42
Environmental and Social Monitoring Report # Semi-Annual Report 18 April 2019 Myanmar: Emergency Support for Chin State Livelihood Restoration Project Prepared by the Department of Rural Development through the Ministry of Agriculture, Livestock and Irrigation for the Government of Myanmar and the Asian Development Bank.

Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

Environmental and Social Monitoring Report

# Semi-Annual Report 18 April 2019

Myanmar: Emergency Support for Chin State

Livelihood Restoration Project

Prepared by the Department of Rural Development through the Ministry of Agriculture, Livestock and Irrigation for the Government of Myanmar and the Asian Development Bank.

Page 2: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

This environmental and social monitoring report is a document of the borrower. The views

expressed herein do not necessarily represent those of ADB's Board of Directors, Management,

or staff, and may be preliminary in nature.

In preparing any country program or strategy, financing any project, or by making any designation

of or reference to a particular territory or geographic area in this document, the Asian

Development Bank does not intend to make any judgments as to the legal or other status of any

territory or area.

Page 3: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

Emergency Support for Chin State

Livelihood Restoration Project

(ESCSLRP)

Project Number: 9185-MYA

Environmental and Social Monitoring Report

Semi-Annual Monitoring Report (July – December 2018)

Table of Contents

LIST OF ACRONYMS .............................................................................................................................................

3 ............................................................................................................................................................................ 4

I. INTRODUCTION .................................................................................................................................................. 4

1. Background ............................................................................................................................................ 4

2. Environmental Safeguard Monitoring ................................................................................................. 6

3. Environmental Clearances .................................................................................................................... 6

Page 4: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

4. Incorporation of Environmental and Social Management Plans into the Project ....................... 6

Contractual Arrangements ........................................................................................................................ 6

5. Institutional Arrangement .................................................................................................................... 7

II. COMPLIANCE TO ENVIRONMENTAL/SOCIAL SAFEGUARDS REQUIREMENTS ................................................. 7

1. Status of Environmental and Social Management Plan Implementation ...................................... 7

2. Compliance to the Environmental and Social Management Plans for Output1 ............................ 8

3. Compliance to the Environmental and Social Management Plans for Output 2 .......................... 9

III. SUMMARY OF ENVIRONMENTAL SAFEGUARD MONITORING ........................................................................ 9

IV. KEY ENVIRONMENTAL ISSUES AND MITIGATION MEASURES IMPLEMENTED ............................................ 10

1. Corrective actions on the previous non-conformances.................................................................. 10

2. Complaints Received Related to the Implementation of the Environmental and Social

Management Plans ................................................................................................................................... 10

V. CONCLUSION .................................................................................................................................................. 13

APPENDICES .............................................................................................................................................. 13

Appendices

A. Environmental and Social Management Plans for Output 1: Restored village access

infrastructure with increased disaster resiliency

B. Environmental and Social Management Plans for Output 2: Restored community

infrastructure with increased disaster resiliency

C. Rapid Environmental Assessment Checklist - Roads

D. Photo Log

E. Project Location Map (Burmese language)

F. Environmental Clearance Correspondences (Burmese language)

LIST OF ACRONYMS

ADB – Asian Development Bank

AP – Affected Person

DRD – Department of Rural Development

Page 5: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

EA – Executing Agency

ECD – Environmental Conservation Department

EIA – Environmental Impact Assessment

ESMP – Environmental and Social Management Plans

ESCSLRP - Emergency Support for Chin State Livelihood Restoration Project

ESS – Environmental and Social Screening

ESSF – Environment and Social Safeguard Framework

GIU – Grant Implementing Unit

GMU – Grant Management Unit

IEE – Initial Environmental Examination

JFPR – Japan Fund for Poverty Reduction

MLFRD – Ministry of Livestock Fisheries and Rural Development

MoALI – Ministry of Agriculture, Livestock and Irrigation

NPT – Nay Pyi Taw

PPE – Personal Protective Equipment

REGDF – Resettlement and Ethnic Groups Resettlement Framework

RP – Resettlement Plan

Page 6: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

4

I. INTRODUCTION

1. Background

Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30

July, cyclone Komen made a landfall in Bangladesh, bringing strong winds and additional

heavy rains to Myanmar, which resulted in widespread flooding across 12 of the country’s 14 states and regions. The following day, on 31 July, the president declared Chin and Rakhine

States as well as Magway and Sagaing Regions as a natural disaster zones. In Chin State, the

monthly rainfall in July measured at a weather station in Hakha was equal to 1-in-1,000 year

rainfall. The combination of heavy rainfall, strong winds, high soil saturation, and unstable

soils in hilly areas caused widespread and devastating landslides particularly in Chin. Landslide

destroyed a large part of the public goods assets needed to support rural livelihoods, most

importantly the rural transport network that allows people to access markets for the sale and

purchase of goods and to access services provided by both public and private sectors.

Approximately 460 miles of rural roads require

restoration in more than seven of Chin’s townships. These roads are generally earth construction, from

four to 18 feet wide and categorized as village to

village and village to town roads. In addition, the

floods and landslides washed away many bridges

and drainage structures to prevent road flooding.

The Asian Development Bank (ADB) approved the

from Japan Fund for Poverty Reduction (JFPR)

funded $8.856 million project in April 2016 under

Emergency Support for Chin State Livelihoods

Restoration Programme (ESCSLRP). The JFPR was

established in 2000 to provide grants for projects

supporting poverty reduction and related social

development activities that can add value to

projects financed by ADB. UNOPS and the

Government of Myanmar’s Department of Rural Development (DRD) signed an agreement on 2 November 2016 to restore the damaged roads

and structures. The Ministry of Agriculture, Livestock and Irrigation (MoALI) and the DRD are

the project customers. The project implementation period is from November 2016 to 31

October 2019. The Project comprises of two outputs as listed below:

Output 1: Restored village access infrastructure with increased disaster resiliency in Chin State’s mostly-affected townships of Tonzang, Tedim, Falam, Hakha, Htantlang, Mindat and Matupi (see Appendix E for map location)

Output 2: Restored community infrastructure, such as damaged water supply pipes ana electricity power supply with increased disaster resiliency in Chin State’s mostly-affected township of Tonzang, Tedim, Falam, Hakha, Htantlang, Mindat and Matupi

Under the Output 1 - The road repair work includes spot filling on existing road surface, slab

culverts, retaining walls, side drain and bio-engineering works in seven priority roads in seven

Page 7: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

5

townships in Chin State. The total length of the roads is 153.1 miles. The progress of the road

repair work during the reporting period is shown in the table below:

Overall work Progress As of 31 December 2018

Road Repair /Spot Improvement Works

on Lot No Township

Length of

Road

(Miles)

%

Progress Time Elapsed

Kyaw Htee Yar- Ze' Phile Road Lot 1

Htantalang 14.0 75% 99%

Lot 2 13.85 20% 99%

Falam-Lailun-Relsing-Khuangli Road Falam 14.0 92% 99%

Pimpih-Khaikam Road Tedim 10.0 98% 99%

Arm Sui-Maa Duu-WaiLuu Road Lot 1

Matupi 11.0 90% 104%

Lot 2 11.0 90% 104%

Zampe Junction-Zampe-Ling

ThukHaicin-Tulkhing Road

Lot 1 Tonzang

13.5 92% 92%

Lot 2 13.5 91% 93%

Shih-Tweli-Doh-Hliah Ring-Thaing Nuu-

Ma Gwe Ing Nuu Road

Lot 1

Mindat

15.3 6% 70%

Lot 2 15.3 15% 75%

Lot 3 15.4 47% 77%

Hakha-Cinkhua Junction Road (6.25

miles) Hakha 6.25 99.7% 100%

70 Feet Long Bailey Bridge in Htantlang

Township Htantlang 40% 51%

Total 153.1 66% 89%

Under the Output 2 - As of 31 December 2018, the progress on the restoration of damaged water

supply pipes and electricity power supply (micro-hydropower) schemes based on revised list of

villages is given below:

Townships No of Damaged

Schemes Total

(No) Completed Remaining Remarks

Tonzang, Tedim,

Falam, Hakha,

Htantlang,

Mindat and

Matupi

Damaged Water

Supply Pipes and

Schemes

(Revised list)

44 16 28 DRD has adopted

Community Based

Development Approach for

community infrastructure

repair works

Tonzang, Tedim,

Falam, Hakha,

Htantlang,

Mindat and

Matupi

Damaged Electricity

Power Supply and

Schemes

(microhydropower) –

Revised List

25 5 20 DRD has adopted

Community Based

Development Approach for

community infrastructure

repair works

Total 69 25 48

Page 8: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

6

2. Environmental Safeguard Monitoring

Emergency Support for Chin State Livelihood Restoration Project (ESCSLRP) was classified as an

Environment Category B project under the ADB policy, as explained below. For ADB, the project

is classified category B for Environment. As this project is emergency assistance, an

environmental assessment and review framework (EARF), has been prepared in accordance

with ADB’s Safeguard Policy Statement (2009) and government laws and regulations. Subproject selection criteria have been formulated to avoid significant adverse environmental

impacts. Subprojects that have potential to cause significant irreversible, diverse or

unprecedented adverse environmental impacts (Category A under ADB SPS (2009)) are not

eligible for funding under the Grant. All subprojects will be screened. Subprojects will be

categorized either B or C. For category B projects, initial environmental examinations and

environmental management plans (EMPs) will be prepared. EMPs will be incorporated in bidding

documents and contract documents to be implemented by contractors and monitored by the

implementing agencies.

Following the UNOPS guidelines, all sub-projects under the project were screened for

environmental and social impacts; followed by Environmental Review and then Environmental

and Social Management Plans (ESMP) were prepared for each subproject before the

tendering. The ESMP contain typical road repair and construction related measures that cover

impacts on air quality from the unpaved road travel and emissions from equipment, water

quality deterioration from camp operation, land clearing, occupational and community health

and safety, among others.

3. Environmental Clearances

Environmental Conservation Department (ECD), Nay Pyi Taw has approved EMPs for road repair

/ spot improvement works on 30 July 2018 (Please refer to Appendix F). The EMPs are being

implemented and constantly monitored at sites.

ECD, Nay Pyi taw has not yet approved the EMP for Bailey bridge but the EMP is being

implemented and constantly monitored at site.

4. Incorporation of Environmental and Social Management Plans into the

Project Contractual Arrangements

The ESMP were integrated in the civil works contract. The contractors were made aware of this

obligation and their safeguard performance during the construction will was supervised and

monitored by UNOPS’ project manager with support of the UNOPS project engineers.

The environment and social impacts of the projects were identified in the Environment and

Social Safeguard Framework (ESSF) and the mitigation measures of these impacts have been

addressed through ESMP. The protection and enhancement of human-wellbeing is a common

demonstrator for both government and donors systems and contributed to the ultimate goal of

sustainable development.

DRD and UNOPS conducted a meeting with local authorities in the project area to create a sense

of social, environmental and safety awareness within all construction activities. During the

meeting, the grievance mechanism was also introduced to local communities living along the

road project.

Page 9: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

7

5. Institutional Arrangement

The DRD with the Ministry of Livestock Fisheries and Rural Development (MLFRD) is the

executing agency (EA) and implementing agency for the project. DRD has established a grant

management unit (GMU) at the DRD in Nay Pyi Taw.

The GMU is responsible for the project’s overall management and coordination. A project

director and a deputy project director/project manager who are responsible for management

and supervision of the activities head the GMU. The GMU is supported by procurement, finance,

communication, gender, safeguard and other specialists as indicated in the organogram.

A grant implementing unit (GIU) has been established at Hakha in Chin State. Seven sub-GIUs

were also established at the respective DRD township offices to coordinate and supervise the

sub-project activities at the township level. The GIU is also supported by procurement, finance,

communication, gender, safeguards and other specialists as indicated in the organogram.

The sub-GIUs have been established at respective townships headed by project manager

and supported by safeguard and monitoring & evaluation specialists. UNOPS represents at

all levels of grant implementation at NPT, Hakha and at the respective townships.

II. COMPLIANCE TO ENVIRONMENTAL/SOCIAL SAFEGUARDS

REQUIREMENTS

The DRD is able to sustain its compliance to the environmental provisions of the ESCSLRP grant covenant. Both, general and specific ESMP form parts of the bidding documents and civil

works contracts. The DRD is implementing the mitigation measures in accordance with the Government of Myanmar and ADB environmental policies and submitting timely semi-annual reports.

ADB categorized the ESCSLRP project as Category B and during the screening process

following environmental issues were identified:

I) Localized issues of air pollution from vehicle and machinery exhaust, including

dust and smoke during construction;

II) Disturbance of river and stream ecology from construction of bridges and other

drainage structures;

III) Removal of vegetation and forest coverage;

IV) Disturbance and damage to wildlife habitat and illegal quarrying, hunting,

fishing, cutting trees etc.;

V) Waste disposal causing scarring of landscape and destruction of vegetation;

VI) Social issues such as noise and disturbance to nearby settlements, disputes,

spread of diseases, and pollution of drinking water sources etc.;

VII) Cut slopes and landslide areas.

1. Status of Environmental and Social Management Plan Implementation

ESMP were implemented in all works contracts for landslide clearance in seven townships as

mentioned above and were monitored on a regular basis by the project engineers from UNOPS , DRD and contractors.

Page 10: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

8

2. Compliance to the Environmental and Social Management Plans for

Output1

As mentioned, the ESMP contain environmental measures that are applicable to all seven

priority roads. Also, these ESMP provide measures to protect air and water qualities, avoid

damages to soil, preservation of forest resources including wildlife, good practices in

construction camp management, liabilities of contractor in damaging local infrastructure,

and operating procedure in cases of chance archeological findings.

Overall, of the 312 mitigation measures prescribed in the ESMP, ESCSLRP achieved 88%

compliance rate (see table below). Partial compliance was achieved in 37 items. A summary

of ESMP Implementation by Road Segment is given below. Appendix A presents the details

of ESMP implementation under this output.

Total No.

Mitigation Measure

Prescribed

in ESMP

% Compliance

ex‐Not

Applicable

Township Road

Segment

Name

Compliance Performance

Yes Partial No

Not Applicable

TONZANG

Zampe

Junction-Zampe-Ling Thuk-Haicin-Tullkhing

48 40 6 0 2 87%

TEDIM

Canadi-Tuisauh-Pimpih-Khaikam

24 20 3 0 1 87%

MINDAT

Shih-Twele-Doh-Hliah Ring-Thaing Nuu-Ma Gwe Ing Nuu

72 60 9 0 3 87%

MATUPI Arm Sui-Maa Duu-WaiLuu Road

48 40 6 0 2 87%

HTANGLANG Ze’phile-Kyaung Htee Yar

48 40 6 0 2 87%

HAKHA Ha Kha-Khwa Be

24 20 3 0 1 87%

FALAM Falam-Lailun-Relsing-Khuangli

24 20 3 0 1 87%

Htantlang Bailey Bridge 24 20 1 0 3 95%

TOTAL 312 260 37 0 15 88%

Page 11: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

9

3. Compliance to the Environmental and Social Management Plans for Output 2

As mentioned, the ESMP contains environmental measures that are applicable to all

installation and rehabilitation of pipelines from natural springs, solar panels and charge

station. This ESMP provides measures to apply to protect the structures and avoid damages.

The communities in different townships are implementing the activities under this output.

Overall, of the 113 mitigation measures prescribed in the ESMP the work carried out for 18

water supply and 5 micro/ solar schemes by the communities do not pose any environmental

threats and there is no specific or general ESMP, as shown below. Appendix B presents the

details of ESMP implementation under this output:

Township

Name Scheme

Total No. Mitigation

Measure Prescribed

in ESMP

Compliance Performance

% Compliance

ex‐Not Applicable

Yes Partial No Not

Applicable

Tedim, Falam, Hakha, Mindat

Damaged water

supply pipes and

schemes

108 72 18 0 18 Done

Community

Based

Development

Approach

(CBDA)

Damaged electricity

power supply and

schemes

(microhydropower)

5 5 0 0 0 Done

Community

Based

Development

Approach

(CBDA)

TOTAL 113 77 18 0 18 86%

Overall 86% compliance had been achieved during the reporting period.

III. SUMMARY OF ENVIRONMENTAL SAFEGUARD MONITORING

Inspections were conducted using an agreed-upon checklist covering the aspects of

regulatory compliance and mitigation measure implementation. The inspections were led by

Project Manager/ Project Engineer supported by environment focal persons. These on-site

inspections focused on active construction fronts and construction camps. Road side

interviews with the site engineers, workers, and residents were conducted to validate

reports, while a facility walk through the campsite allowed monitoring of occupational health,

safety and related mitigation measures. Finally, contractor records were reviewed to confirm

site findings.

In general, if there are any issues, complaints and matters related to the impact of the projects, these matters will be informed to the DRD State Office but so far, no complaints and grievance have been reported from the community or any other stakeholders.

The ESCSLRP has been implementing the output 1 and output 2 activities in an existing road

alignments and also the community infrastructures locations, there is less chance to have

Page 12: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

10

social issues of resettlement and also the case of Land Acquisition. The project has not found

any issues of Resettlement and Land Acquisition till to date.

During the reporting period from July –December 2018, no complaints were received by the

GIU and sub-GIUs offices related to the impacts of road repair /spot improvement works in

seven townships.

IV. KEY ENVIRONMENTAL ISSUES AND MITIGATION MEASURES

IMPLEMENTED 1. Corrective actions on the previous non-conformances

During the reporting period from January to June 2018, several outstanding non

conformances were resolved and these are:

I) Damaged Water supply pipelines at sites are being restored by construction

companies and communities at respective townships.

II) The construction debris and boulders in private land and public places were removed

in all the roads. This corrective action will be continued till the project completed road

repair works.

III) A health awareness campaign was conducted to the workers and staff within project vicinity. Continuous improvement on PPE were observed during the reporting period.

IV) All contractors are from the Chin State with very limited skilled personnel and

resources and capacities, the contractors have shown significant improvement in their

capacity on the traffic management and site management. UNOPS and DRD

engineers still provide sufficient skills and managerial advices to the contractors at sit

as well during meeting.

2. Social Complaints Received Related to the Implementation of the

Environmental and Social Management Plans

During the reporting period from Jan – June 2018, no complaints were received by the GIU

and sub-GIUs offices related to the negative impacts of road repair works carried out on 7

priority roads in seven townships.

GRIEVANCE REDRESS MECHANISM

Grievance redress mechanism is an integral part of the project’s monitoring and information

system. It aims to ensure that feedback is received, that the voices from the poor and

marginalized groups are heard, and that the issues raised are resolved effectively and

expeditiously.

A practical grievance redress mechanism (GRM) has been established as part of the project’s implementation framework. The GRM operates at township (in the GIUs) and at Union levels

(in the GMU) to handle any grievance arising from the Project

In general, if there are any issues, complaints and matters related to the impact of the

projects, these matters will be informed to the DRD Township, then State Office but so far, no

complaints and grievance have been reported from the community or any other stakeholders.

The ESCSLRP has been implementing the output 1 and output 2 activities in an existing road

alignments and also the community infrastructures locations, there is less chance to have

Page 13: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

11

social issues of resettlement and also the case of Land Acquisition. The project has not found

any issues of Resettlement and Land Acquisition till to date.

The table below lists the potential impacts (Positive and negative) of the project on

EGs.

Project Outputs Anticipated

Positive

Effects

Anticipated Negative

Effects

Comments/ Remarks

Output 1:

Village to

village and

village to town

rural access

roads and

associated

bridges

repaired or

restored

Men and women

of working age

from disaster

affected

communities and

surrounding

villages will earn

cash incomes

from being

employed on

roads/bridges

repair works

If modalities for consultation and participation during project preparation and subsequent implementation are not EG sensitive, the following may occur:

- Subprojects may not

meet or match the post-

disaster needs of the

affected EG

communities

- Lack or low participation of the community, particularly women. Consultation with and

participation of EGs will be done at initiation of subproject preparation using a gender-and culturally sensitive approach. Informal and formal leaders of EGs will be engaged to help facilitate the discussions. On contracted works, members of disaster

affected villages may lose

out on employment

opportunities to non-local

laborers recruited or

brought in by contractors.

To mitigate this, contracts

will require employment of

Some men and women

were engaged for landslides clearance works because most of the sites machines were used during the reporting period.

Disaster affected

communities

will regain access

to goods and

services

Villagers regained access again after landslides clearance works ( 65 roads were cleared)

Villagers got access to goods, market and services.

Affected villagers and

Disaster affected

communities

will regain access

to markets to sell

their surplus

produce

Page 14: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

12

Disaster affected

villages and

households will

be able to

restore their

previous

livelihood

local labor from households restored their

previous livelihood activities

such as farming , selling

garden products etc

activities or

restart new

livelihood

sources in the

villages they are

relocated to

Disaster affected

communities particularly for

unskilled jobs.

Most of men and some of

women were engaged in the

repair/ restoration works for

output 2.

After restoration villagers got

their water supply and

electricity system.

Output 2:

Community

infrastructure

and livelihood

assets repaired

or restored

Men and women

of working age

from disaster

affected

communities and

surrounding

villages will earn

cash incomes

through

employment in

repair works

Disaster affected

villages and

households will

be able to

restore their

previous

livelihood

activities or

restart new

livelihood

sources in the

villages they are

relocated to

Page 15: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

13

Output 3:

Asset resilience

and disaster

preparedness

increased

Men and women in Chin communities will be trained

on community based disaster risk management

Once the assets have been repaired or restored, EGs’ general interest in other Project activities may wane. Village leaders (formal and informal) will be engaged to assist with provision of community training. Participation of women will

be encouraged

NA

Chin

communities

will be trained

NA

to operate and

maintain

community

infrastructure

and livelihood

assets properly

The ESCSLRP has been implementing the output 1 and output 2 activities in an existing road

alignments and also the community infrastructures locations, there is less chance to have

social issues of resettlement and also the case of Land Acquisition. The project has not found

any issues of Resettlement and Land Acquisition till to date.

During the reporting period from July to December 2018, no complaints were received by the

GIU and sub-GIUs offices related to the impacts of road repairs/spot improvement works on

7 priority roads in 7 townships.

V. CONCLUSION

This ESCSLRPs semi-annual monitoring report to be prepared is the requirement as per the

ADB SPS 2009 for environmental Category B projects. There are twelve separate contract

packages under this project and all contract packages are in progress.

Overall, the project showed high level of compliance to the ESMP achieving 88% on Putpu1

and 86% on Output 2. Health and safety awareness trainings are being conducted and no

major health and safety issues were reported. During the implementation stage the

construction companies will implement Bio-engineering works for reinstate hillside slope

stability and embankment in the selected seven priority roads.

Currently, the EMPs are being implemented and monitored as the works are in progress in all

sites.

APPENDICES Appendix A- ESMP Output 1: Restored village access infrastructure with increased disaster

resiliency

Page 16: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

14

Sl Mitigation Measures Compliance attained (Yes, No,

Partial, NA)

Comments/Reasons for Partial or Non Compliance

Issues for further action

and target date

Landscape & visual impact

1 Removal of landslides (provisioned in the BoQs as unforeseen) spot filling/ cutting on hill sides/ valley sides. May increase soil erosion; damage the beauty of the landscape:

Avoid excessive cutting and filling; dump landslides, debris materials in a designated places. Minimize widening works.

Yes Minimized the cutting and

widening for roadside drain

All measures have been

complied.

Complied.

Some bio-engineering

techniques were applied to

stabilize the roadside slopes

and tipping areas wherever

necessary as these are

already provisioned in the

BoQ and within the

allocated budget.

2 Remove construction debris Partial Debris are being dumped at

designated areas, except in

steep slope, especially for

foundation of structures on

valley side.

Complied and continue till

project completes

3 Impose traffic controls to reduce public

exposures Yes From time to time, the road

is open for road users at

different locations.

Informed public about the

timing of the work.

Ecology (habitats, flora and fauna)

4 Use of timber materials/ soil/ stones:

Cutting trees by timber suppliers,

extract materials from selected

borrow pits only with quality and

sufficient quantities.

Yes Contractors were encouraged to buy timbers from legally registered timber suppliers, Use surplus soil or use only

approved borrows pits.

Trees will be planted in

May/June as planned as per

BoQ.

Archaeology and cultural heritage

5 Road Alignment:

Avoid road alignment through

important archeological and

cultural heritage sites and places.

N/A No archaeological sites found

along all seven priority roads.

The existing roads pass

through the villages. No

extension of length of road is

required.

N/A

Air quality (emissions and indoor and outdoor air quality)

6.

Use and operation of generators, construction equipment, machinery and vehicles:

• Regular maintenance of all machinery, equipment and vehicles;

• Procure generators with less emission.

Yes

Minor maintenances are done at construction area (workshop) and the major maintenances are done at the nearest towns.

Continue till end of

project.

Water (usage, discharges and risk of floods)

Page 17: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

15

7 Use of water at construction sites and camps. Flooding dues to nearby/neighbor streams/rivers • Avoid use of construction water from

the same source the local communities use

• Avoid camp flooding during rainy

season

Yes

Yes

Contractors were advised to find separate water source and reduce conflicts of water with local communities. Monitor and record the

available data

Use the data, information

etc for further appropriate

solution if damages occur.

Contamination 8 Operation of camp, equipment storage,

repair and fuel depots • Construct septic tanks and soak pits

with appropriate distance to water sources Proper disposal of human wastes during construction

• Install secondary containment around fuel tanks and at fueling stations.

• Prevent oil and fuel spills, control runoff from contaminated areas

Yes

Yes

Yes

Septic tanks located at a distance of 30m or more from underground water sources, like boreholes or hand dug wells. Waste from camps is disposed in pits within the designated areas. The waste from

workshops and fuel tanks

are taken into account.

Complied

Time to time, all

contractor staffs were

continuously reminded and

trained to manage leakage

of fuel and lubricants at

site and will continue until

project completes.

Energy (usage, source, cost etc)

9 Machine

Use labors wherever possible such as

cleaning of existing drains,

bioengineering works and collection of

stone, sands etc

Yes Due to nature of terrain combination of both machine and work force were used. Some source of sand,

stones and aggregates are

far, hence dump trucks are

being used.

Complied where possible.

Materials (quantity and type used)

Page 18: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

16

10. Use of sand, aggregate, stones timber products, gravel, soil from legal sources and avoid resource depletion and degradation: • Encourage contractor to buy from

legally registered and environmental friendly suppliers.

• Avoid extraction of excess materials and disposal of construction materials

Yes

Contractor has obtained the approved clearance and permit from the relevant agencies for the material surface collection of boulders and also other supplies are from the licensed suppliers/ traders.

Mitigation measures

complied.

Waste management

11 Disposal of solid wastes generated by the camp and left over of construction:

Avoid contamination due to improper

disposal of solid wastes generated by

the camp and construction

Partial Sorting wastes by category before disposal e.g. biodegradable wastes such as remains of food and non- bio-degradable wastes such as plastic water bottles are collected in separate collection bins Provided waste collection bins which should be regularly emptied in a designated dumpsite. Disposal of wastes in

approved disposal pits and

recyclable materials to be

recycled and organic wastes

to be composted in a regular

interval.

Some camps were not maintained for waste management but will improve in next reporting period.

All contractor staff were

continuously reminded and

trained to manage waste

and its proper disposal at

site.

Nuisance (noise, dust vibration etc.)

12 Use of generator and concrete mixer, heavy earth moving machines during the construction:

Minimize noise pollution from

generators and mixers disrupt nearby community, public places such as school, hospitals and to workers.

Yes Activities with intensive noise were undertaken during least disruptive times. Consultation was done with the local communities and their acceptance was sought.

Complied.

Transport (transport / traffic plans)

Movement of equipment and traffic management

Impose traffic control measures during

movement of construction machines

and transportation of construction

materials.

Yes Traffic control measures and management was put in place at each working site

in consultation with village

head/local communities.

Complied

Page 19: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

17

Social Issues

13 During the construction, road will be closed at certain frequent interval. • Minimum road traffic and disturbance

to the community day today activities Job Opportunity • Avoid conflicts for job opportunities

between local community and labors from other areas Employment opportunities.

Small Scale business at site • Increase road safety due to improved

road infrastructure.

Yes

Yes

Yes

First provided space for free flow of traffic at structures construction, manage traffic control at each location during road works

Maximum local labor including women workers with equal pay for similar types of jobs were employed by the contractors. No Action Required

Complied.

Maximum available

women labors about 18

% in average were

engaged during

construction.

Economic Opportunity

14 Income source • Generate income to material/

equipment suppliers and local communities

Job opportunity Small scale business at site

• Improvement in livelihoods and

local economies

Yes Contractors were from the

local regions ; and they used

local suppliers and local labor

Complied.

Labor Right during Construction.

15 Employment of labor

Provide laborers and others resident at

the site lodging in a camp setting

outside of any danger zone, food

service facilities, safe drinking water,

adequate washing and bathing facilities

for maintaining personal hygiene, and

access to health care.

Yes Labors are provided with

all the necessary logistics

and hygienic and sanitary

facilities at their work

camps and mobile camps

too.

Contractor to provide all

the necessary items

throughout the

construction phase.

16 Employment of labor: safety

Provide adequate protective gear,

maintain equipment, and train workers

to be skilled in their jobs; record

accident frequency, apply corrective

measures.

Yes All the safety gadgets are

provided to every worker

at site and they are made

to use the safety gadgets

during construction hours.

Complied

17 Set up of construction camps. • Camp facilities should be located at a

distance from nearby communities. • Provide sanitary facilities (dry pit or

pour flush latrines) for workers

Yes Labor camps and site

offices are located far from

the communities. Waste

from camps is disposed in

pits within the

Complied.

Bio-Engineering works designated areas.

Page 20: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

18

18 Stabilize cut slopes/ unstable slopes/ tipping sites

• Plantation, brush layering • Boulder barrier/live check dams • Provide timber crib walls • Provide French drains

Partial

The favorable season for

major bio-engineering items

starts in June. The

construction works is in

progress.

In some roads it was

implemented and further

Bioengineering works will be

implemented in May and

June.

Page 21: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

19

Appendix B - EMP - Output 2: Restored community infrastructure with increased disaster

resiliency

Sl Mitigation Measures

Compliance

attained

(Yes, No,

Partial,

NA)

Comments/Reasons

for Partial or Non

Compliance

Issues

for

furthe

r

action Installation/ Rehabilitation of pipelines from natural springs

1 Preventing contamination at

water sources:

I) Build a structure with roof over the water source to prevent leaves or other debris from contaminating the basin.

II) A fence is needed to

protect the water sources

(springs particularly) from

public access and risk of

contamination.

III) The sand/gravel filter traps sediment before the spring flow enters the collection chamber and has to be changed during periodical maintenance.

Partial

Structures are built with roof cover to prevent leaves and debris entering in to the basin

Fences were provided

by the community

Sand/gravel filters

were provided to trap

sediment

Complied being implemented through community.

Page 22: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

20

2 Pipe Laying:

I) PVC water transmission and distribution piping need to be buried underground (coverage 50cm minimum) to prevent pipe against external damage (e.g. passing vehicles, solar UV radiation, etc.).

II) When conditions do not allow pipes to be buried (i.e. pipe is used above ground), then metal pipe must be used, and supported/braced as excessive movement may lead to leaks and breaks.

III) Outlet pipes and fittings from water storage/basin shall not be PVC pipe due to exposure to solar UV/sunlight. Metal piping and fittings are preferred

Partial

All PVC pipes are

buried 50cm under

ground

Where ever possible

metal pipes were used

Complied being implemented through community

Rural Electrification

3 Solar Panels and Charge Station

I) Provide a shed for

genet (distributed

electrical generator

charge station system)

or pumps that are

accessible for easy

maintenance as regular

maintenance is

important to avoid

Yes

Shed has been provided for the invertor and batteries.

Complied being implemented through community

Page 23: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

21

Appendix C Rapid Environmental Assessment Checklist - Roads

Subproject Title : Emergency Support for Chin State Livelihood Restoration

Location: Chin State, Hakha

Screening Questions Yes No Remarks

A. PROJECT SITING IS THE PROJECT AREA ADJACENT TO OR WITHIN ANY OF THE FOLLOWING ENVIRONMENTALLY SENSITIVE AREAS?

CULTURAL HERITAGE SITE X

PROTECTED AREA X

WETLAND X

MANGROVE X Existing road does not affect

Mangroves.

ESTUARINE X Road passes and crosses estuarine.

BUFFER ZONE OF PROTECTED AREA X

SPECIAL AREA FOR PROTECTING BIODIVERSITY X

B. POTENTIAL ENVIRONMENTAL IMPACTS WILL THE

PROJECT CAUSE…

encroachment on historical/cultural areas; disfiguration of

landscape by road embankments, cuts, fills, and quarries? X

encroachment on precious ecology (e.g. sensitive or

protected areas)? X

alteration of surface water hydrology of waterways

crossed by roads, resulting in increased sediment in

streams affected by increased soil erosion at

construction site?

X Some material may unintentionally

fall in the river (minor spillage)

deterioration of surface water quality due to silt runoff and

sanitary wastes from worker-based camps and chemicals

used in construction?

X

increased local air pollution due to rock crushing, cutting and

filling works, and chemicals from asphalt processing? X Air pollution due to use of heavy

machines.

risks and vulnerabilities related to occupational health and

safety due to physical, chemical, biological, and radiological

hazards during project construction and operation during

project construction and operation?

X Working with heavy machines and in

difficult areas always includes risks.

Page 24: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

22

noise and vibration due to blasting and other civil works? X Construction works always include

noise and vibration.

Screening Questions Yes No Remarks

dislocation or involuntary resettlement of people? X

dislocation and compulsory resettlement of people living in

right-of-way?

X

disproportionate impacts on the poor, women and children,

Indigenous Peoples or other vulnerable groups? X

other social concerns relating to inconveniences in living

conditions in the project areas that may trigger cases of

upper respiratory problems and stress?

X

hazardous driving conditions where construction interferes

with pre-existing roads? X

poor sanitation and solid waste disposal in construction

camps and work sites, and possible transmission of

communicable diseases (such as STI's and HIV/AIDS) from

workers to local populations?

X

creation of temporary breeding habitats for diseases such as

those transmitted by mosquitoes and rodents? X

accident risks associated with increased vehicular traffic,

leading to accidental spills of toxic materials? X

increased noise and air pollution resulting from traffic

volume? X

increased risk of water pollution from oil, grease and fuel

spills, and other materials from vehicles using the road? X

social conflicts if workers from other regions or countries are

hired? X Not reported yet.

large population influx during project construction and

operation that causes increased burden on social

infrastructure and services (such as water supply and

sanitation systems)?

X

risks to community health and safety due to the transport,

storage, and use and/or disposal of materials such as

explosives, fuel and other chemicals during construction and

operation?

X No but there is a minor risk.

community safety risks due to both accidental and natural

causes, especially where the structural elements or

components of the project are accessible to members of the

affected community or where their failure could result in

injury to the community throughout project construction,

operation and decommissioning.

X Properly designed structure and safely

construction sites have very little risk of

affecting local communities.

Page 25: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

23

Appendix D- Photo Log

Falam Township

Final Inspection photos

Page 26: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

24

Htantalang Township

Lot 1_Completed on Kyaung Htee Yar-Ze’Phile road

Pile construction in progress for ABT(1) and Delivery of Bailey Bridge Parts

Matupi Township

Page 27: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

25

Mindat Township

Lot-1 Landslide Clearance wok to open road block

Page 28: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

26

Lot 2 : Precast concrete work in progress

Lot 3 : Slab Culvert Construction work in progress

Tedim Township

Page 29: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

27

Tedim Final Inspection Photos

Tonzang Township

Page 30: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

28

Tonzang Final Inspection Photos

Hakha Township

Page 31: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

29

Completed works on Hakha – Cinkhua Junction road

Page 32: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

30

Appendix-E: Location Maps of Seven Priority Roads in 7 Townships

Page 33: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

31

Page 34: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

32

Page 35: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

33

Page 36: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

34

Page 37: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

35

Page 38: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

36

Appendix F – EMPs Approval from ECD, Nay Pyi Taw

Page 39: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

37

Page 40: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

38

Page 41: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

39

Page 42: Environmental and Social Monitoring Report€¦ · Heavy rains caused floods and landslides in several parts of Myanmar during June 2015. On 30 July, cyclone Komen made a landfall

40