28
Environmental and Social Monitoring Report Semi-Annual Report July – December 2013 NEP: Melamchi Water Supply Project-Subproject 2 Prepared by Safeguards Unit of Project Implementation Directorate (PID), Kathmandu Upatyaka Khanepani Limited (KUKL), for Nepal and the Asian Development Bank.

Environmental and Social Monitoring Report environmental and social monitoring report is a document of the borrower. The views ... 4 Nayapati 2(ka)2 724, 714 Gopal Pudasaini 14,387

Embed Size (px)

Citation preview

Environmental and Social Monitoring Report Semi-Annual Report July – December 2013

NEP: Melamchi Water Supply Project-Subproject 2 Prepared by Safeguards Unit of Project Implementation Directorate (PID), Kathmandu Upatyaka Khanepani Limited (KUKL), for Nepal and the Asian Development Bank.

This environmental and social monitoring report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB's Board of Directors, Management, or staff, and may be preliminary in nature. In preparing any country program or strategy, financing any project, or by making any designation of or reference to a particular territory or geographic area in this document, the Asian Development Bank does not intend to make any judgments as to the legal or other status of any territory or area.

Project Implementation Directorate

Kathmandu Upatyaka Khanepani Limited (KUKL)

Anamnagar, Kathmandu

Loan 1820 (SF), Melamchi Water Supply Project (Sub-project – 2)

BI ANNUAL SOCIAL AND ENVIRONMENT SAFEGUARD MONITORING REPORT

(July 2013 to December 2013)

March, 2014

Submitted by

CDM Smith inc. USA

in association with

TAEC Consult P. LTD and Integrated Consultants Nepal P. LTD

TABLE OF CONTENTS

A. EXECUTIVE SUMMARY ........................................................................................... 1

B. PROJECT DESCRIPTION ........................................................................................ 1

C. SCOPE OF SOCIAL SAFEGUARD IMPACTS ......................................................... 2

D. COMPENSATION AND REHABILITATION .............................................................. 3

E. PUBLIC PARTICIPATION AND CONSULTATION ................................................... 4

F. GRIEVANCE REDRESS ........................................................................................... 5

G. INSTITUTIONAL ARRANGEMENT .......................................................................... 5

H. MONITORING RESULTS/FINDING .......................................................................... 6

I. COMPLIANCE STATUS ........................................................................................... 6

J. FOLLOW UP ACTIONS, RECOMMENDATIONS ..................................................... 7

K. COMPLIANCE OF LOAN COVENANTS RELATED TO ENVIRONMENTAL SAFEGUARDS ..................................................................................................................... 9

L. COMPLIANCE OF ENVIRONMENTAL IN MAJOR CONSTRUCTION ACTIVITIES ... 9

Annexes

1. Photographs of Public Consultations

2. Attendance in Consultative Meetings

KUKL: KVWSIP Loan 1820 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 1

A. Executive Summary 1. The proposed Kathmandu Valley Water Supply Improvement Project1 will support the ongoing efforts of the Government of Nepal towards improving the water supply services in Kathmandu Valley. The project will invest in bulk water transmission and distribution network improvement systems, and will complement past and ongoing Asian Development Bank (ADB) projects.2The resultant synergy is expected to lead to increased efficiencies, greater improvement in service delivery, and higher impact on health outcomes and quality of life for inhabitants of Kathmandu Valley. This biannual report presents the Resettlement Plan (RP) implementing status from July to December 2013. It will be implemented by the Project Implementation Directorate (PID), Kathmandu Upatyaka Khanepani Limited (KUKL), who will address any resettlement impacts, permanent or temporary, during project implementation. 2. The overall project is classified as category C in accordance with ADB Safeguard Policy Statement (SPS). ADB's SPS covers both temporary and permanent impacts Most of the land for the project was previously acquired under the ADB Loan 1820. One parcel of land has been acquired during the reporting period. Altogether 16 households have received NRs 930,354 as compensation amount for the loss of trees during the reporting period. A total of five major consultative meeting were held in community to address the compliance of grievance related social issues. The meeting covered issues of land as well as compensation and other related to project activities. The regular meeting with community is in continuous. The PID KUKL has been addressing grievance resulted from project activities. Altogether seven grievances were filed during the reporting period. Most of the grievances were related to compensation for the loss of private assets. The grievances related to social safeguard is treated immediately within the project entitlement framework and the numbers of grievances related to social safeguard are minimal. The affected households have received compensation in timely manner and the Ap's are satisfied with the compensation rate. The implementing body has complied institutional requirement for the implementation of RP and the RP implementation is continuous. The environmental parameters are also monitored during the reporting period. The monitoring parameters have been compiled by the contractor in project construction activities.

B. Project description 3. Melamchi Water Supply Project (MWSP) has been implementing since December 2000, aiming to improve the overall of water supply and wastewater systems of the Kathmandu Valley. MWSP covers parts of the Indrawati and Bagmati watersheds and project areas include districts of Kathmandu, Lalitpur and Bhaktapur. The key water diversion facilities, headwork and diversion tunnel and access roads are located within Sindhupalchowk district, whereas, the water treatment plant at Sundarijal, water distribution network, balancing reservoirs and the other ancillary structures are located within Kathmandu Valley. The implementation of the project was affected during the conflict period

1 The project was prepared through PPTA 4893-NEP: Preparing the Kathmandu Valley Water Distribution,

Sewerage, and Urban Development Project, approved on 13 December 2006. Due to restructuring of ongoing loans, the work of PPTA started in 2009, and final report was submitted in May 2010.

2 Loan 1820-NEP (SF): Melamchi Water Supply Project was approved on 21 December 2000, and became effective on 28 November 2001. Loans 2058/2059-NEP (SF): Kathmandu Valley Water Services Sector Development Program were approved on 18 December 2003, and became effective on 7 December 2004.

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 2

due to various local and national issues. In the mean time some of the donors withdrew their support for the project in 2005 and 2006. 4. Later in 2008, MWSP was split into two distinct subprojects: (i) Subproject 1: Melamchi River Water Diversion Project covering all project activities in the Melamchi Valley, including the Water Diversion Tunnel (WDT) and Water Treatment Plant (WTP); and (ii) Subproject 2: Kathmandu Valley Water Supply and Sanitation Project to undertake distribution network improvement inside Kathmandu Valley. The implementation responsibilities were entrusted to Project Implementation Directorate (PID), which was formed under the Kathmandu Upatakaya Khanepani Limited (KUKL) Board of Directors, through a MOU signed on 19 April 2009 between Government of Nepal (GoN) [Ministry of Finance (MoF), Ministry of Physical Planning and Works (MPPW)], Kathmandu Valley Water Supply and Management Board (KVWSMB), KUKL and Asian Development Bank (ADB). Resettlement Plans have been prepared with the entitlements, assistance and benefits, provision of business, institutional arrangements, tasks and responsibilities of the each level of the agencies involved in resettlement planning for the project. Under the present loan from ADB (Loan No. 1820 SF). Scopes of the subproject-2 are as follows: - Immediate improvements of water supply services in Kathmandu valley through

augmentation of surface and groundwater sources; - Water quality improvement related works; - Rehabilitation and improvement of water supply and sewer networks at the primary,

secondary and tertiary levels as well as house connections in parts of KUKL service area;

- Design and construction of the Bulk Distribution System (BDS); - Wastewater Systems Improvements in a phased manner; and - Improvement of the Service Management system of KUKL.

5. The ADB Public Communication Policy (PPC 2011) refers the Safeguards Policy Statement (SPS 2009) with respect to information disclosure related to project safeguard documentation states that ADB shall post on its website the safeguard document submitted by the borrower and or/ client. These safeguard documents include Resettlement and Indigenous People Plan (RP & IPP), and the social and safeguard monitoring reports. To comply with the PCP of ADB, the KUKL, PID shall submit one semiannual monitoring reports periodically over the total implementation period of the project, covering Environment, Resettlement and safeguard issues. This also has been spelled out in the project document and loan covenant of KUKL that the borrower/client shall submit the aforesaid reports to ADB. Prior to civil works implementation, all the subprojects selected for construction development to be screened and classified using ADB's classification system. The Kathmandu Valley Water Supply and Sanitation Project is classified C for involuntary resettlement and category C for indigenous people. The project, in terms of its impact has been categorized as in category – C C. Scope of social safeguard impacts 6. The covenants to the loan agreement with ADB , requires that Resettlement Framework (RF) documents be complied during the implementation of project in accordance with ADB's SPS 2009 and RF prepared for the project and agreed between the Borrower and ADB. Any projects that involve land acquisition and resettlement impacts to be prepared RPs and other safeguard reports as required under the scope of approved RP. 7. The MWSDB conducted EIA before the implementation of Melamchi Water Supply Project. It is assumed that most of the environmental issues are have been addressed and mentioned in EIA report. As the MWSDB project separated Melamchi diversion and water distribution into two projects a supplementary IEE has been conducted and approved to address the environmental issues of Kathmandu Valley Water Supply Improvement Project.

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 3

No significance impact will be resulted by the construction activities under the project. Efforts have been continued to minimize environmental and social team in design the project activities. The environmental parameters mentioned in IEE reports have been monitored in project construction activities. 8. There will be no displacement of people, other than temporary relocation of hawkers and mobile vendors during construction. However, during the construction phase there will be temporary inconveniences such as increased vehicle movements that affect the pedestrians of the immediate vicinity of the work. The resettlement plan has been updated periodically and submitted to ADB. The project activities don't displace to any persons and no indigenous people will be affected by Most of the affected households have already received compensation. The compensation for the loss of trees has been paid NRS 930,354 has been paid. D. Compensation and Rehabilitation 9. Land acquisition is one of the major activities under the Load 1820 for Melamchi Project. Land acquisition for public purposes in Nepal is largely governed by the Land Acquisition Act (LAA) 2034 (1977A.D). The LAA sets out compensation standards and benefits such as compensation for lost assets at market value, provision for alternative land and compensation for standing crops and trees. To cover resettlement-related needs of the Project Affected Persons (PAP's), under Loan 1820, it has prepared a Resettlement Policy Framework (RPF), approved by the Cabinet in 2057 (2000 AD). The policy also ensures benefits to non-titled persons such as encroachers and squatters with appropriate displacement allowances for relocation and income restoration assistance. The Compensation Determination Committee (CDC) headed by Chief District Officer is responsible for evaluation of property and its compensation. The RP emphasizes that compensation should enable project-affected people to maintain the existing to better standard of living. RAP compensation and mitigation measures include the following: - Compensation upon acquisition by the project of land, crops and trees. And house or

commercial enterprises. - Displacement allowances - Rehabilitation measures - Loss of government property - Loss of community facilities and resources - Community losses - General counseling

During the RP implementation period ((July to December 2013), a total of 17 households receive NRs. 930,354 amount of compensation. Most of the compensation has been distributed for trees and one of them has been for the demolishment of house. The detail of compensation has been presented in below Table no. 1

Table no 1 Status of compensation payment (July to December 2013) S.N. Address Land

parcel no. Owners name Compensation

Amount ( NRs) Remarks

1 Sundarijal 8(Kha) 315 Jeshdev Tamang 17 Trees 2 Sundarijal 8(Kha) 221 Lalit Shrestha 2,942 Trees 3 Sundarijal 8(Kha) 227 Sita Ghimire 44,568 Trees 4 Nayapati 2(ka)2 724, 714 Gopal Pudasaini 14,387 Trees

5 Nayapati 2(ka)1 637, 641,645,647

Ram chandre Khadka 16,023 Trees

6 Nayapati 2(ka)1 735 Murali Baskota/Rita/Sagar Baskota

2,145 Trees

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 4

S.N. Address Land parcel no.

Owners name Compensation Amount ( NRs)

Remarks

7 Nayapati 2(Kha) 546,548,551

Kumar Bdr. /Ganesh Bdr. /Ramesh/ Kumale/ Mahesh Khadaka

1,554

Trees

8 Nayapati 2(Kha) 508,537 Sudarsan Pokherel 85 Trees

9 Nayapati 2(Kha) 425 Krishna Hari Pokherel 1,622 Trees

10 Nayapati 4(Kha) 888 Ga Parsad Dangal 31,810 Trees 11 Nayapati 4(Kha) 885 Mani Kantha Dangal 19,304 Trees 12 Nayapati 6(Ka) 467 Anjana Dangal 1,114 Trees

13 Gokarna 9(Ka) 388 Narayan/Aananda Raj shrestha 29,750 Trees

14 Gokarna 9(Kha) 187 Mana K.C. 25,418 Trees 15 Gokarna 9(Kha) 182 Laxmi Thapa 5,646 Trees 16 Nayapati 405,734 Sagar Banskota 733,964 House

Total Compensation amount 930,354

E. Public participation and consultation

10. While implementing the RP, an extensive consultation program with project affected people, vendors and land owner was carried out, in line with the requirements pertaining to receive compensation and compensation determination procedure . The public, business owners, affected people and shopkeepers were informed about the possibility of disruption to the business. The consultation also focused for on entitlement matrix of the project and compensation receiving procedure. The tools used for consultations were stakeholder workshops and meetings, interviews, structured questionnaires, and focus group discussions (FGD). These consultations provided inputs for identification of the felt needs of the communities, and the relevant stakeholders. The details of public consultation is shown in below Table no. 2

Table no.2 Public Consultation Matrix

Date No. of

Participants Location Types of

people attended

Topics/ issue discussed

Information disseminated

21 August 2013

Male:12 Female:2

Sundarijal-8 Land owner, PAF, and community leaders

Land acquisition issues, and entitlements

Discussed on the loss assessment and entitlements

22 September 2013

Male:7 Female:2

Sundarijal Local leaders, PAF, project staffs

Pipeline alignment Detail about pipe line alignment and working activities

1 December 2013

Male:8 Female:5

Arubari Local leaders, PAF, project staffs

Sewer line construction

Discussed about the project activities

12 December 2013

Male:23 Female:13

Mahankalchour Community people, PAF, project staffs

Project activities and entitlements

Detail project activities and entitlements

24 December

Male:7 Female:17

Arubari Tole members, project staffs

Traffic management, pipe

Mentioned route for traffic

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 5

2013 line alignment change

management and pipe line alignment

F. Grievance Redress Mechanism 11. A grievance redress mechanism (GRM) has been established (safeguard officer from PID, safeguard expert from DSC, CAPC, contractor and TLO member) in PID to receive, evaluate, and facilitate the resolution of affected people’s concerns, complaints, and grievances about the social and environmental performance at the level of the project. The Safeguard officer from PID has been assigned as coordinator for grievance handling. The GRM aims to provide a trusted way to voice and resolve concerns linked to the project, and to be an effective way to address affected people’s concerns. 12. Altogether7 grievances were filed during this reporting period and among those applications all are settled. Most of the grievances are related to compensation of losses of crops, trees and private properties losses occurred by project activities. Most of them were solved by based in entitlement of the project and understandings with community people. The details of grievances are in Table no. 3

Table no. 3 Detail of grievances during the reporting period

SN Name of person Address Grievance Status

1 Rojina Shrestha Nayapati VDC in BDS zone

Compensation of cop damage in

Settled

2 Sita Ghimire, Shyam Simkhada

Sundarijal, Nayapati and Gokarneshwor VDCs

Land verification Verified

3 Kalika’s Brothers Sundarijal near Bagmati Compensation of land Submitted CDC for decision

4 Sagar Baskota Nayapati VDC Compensation of house

Compensation distributed

5 Shree Krishna Shrestha Gokarneshwor VDC Compensation of Crops

Compensation distributed

6 Ram Krishna Shrestha Gokarneshwor VDC Verification of structure Verified 7 Community of Arubari

(Community grievance) Jorpati VDC Dust pollution due to

construction Contractor is instructed to sprinkle water

G. Institutional Arrangement 13. PID KUKL entrusted with the responsibilities for planning, design, and implementation of the project. The PID KUKL is also responsible to ensure compliance with safeguard requirements of the Government and ADB and for day-to-day monitoring of project progress, including the implementation of resettlement provisions in the project and produce progress report on all aspects concerning to planning, implementation and monitoring of the land acquisition and resettlement issues. Design, Supervision and management Consultant (DSC) have been engaged to carry out the detail design, supervision and management of the projects. The DSC Social Safeguard Specialist is responsible to carry out the social impact assessment issues and to closely work with PID for safeguard implementation. The PID has also engaged Community Awareness and Participation Consultation (CAPC) to carry out the community mobilization activities. The

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 6

CAPC is also responsible for the implementation and monitoring safeguard related activities and RP implementation in field level. H. Monitoring Results/Finding 14. Up to the reporting period, the implementation of RP is continuing. The safeguard team has been working closely with technical design team so to avoid the adverse impact. The grievances related to social safeguard is treated immediately within the project entitlement framework and the numbers of grievances related to social safeguard are minimal. The affected households have received compensation in timely manner and the Ap's are satisfied with the compensation rate. 15. The assessment, monitoring, evaluation and reporting of the resettlement activities will be undertaken by the project. The monitoring and assessment / evaluation of the contractors’ resettlement activities has been carried out by using formats specific to each project and visiting the sites during working hours. The format presents the status of work, problems, mitigation measures adopted by the contractors etc. Such information have been presented in Consultant’s monthly report Environmental and Social Safeguards. Resettlement Plans have been prepared with the entitlements, assistance and benefits, provision of business, institutional arrangements, tasks and responsibilities of the each level of the agencies involved in resettlement planning for the project. I. Compliance Status 16. One full time Senior Social and Environmental Officer in PID KUKL has been recruited since the project beginning. DSC-3 has also mobilized Social Safeguard Expert from October 2013. The experts for the implementation of RP and monitoring of safeguard activates have been recruited. Covenants written into loan agreement that is related to resettlement safeguard are listed in Table no. 4, with the status of compliances up to the reporting period.

Table no.4 Status of Resettlement & Social Safeguard Issued of the Project Covenant Safeguard Applicability Status of

Compliance Resettlement: The Borrower, PID,KUKL shall ensure that:

The project involves involuntary resettlement so RP will be prepared based in Resettlement Framework (RF) agreed upon the Borrower and ADB, the borrowers land acquisition act 2034 and ADB's Safeguard Policy Statement ( 2009)

Directly applicable; compliance with both ADB and GoN requirements

Compiled with

The RP that has been prepared and agreed by the Borrower ADB shall be updated and provide to ADB for review and clearance following detailed design and prior to civil works contract awarded

The RP has been prepared based on RF and being updated periodically and forwarded to ADB for review

Compiled with;

All affected persons are given adequate opportunity to participate in the resettlement planning and implementation

Public participation basis for resettlement planning

Complied with

The RP will be disclosed to the affected persons, who are compensated and assisted prior to displacement from their house, land and assets, before commencement of any works

Required by RF Complied with

Additional assistance is provided for vulnerable groups Required by RF Compiled with Works contracts under the project include requirements to comply with RPs;

Required by RF Complied with

Implementation of the RP is monitored internally by the PID and reported to ADB semiannually

Include as fundamental aspect of safeguard reporting

Complied with

Affected persons have an opportunity to express Purpose of grievance redress Complied with

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 7

grievances at appropriate levels, and each levels are instructed to reslove disputed and implement measures promptly in accordance with the grievance redress process outlined in the RP

mechanism

J. Follow up Actions, Recommendations 17. The monitoring of social safeguard activities and implementation of will be continued during the project implementation. The project will involve in following action for the implementation of RP. - Facilitate for Compensation distribution: The regular distribution of compensation

payment will be facilitated from PID KUKL office. - Facilitate Grievance Handling: It will be facilitated to mobilize CIRT to address the

claims, obstruction and grievances. The CIRT will verify the case related to compensation claims and resettlement close collaboration with project affected families.

- Organize CDC Meetings: The meeting related to compensation distribution will be organized as and when required. Meetings to settle on the issue of resettlement conflict between projects affected families and the project will be organized as and when required.

- Facilitate for Title Transfer: It will be facilitated to follow up activities to be carried out to collect Land Ownership Certificate form Kathmandu Land Revenue Office that have been transferred to KUKL.

- Monitoring of Safeguard Compliance: The regular follow up and monitoring of safeguard compliance will be continued. The project team will be involved in monitoring and provide instruction, if, falls to compile the safeguard compliance to contractor and

- Consultation and dissemination: It will be conducted regular consultative meeting with project affected people and other stakeholder to overcome the possible social problems and right information dissemination. The consultative meeting will be conducted in each project constructed are and inclusive.

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 8

ENVIRONMENTAL SAFEGUARD MONITORING

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 9

K. Compliance of Loan Covenants Related to Environmental Safeguards

Table no. 5 Checklist of Loan Covenants Related to Environmental Safeguards [Amended and Restated Loan Agreement, Loan No. 1820-NEP (SF)]

Project Specific Covenants (Environmental) Status/Issues Schedule 5, Para 20 (b) MWSDB and WUO shall prepare and submit to ADB, within one month of the end of the reporting period: The six-monthly monitoring reports on environmental and social issues affecting the project, within one month of the end of each relevant period; and Annual reports on the monitoring of surface and groundwater in Kathmandu Valley within one month of the end of each fiscal year.

Partially Complied A package for monitoring of various environmental parameters of water, wastewater, air, and noise quality is being formulated. KVWSMB has initiated issuing licenses for using groundwater in the valley.

Schedule 5, Para 24 The borrower shall ensure that by 31 March 2008, the existing environmental management plan (EMP) and resettlement action plan (RAP) shall, in each case, be updated and be divided into two separate plans, one dealing with Subproject 1 activities and the other dealing with Subproject 2 activities, and that such division will be made on a consistent basis and be retained for the duration of the project.

Complied The environmental management plan (EMP) and resettlement action plan (RAP) have already been updated and divided into two separate plans. There is no major resettlement issue including displacement of households and families in Subproject 2

Schedule 5, Para 26 The borrower shall ensure that the Project is implemented and all project facilities are constructed, maintained and operated in strict conformity to (a) all applicable national environmental laws, regulations and procedures, (b) ADB’s Environmental Policy (2002), and (c) the environmental mitigation and monitoring measures detailed in the approved environmental impact assessment (EIA), the SEIA, the relevant SIEEs and the relevant EMP for each of the Subprojects.

Complied The EMP of Subproject 2 has included provisions to mitigate against construction phase impacts confirming to the (a) all applicable national environmental laws, regulations and procedures, (b) ADB’s Environmental Policy (2002), and (c) the environmental mitigation and monitoring measures detailed in the approved environmental impact assessment (EIA).

Project Specific Covenants (Environmental) Status/Issues Schedule 5, Para 27(a) The borrower undertakes to implement the following: Simplification of the environmental and social safeguards management system, including transferring to (i) MWSDB and WUO (as the case may be) overall responsibility for safeguards design, implementation and reporting, and strengthening and increase capacity of MWSDMB’s and WUO’s safeguards division(ii) EMP monitoring consultant responsibility for environmental effects monitoring, and EMP monitoring.

Being Complied Simplification of the environmental and social safeguards management system is currently undergoing. PID of KUKL is responsible for design, implementation and reporting the safeguards system/activities. Monitoring of EMP is expected through the newly mobilized Design and Supervision Consultancy (DSC) and Safeguards unit of PID. Capacity of safeguards division/PID to design and monitor the safeguard plans/programs needs to be improved.

L. Compliance of Environmental in Major Construction Activities Monitoring checklist has been developed as per approved EMP, and IEE submitted by PPTA-4893 and field monitoring for Environmental and Social Safeguards has been started. The issues mentioned below were given priority during monitoring.

• Arrangement of lights, guards, fencing, warning signs, caution board, safety caution ribbon/tape. • Safety of all persons entitled to be upon the site by use of PPE like safety belt, gumboot, respiratory

mask, hand gloves, helmet, jackets with reflectors etc. • Sprinkling of water for checking of road dust. • Proper traffic diversion and implementation of traffic management plan. • Proper storage of construction materials. • Labor camp management. • Proper restoration of road / working sites after completion of specific work. • Disposal of excess excavated materials. • Safety and protection of adjacent properties

KUKL: KVWSIP Loan 1820 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 11

Table no.6 Detailed Environmental and Social Safeguards Monitoring Checklist

S.N.

Environmental Components

related to Project Activities

Status ( Complied/ Partially Complied/ / Not Complied/ Not Applicable)

Packages

Demo Area at Kusunti

(KUKL/ DNI/01/02)

Pilot Project at Kalopool (KUKL/

DNI/01/03)

NakkhuKhola Improvement

s Works Package (KUKL/

DNI/02/05)

Construction of 150 m3

Reservoir & related works at Sundarijal

(KUKL/ DNI/02/07A)

Construction of Water Treatment

Facility, RCC Reservoir & Related Civil

Works at Koteshwor

(KUKL/ DNI/02/15B)

Cluster Removal at

Gokarna (KUKL/

DNI/02/08)

Rehabilitation &

Development of Tube

wells (KUKL/

DNI/02/06B)

Transmission Main From

Sundarijal to Mahankalchour

(KUKL/ BDS/01/01)

Sewerage Network

Improvement Works

Buddhanagar KUKL/WSI/01/

03

Construction of Treatment Facility and Related Civil

Works at TIA, Tubewell Site/ Contract No.-

KUKL/DNI/02/15C

A. Preparation for Construction

1.

Pegging of the land area (permanent and temporary) required by the project

Complied Complied Complied

Completed

Complied Complied

Completed

Complied

2. Prepare RP N/A N/A N/A Complied Complied Complied

3.

Identify the temporary areas required by the project and locate them with proper marking

Complied Complied Complied

Complied

Complied Complied

4.

Consult relevant persons and submit applications to get approvals

Complied Complied Complied

Complied

Complied Complied

5.

Submit such agreement and permits to SC for official information

Complied Complied Complied

Complied

Complied Complied

6. Construct Workforce Camp Complied N/A N/A

Complied Complied Complied

* 7.

Employ local and affected people as per EMP

Partially Complied

Partially Complied

Partially Complied

Completed

Partially

Complied

Completed

Partially Complied

Partially Complied

8.

Baseline photographs of project area (including buildings and temporary sites) and river water quality

Complied Complied Complied

Complied Complied

Complied

9. Prepare traffic Complied Complied Complied N/A Complied

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 12

S.N.

Environmental Components

related to Project Activities

Status ( Complied/ Partially Complied/ / Not Complied/ Not Applicable)

Packages

Demo Area at Kusunti

(KUKL/ DNI/01/02)

Pilot Project at Kalopool (KUKL/

DNI/01/03)

NakkhuKhola Improvement

s Works Package (KUKL/

DNI/02/05)

Construction of 150 m3

Reservoir & related works at Sundarijal

(KUKL/ DNI/02/07A)

Construction of Water Treatment

Facility, RCC Reservoir & Related Civil

Works at Koteshwor

(KUKL/ DNI/02/15B)

Cluster Removal at

Gokarna (KUKL/

DNI/02/08)

Rehabilitation &

Development of Tube

wells (KUKL/

DNI/02/06B)

Transmission Main From

Sundarijal to Mahankalchour

(KUKL/ BDS/01/01)

Sewerage Network

Improvement Works

Buddhanagar KUKL/WSI/01/

03

Construction of Treatment Facility and Related Civil

Works at TIA, Tubewell Site/ Contract No.-

KUKL/DNI/02/15C

plans N/A

B 1. Construction Phase: Physical Environment

1. Adopt cut and fill principle during earthworks

N/A N/A

N/A

Completed

N/A

Completed

N/A N/A

2. Disposal of excess materials in designated area

Complied Complied Complied Complied

Complied

Complied

3.

Apply Bio-engineering for controlling of erosion

N/A N/A N/A

N/A

N/A

N/A

4. Avoid bed Quarrying

N/A

N/A

N/A N/A N/A

N/A

5. Avoid Dumping of waste in the river

Complied

Complied

Complied N/A Complied

N/A

6.****

Construction of toilets in the camps project site

Complied

N/A

N/A Complied N/A

N/A

7. Proper storing of materials in the project area

Complied Complied Complied Complied

Complied Complied

• *TIA work is being implanted in the area controlled by KUKL • *** In the case of Kotehwor, it is only applicable for the construction of reservoir. • **** Kusunti has constructed toilets for the workers, however in the case of Sundarijal and Koteshwor and TIA there are already existing toilets that the

workers are utilizing.

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 13

S.N.

Environmental Components

related to Project Activities

Status ( Complied/ Partially Complied/ / Not Complied/ Not Applicable)

Packages

Demonstration Area

at Kusunti (KUKL/

DNI/01/02)

Pilot Project at Kalopool (KUKL/

DNI/01/03)

NakkhuKhola Improvement

s Works Package (KUKL/

DNI/02/05)

Construction of 150 m3

Reservoir & related works at Sundarijal

(KUKL/ DNI/02/07A)

Construction of Water Treatment

Facility, RCC Reservoir & Related Civil

Works at Koteshwor

(KUKL/ DNI/02/15-B)

Cluster Removal at

Gokarna (KUKL/

DNI/02/08)

Rehabilitation & Development of

Tube wells (KUKL/

DNI/02/06-B)

Transmission Main From Sundarijal to Mahankalchour

(KUKL/ BDS/01/01)

Sewerage Network

Improvement Works

Buddhanagar

KUKL/WSI/01/03

Construction of Treatment Facility and Related Civil Works at TIA, Tube Well

Site/ Contract No.-KUKL/DNI/02/15C

8. Safe handling of toxic wastes N/A N/A N/A

Completed

N/A

Completed

N/A N/A

9. Proper dumping of excess materials

Complied Complied Complied Complied Complied

Complied

10. Proper Quarrying operations N/A N/A N/A N/A N/A

N/A

11. Precautions for Air, Noise and Vibration control

a. Movement of Vehicles Complied

Complied

Complied

Completed

Complied

Completed

Complied

Complied

b. Earthworks Complied Complied Complied Complied

Complied Complied

c.

Stockpiling of construction waste and construction materials

Complied

Complied

Complied

Complied

Complied

Complied

d.

Operation of construction machineries and equipment including crusher

Complied

Complied

Complied

Complied

N/A

Complied

e. Horn honking Complied Complied Complied Completed Complied Completed Complied Complied

B2. Construction Phase: Biological Environment

1.

Vegetation clearance for construction of project structures

N/A N/A N/A

Completed

N/A

Completed

N/A

N/A

2. Fuel wood and NTFPs collection by workforce and

Complied Complied Complied Complied Complied

Complied

KUKL: KVWSIP Loan 182 Biannual Social and Environmental Safeguard Monitoring Report

CDM Smith – TAEC- ICON 14

S.N.

Environmental Components

related to Project Activities

Status ( Complied/ Partially Complied/ / Not Complied/ Not Applicable)

Packages

Demonstration Area

at Kusunti (KUKL/

DNI/01/02)

Pilot Project at Kalopool (KUKL/

DNI/01/03)

NakkhuKhola Improvement

s Works Package (KUKL/

DNI/02/05)

Construction of 150 m3

Reservoir & related works at Sundarijal

(KUKL/ DNI/02/07A)

Construction of Water Treatment

Facility, RCC Reservoir & Related Civil

Works at Koteshwor

(KUKL/ DNI/02/15-B)

Cluster Removal at

Gokarna (KUKL/

DNI/02/08)

Rehabilitation & Development of

Tube wells (KUKL/

DNI/02/06-B)

Transmission Main From Sundarijal to Mahankalchour

(KUKL/ BDS/01/01)

Sewerage Network

Improvement Works

Buddhanagar

KUKL/WSI/01/03

Construction of Treatment Facility and Related Civil Works at TIA, Tube Well

Site/ Contract No.-KUKL/DNI/02/15C

vegetation clearance construction activities

B3. Construction Phase: Socio-Economic Environment

1. Compensation and rehabilitation as per RP

N/A N/A N/A Completed N/A Completed N/A N/A

2.

Reinstatement of damaged community services and infrastructures

Complied Complied Complied

Completed

N/A

Completed

N/A N/A

3.

Avoid influx of outside workforce, money and unwanted activities

N/A

N/A

N/A

N/A

N/A N/A

4.

Project activities relating to health and safety issues at work areas

Complied

Complied

Complied

Complied Complied Complied

5. Avoid dislocation of archeological artifacts, if any

N/A

NA

N/A N/A N/A N/A

6. Proper traffic management at construction sites

Complied Complied Complied Complied Complied N/A

Annex I

Photographs

MWSDB, Official staff and land owner TLO formation in DNI 6

Project construction activities Project team inspection trees to be dislocated

Annex II

Attendance in Consultative Meetings