93
Global Environmental Fund( GEF) /The World Bank The Commercialized Development of Chinese Regenerated Energy Project Phase ? Project of Changjiang’ao Wind Power Field in Pingtan of Fujian Environmental Impact Assessment East China Investigation and Design Institution June, 2004 Hangzhou Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Environmental Impact Assessment · Phase?Project of Changjiang ’ao Wind Power Field completed construction, and went into operation in Oct. 2000. The total capacity is 6000kW with

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Global Environmental Fund( GEF) /The World Bank

    The Commercialized Development of Chinese

    Regenerated Energy Project

    Phase? Project of Changjiang’ao Wind Power

    Field in Pingtan of Fujian

    Environmental Impact Assessment

    East China Investigation and Design Institution

    June, 2004 Hangzhou

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    AdministratorE1048 vol. 1

  • -1-

    Project Name: Phase?Project of Changjiang’ao Wind Power Field in

    Pingtan of Fujian

    Document:: Environmental Impact Assessment Report

    Participated by:

    Yang Jin Master of Science

    Yu lan Engineer

    Li jiapei Senior engineer

    Checked by:

    Yu lan Engineer

    Reviewed by:

    Wang yinlong Senior engineer

    Approved by:

    Rui Bingliang Senior engineer, chief engineer

    EIA Organization: East China Investigation and Design Institute

    EIA Certificate: Guohuanping Class A No. 2001

    Entrusted by: The Arrangement Office of Phase? of Changjiang’ao Wind

    Power Field

  • -1-

    Executive Summary

    1. Preface

    Entrusted by ‘the Arrangement Office of Phase? of Changjiang’ao Wind

    Power Field ’, ECIDI completed “Environmental Impact Assessment of Phase II

    Project of Changjiang’ao Wind Power Field” (EIA) report on June 2004.

    This paper based on EIA is just a summary of main project impact,

    environmental management plan, and environmental monitoring plan for

    Phase? Project of Changjiang’ao Wind Power Field.

    2. Project Descriptions

    Changjiang’ao Wind Power Field lies in inland of bay at the northeast of

    Pingtan County, 10km away from the downtown of Pingtan. Fig.1 shows its

    Ilocation.

    Phase?Project of Changjiang’ao Wind Power Field completed construction,

    and went into operation in Oct. 2000. The total capacity is 6000kW with 10

    units of wind turbine manufactured at BAZAN Company of Spain, all of which

    were BAZAN-BONUS 600kW MK-IV fix-distance blades. It’s planned that total

    installed capacity will be 100.5MW with 67 units of 1.5MW wind turbines of

    Phase? Project of Changjiang’ao. By theoretical calculation, the yearly output

    of wind power will be 273.286GWh, power utilization of 2719h and power to

    the net of 259.622GWh, utilization by selling power of 2583h, and capacity

    coefficient of 0.295.

    Wind turbine units were arranged perpendicular to northeast, the prevail

    wind direction, whereas the 67 turbine units arranged as plum-like shape

    which distances of row/column are 8D(560m)× 5D(350m) around the 10

    turbines of Phase I Project. The general layout of the project is shown at Fig.2.

    The substation locates at the northwest of the pre-central control building.

    The substation connected to the power grid with 2 output loops of 110kV

    voltage.

  • -2-

    The land occupation is total 908.4 mu (1 mu=666.7m 2), in which 478.61mu

    of permanently, and 429.43 mu of temporarily. It’s planned that the

    construction area of each wind turbine is 70m×70m (including land

    occupation of the wind turbine) for pilling up equipment and material and

    turbine installation.

    It’s preliminary estimated that the construction period of Phase II Project is

    24 months after the feasibility research and the loans examined and approved

    by the World Bank.

    The total cost of the project is RMB 859,940,000 yuan.

    3. Surrounding Environmental Conditions

    Changjianao Wind Power Field lies at the inner land area of the bay, the

    northwestern part of Pingtan Island. It locates at the barranca, where Hutou,

    Junshan, yangmei and Yanglei Mountains or hills are in its southeast, and a

    series hills called Yandui, Longtou, Furongzhai in its northwest. The Project

    site lies in the barranca area between two series of mountains and hills , and its

    special geographical location determined its superior wind energy resource.

    There is no big river at the site area, but a relatively small stream called

    Shangpanhu with less flow.

    Cultivated land and forestland are the main land types. The cultivated land

    vegetation is crops, such as potato, wheat, peanut, etc., and the forest land,

    wooden ephedra and a small amount of jequirity trees, black pines and

    wetland pines, which all belong to the shelter forestry.

    Construction area isn’t migratory bird's habitat and migratory route, and no

    rare protected animals were found there.

    The land occupation of the project mainly belongs to Luyang Village,

    Pingyuan town, Zhonglou Village and state-owned Changjiang Forest Farm. At

    present, there is a “Hupuqian Relic Site”, where is 400m away from the

    southwest of 46# wind turbine, which is the Neolithic culture remains about

    5000- 6000 years old, un-developed up to now, and expected to be further

  • -3-

    explored.

    A mining area of 20,000 m2 lies in the northwest of 59# wind turbine, and

    the quartz sand is the main products for sale.

    A Piggery Farm of “Development Co.,Ltd. of Sunshine Ecological

    Agriculture” is building at the north of 44# wind turbine. It is estimated 10,000

    pigs supplied annually.

    4. Main Environmental Impacts

    ( 1) Environmental Impact during construction period

    Noise is mainly caused of construction machines, such as excavating

    machines and the transportation trucks, etc. According to predicting, there is

    only certain acoustic influence to 3 sensitive points which are Shanxianmei,

    Guanlouxia and Hupuqian, the predict noise values of which are 62dB, 61dB

    and 64dB during construction period. Since no sensitive spots in 200m range

    along the entrance road, it’s lightly influences acoustic environmental quality of

    communication noise from transportation vehicles

    Production waster water and domestic sewage are main water pollution

    source. Domestic sewage contains CODCr and BOD5. After being treated by

    septic pit and sewage treatment facilities underground, domestic sewage is

    shed in the forest land nearby directly, consuming in form of evaporating or

    leakage. Production wastes water of construction mainly come from concrete

    mixer and construction machines rinsing. Production wastewater contains oil

    and SS, which is reused after processing.

    Because of the dust source is low and the diameter of particle is relatively

    large, so air impact on surrounding environment is mainly bounded to the

    range of construction. There are no sensitive spots in 200m ranges along the

    construction roads, no impact on atmosphere environmental quality of

    automobile tail gas and dust

    The area of permanent forestland occupation is 749.71mu,which accounts

    for 4.6% of the total forestland area in the site area. Besides the permanent

  • -4-

    land occupation, the temporal land occupation will be recovered after the

    project construction. So the wind power project will not influence the local

    ecological environment.

    It is estimated that the total excavation amount is 42,500m 3, the total

    backfill amount is 49,500 m3.The dreg from access excavation can be used for

    the backfill of wind turbine basis. Through the volume balance of excavate

    and backfill, there are no abandoned discards in project. The soil erosion

    during constructing period is about 1350t, so the water and soil conservation

    plan is needed. And the owner should engage the unit with qualification to edit

    water and soil conservation plan and complete this plan before the project

    starts. After site excavation, concrete poured and site backfilled must be done

    in time to decrease water and soil conservation. In case of construction ending

    temporary occupation land must be restored or vegetation of trees and bushes

    such as wood ephedrine and black pines to prevent erosion. It is not allowed to

    cut other trees around the site except those had to be cut at the project

    occupation land. Discards from road excavation must be transported to

    installing site nearby in time, which are used to backfill the tower base, or piled

    up at the site and covered with engineering cloth to those may not be used

    promptly. Protection slopes of the excavation road sections should be built at

    the end of excavation to avoid soil erosion of slopes.

    The basis of tower is already designed to avoid residents’ houses, there is

    no house needed to be pulled down.

    ( 2) Environmental Impact during operation period

    Pingtan County is an island, where is lack of water resource, except the

    6MW wind power generators installed; power supply mainly depends on the

    provincial grid. In this place, it may meet not only needs of power of Pingtan

    County, but also enhance the reliability of the power supply, as well as reduce

    the pressure of the power supply of the provincial grid, thus local regional

    economy and social continuous development will be stimulated up.

  • -5-

    The main noise source during operation period came from wind turbines .

    According to the confirmed standards of the local Environment Protection

    Bureau (see annex4), standard of Level 2 (60dB) of is in use. Prediction shows that the noise

    value at every sensitive spot meet the Level 2 standard above at daytime and

    only 3 spots of Shanxianmei, Guanlouxia ND sw Hupuqian exceed the

    standard (50dB) slightly at night, the maximun exceeding is only 3.3dB. It may

    be eliminated the unfavorable noise impact that Turbine 39#, 47#, 63# and 64#

    etc are move to the direction of sensitive spots far away 50m-100m.

    The sewage of the staffs can be treated by the existing sewage treatment

    facilities, then discharge into natural ditches. The oil water from the substation

    can be collected into the oil pool, and then transported to the professional unit

    for treatment and it will not affect the surrounding environment.

    Solid wastes are mainly consisting of the domestic rubbish of workers. It’s

    estimated that each person generates 1.0kg wastes every day, the amount of

    the domestic rubbish is about 5.0kg/d. Because the increase of the domestic

    rubbish is relatively small, so we can handle with the rubbish of Phase I Project

    altogether and the rubbish will not affect surrounding environment adversely.

    5 Environmental Management Plan

    Environmental Management Plan includes Environmental mitigation

    action plan, Environmental supervision plan and Environmental monitoring

    plan.

    Environmental mitigation action plan define how to take measures, who

    does, who is responsible authority; Environmental supervision plan guarantees

    the completion of the action plan, and realize the environmental target of the

    project; Environmental monitoring Plan describes monitoring items, frequency,

    method, factor, unit, responsible department and monitoring cost.

    The detailed content may be reviewed at the EIA report.

    Environmental management and monitoring organizations are the

    important insurance for plan completion. Fig. 1 and Fig. 2 are organization

  • -6-

    structuring.

    Fig.1 Environmental management Organization Chart

    The

    World

    Bank

    The arrangement office of Changjiang ’ao ? wind power field

    Supervision Company

    Contractor

    Construction Site Affeced area

    Environmental

    Protection Bureau

    and relevant local

    department

    Monitoring

    unit

    Fujian Changjian’ao ?Wind Power

    Field Co. Ltd.

    Supervising Administration and exclusive

  • -7-

    Fig. 2 Organizational Institution for Environmental Monitoring

    The Pingtan Environmental Monitoring Station works out the monitoring

    reports four times every year of construction period, once each season and

    then once one year during operation period. The report should be given to the

    Phase? Project of the Wind Power Field Arrangement Office, and the report

    is also submitted to the World Bank and Pingtan Environmental Protection

    Bureau at the same time by Phase ? Project of the Wind Power Field

    Arrangement Office.

    6 Analyses of Alternatives

    Fuzhou Environmental Protection Bureau

    Pingtan Environmental Protection Bureau The World Bank

    The arrangement office of Changjiang’ao ? wind power

    Supervision company

    Construction site Project affected areas

    External monitoring

    Contractual and managerial relationship

    Information exchange and submitting report

  • -8-

    (1)“without project” analysis

    If there is no this project, the yearly increase for power demand of Pingtan

    County will continue relying on the provincial power grid . Considering power

    from thermal plant, then the thermal plant will consume more 90,000t coal

    every year, which increase 13,200t of CO2, 1700t of SO2, 890t of NOx every

    year, and produce 21,000t of solid discards at the same time. More pollution to

    local environment will be occurred.

    (2)”alterative project” analysis

    Compared with Changjiang’ao and Longwangtou areas, Longwangtou

    area is not able to install 100,000kw wind power of its natural conditions , and

    construction will generate more impact on surrounding landscape and

    protection zone of drinking water. There is abundant wind-force source at

    Changjiang’ao field and little influence to surrounding environment, so it is

    recommended as the project location.

    7 Public Participation Information Disclosing

    In order to obtain the opinions from the influenced people and social

    groups, flowing 4 methods are adopted:(1) Issue survey sheets to the public

    for specific survey in May, 2004. 15 organizations and 26 personnel’s were

    investigated; (2) A symposium meeting about environment and immigrants was

    held at the Government of Pingtan on May 26, 2004,to consult the opinion of

    impacted residents for project construction. More than 20 impacted residents

    attent the meeting; (3) Let out project information through news media; (4)

    Publicize the “Environment Impact Assessment Report ” for collecting public

    comments and opinions at the office of the Government of Pingtan.

    It is clear from the investigation, local people supported the project

    actively. The public mainly paid close attention to noise, ecology, resettlement

    etc .

    The owner express that they will offer the rational economic compensation

    for permanent land occupation, this compensation fund will be used afforest

  • -9-

    vegetation in other place; temporary occupation land will restore vegetation in

    time after constructing. All compensation of resettlement will be based on state

    standard with the local actual conditions, and ensuring resident's interests.

  • LIST OF CONTENTS

    CHAPTER 1 PREFACE..........................................................................................1

    1.1 Background.............................................................................................1

    1.2 Basis for Environmental Impact Assessment....................................1

    1.3 Scope of Environmental Impact Assessment....................................3

    1.4 Methodology of Environmental Impact Assessment ........................4

    1.5 Project Impacts ......................................................................................5

    1.6 Recommended Mitigation Measures ..................................................6

    CHAPTER 2 SURVEY OF THE PROJECT.........................................................7

    2.1 Geographical Location ..........................................................................7

    2.2 Scope of the Project..............................................................................7

    2.3 Introduction of the Phase I Project of the Wind Power Field ..........7

    2.4 Survey of the Phase II Project of the Wind Power Field .................8

    2.5 Civil engineering ....................................................................................9

    2.6 Ventilating ............................................................................................ 10

    2.7 Construction planning .........................................................................11

    2.8 Installation for the wind turbine......................................................... 12

    2.9 General construction schedule......................................................... 14

    2.10 Labors ................................................................................................ 14

    2.11 General investment of the project.................................................. 14

    2.12 Project characteristics...................................................................... 14

    CHAPTER 3 PRESENT EIA AND ASSESSMENT............................................ 16

    3.1 Brief introduction................................................................................. 16

    3.2 Survey of natural environment.......................................................... 16

    3.3 Survey of Social Environment .......................................................... 19

    3.4 Present Environmental Quality......................................................... 23

    CHAPTER 4 EIA AND MITIGATION MEASURES.......................................... 25

    4.1 Acoustic Environment Impact ........................................................... 25

  • 4.2 Ecologic Environment Impact........................................................... 32

    4.3 Soil eros ion Impact............................................................................. 34

    4.4 Social Environment Impact ............................................................... 38

    4.5 Water Environment Impact................................................................ 41

    4.6 Environment Air................................................................................... 43

    4.7 Solid Wastes........................................................................................ 44

    CHAPTER5 ALTERNATIVES COMPARISON................................................. 45

    5.1 Instruction ............................................................................................ 45

    5.2“Without Project” analysis ................................................................... 45

    5.3 “Alternative project” analysis.......................................................... 45

    5.4 Conclusion ........................................................................................... 48

    CHAPTER6 PUBLIC PAR TICIPATION............................................................. 49

    6.1 Brief Introduction................................................................................. 49

    6.2 Method of Public Participation .......................................................... 49

    6.3 Investigation of Public Participation................................................. 49

    6.4 Information Disclosing..................................................................... 55

    CHAPTER7 ENVIRONMENTAL MANAGEMENT PLAN .............................. 56

    7.1 Composition of environment management plan (EMP)................ 56

    7.2 Environmental management and environment monitoring

    organizations..................................................................................................... 57

    7.3 Environmental management plan .................................................... 61

    7.4 Training plan for environmental protection ..................................... 71

    7.5 Work schedule..................................................................................... 72

  • Table List

    Table 1-1 The Scope of EIA ............................................................................3

    Table 1-2 Environmental Protection Goal.....................................................3

    Table 2-1 Characteristics of the Phase II Project........................................ 14

    Table 3-1 Meteorological index of Pingtan ................................................... 16

    Table 3-2 Index of village and town affected by the Project...................... 20

    Table 3-3 Area of Ecologic public welfare forest of villages involved ....... 21

    Table 3-4 Monitoring result of noise at the Project Site (daytime)............ 24

    Table 4-1 Average noise level of main construction machines ................. 25

    Table 4-2 Calculation result of divergence decline of construction at

    daytime....................................................................................................... 26

    Table 4-3 Noise impact forecasting during operation period .................. 29

    Table 4-4 Noise impact forecasting around turbine location Adjusted..... 32

    Table4-5 Land Occupation Requisition Table .............................................. 32

    Table 4-6 The Statistical Table of Vegetation Requisition for Phase?

    Project of Changjiang’ao......................................................................... 34

    Table 4-7 Excavation/fill back Balance Table ............................................... 35

    Table 4-8 Statistical Table of Cultivated Land Requisition for Phase?

    Project of Changjiang’ao......................................................................... 39

    Table 6-1 Investigated units ......................................................................... 50

    Table 6-2 Composition of Inquired individuals and the ir Occupation .... 50

    Table 6-3 Public Participation Survey Result( unit) .............................. 52

    Table 6-4 Public Participation Survey Result( individual) ................... 53

    Table6-5 Reports on Changjiang’ao ? by News Medium...................... 55

    Table 7-1 Environmental Impact Mitigation Measures............................. 62

    Table 7-2 The environmental supervision plan......................................... 66

    Table7-3 Environmental Monitoring Plan ................................................... 68

    Table 7-4 Training Plan................................................................................. 72

  • Table 7-5 Time Schedule for Environmental Management..................... 73

    Figure List:

    Fig.2-1 Present Status of the Phase I Project of Changjiang’ao Wind

    Power Field ..................................................................................................8

    Fig.3-1 Present vegetations at the site ......................................................... 18

    Fig 3-2 Exploitation area at the quartz mine ................................................ 22

    Fig. 3-3 Building Piggery Farm ....................................................................... 23

    Total .................................................................................................................... 32

    Fig7-1 Environmental management Organization Chart ........................... 57

    Fig7-2 Organizational Institution for Environmental Monitoring............. 61

    Attached figure:

    Fig.1 Geographic Location of the Project

    Fig.2 Location of Sensitive Spots

    Annex:

    1 Certification of the Forest-Resource Administration Station of Pingtan

    County of Fujian Province

    2 Certification of Culture Administration Bureau (Sports Bureau) of Pingtan

    County

    3 Tables of The public questionnaire (group,& individual) for EIA of the

    Phase II Project of Pingtan Changjiang’ao Wind Power Field

    4 The confirmed standards for EIA of the Phase II Project of Pingtan

    Changjiang’ao Wind Power Field

  • - 1-

    Chapter 1 Preface

    1.1 Background

    Pingtan County lies in the coastal area of the east of Fujian, 128km away

    from Fuzhou City. The whole county is made up of numerous islands; the

    largest island is Haitan Island, which is the first largest island in Fujian

    Province. The place nearest to the land is 2~3 nautical miles..

    Pingtan Island locates northwest of the strait in Pingtan County. There are

    tow mountains, Hutou Mountain ~ Jun Mountain ~ yangmei Mountain ~ Yanglei

    Mountain in the southeast of field location, Yandui Mountain ~ Longtou

    Mountain ~ Furong Stockaded Village in the Northwest. The wind power field

    lies in the barranca area between two mountains, its special geographical

    position has determined its superior wind energy resource.

    Pingtan county and neighboring Fuqing City are both the poor area of the

    waterpower recourses , power come from the province grid mainly. The

    Changjiang’ao ? wind power field will assigned 67 sets of wind turbines of

    1.5MW grade altogether, the total installation capacity of 100.5MW and yearly

    power yield of 260 million kW.h to electric wire netting.

    In this place establishing wind-intensity power plant, not only can meet the

    needs of using power of Pingtan county, and enhance the reliability of the

    power supply, but also can offer superfluous power sources for Fuqing city to

    reduce the pressure of the power supply of the provincial grid, thus local

    regional economy and social continuous development will be stimulated up.

    1.2 Basis for Environmental Impact Assessment

    As required by the World Bank, an Environmental Impact Assessment (EIA)

    report must be prepared for the Pingtan Changjiang’ao ? Wind Power Project.

    The project has been assigned a Category ‘B’ rating under the World Bank’s

    requirements.

  • - 2-

    The EIA report analyzes and estimates the impact of project construction

    on the ecological, Acoustic, social environments. It describes the existing

    environmental and socio-economic conditions that could be affected adversely

    or beneficially by the project, identifies potentially significant impacts, and

    recommends measures for mitigating the serious negative impacts. The report

    also suggests necessary measures for enhancing beneficial impacts.

    The following state and provincial policies, regulations and standards

    have been followed in preparing the EIA report.

    (1)Law of the People ’s Republic of China( Dec.1989)

    (2)Environmental Assessment law of the People ’s Republic of China( Sep.

    2003)

    (3)Law of the People’s Republic of China on the Conservation of water and

    Soil( Jun. 1991)

    (4) land Control Law in the People's Republic of China( Jan.1999)

    (5)Forestry Law of the People ’s Republic of China( Apr.1998)

    (6)Regulations of the People ’s Republic of China Concerning prevention of

    Environmental Noise Pollution( Mar.1997)

    (7) Law of the People’s Republic of China on Prevention of Environmental

    Pollution by Solid Wastes (Apr. 1996)

    (8) Law of the People’s Republic of China on the Prevention and Control of

    Water Pollution (May 1996)

    (9)Environmental protection management rule of the construction project( Nov.

    1998)

    (10) Land Administration Law of the People’s Republic of China (Dec.1998)

    (11) Environmental protection Rule of Fujian

    (12) Outline of National Ecological Environment Protection (the State Council,

    Dec. 2000)

  • - 3-

    (13) Classification of Environmental Protection Management for Construction

    Projects [Jan. 19, 2003].

    (14) Technical Guidelines (general as well as atmospheric , ground water and

    acoustic environment) of Environmental Impact Assessment (HJ/T2.1~

    2.3–93/2.4 – 1995)

    (15) Notification of Strengthening Environmental Impact Assessment

    Management for Construction Project Funded by International Monetary

    Organization

    (16) Feasibility Study Report of Changjiang’ao ? Wind Power Field

    1.3 Scope of Environmental Impact Assessment

    The scope of EIA covers the wind power field, the land taken up by project

    construction, central control building and the surrounding area .The scope is

    shown in table1-1.

    Table 1-1 The Scope of EIA

    EIA factor Scope

    1 Water environment

    Water areas (Shangpan brook) in the project area.

    2 Acoustic environment

    Sensitive points in the project area and in 200m ranges around, including the village and school, as shown in table 1-2.

    3 Ecological environment

    Forestland, cultivated land in the project area and 1km range around, including the animals and plants.

    Table 1-2 Environmental Protection Goal

    Village Name the nearest distance from

    the air blower( m) Request

    1 Shangpan 370

    2 Shanxianmei 145

    3 Fengmei 400 4 Wufeng 275

    5 Yuyao 200

    6 Guanlouxia 160 7 Lulou 535 8 Xibianlou 275

    9 Yangjia 325 10 Kunhulou 290

    ? level of “the noise standard in the urban area”( GB3096- 93) ( 60dB in

    daytime? 50dB at night) ;

    ?level of “the standard of atmosphere environmental quality”( GB 3095- 1996)?

  • - 4-

    11 Luyang middle

    school 635

    12 The Pig farm 300 13 HUpuqian 120

    1.4 Methodology of Environmental Impact Assessment

    1.4.1 Data Collection and Field Investigation

    Two environmental surveys of the project area and its surroundings were

    initiated in Nov.2002 and in May.2004.

    Survey staff has monitoring acoustic environmental quality within the

    project-affected area, conduct survey of terrestrial animals and plants in the

    project area, and consulted the relevant department of Pingtan county.

    1.4.2 Methods of Analysis

    Qualitative methods were used to analyze the extent of potential impacts

    during construction and operation period.

    Quantitative analytical methods were used to analyze the extent of

    potential impacts of acoustic environment.

    1.4.3 Public Participation

    During preparation of the EIA report, the report stressed on the public

    participation in project survey according to the current relevant Chinese laws

    and regulations.

    The affected people and social groups were interviewed and the

    environment & resettlement symposium was held. The questionnaire were

    printed and distributed for obtaining opinion.

    At the same time, the information about project construction and

    environmental protection was often publicized on local news medium to make

    masses have deep knowing about the project.

    EIA report of the project will be made available for public review in the

    office of Pingtan County.

  • - 5-

    1.5 Project Impacts

    1.5.1 Benefits of project

    Wind energy is the regenerated energy, Chinese Government encourages

    to develop wind-force resources.

    The project is to offer power of 260 million kw.h to Fujian Province grid

    every year. Wind power project can be complementary with hydraulic power

    generation project in Fujian Province and can offer superfluous power sources

    for the provincial grid .

    Construction of this project will guarantee Pingtan county and Fuqing

    City’s developing demand for electric load, reduce the corresponding line

    power loss, realize energy diversification of electricity, improve the quality and

    dependability of electric wire netting, bring about an advance in regional

    economy.

    1.5.2 Negative impact

    Construction of Changjiang’ao project is predicted to have following main

    negative impacts:

    (1) Construction Period

    Construction of this project will cause impacts such as water pollution,

    atmospheric pollution, noise, soil erosion, vegetation destroyed etc. If

    untreated production wastewater and domestic sewage of workers discharged

    directly into the river in the project area, the quality of river will deteriorate.

    The noise of constructing has influence on constructors and nearby village,

    the waste gas has influence on the constructors mainly.

    Construction will take up some cultivated land and forestland. It cause a

    certain influence to the local ecological environment. Excavating and backfill

    will cause water and soil loss.

    There is a “Hupuqian Relic site” 400m southwest off 46# wind turbine,

    which is the Neolithic culture remains about 5000- 6000 years old, with an area

  • - 6-

    of 2500m2.In construction period, construction is forbid in this area.

    (2) Operation Period

    It will produce the noise that the air blower is operated, and bring certain

    adverse effect on acoustic environment of nearby village. Land occupation

    forever will cause a certain influence to local ecological environment, water

    and soil conservation, etc.

    1.6 Recommended Mitigation Measures

    The environmental mitigation measures in construction period of the

    project includes water environmental protection, atmosphere environmental

    protection, protection of acoustic environment, ecological environmental

    protection, water and soil conservation, protection of historic relic site, etc.

    We have already made the detailed environmental management plan,

    which contains environmental mitigation action plan, environmental

    supervision plan and environmental monitoring plan.

  • - 7-

    Chapter 2 Survey of the Project

    2.1 Geographical Location

    Changjiang’ao Wind Power Field locates at the inner bay area, where is

    about 10 kilometers away from the downtown of Pingtan. It faced to Taiwan

    Ditch on the Northeast, and Haitan Ditch on the South-West. Fig.1 shows its

    geographical location.

    2.2 Scope of the Project

    67 units of the wind power turbine will be installed at the newly built wind

    power field, the total volume of which reaches to 100.5MW, and it will supply

    the power of 260 mega-kW.h to the power grid.

    2.3 Introduction of the Phase I Project of the Wind Power Field

    The phase I project located at the central area of the planned wind power

    field, where is showed at Fig.2.

    6000kW of power units were installed at the phase I Project, the total

    investment is RMB 600,000. 10 units of wind turbine manufactured at BAZAN

    company of Spain, all of which were BAZAN-BONUS 600kW MK-IV

    fix-distance screw blades, and the unit capacity is 600kW. The diameter of the

    wind turbine is 44m, each wind turbine consists of 3 blades and and the hight

    of the tower is 50m.

    The output voltage of the wind turbines is 690V, and the power connected to

    the Pingyuan Transformer substation as single 35kV loop after one level

    transformed, of which the 35kV power facilities is a single bus loop that layed

    out on the wind power field composed of the 10 sets of wind turbines, of which

    the central control building was at the central area, where 100m away on the

  • - 8-

    north of the turbine7#, and the building was designed as 20MW power output

    in advance.

    The Phase I Project occupied 13 mu (1mu=667 m2) of lands permanently,

    and about 20 mu for construction period use temporarily, all of which were

    forest lands of state-run Changjiang Forestry Farm.

    The Phase I Project began to construction from Oct.1,1999, and the 10

    turbines generated power to the power grid smoothly on Oct.5, 2000, and it run

    well since then. To June 2002, 27.17 million kW.h power in total was generated,

    in which 14.49 million kW.h power was sent to the power grid in 2001, and its

    annual output reached to 2520h. The present status of the Phase I Project is

    shown at Fig.2-1 .

    View of the wind power field Base of the wind turbine

    Fig.2-1 Present Status of the Phase I Project of Changjiang ’ao Wind Power Field

    2.4 Survey of the Phase II Project of the Wind Power Field

    2.4.1 Layout of the wind turbines

    Wind turbine units were arranged perpendicular to the prevail wind direction

    North-east, whereas the 67 turbine units arranged as plum-like shape which distances

    of row/column are 8D(560m)� 5D(350m) around the 10 turbines of Phase I Project. The

    general layout of the project is shown at Fig.2.

    2.4.2 Selection type of the wind turbine

    From the feasibility research of the project, it’s planned to choose the wind turbine

    units that are 1.5MW, varied blade -distance, constant frequency and varied speed. The

  • - 9-

    rated power of the turbine is 1.5MW, the diameter of its blade is 70.5m, the height of its

    wheel hub is 65m, the starting wind-speed is 4.0m/s, its rated wind speed is 12.0m/s and

    the tangent wind speed is 25.0 m/s.

    2.4.3 Electrical

    The scope of the Phase II Project of Pingtan Changjiang’ao Wind Power Field is

    67� 1.5MW, and its transformer substation locates near the pre-central control building.

    The transformer substation connected to the power grid with 2 output loops of 110kV

    voltage.

    The output power lines connect the generator to transformer directly, and it sends

    power of 10kV with the group composed of 5 units of generator. At the high voltage end

    of the 1 st level transformer, the cable of HLYFGV22-10-3x95 connects to the ring bus of

    10kV, then the group of composed of 5 units connects the 10kV bus of the wind power

    field with 2 cables of HLYFGV22-10-3x120. The 1st transformer located at the bottom of

    the tower, which is SCB10-1600/10 dried transformer, and the ring-bus box locates at

    the 5 wind power turbines near the 110kV transformer substation. The distribution facility

    of the group composed 5 generators consists of ring-bus box and power switches with

    fuse. It ’s calculated that the total power loss from the bottom of the tower to the 10kV

    bus of the 110kV transformer substation of the wind power field is 105.4kW, and the

    average loss of each unit is 21.1kW.

    2.5 Civil engineering

    2.5.1 Base of the wind power turbine

    It’s planned to choose the independent reinforced concrete large C30 plate base

    for the wind turbine tower, of which the lower size is 18� 18m, the height is 1-2m, the

    upper size is 6� 6m, and the volume of the concrete is about 600m3.

    According to the different geological condition of the units, the depths of bases are

    about 5m, which tops reach the same height as the ground surface, and the support

    levels are common medium sands. Construction for the pits of the bases are open dug

    with slops.

  • - 10-

    2.5.2 Central control building

    The central control building is expanded to 4 meters of the previous, which 2 office

    rooms are increased on the 1st floor, and enlarged the areas of the 2nd and 3 rd floors

    which were former semi-layer of cables and main control rooms. He total enlarged area is

    100m2.

    2.5.3 Power distribution facility room and transformer room

    There are 2 layers of the Power distribution facility rooms, 10kV power distribution

    facilities and capacitance room on the 1 st floor, which height is 4.80m, and 110kV GIS on

    the 2nd floor, the layer is 9.60m high. The main transformer rooms of 1#, 2#, and 3# are

    on the ground floor, which layer height is 14.40m, and the total area is 965m 2.

    2.6 Ventilating

    It’s natural ventilation and mechanical exhaust on the semi-layer of cables, and it

    should not be less than 6 times per hour (6/h) to exchange the remain heats in the

    rooms. One T35-11 axial-flow fan is selected which ventilation volume is 1364m3/h.

    Natural ventilation and mechanical exhaust are used for the 110kVGIS distribution

    facility room and it normally exc hanged the air not less than 2 times per hour (2/h). The

    input ventilation is at the lower part of the room, whereas the output exhaust connects

    out of the room and higher than the roof. The milti-flow fan of SWF-I is selected, which

    total ventilation volume is 5252 m3/h.. The upper part accident ventilation system is

    installed in the room, and its total exchanging ventilation times should not be less than 4

    every hour. The anti-corrode axial-flow fan of BT35-11 is selected which ventilation

    volume is 1905 m3/h. In case of accidence, the normal ventilation system runs and the

    accident ventilation system started at the same time. Anti-corrode fan is selected and

    ventilation pipes are painted with anti-corrode oil paints .

    Natural ventilation and mechanical exhaust are used for the 110kV power

    distribution facility and capacitance rooms. The ventilation amount is counted according

    to the temperature should not higher than 40? . 3 axial-flow fans of T35-11, each

    ventilation volume is 5881m 3/h.

  • - 11-

    Natural ventilation is used at the main transformer room, and the ventilation amount

    is counted according to the temperature should not exceed 45? .

    2.7 Construction planning

    2.7.1 Communication

    (1) Present communication facilities

    To outer areas, it’s by ships from Port Lianggong of Pingtan to Xiaoshandong of

    Fuqing, where the Provincial highway connects express highway from Fuzhou to

    Xiamen. At present, Port Lianggong of grade 5000t is the largest port of Pingtan, and

    Changjiang’ao Wind Power Field is about 28km away from Port Lianggong.

    Changjiang’ao Wind Power Field connects downtown of Pingtan via highway of

    Pingtan to Suao, then to Port Lianggong from the county highway of Pingtan. It’s in

    convenience around the Wind Power Field.

    (2) Large (long) goods shipping

    For the w ind power generator units which capacity is 1.5MW, it’s normal

    shipping of the turbine cabin which is the heaviest part, while the blades that is the

    longest parts(its length is about 34m) need to be considered as super long shipping.

    All cabins and blades are import equipment that were shipped by ocean ships to

    Port Mawei of Fuzhou, then to Port Lianggong of Pingtan by smaller ships, and

    finally to the site by flat truck. The roads for transportation are county or village

    highways which radii meet the needs for large equipment.

    2.7.2 General layout of the site

    67 units of the wind turbine will be arranged at the planned field. According to

    construction planning, it’s considered that each unit occupies the area of 25� 25m. The

    construction site for each unit arranges on the spot, and a land of 70 � 70m is

    considered as the construction site of each unit because of the pile of equipment and

    the materials as well as installation of cabin and blades, where includes the land

    occupied by the wind turbine.

  • - 12-

    According to the system planning, the wind power field connects the power grid with

    110kV, which output cables are 2 loops to the 110kV Beicuo transformer substation

    where is 15km away on the South. The transformer substation of the wind power field

    locates at the central north of the site, which is enlarged to the built substation of the

    phase I project of Pingtan Wind Power Field. The 110loops output to the south, and it’s

    in convenience of the loops.

    Construction and watching paths in the site are built with silt and gravels, and the

    length of the newly built roads is 31.50km, which width of the base is 4.5m.

    2.7.3 Construction of the principal engineering

    Since construction works of the field are the same to others, and their routes are long,

    a temporary construction base at the central site would be built for convenience of works,

    in which arranged temporary living houses, storages etc. Removal air -compress and

    concrete-mix station will be set according to the characteristic independence for each

    unit.

    2.7.4 Construction for the base of the wind turbine

    The base of the wind turbine is mass concrete, which is built at only one time.

    2.7.5 Construction for other buildings

    The schedules for the central control building, power distribution rooms and

    transformer rooms etc. are like follows: excavation of bases, concrete mix of bases,

    concrete mix for the column, concrete plates and beams, laying bricks of the wall,

    windows and doors installation, decoration for inner and outer parts, electrical facilities in

    the rooms, decoration and installation for inner and outer remain parts, and finally

    finished.

    2.8 Installation for the wind turbine

    2.8.1 Main mechanical equipment

    main crane : 300t track crane

    associate : 80t hydraulic stretch track crane

  • - 13-

    track cranes may be got by renting.

    2.8.2 Layout of the installation site

    The main parts of the wind turbine include blades, cabin, rectifier hub, wheel hub,

    and the tower cylinder etc. Generally, all parts are shipped to the installation site directly.

    The location of the parts piled at the site depends on their size and the installation

    schedules.

    According to the weight of the cabin, includes the wheel hub, and the feature of the

    track crane, it’s determined that the distance from the center of the track crane to the

    center of the wind turbine base is about 15m (i.e. the range of the track crane). The

    installation length for hanger of truss on the ground is 75m.

    It’s demanded that the wheel hub, blades, and the rectifier hub will be installed on

    the ground, and the total length from the center of the wheel hub to the end of the blade

    is about 35m.

    2.8.3 Method of installation

    The procedure for separately installation of the parts include the frame of the tower

    should be as follows:

    The bottom, middle and upper parts of the tower should be separately installed in

    order. It should be connected to the technical specification between the bottom part of

    the tower and the upper flange panel of the wind turbine base joint part, as well as the

    end flange panels between tower frames.

    The blade and pilot systems should be locked before the cabin installation. When

    installing, hanging up the cabin about 0.15m on the ground, checking if the steel rope

    system meet the demand of intensity, then keep on starting track crane after approval,

    and the cabin is lifted slowly to the upper location of the tower, it’s connected properly

    between the bottom grange of the cabin and the top of the tower.

    The wheel hub, blades and the rectifier hub are installed assembly on the ground. It

    should keep 3 blades balanced while the track crane lifts the wheel, and the wheel and

    cabin joint reliably via flanges as the center of the wheel rises slowly to the front of the

    cabin.

  • - 14-

    The wind turbine installation is accomplished when all operation above finished, and

    mechanical equipment removed.

    2.9 General construction schedule

    According to the condition of hydrology, meteorology, terrain, geology and

    communication of the site area, as well as the circumstance of the project, the general

    time limit of the project is preliminary estimated as 24 months after the feasibility

    research and the loans examined and approved by the World Bank, under the

    consideration of one set of track cranes rented and installation of the wind turbine one

    by one.

    2.10 Labors

    After the Phase II project of Changjiang’ao Wind Power Field completion, 15 staffs

    are specified, and staffs work in 3 shifts.

    2.11 General investment of the project

    It’s estimated that the general investment of the project is RMB 85.994 million

    yuan.

    2.12 Project characteristics

    Table 2-1 shows the characteristics of the Phase II Project of Changjiang’ao Wind

    Power Field.

    Table 2-1 Characteristics of the Phase II Project

    Order & Name Unit Amount Note I Wind Power resource

    1 Annual Average wind speed m/s 8.21 70m above the ground

    2 Wind power density W/m 2 476

    3 Prevail Wind direction N, NNE, NE 4 Ratio of Prevail Wind direction % 66

    II Main Equipment

    1 Main Mechanical& Electrical Equipment

    Wind Power Generator

  • - 15-

    Order & Name Unit Amount Note

    Quantity set 67

    Rated Power kW 1500 Number of Blades 3

    Diameter of Wind Wheel m 70.5 Swept Area of Wind Wheel m2 3903

    Speed of Wind Wheel rpm 11~ 22 Variable

    Tangent Input Wind Speed m/s 4

    Rated Wind Speed m/s 12

    Tangent Output Wind Speed m/s 25 Safety Wind Speed m/s 59.5

    Height of Wheel Hub m 65

    Rated Voltage V 690 Central Monitor System set 1

    2 Complete Output Engineering To Beicuo Transformer Substation

    110 kV Separation set 2 2Loops, 110kV Transmission Lines km 15

    III Civil Engineering 1 Central Control Building 1 Type Frame Structure

    Feature of the Base Medium Sand

    2 Base of Wind Power Generator hole 67

    Type Independent Feature of the Base Medium Sand

    3 Permanent Occupation Land hm2 31.63 474.55mu

    Area of Wind Power Turbines hm2 4.18 Area of Transformer Substation hm2 0.46

    Area of Site Roads and Sub-cable hm2 26.99 IV Construction 1 Amount of Main Engineering

    Excavation of Wind Turbines and Transformer Substation m

    3 30,000

    Fill of Wind Turbines and Transformer Substation

    m3 42,000

    Excavation of Site Roads m3 12,500

    Fill of Site Roads m3 7,500

    2 Main Building Materials

    Cement t 18615 Reinforcing Steel Bar t 1749

    Steel t 640

    Timber m3 374 Sand & Stone m3 121355

    3 Newly Built Roads km 31.50

  • - 16-

    Order & Name Unit Amount Note

    4 Construction Time Limit

    Total Time Limit month 24 Installation & Debug week 28

    5 Rent lands for Construction hm 2 18.85

    Chapter 3 Present EIA and Assessment

    3.1 Brief introduction

    The natural and social environments, as well as present environment quality of the

    project site and its surrounding areas are mainly introduced in the chapter.

    3.2 Survey of natural environment

    3.2.1 Climate

    Pingtan locates at the edge of the Eurasia, and it is typical subtropical monsoon

    climate. The climate feature is that the dry and rain season is separated obviously, and

    it’s warm in winter and cool in summer, it’s rare of frost and snow.

    Table 3-1 lists the climate index of the project area that is according to the statistics of

    Pingtan Metrological Station.

    Table 3-1 Meteorological index of Pingtan

    Item Unit Value Item Unit Value

    Annual average temperature

    �C

    19.5 Annual gale days(minimum)

    d 51

    Extremely high temperature

    �C

    37.4 Annual fog days d 23

    Extremely low temperature

    �C

    0.9 Annual fog

    days(maximum d 35

    Annual average precipitation

    mm 1151.5 Annual fog days(minimum)

    d 9

    Annual precipitation days d 131.0

    Annual thunderstorm(average) d

    24.4

    Annual gale days(average) d 98.3

    Annual thunderstorm(maximum) d

    36

    Annual gale days(maximum)

    d 176 Annual thunderstorm(minimum)

    d 17

    Annual average wind speed m/s 8.25 Prevail wind direction

    NE

    Rare snow, no snow gathered and rime

  • - 17-

    Pingtan Wind Power Field locates along the coast, and its principal meteorological

    disaster is typhoon (the tropics cyclone and thunderstorm.

    According to the statistics of typhoon in Fujian Province, there are 6 tropical cyclones

    influenced Pingtan Island annually, and their wind speeds are mostly under 25m/s, while

    those greater than 25m/s are in 20 hours by average.

    Thunderstorm is one of the disasters of the area. The distinguishing feature of

    thunderstorm in Fujian Province is that they mostly occurred in inner mainland and less

    along the coast and islands. The annual-average- day of Pingtan County is 24.4d.

    3.2.2 Topography and geology

    It’s mainly ocean deposit plains of Pingtan’s topography, and it shows the feature of

    island-bulge. The planned project site locates at the north area of Pingtan, where the

    terrain slopes gently, that belongs to the coastal wind deposit plain and separate

    remnant hills, which may be divided as remnant hill district (diorite) and plain(diorite and

    granite) in geological units.

    According to of the State Bureau of

    Seismology in 1990, the basic earthquake intensity of the site area is 7.

    3.2.3 Soil

    There are 6 types of soil in Pingtan, that are brick-red soil, coastal sand, salt soil, rice

    soil, red soil and wet soil, which are 46%, 23.3%,3.16%, 0.66%, 0.45% and 0.19% of

    total land squares. All of them are thin layers and low nutrient. Black pines and jequirity

    trees are suited to be planted at the brick-red soil and red soil, whereas wood ephedrine,

    wet-land pines and artificial trees are appropriate growing at the coastal sand, salt soil,

    rice soil and wet soil.

    Soil at the project area is mainly coastal sand soil.

    3.2.4 Hydrology

    There is no river in Pingtan, and surface runoff is weak there. It’s lack of water area,

    where is mainly depends on rain and underground water.

    There is no river in the planned project site area, and only a small stream called

  • - 18-

    Shangpanhu, which flow is small.

    3.2.5 Vegetation

    The project locates at wind gap, where the weather is bad, and the present vegetation

    crops and coastal windbreak forest. Sweet potato, wheat, peanut and other crops are

    planted in the farmland. Wood ephedrine is the main plants with small amount of

    jequirity trees, black pines and wetland pines in the forest. Please see Fig. 3-1.

    Fig.3-1 Present vegetations at the site

    3.2.6 Terrestrial animal

    From the investigation of our Institute for the project area in May 2004, no migratory

    birds and rare protected animals were found.

    It’s confirmed by the Protection & Management Station of Wild Animal in Pingtan that

    here is neither habitat place of migratory birds, nor rare protected animals, where are

    only small wild animals such as sparrows and voles etc.

    3.2.7 Soil erosion

    From the primary statistics results of the satellite remote sensing investigation, the soil

    erosion area in Pingtan is 96 km2,.7km2, which is 33.05% of all land there, in which light

    erosion 6.28 km2, Medium 14.36, and heavy erosion 6.53 km2. The reason of erosion is

    mainly wind erosion. The soil erosion at the planned project site area is considerably

    heavy, where belongs focal administration district.

  • - 19-

    3.3 Survey of Social Environment

    3.3.1 Regional economy

    There are 5 towns and 10 villages governed in Pingtan County, where its total

    population is 387,000, in which non-agricultural population is 15.1%, the density of

    population is 1249 person/ km2.

    Luyang village, Town of Pingyuan, Zhonglou village and Changjiang region of

    State-run Forest Farm are mainly related of the project site.

    Luyang village’s total area is 14.86km 2, its population 6737 in 2003, which is 1.7% of

    that of the County, and its population density is 453persons/km 2. Agriculture is the

    primary in Luyang’s economy and sweet potato, wheat, peanut are main crops there.

    Output of peanut occupies a larger amount in the County, and its output per mu yields is

    comparatively high. Total output value of agricultural, forest, livestock and fishing is RMB

    4,014 yuan.

    Town of Pingyuan’s total area is 23.68km2, its population 25,000 in 2003, which is

    6.7% of that of the County, and its population density is 1056 persons/km2. Planting is

    the primary in Town of Pingyuan and the total output value of agricultural, forest,

    livestock and fishing is RMB 6,938 yuan.

    Zhonglou village’s total area is 17km 2, its population 22,000 in 2003, which is 6% of

    that of the County, and its population density is 1,294 persons/km 2. Agriculture and

    aquatic are main production, that peanut and aquatics are main export products there.

    Total output value of agricultural, forest, livestock and fishing is RMB 6,558 Yuan.

    3.3.2 Present land use

    Farmland and forest are main types at the project area, land occupation involves

    Luyang and Zonglou village, Town of Pingyuan and State-run Forest Changjiang Region.

    4667 mu in total area of the State-run Forest Changjiang Region will be occupied, in

    which forest 4096mu include shelter-forest 3884mu, economical forest 68mu and

    technical experimental forest 142mu. The shelter-forest is mostly composed of wood

    ephedrine, and less wetland pines with a small amount of jequirity trees. Economical

  • - 20-

    forest is mainly made up of oranges and tangerines. No migratory birds and rare

    protected animals were found. The timber stored up of the region is 5,460 m3 at the end

    of 2001. 2 staffs (protectors) were employed in the region, and no other persons living

    there.

    Table 3-2 shows indexes of villages and towns affected by the Project.

    Table 3-2 Index of village and town affected by the Project

    Town or Village

    Village Population Farmland (mu)

    Forest (mu)

    Lubei 568 695.6 483 Luyang

    Yangzhong 1583 1621.1 317.6

    Fengmei 2158 732.2 1470 Jianhu 1215 524.6 825

    Liaoyuan 4287 1482.4 660

    Shanxianmei 1842 626.3 1335

    Shangpan 1859 678.4 1192

    Rongshan 1228 386.5 889

    Town of

    Pingyuan

    Wufeng 2196 649.3 149 Guanshan 2800 1073 2749

    Kunhu 1295.8 592.1

    State-run Changjiang Forest region

    4026

    3.3.3 Tourism resource

    Pingtan County is rich in coastal tourism resources, and Haitan Scenic spot is

    confirmed as one of the National key scenic spots.

    There’s no scenic spot at the Project area, only Junshan Scenic spot is near the site

    where locates at the south-east, the direct distance between them is about 3 km. The

    location of Junshan is shown at Fig.1.

    3.3.4 Wind power resource

    The direction of prevail wind at Changjiang’ao Wind Power Field is NE, that the wind

    speed declines weaker from the north to the south at the site area. According to the

    hourly data of 8760 hours in the representative year to the wind speed and direction

    from the observation tower located at the north of the site, it’s determined that the

  • - 21-

    annual average wind speed at 70m above the ground is 8.21m/s, density of the wind

    power is 476W/m 2, therefore there is 140,000kW of wind power at the site.

    Changjiang’ao Wind Power Field is rich superiority in wind power resource.

    3.3.5 Fishery

    There are vast coastal beach and water area in Pingtan, and plenty of aquatic

    products, where includes 80 fishery resource maintain regions . According to the function

    diversion districts from < Function diversion districts of the sea in Pintan> (Bureau

    of Sea and Fishery of Pingtan, Aug. 2002), the fishery resource and maintain areas

    are mainly distributed at the south -east of the Project site. There’s no fishery

    port,aquatic maintain, increasing and capture areas region near the beach of the Project

    site, therefore no influence to the fishery resource.

    3.3.6 Ecologic public welfare forest

    From (Sep.2001), it’s determined that the area of state ecologic public welfare forest

    is 82,207mu, and the area of Provincial ecologic public welfare forest is 65,502mu.

    All forest lands of Shangpan, Rongshan,Jianhu village of Pingyuan Town, and Lubei

    of Luyang Village, Guanshang of Zhonglou Village, and State-run Forest Fam

    Changjiang Region belong to State or Provincial ecologic public welfare forest which are

    also shelter-forest. Table 3-3 shows the detail.

    Table 3-3 Area of Ecologic public welfare forest of villages involved

    Unit:mu Town/Village State ecologic public

    welfare forest

    Provincial ecologic public

    welfare forest

    Pingtan County 82,207 65,502

    Luyang Village 704 9,484

    Town of Pingyuan 2,484 5,733

    Zhonglou Village 1,099 9,067 State-run Forest

    Farm

    17,153 161

    Forest Farm of Changjiang Region

    4,026 /

  • - 22-

    3.3.7 Cultural relic and historic site

    There is a long history in Pingtan, and abundant cultural relic, where is one of the

    earliest ancients of Fujian Province.

    There is the County relic protection spot Hupuqian Relic, that is 400m away from the

    south-west of the 46# wind power turbine. This relic locates at the south -west slop of a

    small hill, where is at the east of Hupuqian Village of Pingyuan Town, which the height is

    15m and its area is 2500m2. It ’s a historic relic of the Neolithic Age of 5,000-6,000 years

    ago, and it’s not exploited now, and it needs further criticism research. The location of

    the relic is shown at Fig.2.

    There is no other cultural relic spot found near the Project site.

    3.3.7 Mineral resource

    Rock, quartz sand and sea salt etc are main mineral resources in Pingtan.

    There is quartz sand mine is at the northwest of the planned 59# wind power turbine,

    which area is about 20,000m 2, and its products are quartz sands for selling. Fig.3-2

    shows the mine.

    Fig 3-2 Exploitation area at the quartz mine

    3.3.8 Breeding

    A piggery farm is under building at the north of 44# wind power turbine, which belongs

    to ‘Sunlight ecology Agricultural Development

    Ltd. Co.’. It’s estimated that 10,000 pigs will be output by the farm when it is builted.

  • - 23-

    Fig.3-3 shows the building piggery farm.

    Fig. 3-3 Building Piggery Farm

    3.4 Present Environmental Quality

    The site of Changjiang ’ao Wind Power Field belongs to the village inhabitant area,

    and the present acoustic environment follows the Standard 1 of (GB 3096-93), that is 55dB at daytime and 45dB at night. While the

    project is under building or completed, it’s a mixed area with inhabitants, commercial

    and industry, the sensitive spots around the Wind Power Field follow the Standard 2

    during its operation that is 60dB at daytime and 50 dB at night. The environmental

    atmosphere must meet the demand of Standard 1 of (GB 3095-1996). Above standards have been confirmed by the

    environmental Bureau in Pingtan(see annex4).

    There are large amount of ecologic public welfare forest in the project site at present,

    which are good at shelter for wind and sand, and less inhabitants live at the site, no

    obvious air pollution source there, the quality of air is good.

    To understand the present acoustic quality of the planned project area, our Institute on

    May24 2004 did monitoring for the present acoustic environment, and the Noise Statistic

    Analyzer of AWA6218B was used. The measurement spots are mainly considered to the

    location of the present noise source and sensitive spots, which location is shown at

    Fig.2 and the result see Table 3-4.

    From the result of monitoring, it’s obviously that the monitored spots that are near the

  • - 24-

    communication source, such as spot2#, 3#and 4#, their noise are all exceed the

    Standard 1 of (GB 3096-93), whereas all

    others meet the Standard 1 when they were not interference of communication.

    Table 3 -4 Monitoring result of noise at the Project Site (daytime)

    No. Location of the measurement spot Leq(dB)

    1 On the road to the site, at the north-east

    of the pre-wind power site

    50.4

    2 Under 7# wind turbine, 1m to it 60.8

    3 Between 8# and 9# wind turbines 57.7

    4 160m to 7# wind turbine, vertical to the blade surface

    55.3

    5 160m to 7# wind turbine, parallel to the blade surface

    52.8

    6 Office building of Luyang Village 49.3

    52.6(no

    traffic)

    7 Shangpan village, at the side of highway

    73.8 (traffic)

    8 Spare land of the south to Shangpan, and the north to Shanxianmei,the nearest distance to the wind turbine is 300m

    48.2

    54.2(no traffic)

    9 Primary School of Shanxianmei

    67.6

    (traffic) 10 Piggery Farm 44.6

    STANDARD 55

    *The list wind turbines are 1#-10# wind turbines of the Phase I Project of Changjiang’ao Wind Power Field, which are in operation.

  • - 25-

    Chapter 4 EIA and Mitigation Measures

    4.1 Acoustic Environment Impact

    4.1.1 Construction stage

    4.1.1.1 Construction mechanical noise

    Civil engineering mainly includes excavation of the base of wind turbines,

    installation site leveling, construction of newly built roads at the site and

    building production and living construction etc.

    Construction noise is generated from construction machines of civil

    excavation and transportation. Machines such as concrete mixers, pneumatic

    drills, excavators, heavy trucks etc as well as transportation trucks generate

    noise when they run. The average acoustic level of primary construction

    machines is listed at Table 4-1. Generally, Noise impact is only considered at

    daytime, as it didn’t work at night during construction period. According to the

    schedule for construction, the concrete was centralized mixed of movable

    mixers, the main construction machines at each wind turbine are pneumatic

    drills and excavators. The construction noise at daytime is primarily considered,

    which source intensity is counted as 84dB.

    Table 4-1 Average noise level of main construction machines

    Machine name Noise level(dB) Noise limitation

    (daytime,dB)

    Concrete mixer 64 75 Pneumatic drill 84 85

    Excavator 80 75

    Carry truck 80 Note: (1) Listed data is measured at 15m to the noise source.

    (2) Noise limitation is the related standard value on (GB 12523-90).

    Investigation at the site shows that the construction site is smooth terrain, no objects

    sheltered around. It’s mainly considered the geometric divergence decline and ground

  • - 26-

    additional divergence decline of the point acoustic source to forecast the noise impact of

    construction machines. According to , the basic formula for geometric divergence decline for non-direction

    acoustic source is selected:

    LA(r) = LA(r0)-20lg(r/r0)-AEXC

    In which:

    LA(r): noise A pressure of the forecast point(dB)

    LA(r0) : noise A pressure of the reference point(dB)

    r: distance between the forecast point and noise source(m)

    r0: distance between the reference point and noise source (m),

    15m selected

    AEXC: additional divergence decline of ground effect,

    AEXC=5 lg(r/r0), the maximum value of forecast result is 10dB.s

    Construction noise is merged from several machines run simultaneously. According to

    the feature of constructionfor the wind power field, each unit is a cons truction spot, and

    several spots run in turn, and the quantity of machines is comparatively small at the

    same time and same spot, therefore the noise level of several machines is counted as

    87dB (15m).

    Table 4 -2 Calculation result of divergence decline of construction at

    daytime

    Unit:dB

    r(m) 50 100 135 180 Standard

    single 77 71 63 60 57 L(r)

    multiple 80 74 66 63 60

    60

    Table 4-2 shows that construction noise affects surrounding acoustic environment

    greatly at daytime, in case of a single machine at 135m, noise decreasing may be

    meet level 2 of (GB 3096-93), whereas

    several machines need the distance 490m to meet the standard level 2.

    Compare to Table 1-2, it’s clear that only 3 sensitive spots of

  • - 27-

    Shanxianmei,Guanlouxia and Hupuqianwill be affected from the construction noise in

    varying degrees. In order to mitigate the influence of construction noise to surrounding

    sensitive spots, Low noise machines should be selected, and the maximum noise

    value of each machine should be less than 100dB(at 1m).

    4.1.1.2 Communication noise at the site

    31.50km of roads will be newly built at the site, which is made of clay-crushed

    stones, and the width of the base 4.5m. Communication

    noise will be generated when transportation trucks run during construction. The main

    building materials for the project including steel-bars, cement, sand and stones, timber

    as well as carbines of the generator (51.40t), and blades which length is 34.0m need

    to be transported. Total amount of transportation is comparatively small, which

    includes 374m 3 of timber, 19,000t of cement, 2,389t of steel and reinforced bar,

    121,000t of sand and stone, 67 groups of carbines and blades. The communication

    noise is less because of less increase of traffic flow. It’s clear that there is basically no

    distribution of sensitive spots (village and school etc) along both sides of roads to the

    project site, and communication noises of trucks impact the acoustic environment very

    small.

    4.1.2 Operation stage

    The primary noise source during operation period of the wind power field is the noise

    of the wind turbine unit. 67 of 1500kW wind power units which noise level is 105dB,

    and the wheel height is 65m, its diameter of blades is 70.5m. Considering that the

    height of the turbine to the ground is comparatively high,(100 m) to the turbine is small

    and it’s neglected at forecasting, the only factor of geometric divergence decline is

    selected during noise impact forecasting.

    According to the , Following

    formula is in use:

    LA(r) =LwA-20lgr-11

    In which:

    LA(r) is the noise value of the forecast spot (distance=r), dB,

  • - 28-

    LwA is the value of the noise source, dB,

    r is the distance to the forecast spot, m.

    LA =10lg[ S] ]10lg[101

    1.0∑=

    =n

    i

    LA

    AiL

    Influence of merging the noise of various wind power turbine should be in

    consideration of the noise intensity of the forecast spot.

    In which:

    LA: level A acoustic intensity of various noise sources merged.

    LAW: A acoustic intensity of a single noise source.

    In forecasting, it mainly analyzes the impact extents of the turbine noise to

    13 of sensitive spots nearby, including Shangpan, Shanxianmei, Fengmei,

    Wufeng, Yuyao, Guanlouxia, Lulou, Xibianlou, Yangjia, Kunhulou, Luyang

    Middle School, and planned Piggery Farm. The distances of each sensitive

    spot to the wind turbine is shown at Table 4-4. In order to forecast the influence

    of noise to the sensitive villages of the Wind Power Field, and acoustic impact

    forecast was done at the selected forecast spots where the nearest spot to the

    wind turbine at each village. Fig.2 shows the location of the forecast spot.

    The height of the wheel hub is 65m, and the lowest point to the ground is

    30m high because of the high turbine wheel. Because of the smooth terrain

    and considerably low of buildings of sensitive spots and vegetations to the

    wind turbines, there is no shelter to the noise of turbine, and it’s not under

    consideration.

    The forecasting value of noise where is the nearest spot to the turbine of

    every sensitive spot is shown at 4-3.

  • - 29-

    Table 4-3 Noise impact forecasting during operation period

    Noise value at forecast spot(dB) No. Village Nearest

    turbine

    Nearest

    distance

    To the Turbine (m)

    Affect

    value

    Backgro

    und At daytime

    Merged

    value

    Increase

    d value

    6# 500

    5# 710

    4# 995

    12# 370

    11# 705

    22# 660

    21# 665

    1 Shangpan

    20# 840

    47.5 52.6

    (no vehicle) 73.8

    (vehicle

    passed by)

    53.8

    (no vehicle) 73.8

    (vehicle

    passed by)

    1.2

    (no vehicle) 0

    (vehicle

    passed by)

    29# 505

    28# 755

    39# 145

    38# 480

    2 Shanxianmei

    37# 820

    51.7 54.2(no

    vehicle)

    67.6 (vehicle

    passed by)

    56.1(no

    vehicle)

    67.7 (vehicle

    passed by)

    1.9(no

    vehicle)

    0 (vehicle

    passed by)

    39# 450

    38# 770

    48# 400

    47# 665

    3 Fengmei

    46# 945

    46.1 48.2 50.3 2.1

    48# 275

    47# 500

    46# 775

    56# 375

    55# 655

    4 Wufeng

    54# 915

    48.7 48.2 51.5 3.3

    56# 200

    55# 460

    54# 730 65# 460

    5 Yuyao

    64# 710

    49.8 48.2 52.1 3.9

    64# 200

    63# 160

    62# 500

    6 Guanglouxia

    61# 525

    52.6 48.2 53.9 5.7

  • - 30-

    64# 535

    63# 535

    7 Lulou

    62# 725

    43.5 48.2 49.5 1.3

    64# 715

    63# 420

    62# 275

    61# 450

    8 Xibianlou

    60# 775

    48.4 48.2 51.3 3.1

    60# 325

    67# 435

    61# 605

    9 Yangjia

    62# 920

    46.7 48.2 50.5 2.3

    59# 290

    58# 325

    57# 610

    10 Kunhulou

    56# 490

    46.7 48.2 51.4 3.2

    67# 635

    59# 660

    58# 840

    11 Luyang

    Middle School

    66# 725

    43.1 54.2 54.5 0.3

    37# 650

    36# 360

    35# 525

    45# 300

    44# 395

    12 Planned

    Piggery Farm

    43# 675

    49.2 44.6 50.5 5.9

    39# 330

    38# 290

    37# 530

    13 NE

    Hupuqian

    46# 415

    48.8 48.2 51.5 3.3

    46# 345

    47# 120

    14 SW

    Hupuqian

    48# 350

    53.3 48.2 54.5 6.3

    Table 4-3 shows that the noise value of all sensitive spots except Shangpan

    and Shanxianmei meet level 2 standard (60dB) of at daytime, and only 3 spots of Shanxianmei, Guanlouxia

    and SW Hupuqian exceed the level 2 standard a little bit at night. The sound of

    wind is the primary background noise, and itis related to its speed, the higher

  • - 31-

    the speed, the greater the sound of wind. The noise(Leq) may be over 70dB,

    when the speed of wind (U10) reaches 10m/s above.

    The annual average wind speed at the project site is 8.21m/s at the spot

    above 70m on the ground, that is, U10 is about 6.3m/s, while the rated wind

    speed is 12m/s at the planned wind power field. Since the local wind speed is

    high, the background noise is also great; therefore the noise impact of turbines

    to local villages is relatively small.

    Proper adjustment of the turbine location may be considered to decrease the

    noise impact of turbines to Shanxianmei, Guanlouxia and Hupuqian at largest

    extent.

    Table 4-4 shows the noise value of above sensitive spots after the location of

    wind turbines adjusted. It also shows that the value of noise generated by the

    wind turbine at the sensitive spot may be less than 50dB, only if the location of

    the turbine 39#, 64#, 63# and 47# adjusted properly, and increased the

    distance 50-100m between turbine and sensitive spot.

    Therefore, incase of not or less increasing interfere of tail flow among

    turbines, proper adjustment locations of turbine 39#, 64#, 63# and 47# may

    decrease the impact of turbines to the sensitive spots to the lowest extent, and

    the power output didn’t be or less influenced.

  • - 32-

    Table 4 -4 Noise impact forecasting around turbine location Adjusted

    Un-adjusted

    location

    Adjusted location Village Nearest

    turbine

    Nearest distance

    to turbine

    m)

    Noise at Forecast

    Spot

    (dB)

    Nearest distance

    to turbine

    Noise at Forecast

    Spot (dB)

    Distance

    Increasing

    (m)

    29# 505 505 -

    28# 755 755 -

    39# 145 195 50

    38# 480 480 -

    Shanxianmei

    37# 820

    51.7

    820

    49.8

    -

    64# 200 250 50 63# 160 260 100

    62# 500 500 -

    Guanlouxia

    65# 525

    52.6

    525

    49.8

    -

    46# 345 345 -

    47# 120 220 100

    SW Hupuqian

    48# 350

    53.3

    350

    49.7

    -

    4.2 Ecologic Environment Impact

    4.2.1 Impact on vegetation

    It’s necessary that definite land occupation is needed for the base of wind

    turbines, 110kV substation, roads at the site, cable in the earth and

    construction site. Land occupation of the project is shown at Table 4-6.

    Table4-5 Land Occupation Requisition Table

    Unit: mu

    Temporary land occupation

    Permanent land occupation

    Forestry

    land Cultivated

    land Forestry

    land Cultivated

    land

    Total

    The Bases of wind turbine - - 43.10 19.68 62.78 The area for

    installing and construction

    294.83 134.60 - - 429.43

    110kV step-up substation - - 6.98 - 6.98

    Access and cable buried - - 404.8 0.25 404.8

    Subtotal - - 3.80 19.93

  • - 33-

    Total 294.83 478.61 908.04

    Table 4-6 shows areas of various forest types of land occupation of the

    project. Total area of permanent occupation of forest is 458.68mu; in which

    wood ephedrine is the main vegetation that is windbreak forest to play an

    important role of wind-proof and sand-fixation, and 1.88mu of oranges, 3.75mu

    of jequirity trees, 0.93mu of pine trees, and a small amount of land for

    forest-planting. It shows that the quantity of oranges, jequirity trees and pines

    is less at the permanent land occupation of the site, and its impact is not

    evidence. The land occupation of the Project is only 4.6% of the total forest

    area at the district involved, there’s less impact to the local region. In the scope

    of permanent land occupation of the Project, 19.93 mu of farmland was

    included, which crops are sweet potato, wheat and peanut etc. Because of less

    amount of farmland, that it’s only 0.1% of total local farmland(16418.6mu), less

    impact to the local farmland vegetation is occurred.

    Besides permanent land occupation, temporary occupation of part forest

    and dry farmland is needed for installation wind turbines, which types are the

    same as permanent occupation. The ecologic impact of construction

    occupation is temporary, it will be disappear when the wind power field runs

    after construction completed, and wood ephedrine and other local trees are

    planted.

  • - 34-

    Table 4-6 The Statistical Table of Vegetation Requisition for Phase?

    Project of Changjiang’ao

    Unit: mu

    Town&forestryWooden Chinese

    ephedra Mandarin trees Lovesickness trees Pine

    Total land occupation

    Temporary

    Land

    OccupationTotal land occupation

    Temporary

    Land

    OccupationTotal land occupation

    Temporary

    Land

    OccupationTotal land occupation

    Temporary

    Land

    Occupation

    The state-owned

    forestry 134.26 57.68 7.35 6.41 0 0 20.16 19.23

    Luyang 177.6 44.87 7.35 6.41 0 0 6.41 6.41

    Pingyuan 284.47 96.14 0 0 29.39 25.64 0 0

    Zhonglou 57.87 12.82 0 0 0 0 0 0

    Total 654.2 211.51 14.7 12.82 29.39 25.64 26.57 25.64

    Note: “Total land occupation ”means the total area of permanent land occupation and

    temporary land occupation.

    4.2.2 Animals

    The planned project site is far from the coastal water area, which the

    nearest distance is greater than 500m, and no fishery district nearby.

    No protected animal was found at the project area, and there is no habitat

    or migration route of migratory birds, that is shown at Annex 2.

    No impact was involved to wild animals of the Project.

    4.3 Soil erosion Impact

    4.3.1 Forecast stage of soil erosion

    Forecast soil erosion is divided to two stages, construction period and

    operation period. During construction, construction activities as smoothing the

    sites, base excavation, waste soil piled or filled and part of trees cut will

  • - 35-

    destroy facilities of water and soil conservation.

    During operation, water and soil conservation may be under control

    efficiently in case of proper prevention measures, but soil erosion may be

    occurred to some extent because the primary terrain was interfered, and it

    needs time for vegetations to be returned to normal.

    Soil erosion during operation stage is much smaller than that in

    construction. Construction is the important stage for soil erosion forecast and

    prevention.

    4.3.2 Discard volume

    The filling volume of soil and stone is shown at Table 4-7.

    Table 4-7 Excavation/fill back Balance Table

    Unit: m3

    The excavating volume

    The fillback volumn

    The Dregs volumn

    Wind turbine and

    step-up substation

    30,000 42,000 -12,000

    Access 12,500 7,500 5,000

    Total 42,500 49,500 -7,000

    It’s clear from Table 4-7,that total excavation is 42,500m3, and fill 49,500m3

    in construction, while small amount of discard soil may be used as filling the

    base of the wind turbines. From volume balancing of soil and stone, there is no

    discard of the project.

    4.3.3 Destroyed facilities of soil conservation

    The main facilities of water and soil conservation at the scope of the project

    site are forestlands , and total interfered previous terrain area 908.04mu(605,

    360m2), in which the area of water and soil conservation is 753.51mu(502,

    340m2), including that of permanent 458.68mu(305,786m 2), and temporary

    294.83mu(196,560m2).

  • - 36-

    4.3.4 Amount of soil erosion

    Because of the different components of lost materials, experience formula is

    selected to forecast the interfered land that is bared surface. Following is the

    calculation formula:

    Q = m � A� a

    In which:

    Q is increment of water and soil erosion (t);

    M is average soil erosion intensity increment around the construction of the

    project (t/km 2.a), 1500t/km 2.a of forestland, 0t/km 2.a of farmland;

    A is the surface area interfered (km 2);

    a is erosion time(year), I year for permanent occupation and 3 years for

    temporally occupation.

    From calculation, total erosion increment amount of construction of the

    Project is about 1350t.

    4.3.5 Harmfulness of soil erosion

    Wind erosion is the primary soil erosion type at the site area, and the

    forestlands at involved Town of Pingyuan, Luyang and Zhonglou Village, and

    state-run forest farm are all protection forest mainly composed of wood

    ephedrine trees, that play an important role to wind-proof and sand-fixation.

    During construction of the project, 749.71mu forestland in total is occupied

    temporarily or permanently, which is 4.6% total amount of the regional forest

    area involved.

    Occupation of forestland will decrease the function of windproof and

    sand-fixation, but it will still play the role of wind-proof and sand-fixation by the

    surrounding protection forest, and the soil erosion caused from wind will be

    limited around the areas of turbines. Harm of soil erosion of the project is

    considerably small.

  • - 37-

    4.3.6 Prevent measures for soil conservation

    (1) Installation site

    It’s planned that there is a certain area installation site for each wind

    turbine, and a temporally construction base will be established in the site.

    429.43mu land is needed as temporary occupation for construction. It should

    be strictly followed the design requirement to decrease the construction

    occupation. After excavation, it’s necessary to pour concrete and fill at the site

    in time, to decrease erosion. After construction completion, temporary

    occupation should be return to normal in time or v