Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
UNCONTROLLED DOCUMENT WHEN PRINTED
Environmental Management System
Underground Operation
ENVIRONMENTAL MANAGEMENT PLAN
Revision Issue Date Originator Reviewed Approved
DRAFT 1/12/08 C. Ellis K. Barry, D. Webb, M. Bobyldyk, B. Corbett, P. Webster
0 8/12/08 C. Ellis B. Corbett K. Barry
1 3/02/09 C. Ellis C. Ellis K. Barry
Doc No: EMP_0006 Greenhouse Gas
Minimisation Plan
Doc Owner: Environmental Advisor – Integra Underground Operation
Approval:
Health, Safety, Environment and Training Superintendent Integra Underground Operation
Signed:
Date:
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 2 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
Table of Contents
1. Introduction -------------------------------------------------------------------------------------------- 3
2. Purpose ------------------------------------------------------------------------------------------------ 3
3. Scope --------------------------------------------------------------------------------------------------- 3
4. References -------------------------------------------------------------------------------------------- 4
5. Definitions ---------------------------------------------------------------------------------------------- 4
6. Development of Environmental Management ------------------------------------------------- 4
6.1. Guiding Principles -------------------------------------------------------------------------- 4
6.2. Background ---------------------------------------------------------------------------------- 5
6.3. Opportunities -------------------------------------------------------------------------------- 9
6.4. Feasibility of Options --------------------------------------------------------------------- 10
7. Procedural Requirements ------------------------------------------------------------------------- 12
7.1. Monitoring Requirements ---------------------------------------------------------------- 12
7.2. Reporting Requirements ----------------------------------------------------------------- 13
8. Reviews ----------------------------------------------------------------------------------------------- 13
9. Auditing ------------------------------------------------------------------------------------------------ 13
10. Corrective Actions ---------------------------------------------------------------------------------- 14
11. Document Control ----------------------------------------------------------------------------------- 14
12. Records ----------------------------------------------------------------------------------------------- 14
13. Roles and Responsibilities ------------------------------------------------------------------------ 14
13.1. Manager of Mining Engineering -------------------------------------------------------- 14
13.2. Health, Safety, Environment and Training Manager ------------------------------ 15
13.3. Technical Services Manager------------------------------------------------------------ 15
13.4. Manager of Engineering ----------------------------------------------------------------- 15
13.5. Manager of Electrical Engineering ---------------------------------------------------- 15
13.6. CHPP Production Superintendent ----------------------------------------------------- 15
13.7. Environmental Advisor ------------------------------------------------------------------- 15
13.8. Ventilation Officer ------------------------------------------------------------------------- 16
13.9. Purchasing Officer ------------------------------------------------------------------------ 16
14. Associated Documentation ----------------------------------------------------------------------- 16
15. Appendices ------------------------------------------------------------------------------------------- 16
15.1. Appendix 1 ---------------------------------------------------------------------------------- 16
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 3 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
1. Introduction
This Greenhouse Gas Minimisation Plan forms part of a group of Environmental
Management Plans at the mine. The plans deal with major environmental issues requiring
management as prescribed by relevant consent approval authorities, and additional issues
identified during Integra Coal’s risk management process as potentially high-risk activities at
the underground operation.
This Greenhouse Gas Minimisation Plan outlines the actions required and persons
responsible in order for the organisation to reduce potential Greenhouse Gas emissions in
order to continually improve environmental performance at the Integra Coal Underground.
2. Purpose
This Greenhouse Gas Minimisation Plan has been structured to reduce potential
Greenhouse Gas emissions, more specifically this plan is designed to;
a) identify options for minimising greenhouse gas (GHG) emissions from underground
mining operations, with a particular focus on capturing and/or using these emissions
(covered in Section 6.3);
b) investigate the feasibility of implementing each option [covered in Section 6.4];
c) proposed the measures that would be implemented in the short to medium term on
site [covered in Section 6.4]; and
d) include a program to monitor and report of the effectiveness of these measures
[covered in Section 7].
3. Scope
This Greenhouse Gas Minimisation Plan applies specifically to Integra Coal Operation’s
Underground Mine. It identifies options for minimising GHG emissions from the underground
mining operations and other major support activities. It does not cover the coal washing and
dispatch process as this occurs at the Integra Coal Operations Open Cut site.
The mine’s hazard management plans (specifically HMP_0101 – Mine Atmosphere and
HMP_0103 – Spontaneous Combustion) are in place to ensure the safety of the workforce,
and must be adhered to at all times. If any inconsistency of gas management occurs as a
result of this Greenhouse Gas Minimisation Plan, the HMP_0101 and HMP_0103 documents
shall prevail.
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 4 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
4. References
Intergovernmental Panel on Climate Change – Glossary of Terms 1995
Australian National Greenhouse Accounts Factors Workbook – November 2008
Project Approval 06_0213 – Glennies Creek Underground Coal Project (NSW Department of
Planning)
5. Definitions
Greenhouse Gas (GHG) – Any gas such as water vapour (H2O), carbon dioxide (CO2),
nitrous oxide (N2O), methane (CH4) and ozone (O3) that contribute to the greenhouse effect
when released into the Earth’s atmosphere. In the context of this plan the term greenhouse
gas relates primarily to methane and carbon dioxide as these are the principle GHGs
emitted.
Ventilated Air Methane (VAM) – Dilute methane contained within the main ventilation circuit
which circulates throughout the mine prior to being expelled through the main ventilation
fans.
6. Development of Environmental Management
6.1. Guiding Principles
• We understand the issue of climate change is of fundamental importance to the
environmental, economic and social sustainability of the planet, and that it can affect
our business activities.
• We recognise the existence of scientific evidence of global warming, and that this is
directly related to the increase in concentration of greenhouse gases in the
atmosphere associated with anthropogenic activities.
• It is our understanding that climate change can have implications for our strategic
plans, and that therefore actions should be undertaken to evaluate the risks to our
business, minimising vulnerabilities and maximising opportunities.
• It is our understanding that coal and other fossil fuels will continue to have an
important role in the global energy matrix, and that there is a need to strive for a
balance between energy security and climate security.
• We consider that the development and dissemination of technology are fundamental
aspects for dealing with climate change.
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 5 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
• We are committed to participating in the global effort seeking to stabilise the
concentration of greenhouse gases in the atmosphere at acceptable levels and by
employing our best efforts according to the regulations in force and aligned with
these guiding principles, promoting coordinated actions at our operation in order to
obtain this objective.
• We recognise that the nature of our industrial activity and size of our operation can
potentially result in significant greenhouse gas emissions.
6.2. Background
Integra Coal Underground has a mining lease that covers the Middle Liddell, Hebden and
Barrett coal seams within Coal Lease 382, additional coal seams also exist within the
interburden of the lease area. Integra currently has approval to mine 17 longwall panels in
the Middell Liddell seam along with the associated development roadways and to undertake
a cut and flit trial. Integra is currently completing the environmental assessment for mining
within the Hebden and Barrett seams, and plans on conducting both longwall and bord and
pillar extraction within these seams, along with the development of associated underground
roadways.
The total remaining coal reserves within all the above mentioned areas is in the vicinity of 80
million tonnes.
It is noted that GHG emissions may fluctuate based on the strata conditions, i.e. varying
ventilation connectivity to under and overlying seams based on localised strata conditions,
and also the production rate, i.e. underground coal recovery, due to the fact that methane is
released from the coal seam bodies during the mining process and subsequently. As such
the rate of mining will effect methane emissions, as will as a number of other external factors
such as barometric pressure, strata conditions and the integrity of ventilation control devices
that separate the goaf areas from the mine ventilation network. Electricity use and hence
GHG emissions from the electricity generation activities elsewhere, is also linked to coal
production. For example, if the conveyor system is loaded with coal it draws more load and
hence uses more electricity than if there was no coal on the conveyor system. Additionally
all the main mining systems, that is, the longwall mining system, continuous miners and
shuttle cars, are electrically powered and utilise more electricity to achieve higher levels of
production.
As such, in order to evaluate the mines emissions with respect to the minimisation activities
implemented, the GHG emissions will need to be measured against the Run of Mine (ROM)
coal productions levels, to give a Greenhouse Performance Indicator (GPI). The GPI will be
calculated by dividing the total GHG emissions for any specific period by the ROM coal
produced for the same period, and will be used in conjunction with data such as volume of
GHG captured and used for power generation, to determine how effective the measures
implemented have been.
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 6 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
While the total GHG emissions will be monitored and reported, simply reporting this number
without assessing other external factors over the reporting period would not allow the
efficiency of the minimisation activities to be assessed.
Currently GHG exits the mine through two main processes, the first being a number of
surface to goaf gas drainage boreholes (Figures 1, 2, and 3), some of which are currently
connected to the Glennies Creek Power Station (Figure 4), which utilises the waste methane
to generate electricity which is subsequently fed into the State’s power grid for distribution.
The second process is mine ventilation which utilises two fans to draw air through the mine
to the exit point at the ventilation shaft site (Figure 5). These two processes as discussed
later, form the major routes to liberate GHG emissions, and as such have been targeted in
this GHG Minimisation plan.
While Integra Coal aims to reduce and manage GHG emissions, it is noted that as the
underground mine workings increase in area, the GHG emissions may increase due to the
increased surface area of underground workings and hence increased liberation of coal
seam methane. As a result, it is important to implement all practical options identified in this
report.
Figure 1: Surface to goaf gas drainage borehole with extraction equipment fitted.
Stack
Gas extraction fan
Fencing
Borehole to underground
goaf
Waste gas exits here
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 7 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
Figure 2: Surface to goaf gas drainage borehole free venting (due to buoyancy of gasses).
Figure 3: Surface to goaf gas drainage borehole with connection to the Glennies Creek
Power Station.
Lightning protection
Stack
Condensate collector
Borehole to underground
goaf
Telemetry equipment
Pipeline to power station
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 8 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
Figure 4: Glennies Creek Power Station (showing 5 of the 10 generators present)
Figure 5: The main ventilation fans.
Fan # 2
Ventilation shaft
Fan #1
Gas monitoring room
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 9 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
6.3. Opportunities
In order to investigate options for minimising greenhouse gas emissions at Integra Coal
Underground, a review of the major greenhouse gas sources was conducted.
The review identified the following three major sources of direct GHG emissions, listed from
highest to lowest GHG emission levels.
1. Mine ventilation air which exits the mine from the upcast shaft at the Ventilation Shaft
Site on Forest Rd (Figure 5).
2. Surface to goaf gas drainage boreholes, which remove coal seam methane from the
longwall goafs during and subsequent to longwall extraction (Figures 1, 2 and 3).
3. Combustion of automotive diesel oil which is used to fuel some underground mine
vehicles and surface plant.
It was also noted that the purchase of electricity, although not a direct GHG emission,
contributes significantly to GHG emissions.
A summary of the major GHG emissions is listed in Table 1. Note that the conversion factors
to give tonnes of CO2 equivalent emissions were calculated using the Australian National
Greenhouse Accounts Factors Workbook – November 2008.
Table 1: Major GHG emission sources
Activity Tonnes of CO2-e emitted
Mine Ventilation through main fans (06-07 period) 594,300
Surface to goaf gas drainage boreholes (06-07 period) 191,100
Combustion of diesel fuel (07-08 period) 4,408
Electricity used (07-08 period) 31,158
From the review, a number of GHG reduction options were identified to be further
investigated. These included.
1. Capturing and flaring methane from the surface to goaf gas drainage boreholes.
2. Capturing and piping methane from an increased number of surface to goaf gas
drainage boreholes to the Glennies Creek Power Station.
3. Modification of the mine ventilation system to decrease VAM (Ventilated Air
Methane).
4. Increasing gas emissions from surface to goaf gas drainage boreholes to reduce
VAM and increase methane quantities captured and reused.
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 10 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
5. Use ventilated air methane (VAM) as combustion air in methane powered
generators.
6. Investigate VAM destruction/utilisation technologies.
7. Relocated air compressors to more efficient position.
8. Undertake pre drainage of the Hebden Seam and utilise gas in the Glennies Creek
Power Station.
The feasibility of the above options are discussed in Section 6.4.
6.4. Feasibility of Options
In Section 6.3 eight options were identified as having potential for GHG emission reductions.
The feasibility assessment for these options was predominantly carried out by Energetics
Pty Ltd, who were contracted to complete a “Methane Management Strategy” in consultation
with Integra Coal. It is noted that given the timeframe this Minimisation plan was required in,
some feasibility investigations are still ongoing. As a result, this document will be reviewed
and updated as per Section 8, and information relating to the feasibility of options will be
updated in due course.
Investigation of option feasibility;
1. Flare methane from surface to goaf gas drainage boreholes – Determined as
feasible, but less desirable than capturing and reusing methane from the surface to
goaf gas drainage boreholes. To be implemented only if option 2 (capture and pipe
methane to existing generator) does not proceed.
2. Capture and pipe methane to existing generator – Determined as feasible, with
actions to be implemented as per Table 2.
3. Modification of the mine ventilation system to decrease VAM – Currently still
determining feasibility.
4. Increasing gas emissions from surface to goaf gas drainage boreholes to reduce
VAM and increase methane quantities captured and reused - Determined as feasible,
with actions to be implemented as per the final action on Table 2.
5. Use VAM as combustion air – Currently still determining feasibility.
6. Investigate VAM destruction/utilisation technologies – Currently still determining
feasibility
7. Relocate air compressors to more efficient position – Determined as feasible, with
actions to be implemented as per Table 2.
8. Pre drainage of the Hebden Seam – Currently still determining feasibility.
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 11 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
Table 2: Proposed GHG emission reduction measures to be implemented
Proposed measure Date to be
implemented
Person Responsible
Connection of surface to goaf gas
drainage boreholes 8/3 and 8/4 to
the Glennies Creek Power Station
January 2009 Technical Services Manager in
consultation with the operator of
Glennies Creek Power Station
Connection of surface to goaf gas
drainage boreholes 9/3 and 9/4 to
the Glennies Creek Power Station.
Expected by
April 2009
(subject to mine
schedule)
Technical Services Manager in
consultation with the operator of
Glennies Creek Power Station
Connection of surface to goaf gas
drainage boreholes 10/1, 10/2, 10/3,
10/4 and 10/5 to the Glennies Creek
Power Station
Expected by
April 2010
(subject to mine
schedule)
Technical Services Manager in
consultation with the operator of
Glennies Creek Power Station
Relocation of air compressors to
Forest Rd Ventilation Shaft Site,
and subsequent reticulation of
compressed air underground
August 2009 Manager of Engineering
Connection of future surface to
goaf gas drainage boreholes for
the Middle Liddell seam (exact
locations currently undetermined)
as required for extraction of
longwalls 11 through 17, to the
Glennies Creek Power Station
As they
become
operational
Technical Services Manager in
consultation with the operator of
Glennies Creek Power Station
Leave connections of gas drainage
boreholes open to Glennies Creek
Power Station, subsequent to
Integra Coal gas drainage
infrastructure being moved to
newer boreholes
Ongoing Technical Services Manager in
consultation with the operator of
Glennies Creek Power Station
It is noted that completion of actions within Table 2 may be subject to land access
agreements, additional regulatory approvals and land owner consent and/or environmental
and community impact assessment. While Integra Coal will aim to implement the above in
the timeframe listed. It should be recognised that the complexity of some options may result
in extended timeframes.
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 12 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
7. Procedural Requirements
7.1. Monitoring Requirements
In order to evaluate the effectiveness of this Plan, various data will need to be collected and
analysed in order to accurately determine if the plan is being effective. This data would
include electricity use, diesel use, methane emissions and waste volumes.
Table 3 outlines the persons responsible for the provision of data to allow the reporting
requirements in Section 7.2 to be fulfilled.
Table 3: Data required for reporting purposes
Data Frequency Person Responsible
Site electricity use Biannually in January and July (for the
previous 6 months)
Manager of Electrical
Engineering
Site diesel use Biannually in January and July (for the
previous 6 months)
Purchasing Officer
Methane emissions Biannually in January and July (for the
previous 6 months)
Ventilation Officer
ROM coal
production
Biannually in January and July (for the
previous 6 months)
CHPP Production
Superintendent
Methane utilised to
generate power
Biannually in January and July (for the
previous 6 months)
Operator of Glennies
Creek Power Station
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 13 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
7.2. Reporting Requirements
A report based on the data collected in Section 7.1 will prepared in February and August of
each year and a summary of the data contained within the reports will be included within the
Annual Environmental Management Report.
Information to be contained within the report will include:
• GHG emissions by source;
• total greenhouse gas emissions;
• GHG emissions captured and reused in reporting period (preceding 6 months);
• activities carried out in the reporting period to reduce GHG emissions;
• Calculation of the Greenhouse Performance Indicator;
• comments regarding the effectiveness of the activities carried out to reduce GHG
emissions
• a comparison of the Greenhouse Reporting Indicator against previous indicators;
• an explanation of the changes in GHG emissions from the base data (to be contained
within the first report);
• any other information deemed relevant to GHG emission reporting; and
• outcomes / progress of further reduction option investigations.
8. Reviews
The review of this document will be in line with the sites Environmental Management
Strategy (OMP_0200). That is, reviews will be conducted annually, after independent
environmental reviews and as required by relevant consent conditions. The purpose of the
review is to ensure that the Environmental Management System, including this document,
remains suitable, adequate and effective.
9. Auditing
Internal and external audits of this Environmental Management Plan will be carried out as
per the Environmental Management Strategy (OMP_0200). Internal and external audits
shall be objective, and be conducted by persons or an organisation not associated with the
preparation or implementation of the Environmental Management Plan being audited.
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 14 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
After an Environmental Audit is completed, and if changes are recommended to the
Greenhouse Gas Minimisation Plan (EMP_0006), Integra shall review and, where
necessary, revise the Greenhouse Gas Minimisation Plan to the satisfaction of the Director-
General (NSW Department of Planning). The revised Greenhouse Gas Minimisation Plan
will be submitted to the Director-General within 6 months of the audit and revision.
10. Corrective Actions
Any non-compliance with this Environmental Management Plan will be managed in accordance with the Environmental Management Strategy (OMP_0200).
11. Document Control
Integra will maintain a Document Control System which is available to all personnel. The system will contain all approved Environmental Management Plans, Procedures, and Registers etc and be administered by a Document Control Administrator.
Any request for change shall be via the “FRM_0088 Document Change Request” Form
which can be obtained from the Document Administrator or be downloaded from the
Document Control Database via the Integra Coal intranet.
12. Records
All information pertaining to this Environmental Management Plan shall be maintained within the Integra Underground’s documents control record system.
All records are stored so that they are legible, readily retrievable and protected against
damage, deterioration and loss. Records are maintained for a minimum of 4 years.
13. Roles and Responsibilities
13.1. Manager of Mining Engineering
The Manager of Mining Engineering is accountable for the Environmental performance of the
Integra Coal Underground operation.
The Manager of Mining Engineering is also responsible for the provision of resources to
enable the implementation and ongoing reviews of this management plan.
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 15 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
13.2. Health, Safety, Environment and Training Manager
The Health, Safety, Environment and Training Manager is responsible for appointing and
managing the Environmental Advisor so as to ensure that all required actions are being
completed by the Environmental Advisor.
13.3. Technical Services Manager
The Technical Services Manager is responsible for ensuring the actions outlined in Table 2,
allocated to Technical Services Manager are conducted as per the required timeframe.
13.4. Manager of Engineering
The Manager of Engineering is responsible for ensuring the actions outlined in Table 2,
allocated to the Manager of Engineering are conducted as per the required timeframe.
13.5. Manager of Electrical Engineering
The Manager of Electrical Engineering is responsible for providing information as designated
in Table 3.
13.6. CHPP Production Superintendent
The CHPP Production Superintendent is responsible for the provision of information as
designated in Table 3.
13.7. Environmental Advisor
The Environmental Advisor is responsible for:
• the collection of data from nominated persons under this Minimisation plan as
required to complete the 6 monthly reports;
• the collation of data into the 6 monthly report and review of any outstanding actions,
and subsequent notification to the action owner;
• the completion of the Annual Environmental Management Report;
Underground Operation Environmental Management Plan EMP_0006
Document Owner Issue Number / Date: Next Review Date: Page: Environmental Advisor 1 / 03-02-2009 03-02-2010 16 of 16
UNCONTROLLED DOCUMENT WHEN PRINTED
• ensuring the information required is displayed on the Integra Coal website; and
• the review of this document as required under Section 8.
13.8. Ventilation Officer
The Ventilation Officer is responsible for the provision of information as required in Table 3.
13.9. Purchasing Officer
The Purchasing Officer is responsible for the provision of information as required in Table 3.
14. Associated Documentation
OMP_0200 – Environmental Management Strategy
HMP_0101 – Mine Atmosphere Hazard Management Plan
HMP_0103 – Spontaneous Combustion Hazard Management Plan
15. Appendices
Appendix 1 - Excerpt from Project Approval 06_0213
15.1. Appendix 1
Excerpt from Project Approval 06_0213;