categories and operational requirements for waste disposal sites (OG No. 117/07).

Sand from the screens sand grease will be washed and transported to the a non-dangerous (solid) waste disposal site in accordance with the Ordinance on the methods and conditions for the waste disposal, categories and operational requirements for waste disposal sites (OG

Costs included in the operating costs

Investor or user of structure

Environmental Protection Inspector; Site manager

Page 30: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

30

Stage Impact Remediation measures Additional costs Responsibilit y Implementation Supervision

No. 117/07).

Oils and greases from grease trap, which represent hazardous waste, shall be collected in closed tanks and taken for incineration in accordance with the Rules on Types of Waste and the Law of Waste OG 27/96).

Service Waste sludge The stabilized sludge, freed from any excess water, with the dry substance content of no less than 35%, shall be collected in separate closed tanks and transported to the a non-dangerous (solid) waste disposal site in accordance with the Ordinance on the methods and conditions for the waste disposal, categories and operational requirements for waste disposal sites (OG No. 117/07). Before disposal, the stabilized sludge eluate composition shall be determined according to the said Regulations.

In case the sludge and/or sludge compost is used on agricultural and/or forest lands, the conditions of disposal shall meet fully the Regulations on Protection of Agricultural Land against Pollution by Harmful Substances (Official Gazette 15/92) and Regulation on good agricultural practice concerning fertilizer use (OG No. 56/08).

Costs included in the price of construction

Contractor or Investor during service

Environmental Protection Inspector, Site manager

Service Submarine outlet Submarine outfall and diffuser shall be regularly inspected (once a year in spring) and potential defects repaired.

Costs included in the operating costs

Contractor or Investor during service

Environmental Protection Inspector, Site manager

Service Environment To prevent the development of insects in the Plant area, in the design it is necessary to avoid creation of “dead spots”, i.e. stagnant waters. On all traffic and other surfaces in the Plant area, standing of water shall be prevented by adequate inclinations and catchwater manholes.

To maintain hygienic conditions of work and clean environment of the Plant, it is necessary to reduce staying of birds on the Plant. For this purpose adequate construction measures shall be used such as loose wires (cables) on all fences and parts of the Plant the birds might perch upon. In order to prevent creation of “cultural desert” and to improve the scenery, all unoccupied surfaces at the Plant site shall be planted with autochthonous vegetation, i.e. according to the chosen horticultural design.

During exploitation, for protection against rodents the deratization of the sewage system shall be made using paraffinized baits attached with wire in the inspection manholes (200 g/50 m).

Regular washing and cleaning of all working zones and roads shall be ensured.

Costs included in the price of construction

Contractor or Investor during service

Environmental Protection Inspector; Sanitary inspection, Site manager

Service Protection of ground waters For protection of ground waters against pollution by waste waters, all Costs included in price of Contractor or Environmental

Page 31: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

31

Stage Impact Remediation measures Additional costs Responsibilit y Implementation Supervision

sewer, manhole and tank joints shall be watertight. All working and traffic surfaces at the Plant site shall be provided with the drainage system and shall be regularly washed and cleaned during Plant operation with the washing water discharge to the Plant inlet structure.

construction or as operation costs

Investor during service

Protection Inspector; Water management inspection, Site manager

Service Connection to the drainage system

When issuing an authorization or opinion to industrial plants or small businesses that are going to be connected to the system or the Plant (either through the combined or separated system section), the utility company shall issue the authorization prescribing the obligation of an organized and regular wastewater monitoring, as well as the obligation, in case of the change of technological process in any plant unit, for such opinion – authorization to be obtained again, everything in order to prevent inflow of toxic and aggressive waters that might cause stoppage of the Plant.

Costs included in operation costs

Communal company

Water management inspection; Environment protection inspection, Site manager

Incidents Flowing of wastewaters To prevent flowing of water out of the Pumping Station tank in case of the pump failure, the Pumping Station shall be constructed and operated in the following conditions: - next to the operating pump a stand-by pump with the same

characteristics shall be installed, which will automatically start pumping when the waste water level in the pump tank rises;

- for the case water level continues to rise, an alarm system connected to the control service shall be foreseen;

once the control service receives the alarm, it shall remedy the defect in the Pumping Station within 30 min, using a portable diesel alternator, a spare pump, or other auxiliary equipment that always must be available for emergency interventions.

Cost included in the price of construction

Communal company

Sanitary inspection, Site manager

Incidents Failure of the Plant In order to alleviate the consequences of ecological incidents due to the failure of the Plant or any parts thereof, the Plant shall be constructed as at least two independent units with the same technological process.

By a system of valves, channels and by-passes the operation of individual parts of the Plant shall be made possible, with the switching off of the damaged components.

The power supply to the Plant shall be from at least two independent energy sources with automatic connection.

Cost included in the price of construction

Communal company

Construction inspection, Site manager

Incidents Fire As a fire-fighting measure, in all buildings containing electro-mechanical equipment and electrical installations the fire extinguishers of “dry” type shall be provided in conformity with the applicable standards and as the protective measures due to the risks of explosion. At the Plant location, an outdoor hydrant network shall be constructed in accordance with the Regulations on Technical Norms for Fire Hydrant Network.

Cost included in the price of construction

Communal company

Construction inspection, Site manager, Fire inspection

Page 32: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

32

Stage Impact Remediation measures Additional costs Responsibilit y Implementation Supervision Incidents Corrosion To be protected against exhaust gas and vapour corrosive action, all

metal parts of Pumping Stations and the Plant shall be either made of the corrosion-resistant metals or adequately protected against corrosion.

Cost included in the price of construction

Communal company

Construction inspection, Site manager

Incidents Water Protection The occurrence of cracks on the sewers and tanks for wastewater and waste substances shall be prevented by proper calculation and construction, taking into account also undesirable effects of earthquakes in the respective seismic zone.

Cost included in the price of construction

Communal company

Construction inspection, Site manager

Page 33: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

33

Annex No 7.2: Monitoring Plan

Phase Monitoring Parameter

Monitoring Place

Monitoring Method Monitoring Time

Additional Costs

Responsibility

Execution Supervision Baseline See water

� see water temperature (oC) � pH � diluted oxygen

concentration (mg O2/l) � dispersed matter

concentration (mg/l) � BOD5 (mg O2/l) � COD (mg O2/l) � total nitrogen concentration

(mg N/l) � total phosphorus

concentration (mg P/l) � total oil and grease

concentration (mg/l) � mineral oil concentration

(mg/l) � salinity (%) � transparency (m) � ammonia (mg N/l) � nitrite (mg N/l) � nitrate (mg N/l) � orthophosphate (mg P/l) � chlorophyll "a" (mg/m3) • bakar (µg Cu/l) • cink (µg Zn/l) • kadmij (µg Cd/l) • olovo (µg Pb/l) • total coli forms (b.c./100 ml) • Faecal coliform FC

(f.c./100 ml). • Faecal coliform i FS (f.s

/100 ml)

Seawater quality shall be monitored at twelve stations, concentrated at radius of 300 m and 900 m distance from the end of the submarine outfall, at the depth 0,5 m, 10 m and 20 m bellow the see surface

By applying good laboratory practices, the samples shall be kept unchanged or their change reduced to minimum between sampling and testing. For testing of see waters, standard methods prescribed by National Institute for

Water samples for testing shall be taken 4 per year. Start monitoring one year before the beginning of the Plant operation.

Costs to be included in operation costs, cca 3000 kn/sample.

Communal company

Institute of Public Health; Environment protection inspection; Water management inspection

Baseline See Water According to the Law on Environmental protection (Official gazette No. 82/94 and 128/99) a subordinate regulation of the Republic of Croatia has been developed - Regulation on

At the 10 locations in 200 m coastal zone.

For testing of see waters, standard methods prescribed by National Institute for Standardization shall be used.

The program of continuous monitoring of seawater sanitary quality is implemented from May 1st to the end of the bathing season (end of September). Samples

- Šibenik County Institute of Public Health; Environment protection inspection;

Page 34: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

34

Phase Monitoring Parameter

Monitoring Place

Monitoring Method Monitoring Time

Additional Costs

Responsibility

Execution Supervision Bathing Water Quality Standards (Official gazette No. 33/96). The Regulation defines the criteria for sampling, testing methods and assessment of sea water quality on beaches. This Regulation is based on the Council Directive of EEC concerning the Quality of Bathing Waters 76/160/EEC, Official Journal of EEC No. L281/47-52), Guidelines for coastal recreational waters in the Mediterranean of the Mediterranean Action Plan of the United Nations Environment Programme (UNEP/MAP) and the criteria of the World Health Organization (WHO). Bacteriological parameters::

• total coli forms TC • Faecal coliform FC • Faecal coliform i FS

Seawater quality testing at Vodice-Srima-Tribunj marine beaches has been tested separately of this project, according to the Regulation on Bathing Water Quality Standards (OG No. 33/96) it has been tested in 10 locations. Testing has been made through the entire bathing season and it represents an indirect control of submarine outfall impact on coastal sea quality. Apart from the measured parameters from the Regulation, salinity measurement is compulsory

have to be taken on beaches at least every 15 days, 10 times in bathing season

Baseline Flora i fauna • Research on flora and

vegetation at the plant site

flora and vegetation at the plant site; plankton and benthos

According to special program

Start monitoring one year before the beginning of the Plant operation

Costs to be included in operation costs, will be established upon

Communal company

Environment protection inspection;

Page 35: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

35

Phase Monitoring Parameter

Monitoring Place

Monitoring Method Monitoring Time

Additional Costs

Responsibility

Execution Supervision • Research on benthos

communities near the Irelands Lukovnik and Logorun

• Research on plankton communities - Kaprijski Channel

communities in the see construction

Baseline Noise Level � <55dBA by day � < 45 dBA by night but not higher than as-found (baseline)

At the western Plant boundary

By day and night during working hours, two measurements/year (during five days) one year before the beginning of the Plant operation; Near pump stations five day in the first year after construction. Measurements start one year before the beginning of the Plant and pumps operation

Costs to be included in operation costs, 10000 kn /measurement

Communal company

Environment protection inspection; Work safety inspection

Baseline Air � wind direction and speed

(m/s) � air temperature (oC) � air humidity (%) � precipitation (mm/min) � ammonia (µg NH/m3) � hydrogen-sulphide (µg

H2S/m3) � mercaptans (µg C2H5SH/m3)

Station located next to the SE Plant boundary

It has to be mobile, i.e. usable in a larger area. Testing shall be done by methods and in the way as set forth in Regulations on Permissible Air Quality Limit Values (Off. Gazette 133/05)

Atmosphere monitoring should start at least one year before the beginning of the Plant operation. Minimum number of samples per year is 2 (in cold and warm period of the year during 10 days)

Costs to be included in operation costs, cca 10000 kn/measurement

Comunal company

Environment protection inspection

Construction Air

- dust concentration - machine exhaust gases

Building Site Visual During dry season Cost included in the price of construction

Contractor Environmental protection inspector; Supervising engineer

Construction Noise Building Site Noise level measuring equipment

Noise level must be measured on each building site during the construction according to valid regulations, at least once a year. Measuring shall be carried out by an authorized company registered for such

Costs included in the price of construction

Contractor Environmental protection inspector; Labour inspection; Supervising engineer

Page 36: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

36

activity. Before starting any works the Contractor shall prepare the design of protection against noise at the building site

Construction Waste and surplus material disposal

Building site and landfill Control of Contractor’s actions

Once a month Costs included in the price of construction

Contractor Environmental protection inspector; Supervising engineer

Construction Ground Waters - watertightness

Collectors, pipelines and network facilities

Watertightness test certificate

During construction Costs included in the price of construction, cca 150kn/m3, 20 kn/m

Contractor Supervising engineer

Construction Sanitary Conditions

Building site According to the Regulations on Buildings Subject to Sanitary Control and the Method of carrying out such Control during their Construction (OG 48/00)

During construction Costs to be included in price of construction

Contractor Sanitary inspection

Construction Air - concentration of dust Construction site Visually During construction, in dry weather

Costs included in the costs of work

Contractor Environmental Protection Inspector

Page 37: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

37

Phase Monitoring

Parameter Monitoring

Place Monitoring Method Monitoring

Time Additional

Costs Responsibility

Execution Supervision Operation See water

� see water temperature (oC) � pH � diluted oxygen

concentration (mg O2/l) � dispersed matter

concentration (mg/l) � BOD5 (mg O2/l) � COD (mg O2/l) � total nitrogen concentration

(mg N/l) � total phosphorus

concentration (mg P/l) � total oil and grease

concentration (mg/l) � mineral oil concentration

(mg/l) � salinity (%) � transparency (m) � ammonia (mg N/l) � nitrite (mg N/l) � nitrate (mg N/l) � orthophosphate (mg P/l) � chlorophyll "a" (mg/m3) • copper, (µg Cu/l) • zinc (µg Zn/l) • cadmium (µg Cd/l) • lead (µg Pb/l) • total coli forms (b.c./100 ml) • Faecal coliform FC

(f.c./100 ml). • Faecal coliform i FS (f.s

/100 ml)

Seawater quality shall be monitored at twelve stations, concentrated at radius of 300 m and 900 m distance from the end of the submarine outfall, at the depth 0,5 m, 10 m and 20 m bellow the see surface

By applying good laboratory practices, the samples shall be kept unchanged or their change reduced to minimum between sampling and testing. For testing of see waters, standard methods prescribed by National Institute for Standardization shall be used.

Water samples for testing shall be taken 4 per year.

Costs to be included in operation costs, cca 3000 kn/sample

Communal company

Institute of Public Health; Environment protection inspection; Water management inspection

Operation See Water According to the Law on Environmental protection (Official gazette No. 82/94 and 128/99) a subordinate regulation of the Republic of Croatia has been developed - Regulation on Bathing Water Quality Standards (Official gazette No. 33/96). The

At the 10 locations in 200 m coastal zone.

For testing of see waters, standard methods prescribed by National Institute for Standardization shall be used.

The program of continuous monitoring of seawater sanitary quality is implemented from May 1st to the end of the bathing season (end of September). Samples have to be taken on beaches at least every 15

- Šibenik County Institute of Public Health; Environment protection inspection;

Page 38: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

38

Phase Monitoring Parameter

Monitoring Place

Monitoring Method Monitoring Time

Additional Costs

Responsibility

Execution Supervision Regulation defines the criteria for sampling, testing methods and assessment of sea water quality on beaches. This Regulation is based on the Council Directive of EEC concerning the Quality of Bathing Waters 76/160/EEC, Official Journal of EEC No. L281/47-52), Guidelines for coastal recreational waters in the Mediterranean of the Mediterranean Action Plan of the United Nations Environment Programme (UNEP/MAP) and the criteria of the World Health Organization (WHO). Bacteriological parameters::

• total coli forms TC • Faecal coliform FC • Faecal coliform i FS

Seawater quality testing at Vodice-Srima-Tribunj marine beaches has been tested separately of this project, according to the Regulation on Bathing Water Quality Standards (OG No. 33/96) it has been tested in 10 locations. Testing has been made through the entire bathing season and it represents an indirect control of submarine outfall impact on coastal sea quality. Apart from the measured parameters from the Regulation, salinity measurement is compulsory

days, 10 times in bathing season

Operation Flora i fauna • Research on flora and

vegetation at the plant site • Research on benthos

communities near the

flora and vegetation at the plant site; plankton and benthos communities in the see

According to special program

Every second year Costs to be included in operation costs, will be established upon construction

Communal company

Environment protection inspection;

Page 39: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

39

Phase Monitoring Parameter

Monitoring Place

Monitoring Method Monitoring Time

Additional Costs

Responsibility

Execution Supervision Irelands Lukovnik and Logorun

• Research on plankton communities - Kaprijski Channel

Operation Wastewater At Plant inlet: • Total suspended substance

mg/l At Plant outlet: • pH-value, conductivity � Total suspended substance

< 150 mg/l � BOD5 (mg O2/l) � COD (mg O2/l) � total phosphorus

concentration (mg P/l) � total oil and grease

concentration (mg/l) � mineral oil concentration

(mg/l) � anionic detergents � total phenols

At Plant inlet and outlet By using good laboratory practices samples shall be kept unchanged or their change reduced to minimum between sampling and testing. For testing of surface and waste waters use standard methods as prescribed by National Institute for Standardization. In quality assessment, the inflow samples differing significantly from usual ones, such as in case of heavy rains, shall not be taken into consideration.

Monitoring of the parameters shall be carried out once a month in the first year after the WWTP completion. Afterwards, frequency will depend on testing results i.e. wastewater quality and treatment efficiency in compliance with the Regulations on Limit Values of Parameters, Hazardous and Other Substances in Wastewater (OG No. 40/99, 06/01). If effluent quality at the WWTP exit is satisfactory, testing can be reduced to 4 times a year. Should one of four samples fail to meet the required standards, 12 samples shall be taken again next year.

Costs to be included in operation costs, cca 3000 kn/sample

Communal company

Institute of Public Health; Environment protection inspection; Water management inspection

Operation Industrial wastewater At connection to the sewage system

By using good laboratory practices samples shall be kept unchanged or their change reduced to minimum between sampling and testing. For testing of surface and waste waters use standard methods as prescribed by National Institute for Standardization

As agreed by the Utility Company

As agreed by the utility company

Industry Utility company/water-right inspection / environmental protection inspection

Page 40: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

40

Phase Monitoring Parameter

Monitoring Place

Monitoring Method Monitoring Time

Additional Costs

Responsibility

Execution Supervision Operation Sludge

� daily quantity of treated and dewatered sludge (m3/d)

� daily sludge dry substance content (l/d),

� total nitrogen concentration (mg N/kg D.S.),

� total phosphorus concentration (mg P/kg D.S.),

� total kali concentration (mg K/kg D.S.),

� cadmium concentration (mg Cd/kg D.S.),

� chromium concentration (mg Cr/kg D.S.),

� lead concentration (mg Pb/kg D.S.),

� zinc concentration (mg Zn/kg D.S.),

� harmful organic matter concentration (PCB, HCH etc.) (mg/kg D.S.)

Tank for stabilized and dewatered sludge ready for transport

Sludge shall be tested using standard methods, i.e. the methods set forth by National Institute for Standardization. To ensure control of possible environmental impact, a permanent monitoring of hazardous substance concentration in treated sludge is necessary.

12 per year, equally distributed

Costs to be included in operation costs, cca 4000 kn/sample

Communal company

Environment protection inspection

Operation Air � wind direction and speed

(m/s) � air temperature (oC) � air humidity (%) � precipitation (mm/min), � ammonia (µg NH/m3)<70, � hydrogen-sulphide (µg

H2S/m3)<2, � mercaptans (µg

C2H5SH/m3)<1

Station located at the SE Plant boundary

It has to be mobile, i.e. usable in a larger area Sample testing shall be done using methods and in the way as set forth in the Decree on Permissible Air Quality Limit Values (Official Gazette no. 133/05)

Minimum number of samples per year is 2 (in cold and warm period of the year during 10 days) Ones per year in warm period sample near the pump station will be taken

Costs to be included in operation costs, cca 10000 kn/measurement

Communal company

Environment protection inspection

Operation Noise Noise level < than that permissible for land industrial use, as per Art. 5, paragraph 5 (table) of the Regulations on Highest Permissible Noise Levels in Rooms where People Work and Live (Official Gazette 145/04).

Noise at the western Plant boundary

By day and night during 5 days, two measurements per year for two years after the beginning of each Plant construction phase. In the first year, samples( during 5 days) near the pump station will be taken

Costs to be included in operation costs, will be established upon construction

Communal company

Environment protection inspection

Page 41: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

41

Phase Monitoring Parameter

Monitoring Place

Monitoring Method Monitoring Time

Additional Costs

Responsibility

Execution Supervision Operation Flora i fauna

• Research on flora and vegetation at the plant site

• Research on benthos communities near the Irelands Lukovnik and Logorun

• Research on plankton communities - Kaprijski Channel

flora and vegetation at the plant site; plankton and benthos communities in the see

According to special program

Start monitoring ones in a two years

Costs to be included in operation costs, will be established upon construction

Communal company

Environment protection inspection;

Operation Submarine outlet

Along the pipeline Diving inspection and syringe

Submarine outfall and diffuser shall be regularly inspected (once a year in spring) and potential defects repaired.

Costs to be included in operation costs, will be established upon construction

Communal company

Environment protection inspection; Water management inspection

Operation Watertightness Pipelines Control of corrosion resistance and watertightness of the pipes

According to sewerage network maintenance plan

Costs to be included in operation costs, cca 150kn/m3, 20 kn/m

Communal company

Water management inspection

Operation Rodents Inspection manholes (200 g/50 m)

Records of solid paraffinized baits consumption

According to sewerage network maintenance plan

Costs to be included in operation costs

Communal company

Sanitary inspection

decomm. The Investor is required to prepare a separate document in which all issues related to closing of the WWTP of the Ogulin wastewater sewage and treatment system will be elaborated. According to the Regulations on Environmental Impact Assessment, this kind of works can be the subject matter of a special Study.

Please note that if costs are not expressed in unit or total price, these monitoring costs are than pa rt of the annual remuneration for the person(s) res ponsible for monitoring activities (e.g. contractor , regional inspectorate) and will not be deducted fro m the project loan. Some prices are shown in a uni t price because the total cost will depend on the f requency of sampling determined during operation based on quality and inspection's orders.

Page 42: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2
Page 43: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

43

7.4. List of laws and bye-laws relevant to environm ental protection in the Republic of Croatia - Environmental Protection Act (OG 110/07) - Law on Nature Protection (OG 70/05) - Water Act (OG 150/05) - Waste Act (OG 178/04, 153/05, 111/06, 60/08) - Air Protection Act (OG 178/04) - Law on Physical Development and Construction (OG 76/07) - Act on Financing of Water Management (OG 150/005) - Municipal Services Act (OG 26/03, 82/04, 110/04, 178/04) - Maritime Act (OG 181/04) - Law on Protection from Noise (OG 20/03) - National Water Protection Plan (OG 8/99) - Plan of Intervention in Cases of Accidental Sea Pollution in the Republic of Croatia (OG 8/97) - Decision on Water Classification (OG 77/98) - Regulation on the Boundary Values of Parameters of Hazardous and other Substances in

Wastewaters (NG 40/99, 6/01 and 14/01) - Decision on Hazardous Substances in Water (OG 78/98) - Decision on Sea Quality Standards on Beaches (OG 33/96) - Decision on Limit Values of Pollutants in Air (OG 133/05) - Decision on Limit Values of Pollutants in Air from Stationary Sources (OG 133/05) - Decision on Critical Levels of Pollutants in Air (OG 133/05) - Decision on Locations of Monitoring Stations in National Air Quality Monitoring Network (OG 4/02) - Regulations on monitoring of emission of pollutants in air from stationary sources (OG 1/06) - Regulations on issuing of licences for monitoring of air quality and emission of pollutants

from stationary sources (OG 79/06) - Decision on categories, kinds and classification of waste, with waste inventory and list of hazardous waste (50/05) - Regulation on assessment of environmental impact (OG 64/08) - Ordinance on information and participation of the general public and the public concerned

in environmental matters (OG No. 64/08) - Regulations on limit values of indices of hazardous and other substances in waste water

(OG 40/99, OG 6/01, 14/01) - Regulations on sanitary quality of drinking water (OG 182/04) - Regulations on types of waste (OG 27/96) - Ordinance on the methods and conditions for the waste disposal, categories and

operational requirements for waste disposal sites (OG No. 117/07). - Regulations on protection of agricultural land from pollution by hazardous substances (OG 15/92) - Regulation on good agricultural practice concerning fertilizer use (OG No. 56/08). - Regulations on maximum permissible noise levels in working and living environment (OG

145/04)

Page 44: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

44

The fundamental law regulating the problems of environmental protection in the Republic of Croatia is the Environmental Protection Act (OG 110/07). This law regulates the issues of environment protection, reduction of risks for human health and lives, ensuring and improvement of the quality of life for the benefit of present and future generations. The environment protection promotes overall conservation of the quality of the environment, conservation of natural communities, rational and environment-friendly use of natural sources and energy, as the basic precondition for healthy and sustainable development. The efficiency of national environmental control is supported by the Croatian Parliament and the Government of the Republic of Croatia, and by the representative and executive agencies of local administration, through issuing of environmental protection strategies and programs, and other documents relevant to environmental protection. Professional activities in environmental protection and enforcement of environmental protection measures are supported by national government agencies and agencies of local administration in charge of environment protection, as well as by legal entities registered for carrying out professional work on environment protection. Citizens, as individuals or organized in societies for environmental protection, professional associations and other non-governmental organizations, also contribute to achieving of the goals of environmental protection and implementation of efficient environmental protection. The local administration unit regulates, organizes, finances and promotes the environmental protection activities of regional or local importance. For the purpose of achieving of coordinated economic development in accordance with the requirements of environmental protection, and of the professional and scientific basis for regulation of certain issues, the Government establishes the Council for Environmental Protection (hereafter: the Council), consisting of scientists, professionals and public activists. The Council issues the opinions, proposals and evaluations on coordination of environmental issues and economic development, and on documents proposed by the Government and the Parliament. Legal entities registered for professional activities in environment protection carry out the tasks related to monitoring of the environment status, prepare basic data and environment protection studies, prepare and elaborate the environmental impact studies, and conduct professional training in environment protection activities. The environmental protection is based on respecting of the principles of international legislation on environmental protection, generally accepted principles, respecting of scientific knowledge and best worldwide practices. The documents regulating environmental protection in the Republic of Croatia are, as follows: - Strategy of environmental protection , defining and directing, on a long-term basis, the goals of environment management in accordance with the overall economic, social and cultural development of the country, issued by the Parliament on the proposal by the Government,

Page 45: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

45

- Environmental protection programs for the territory of the County and the City of Zagreb,

containing the basic goals, conditions and criteria of environment protection in general, priority measures in components and spatial entities, and working out of the principles and guidelines of environmental protection contained in the Strategy. The environment protection program for the territory of a County or of the City of Zagreb is issued by the relevant County Assembly, or the Assembly of the City of Zagreb. The programs covering minor city or municipality areas are issued by the city or municipal council, when it is necessary to protect the environment in a specific city or municipal area to preserve cultural, historical, aesthetic and natural features of the landscape.

- Environment status reports are prepared every two years for the purpose of the Strategy

and the Programs, and other documents relevant for environment protection. Implementation of environmental protection is based on: - Environment quality standards , containing limit values for specific components of the

environment and for highly valuable, sensitive or endangered areas, defined by special regulations, if not already defined by the law.

- Environmental impact assessment, intended to provide application of the precaution

principle by adjusting and modifying of the planned project, construction, reconstruction or activity to the receiving capacity of the environment in the given area. The environmental impact assessment helps to perceive the possible adverse effects of the intended project on soil, water, air, forests, climate, human health, flora and fauna, landscape, cultural heritage, their mutual relations, taking into account other planned projects and possible interactions with existing and planned projects in the given project area. The Government defines, by its regulations, the projects that require the assessment of environmental impact, the contents, terms and methods of preparing of environmental impact studies, methods of assessment and reaching of conclusions on the intended project, ways of informing the public, and the terms and methods of public participation in decision-making, rights and duties of the parties in the process, etc. The impact of the project on the environment, its evaluation and its acceptability is assessed by the commission on the basis of the study of environmental impact. The solution giving or refusing approval of the intended project is issued by the National Authority for Environmental Protection.

- Physical plans that must include measures of protection of soil, water, air, forests, climate,

human health, flora and fauna, landscape, cultural heritage, waste management measures, noise protection and fire protection measures, and other measures for protection of the environment.

- Environment monitoring. In all projects where the assessment of environmental impact is

mandatory, the legal entities shall, through authorized firms, measure the emissions and keep the records, measure the emissions or participate in such measuring, proportional to their participation in environment pollution, and participate in monitoring of natural and other phenomena resulting from environment pollution.

Page 46: Environmental Management Plan - World Bank · PDF filetreatment plant via long submarine outfall that will be situated southwest of the straight ... Environmental Management Plan 2

Coastal Cities Control Pollution Project

Environmental Management Plan

46

- Inventories of environment pollution , kept by the County or City of Zagreb office in charge of environmental protection.

- Environment protection information system , established by the National Authority for

Environmental Protection, in cooperation with the ministries and national administration agencies.

- Environmental protection intervention plans, etc. Administrative control over implementation of the Environment Protection Act and regulations based on the Act is exercised by the National Authority for Environmental Protection. Implementation of enforcement of the Act, regulations and other individual acts, conditions and operating methods of legal entities, and of environment protection measures are inspected by the environment protection inspector and other inspectors within their respective capacities. The environment protection inspection may also be performed by another employee of the National Authority for Environmental Protection, if authorized by the Director. The inspection on the first level is carried out by the County office (or City of Zagreb office) in charge of environment protection, and on the second level, by the National Authority for Environmental Protection. Besides the above agencies, in the Republic of Croatia there are many professional institutions and non-governmental organizations dealing with environment protection. The list of legal entities authorized by the Ministry of Environmental Protection, Physical Planning and construction for professional activities in the field of environment protection is given on the Ministry web-site. Finally, besides the above fundamental law, the problems of environment protection are dealt with by a number of other laws and bye-laws, the most important of them being listed in this annex.