Upload
others
View
3
Download
0
Embed Size (px)
Citation preview
ENVIRONMENT IMPACT ASSESSMENT REPORT
AND
ENVIRONMENT MANAGEMENT PLAN
For
M/S PUNJAB ACIDS-CHEM PVT. LTD. Village Behra, Behra-Gulabgarh Road, Distt- Mohali
Punjab.
By
Vardan Environet D--142, Sushant Lok-III,
Golf Course Extension Road, Sector-57, Gurgaon
July, 2014
2
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
INDEX
Chapters Page No.
PROJECT AT A GLANCE 07
TORs ISSUED BY EAC 09-13
COMPLIANCE OF TORs 15-20
EXECUTIVE SUMMARY 22-38
FINAL EIA 40
INTRODUCTION 40
SCOPE & METHODOLOGY 43
PROFILE OF THE COMPANY’ & PROMOTERS 45
BASELINE ENVIRONMENTAL SETTING 47
4.1 State 47
4.2 District SAS Nagar 48
4.3 Project Site 48
4.4 Study Area 53
4.5 Climate 55
4.6 Temperature 56
4.7 Rainfall 57
4.8 Humidity 58
4.9 Cloudiness 59
4.10 Winds 59
4.11 Drainage 61
4.12 Land Use 61
4.13 Forest 61
4.14 Flora & Fauna 61
4.15 Demographic & Socio Economic Scenario 62
5. ENVIRONMENTAL BENCH MARK
CONDITIONS IN THE STUDY AREA 64
5.1 Ambient Air Quality 64
3
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
5.2 Water Quality 74
5.3 Ambient Noise Quality 79
5.4 Soil 81
6. PROJECT DESCRIPTION 84
6.1 General 84
6.2 Raw Materials 84
6.3 Finished products & Installed Capacity 84
6.4 Installed Capacity 85
6.5 Facilities at the Plant 85
6.6 Machinery 86
6.7 Power 86
6.8 Water Supply 86
6.9 Manpower 87
6.10 Manufacturing Process 89
6.11 Waste Handling 101
6.11.1 Liquid waste 101
6.11.2 Solid waste 101
6.11.3 Hazardous waste 102
6.12 Pollution Control Measures 102
6.12.1 Air Pollution 102
6.12.2 Water Pollution 102
6.12.3 Noise Pollution 104
7. ENVIRONMENTAL IMPACT ASSESSMENT 105
7.1 Present Environment 105
7.2 Probable Impact on Environment 105
7.3 Development Stage: - (Short Term) 106
7.4 Operational Stage: - (Long Term) 107
8. ENVIRONMENT MANAGEMENT PLAN 110
8.1 General 110
8.2 Air Environment 110
4
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
8.2.1 Flue Gas Emission/Fugitive Emission Control 111
8.3 Water Environment 111
8.4 Land Environment 112
8.5 Solid Waste 112
8.6 Noise Environment 112
8.7 Green Belt 113
9. ENVIRONMENT MONITORING PROGRAMME 114
10. OCCUPATIONAL HEALTH 117
10.1 General 117
10.2 Occupational Environment 117
10.2.1 Man & Physical, Chemical & Biological Agents 117
10.2.2 Man and Machine 118
10.2.3 Man and Man 118
10.3 Occupational Hazards 118
10.4 Mitigation Measures 120
10.5 Safety Precautions & Suggestions 124
11. CORPORATE SOCIAL RESPONSIBILITY
AND ENVIRONEMNT POLICY 126
12. FIRE FIGHTING 130
13. RAIN WATER HARVESTING 139
14. EXPENDITURE ON ENVIRONMENTAL MEASURES 145
List of Figures:
1.1 Key Plan of the Area 41
4.1 Location Plan 49
4.2 Location on Satellite Imagery 50
5
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.3 Layout Plan 51
4.4 LULC Map 52
4.5 Details of the Study Area 53
4.6 Wind-rose Diagram 60
5.1 Location of Monitoring Stations (Air) 65
5.2 Surface water /Ground water Monitoring Stations 75
5.3 Location of Monitoring Stations (Noise) 80
5.4 Soil Monitoring Station 82
6.1 Water Balance Flow Diagram 88
6.2 Manufacturing Process 93, 95, 97, 99,100
6.3 Flow Chart of APCS 103
List of Tables:
1.1 Location Details 42
4.1 Villages of the Study Area 54
4.2 Monthly Average Temperature 56
4.3 Monthly Average Rainfall 57
4.4 Monthly Humidity 58
4.5 Summary of Key Demography Statistics 62
4.6 Occupational Structure 63
5.1 Ambient Air Monitoring Stations 66
5.2 Ambient Air Quality 67
5.3 AAQ Results 69-71
5.4 Frequency Distribution 72
5.5 Water Monitoring Stations 74
5.6 Result of Surface Water 76
5.7 Result of Ground Water 77-78
5.8 Noise Levels 81
5.9 Result of Soil Samples test 83
11.1 Details of CSR 127
6
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
12.1 Fires Classification & Extinguishing Media 133
14.1 Cost of EPM 145
List of Annexure:
I Proceeding of Public Hearing
II Safety data Sheet
III Air Modeling output data
IV TSDF site Membership
V Consent Validity
VI Compliance of NOC
VII Stack Analysis report by PPCB
VIII Plant Photographs
Uploaded as
separate
document
7
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
PROJECT AT A GLANCE
1. Name of Project Punjab Acids-Chem. Pvt. Ltd.
2. Location Village Behra, Tehsil- Derabassi, Distt- Mohali, Punjab
3. Product Sulphuric Acid, Alum, Olem, Di-Methyl Sulphate, Sodium, Bi-
Sulphite, Sulphamic Acid & Liquid SO3
4. Capacity (TPD) Existing Proposed Total
Sulphuric Acid 75 125 200
Alum 200 Nil 200
Oleum Nil 70 70
Di-Methyl
Sulphate
Nil 30 30
Sodium Bi-
Sulphite
Nil 30 30
Sulphamic Acid Nil 30 30
Liquid SO3 Nil 30 30
5. Type of Project Industrial Chemicals
6. Cost of the Project 4426 lakhs
7. Total Land 10 Acres
8. Power
Requirement
699 KW
9. Source of power From Punjab State Power Corporation Ltd
10. Source of Water
Supply
Own Tube well
11. Quantity of Water
(KLD)
Existing Additional Total
60 185 245
12. Effluent Quantity Nil
13. Effluent treatment
Domestic = STP
Process = Nil
14. Alternate source
of power
1 No. DG Set (700KVA), 1 No. DG Set (325KVA), 1 turbine
350KVA
15. Air Pollution
Control
Multi-cyclones, Alkali Scrubber & Stack
16. Solid Waste Solids from APCD, Ash from Boiler Furnace
17. Hazardous waste Used oil from DG Set, Sulphur Sludge, Spent catalyst
18. Rain Water
Harvesting
12960m3/annum
8
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TERMS OF REFERENCES ISSUED BY
EAC
9
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
10
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
11
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
12
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
13
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
14
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
COMPLIANCE OF TERMS OF
REFERENCES
15
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Sr.
No.
Observations Compliance
1. Executive summary of the project. Given in EIA report
from Page no 22 to 38
2. Justification of the project. Due to increased
demand of the existing
product. The unit is
intent to expand their
existing Manufacturing
capacity.
3. Photographs of the existing and proposed plant area. Refer Annexure-VIII
4. Compliance to the conditions stipulated in the Environmental
Clearance/ NOC granted by the SPCB.
Refer Annexure- VI
5. A certified copy of the report of the status of compliance of the
conditions stipulated in the environmental clearance and Consent
to Operate for the ongoing/ existing operation of the project by
the Regional Office of the Ministry of Environment and Forests
and SPCB.
Refer Annexure- VI
6. Recent monitoring report from SPCB, which shall include data
on AAQ, water quality, solid waste etc. shall be submitted.
Refer Annexure- VII
7. Has the unit received any notice under the Section 5 of
Environment (Protection) Act, 1986 or relevant Sections of Air
and Water Acts? If so, compliance to the notice (s).
No
8. The earlier questionnaire for industry sector should be submitted
while submitting EIA/ EMP.
Submitted
9. Promoters and their back ground. Given in EIA report at
Page no 45
10. Regulatory framework. Given in EIA report at
Page no 45.
11. A map indicating location of the project and distance from
severely polluted area.
5 km from severely
polluted area. Given in
EIA report at Page no 50
& 52
12. Project location and plant layout. Given in EIA report at
Page no 49, 51
13. Infrastructure facilities including power sources. Refer Page 85, 86
14. Total cost of the project along with total capital cost and
recurring cost/ annum for environmental pollution control
measures.
Total project cost: 4426
lacs, capital cost for
environment protection
measures- 29 lacs, &
recurring cost- 3 lacs
15. Project site location along with site map of 10 km. area and site
details providing various industries, surface water bodies, forests
Refer page no.50, 52
16
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
etc.
16. Present land use based on satellite imagery for the study area of
10 km. radius. Details of land availability for the project along
with supporting document.
Refer page no. 52,50
17. Location of National Park/ Wild Life Sanctuary/ Reserve Forest
within 10 km. radius of the project.
There are no National
Park/ Wild Life
Sanctuary/ Reserve
Forest within 10 km.
radius of the project.
18. Permission, if any from the State Forest Department. Not required
19. Details of the total land and break-up of the land use for green
belt and other uses.
Refer Page no. 52
Figure-4.4
20. List of products along with the production capacities. Sulphuric Acid -200 TPD
Alum - 200 TPD
Oleum - 70 TPD
Di-methyl Sulphate-30 TPD
Sodium Bi-Sulphite- 30 TPD
Sulphamic Acid -30 TPD
Liquid SO3 - 30 TPD
21. Detailed list of raw materials required and source, mode of
storage and transportation.
Page no. 84
Para no – 6.2
22. Manufacturing process details along with the chemical reactions
and process flow chart.
Refer page no 89-100
Para no 6.10
23. Site-specific micro-meteorological data using temperature,
relative humidity, hourly wind speed and direction and rainfall is
necessary.
Referred in page no.56 –
59
Para no – 4.5 , 4.6 , 4.7 ,
4.8 , 4.9 ,4.10
24. Ambient air quality monitoring at 6 locations within the study
area of 5 km. aerial coverage from project site as per NAAQS
notified on 16th September, 2009. Location of one AAQMS in
downwind direction.
Done, Refer page no.
64- 73
25. One season site-specific micro-meteorological data using
temperature, relative humidity, hourly wind speed and direction
and rainfall and AAQ data (except monsoon) for PM10, PM 2.5,
SO2, NO x including VOCs shall be collected. The monitoring
stations shall take into account the pre-dominant wind direction,
population zone and sensitive receptors including reserved
forests. Data for water and noise monitoring shall also be
included.
Included in EIA report,
Refer page no. 64- 73
26. Air pollution control measures viz. Multi-cyclone and bag filter
etc. shall be proposed for the effective control of gaseous
emissions within permissible limits.
APCDs are proposed
like Multi-Cyclone in
Boiler, Alkali Scrubber
in Sulphuric Acid/ Alum
plant
27. Details of VOC monitoring system in the working zone Refer Page no.111, Para-
17
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
environment, if any. 8.2.1
28. Name of all the solvents to be used in the process and details of
solvent recovery system.
Refer Page – 95,100
29. Design details of ETP, incinerator, boiler, scrubbers/ bag filters
etc.
Refer Page- 103
30. Details of water and air pollution and its mitigation plan. Given in EIA report at
Page no- 106, 108, 110,
111.
31. Action plan to control ambient air quality as per NAAQS
Standards notified by the Ministry on 16th September, 2009.
Parameters are within
the prescribed limit
according to NAAQS
Standards notified by the
Ministry on 16th
September, 2009. , but
APCDs are proposed
like Multi-Cyclone in
Boiler, Alkali Scrubber
in Sulphuric Acid/ Alum
plant
32. An action plan to control and monitor secondary fugitive
emissions from all the sources.
Given in EIA report at
Page no 111
33. Determination of atmospheric inversion level at the project site
and assessment of ground level concentration of pollutants from
the stack emission based on site-specific meteorological
features. Air quality modeling for proposed plant.
Refer Annexure no III
34. Permission for the drawl of ground water from CGWA. Water
balance chart including quantity of effluent generated recycled
and reused and discharged.
CGWA permission is
applied for. Water
balance chart is given on
Page no. 86 Fig no – 6.1
35. Action plan for `Zero’ discharge of effluent shall be included. Complied, it’s a zero
discharge unit.
36. Treatment of phenol in the effluent, if any. No phenol is present in
the effluent
37. Ground water quality monitoring minimum at 6 locations shall
be carried out. Geological features and Geo-hydrological status
of the study area and ecological status (Terrestrial and Aquatic).
Refer page no 74 & 78
Table – 5.7, Geological
features: Alluvium, Geo-
hydrological status:
Major Water bearing
formation - Sand , Pre-
monsoon depth to water
level - 4.1-13.02 , Post-
monsoon depth to water
level - 4.1-12.89 , Long
term water level trend in
18
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
10 yrs- Fall -0.11 to 0.80
m/yr
38. The details of solid and hazardous wastes generation, storage,
utilization and disposal particularly related to the hazardous
waste calorific value of hazardous waste and detailed
characteristic of the hazardous waste. Action plan for the
disposal of fly ash generated from boiler shall be included.
Given in EIA report at
Page- 102, Refer Para -
6.11.3
39. Explore the possibility to use fuel other than wood. Other than wood, there
can be Oil, electric or
LPG boilers.
40. Precautions to be taken during storage and transportation of
hazardous chemicals shall be clearly mentioned and
incorporated.
Given in EIA report,
Refer chapter 10 ,
Para no. – 10.5 at Page
no- 124
41. Authorization/ Membership for the disposal of solid/ hazardous
waste in TSDF.
Refer Annexure- IV
42. List of hazardous chemicals (as per MSIHC rule) with toxicity
levels.
Details given in the
safety data sheet on
Annexure-II
43. A write up on “Safe Practice” followed for hazardous chemicals
including methanol handling, storage, transportation and
unloading to be submitted.
Details given in the
safety data sheet on
Annexure-II
44. A write up on “Treatment of Workers” affected by accidental
spillage of hazardous chemicals including methanol.
Details given in the
safety data sheet on
Annexure-II
45. Locating the plant in open area instead of covered to be
reviewed in view of safety consideration.
Reviewed
46. An action plan to develop green belt in 33% area. Refer Chapter – 8
Para – 8.7 at Page-113
47. Action plan for rainwater harvesting measures at plant site shall
be included to harvest rainwater from the roof tops and storm
water drains to recharge the ground water.
Refer Chapter -14, from
Page-153
48. Details of occupational health programme :-
i. To which chemicals, workers are exposed directly or
indirectly.
ii. Whether these chemicals are within Threshold Limit Values
(TLV) / Permissible Exposure Levels as per ACGIH
recommendation.
iii. What measures company has taken to keep these chemicals
within PEL /TLV.
Refer Chapter – 10 at
Page-117 and safety data
sheet on Annexure-II
19
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
iv. How the workers are evaluated concerning their exposure to
chemicals during pre-placement and periodical medical
monitoring.
v. What are onsite and offsite emergency plan during chemical
disaster.
vi. Liver function tests (LFT) during pre-placement and
periodical examination.
49. Details of occupational health surveillance programme. Details given in Chapter
– 10 at Page no- 117
50. Socio- economic development activities shall be in place. Given in EIA report,
Refer chapter 11 at
Page-126
51. Detailed Environment Management Plan (EMP) with specific
reference to details of air pollution control system, water &
wastewater management, monitoring frequency, responsibility
and time bound implementation plan for mitigation measure
shall be provided.
Given in EIA report,
Refer Chapter- 8, Page
no- 110
52. EMP shall include the concept of waste-minimization, recycle /
reuse / recover techniques, energy conservation and natural
resource conservation.
Included, Refer Chapter-
8, Page no-110
53. Corporate Environmental Responsibility
(a) Does the company have a well laid down Environment
Policy approved by its Board of Directors? If so, it may
be detailed in the EIA report.
(b) Does the Environmental Policy prescribe for standard
operating process/ procedures to bring into focus any
infringement/ deviation/ violation of the environmental or
forest norms/ conditions? If so, it may be detailed in the
EIA report.
Refer chapter – 11 at
Page-126
54. What is the hierarchical system or Administrative Order of the
Company to deal with the environmental issues and for ensuring
compliance with the EC conditions? Details of this system may
be given.
Refer chapter – 11 at
Page-126
55. Does the company has a system of reporting of non- compliance
/ violations of environmental norms to the Board of Directors of
the Company and / or shareholders or stakeholders at large? This
reporting mechanism should be detailed in the EIA report.
Refer Page no- 128
56. At least 5% of the total cost of the project should be earmarked
towards the Enterprise Social Commitment based on Public
Refer Page no- 127
20
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Hearing issues and item-wise details along with time bound
action plan should be prepared and incorporated.
57. Total capital cost and recurring cost/ annum for environmental
pollution control measures.
Total project cost: 4426
lakhs, capital cost for
environment protection
measures- 29 lakhs, &
recurring cost- 3 lakhs
58. Public hearing issues raised and commitments made by the
project proponent on the same should be included separately in
EIA/ EMP Report in the form of tabular chart with financial
budget for complying with the commitments made.
Refer Public hearing
Document
59. Any litigation pending against the project and / or any direction /
order passed by any Court of Law against the project, if so,
details thereof.
No litigation is pending.
21
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
EXECUTIVE SUMMARY
22
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
1.0 INTRODUCTION:
M/s Punjab Acids-Chem. Pvt. Ltd. is proposing to enhance capacity of the unit &
addition of chemical products like Oleum, Di-Methyl Sulphate, Sodium Bi-
sulphite, Sulphamic Acid & Liquid SO3 at Village Behra, Tehsil Derabassi, Distt.
Mohali, Punjab. As per MoEF, GOI Notification dated 14-09-2006 they are
required to have Environmental Clearance for their project before establishing the
same. As per schedule of the Notification the Organic Chemical Industries are
listed at S. No. 5(f) and General Conditions given in the Notification are
applicable to the unit. Further, the project is to be treated as Category ‘A’ and thus
the Environmental clearance is to be given by the Central Govt. (MoEF). One of
the conditions of the TOR is to have Public Hearing, which has been organized by
PPCB on dated 15th January, 2014. Result of the same has been included in EIA
report as Annexure-I. This document is the summary of the Final EIA Report.
2.0 ENVIRONMENTAL BENCH MARK CONDITIONS:
In order to know the impact of the project on various parameters, it is necessary to
know their existing levels. The anticipated effect of the pollutants from the project,
if any, shall be superimposed on this to assess the final levels as compared to the
permissible limits.
Monitoring stations were established at eight different places within the study area
and the existing levels of various parameters in respect of the following were
observed to see their quality.
I) Ambient Air
II) Ground & Surface water
III) Noise
23
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
IV) Soil
It has been seen that all parameters are well within the permissible limits.
Demographic, Socio Economic aspects & Eco Biodiversity angles were also
studied & results documented.
3.0 PROJECT DESCRIPTION:
3.1 General
The Punjab Acids-Chem. (P) Limited located at Village Behra, Tehsil Dera Bassi,
and Distt. S.A.S. Nagar Mohali, Punjab is about 6 Kms from Dera Bassi Bus
Stand and about 26 Kms from Chandigarh (U.T) Bus Stand. It is about 6 km from
Chandigarh – Ambala Highway. The unit has 10 acres existing land. No additional
land is required for expansion. The total cost of the project is 4426 lacs.
3.2 Machinery
Following machinery will be finally in position within the unit:
3.3 Manufacturing Process:
1) Sulphuric Acid Manufacturing Process:
The manufacturing process for Sulphuric Acid as practiced in the plant at
the present time is described as under:
S.NO. EQUIPMENT NAME
1 Reaction Vessels
2 Condensers, Heat Exchanger
3 Decanters/Centrifuge
4 Cooling Tower
5 Storage Tanks
6 Steam Boiler (6 TPH)
24
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
(a) Sulphur: Solid sulphur of 99% purity from sulphur storage yard is
charged by wheel-barrows to the sulphur melter-cum-settler. The molten
sulphur from the melter compartment flows to the sulphur settler
compartment. The melter has capacity equivalent to more than two days
consumption at the rated sulphur utilization. The melter chamber is
divided into three compartments for removal of any ash particles
(suspended solids) by settling. With an initial ash content of 0.2% in the
dirty molten sulphur, the ash content in the sulphur in the last
compartment of sulphur settler will not exceed 0.02% (200 ppm).
From the last pumping compartment molten sulphur at about 1350C is
pumped by means of one of the submerged centrifugal sulphur pumps to
the sulphur burner. The molten sulphur is pumped to the burner through a
steam jacketed and insulated pipe line and is controlled by a flow
regulating valve. The sulphur burner is of a horizontal type lined with
refractory and insulating material. The combustion of molten sulphur is
fully completed in the burner.
(b) Air and Gas System: The combustion air for burning of the sulphur
and for conversion of SO2 to SO3 is provided by the air blower via the
drying chamber. The air blower after the filtration of air on its suction side
forces clean air through a drying tower where 98.4% sulphuric acid is
circulated. The filtered and dried air goes to the sulphur burner.
The gases leaving the sulphur burner have around 11% SO2 at a
temperature of around 980 deg. C. These gases pass through waste heat
boiler No. 1 where saturated steam is produced at a pressure of about
32kg/cm2. The waste heat boiler no. 1 and super heater are designed
according to the process requirement and the temperature control of the
outlet gases is achieved through by-passing of a part of the hot gases
25
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
leaving the burner through a refractory lined duct line fitted with heat
resisting valve. It is thus possible to control the temperature of the gases
entering the first bed of the converter at the desired level.
Before entering the converter the gases pass through a special type of
lower type HGF filter which removes minor quantities of dust which might
reach this point. The filter is loaded with crushed and cleaned filter media
and is completely insulated. The gases leaving the HGF filter enter the first
bed of the converter at around 430 deg. C and come out at around 600 deg.
C. Vanadium pent oxide (V205) catalyst is used for the conversion of SO2
to SO3. These gases are cooled in a waste heat boiler No. 2 where steam is
raised at around 32 kg/cm2 and superheated to 370 deg. C. For proper
control of temperature, gas entering the second bed of the converter at
around 525 deg. C. is cooled to around 440 deg. C before entering the third
pass by passing the gas on the tube side of the hot heat exchanger which in
turn heats the gases coming from the cold heat exchanger. A by-pass valve
is provided on the tube side of the hot heat exchanger for proper control of
the gases entering the third bed of the converter. The gases come out of the
third bed of the converter at around 4650 C. are cooled on the tube side of
the cold heat exchanger to a temperature of around 2500 C which after
further cooling enter the interpass absorption tower where SO3 is absorbed
by means of sulphuric acid (98.4%) and the remaining gases coming out of
the interpass absorption tower at about 700 C are first heated on the shell
side of cold heat exchanger where the temperature is raised to around 3300
C. the gases then pass through the shell side of the hot heat exchanger
where the temperature is raised to around 425oC. before entering the fourth
bed of the converter. For proper control of temperature of the gases
26
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
entering the fourth bed of the converter, a by-pass on the tube side of the
cold heat exchanger is provided.
The fourth bed of catalyst is the largest of all the beds. The relative higher
contact time (lower space velocity) with negligible initial SO3
concentration causes a very high deg. of SO2 conversion to SO3. The
overall conversion of SO2 to SO3 obtain in the converter is more than
99.7%. The gasses pass through an economizer where they are cooled to
around 200 deg. C. These gases after further cooling enter the final
absorption tower then SO3 in the gases gets absorbed in the tower. The
remain gases containing mostly N2 (93%) and O2 (7 %) is passes through
demister and are vented through the alkali scrubber and then to stack. The
condition is of operation are controlled in such a manner that this
remaining gases escaping through the chimney are kept as per MINAS
standard.
A caustic alkali scrubber has been installed before the vent to chimney, for
absorbing any excessive quantity of unconverted SO2 gas that may
otherwise be released during the start-up for shutdown of such units as
well as during any plant disturbances.
(c) Acid System: 98.4% sulphuric acid is circulated in the air drying
tower, interpass absorption tower and final absorption tower. This ensures
optimum drying in case of drying tower and maximum absorption
efficiency of SO3 in the absorption towers. All the towers have common
acid pump tank. The air drying tower is used for drying of air coming from
the main air blower so that the moisture content in the dried air is removed
as per the process requirements. Interpass absorption tower removes SO2
coming from the third bed of the converter so that the gases entering the
27
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
fourth and final bed is free of SO3. This enhances the conversion of SO2 to
SO3 in such a way that the exhaust gases coming from the final absorption
tower are free of SO2.
The circulating acid is collected in a common acid pump tank. The acid
strength in the pump tank is controlled automatically with online acid
strength analyzers by feeding the required quantity of water through
automatic control valve and rotameter. The acid pump tank is fitted with a
vertical submerged acid circulation pump which feeds acid to the towers
via shell tube acid coolers of pore free alloys with latest design. These acid
coolers cool the acid before feeding the towers. The acid is cooled by shell
tube cooler, fed with closed circuit of cooling water. The tapping for the
product acid is taken from the outlet of the acid coolers.
2) Oleum:
Oleum is a dense colorless liquid which is formed by absorbing sulphur
trioxide gas in sulphuric acid. Oleum reacts like a mixture of sulphur
trioxide and Sulphuric acid but contains Pyro-sulphuric Acid (H2S2O7), the
composition of which corresponds to 45% sulphur trioxide. The sulphur
Trioxide gas is to be taken after the 3rd pass of converter of existing
Sulphuric acid plant to the Oleum absorption Tower from the bottom &
concentrated 98.4% Sulphuric Acid is to be fed from the top of the Oleum
absorption tower. The feed of sulphuric acid in the Oleum absorption
tower is to be maintained through Rota Meter, Oleum strength Monitor &
continue circulation of Oleum in the absorption tower. During the proper
Mixing/absorption of SO3 gas with H2SO4, the temperature will also
increased with exothermic reaction, to cool down the Oleum and maintain
the proper required temperature, the Oleum is to be cooled through Plate /
Shell type Oleum cooler.
28
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
3) Sulphur Trioxide (Liquid):
The Oleum Liquid is to be fed to SO3 Generator through Oleum Heater.
The evaporation with the help of steam is to be achieved to get the pure
gaseous vapours, which will be condensed in the SO3 condenser. The cold
water will be fed to SO3 condenser to get the proper production of liquid
sulphur trioxide & which will be stored in the jacketed Storage Tanks. The
liquid sulphur trioxide (24%) SO3 will be supplied to DMS plant from
these tanks only.
4) Di-Methyl-Sulphate
1. Methanol is Vaporized & the pre-heated Vapors are fed continuously
in a Catalyst Bed Reactor (Temp 240 to 250oc) to convert the methanol
into Di-Methyl-Ether (DME)
2. Di-Methyl-Ether thus formed is Sulphonated with Liquid SO3 to get
crude Di-Methyl-Sulphate (DMS) which is further purified by Vacuum
distillation to get pure DMS.
Reaction:
2CH3OH CH3OCH3+H2O
CH3OCH3+SO3 (CH3)2 SO4 {DMS}
1) Methanol is pumped from main storage tank continuously into
methanol vaporizer, vapors of methanol is passed thru two nos. heat
exchangers to superheat the methanol vapors which then fed continuously
into catalytic reactor containing alumina catalyst temperature of 250-260o
C is maintained in the reactor for conversion of methanol to Di-Methyl-
Ether, unconverted methanol is 15-20%. This DME+UN converted
methanol + water of reaction is taken into stripping col. To get pure DME
CAT
29
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
vapors, methanol + water mix. Is fed to methanol recovery col. To get pure
methanol which is reused?
2) DME from DME STRIPPING COL. Is fed into a sulphonater where
it reacts with liq. SO3 to get crude DMS.
3) Crude DMS from storage tank is fed into DMS distillation unit
continuously to get pure DMS which is stored in storage tanks as finished
product.
4) Bottom residue of distillation kettle containing some DMS and spent
acid is taken into another DMS recovery unit to recover left over DMS,
spent acid & small quantity of water is to be used alum plant and for
cooling in sulphuric acid plant.
5) Sulphamic Acid (SMA)
Chemical Reaction:
NH2CO2 + H2SO4 = 2NH3SO3H + CO2
(Urea + Sulphuric Acid) = (SMA)
98%
Urea is reacted with mixture of 98% Sulphuric Acid & 65% Oleum at
elevated temp. SMA thus formed is separated by diluting the reaction mass
& then filtering the slurry of SMA Thus formed wet cake of SMA is dried
and packed.
CO2 formed during reactions is vented out after scrubbing. Spent dilute
Sulphuric Acid is used in the manufacture of Alum etc.
30
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
6) Sodium bi-sulphite:-
Sulphur dioxide gas is purged in a Reactor containing Caustic solution
under agitating and circulation. Reaction takes place and crystallization
started after saturation of Mother Liquor. Then entire material is
centrifuged to separate solid wet cake of Sodium bi-sulphite which is dried
in Flash Dryer get dry Sodium bi-sulphite pure product. The Mother liquor
collected and recycled to prepare next batch.
Chemical Reaction:-
NaOH + SO2 NaHSO3
3.4 Facilities at the Plant
The firm has already acquired 10 acres of land where part factory building has
been constructed and remaining building, and some other ancillary structures are
proposed to be constructed for expansion. It provides adequate space for the
following areas of working:-
1. Storage for raw material and finished goods.
2. Plant and Machinery
3. Store
4. Offices
5. Toilets
6. Water storage tanks
Open space will be landscaped and trees will be planted in due course of time.
31
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
3.5 Emissions:-
There are no emissions from the process as no gaseous material is generated. All
materials which become vapors during process are condensed through series of
condensers, as all process occur in tightly closed system. However there may be
some secondary emissions due to moving of vehicles which will be controlled
through sprinkling of water.
3.6 Waste Handling Treatment:-
Liquid Waste:-
There will be no generation of waste from manufacturing process. The domestic
effluent shall be treated through STP. The domestic treated water will be used for
plantation.
Solid Waste:-
Solid wastes in the unit are from the following sources.
i) Solids from APCD.
ii) Ash from the Boiler furnace
Solids from APCD will be disposed off at designated land filling site. Ash from
boiler will be sending to land fill site.
Hazardous Waste:-
The Hazardous wastes generated from the unit are Sulphur Sludge, Catalyst dust and
used DG Set oils. The Sulphur sludge & Catalyst Dust will be sent to TSDF site
Nimbuan Dera Bassi for final disposal & used oil from D.G. Set shall be sold to
recyclers. There are no other hazardous wastes.
32
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
POLLUTION CONTROL MEASURES:-
(i) AIR POLLUTION:-
Three stacks already exist in the industry and one more stack will be installed with
the boiler. The existing stacks are attached with alum plant and with DG sets. The
fuel used for boiler will be biomass. Diesel is used for DG set. The main pollutants
are particulate matter and gaseous emissions.
(ii) WATER POLLUTION:-
Water is already used in the process as well as domestic purpose. After expansion the
consumption of water will be increased. Waste water from the toilets will be treated
through septic tank. The domestic effluent shall mainly be used for plantation.
(iii) NOISE POLLUTION:-
There is some noise producing machineries such as ID Fan, Blowers etc. All these
machines are spread at different places within the covered sheds. Thus no noise of
significant level should go outside the working area which may disturb the general
noise environment. DG set will be installed with canopy.
ENVIRONMENT IMPACT ASSESSMENT & MITIGATION
MEASURES:
General:
Various Environment factors as existing in the project area which possibly could
be affected by the activities have been assessed & identified as below:
(i) Ambient Air
(ii) Water Quality
(iii) Noise
(iv) Land use pattern
33
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
(v) Soil and Agricultural
(vi) Demography and socio-economic pattern.
(a) SHORT TERM-CONSTRUCTION STAGE:-
Air:
It is an existing unit which is already in production. There is no point source of Air
Pollution during construction phase. The only source will be the dust generation
due to excavation, construction and plying of vehicles within unit. Some emission
may be expected from vehicles plying in the area for transportation of material etc.
Kerosene oil shall be provided to the labour so that they do not burn wood for
cooking etc.
Water:
Requirement of water during construction activity will be about 1.0 m3/day and
there will be no waste discharge as the same will be used completely. However,
during monsoon some malba etc may get washed due to run off from the site.
There is a natural ‘nallah’ near the land which takes the entire run off from the
area. Thus, there will be no impact of the unit on water Environment.
Noise:
Some noise may be expected from the working of the machinery for replacement
and repair purposes and movement of vehicles. Steps will be taken to reduce its
effect by resorting to staggering of various operations. Even otherwise since there
will not be any large scale machinery; the activity is not likely to have any
significant effect on the overall noise environment.
Land:
It is an approved FEZ area; the land at site is leveled as such no leveling is
required. Natural drainage will not be disturbed. Solid waste from construction
34
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
activities will be used within the premises under roads & refilling. There will not
be any significant impact on land in general.
Socio Economic:
The project does not involve any displacement of population or rehabilitation of
any kind. Rather it will provide employment to local people in the shape of
additional man power required for the units, & will boost the economy of the area.
It will have some positive impact, although not to a large extent.
(b) LONG TERM-OPERATIONAL STAGE:-
After the unit starts production the operational impacts and their mitigation
measures could be as under:
(i) Air Environment
There is the source of likely pollution which is PM emission from the Boiler
furnaces & mist from Sulphuric Acid plant/Alum Plant. All the processes are
closed circuits as such emissions to the open atmosphere will be minimum.
However, APCD, Multi –Cyclone will be installed on boiler & Alkali Scrubber on
Sulphuric Acid/Alum plant already been provided to neutralize Acid mist. So there
will be not any effect on the Air Environment.
(ii) Water Environment
About 8.0 m3/day waste water is generated from existing unit. This will be treated
through STP. There is no discharge of water from industrial process. Treated
domestic water has been being discharged on land for irrigation. Treated effluent
will not be thrown in any water body. Thus water environment is not likely to be
affected. Further, ground water will be balanced through recharge by rain water
harvesting from the roof top to the extent about 12960m3/annum through recharge
35
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
wells. Thus pressure on underground water will be reduced. This will have some
positive effects.
(iii) Land Environment
It is existing unit and no additional land required for expansion and located in Free
Enterprises Zone. Thus there will not be any significant adverse effect on the
existing general land environment with the coming up of the project. Soil quality in
the area will not be affected.
(iv) Noise Environment
There will be no noise producing machinery or equipment except ID fans &
Blower etc. which will be placed at different places within the closed sheds
causing least disturbance in the area. There is no likelihood of any significant
change in noise environment. Noise Environment in the area thus, will not be
affected.
(v) Socio Economic Pattern
After expansion project will provide more employment to local people in the field
of running plants and maintenance of machinery, APCD & security etc. Thus it
will have positive effect on the employment potential in the area.
CONCLUSION:-
In view of the proper pollution control measure proposed for the unit as
stated above it is concluded that there will be improvement in the
development of commercial activities, generation of direct and indirect
employment opportunities & the overall, improvement of Quality of life in the
surrounding area.
36
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.0 ENVIRONMENT MANAGEMENT PLAN:
To achieve the results as per the measures proposed for mitigation of the various
pollutants, the following management practices have been suggested for various
factors.
Air Environment
Cyclone & Alkali Scrubber shall be provided to arrest SPM from flue gases to
keep it within permissible limits. All vehicles for service activities at the project
site shall be checked for vehicular emission. The agencies will be asked to keep
them within prescribed limits. Tree plantation shall be done along the boundary
which will further improve the air Environment in general.
Water Environment
Water shall be drawn from existing tube well. During construction toilet facilities
shall be provided to labour with septic tank. Finally, waste water from the toilets
shall be taken to septic tank through underground delivery system and treated to
tertiary level. The treated water will be discharged on land for irrigation within the
premises. It will not be thrown outside either on land or in any water body. Roof
top rain water shall be harvested and used for ground water recharge to minimize
effect of withdrawal of water from the underground.
Noise Environment
During Construction stage “NO HORN” signs will be displayed at prominent places.
The drivers shall be directed not to blow horn unnecessarily. Vehicle owners will be
asked to maintain them in proper condition. During operational stage noise creating
machinery such as blower, ID Fans etc will be housed different places within closed
sheds so as not to disturb the noise level in the area.
37
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Land Environment
To avoid erosion of the top soil the development is planned in the shortest possible
time and land-clearing activity shall be kept to the absolute minimum by working
at the specific sites one by one where construction is to take place so as to increase
detention and infiltration. Natural waterways/drainage pattern shall be maintained
by providing culverts where needed. The requirements of sand and aggregates for
the construction works will be met through venders. The land use is thus so
planned that there is minimum adverse impact.
Solid Waste
The solid waste generated from the construction activities shall be effectively
recycled within the project site. The other solid wastes from the APCD shall be
dumped in a dumping pit of R.C.C. and disposed off in the designated land fill
places.
Monitoring of various parameters will be done at frequent intervals in the study
area, so as to ensure that no deterioration takes place. The results of the monitoring
shall be documented and watched properly. The frequency of the checking is as
under:
S.No. Item Parameters to be
checked
Frequency
1 Ambient Air PM10 & PM2.5, NOX & SO2 Every six months
2 Vehicles PUC Every Quarter
3 Noise Level dB (A) Once in a year
4 Ground water As per IS 10500 Once in a year
In order to ensure the implementation of the EMP, a structured Environment
Management Cell (EMC) interwoven with the existing management system will
be created. This will include:-
38
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Representative of the management
Process in charge
In charge maintenance Dept.
A representative of Environment consultants.
All actions of the cell shall be documented.
5.0 COST OF ENVIRONMENT PROTECTION MEASURES:
S.No Title Capital Cost
Lacs
Recurring Cost
- Lacs
(Annum)
1 Air Pollution Control 15.0 2.0
2. Noise Pollution Control
(Including cost of Landscaping,
Green Belt)
4.0 ---
3. Solid Waste Management 2.0 0.5
4. Environment Monitoring and
Management (Including
Establishment of Laboratory)
8.0 0.5
Total 29.0 3.0
39
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
ENVIRONMENT IMPACT ASSESSMENT REPORT
40
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-1.0
INTRODUCTION
M/s Punjab Acids-Chem. Pvt. Ltd. is proposing to enhance capacity of the unit &
addition of chemical products like Oleum, Di-Methyl Sulphate, Sodium Bi-
sulphite, and Sulphamic Acid & Liquid SO3 at Village Behra, Tehsil Derabassi,
and Distt. Mohali, Punjab. As per MoEF, GOI Notification dated 14-09-2006 they
are required to have Environmental Clearance of their project before establishing
the same. As per schedule of the Notification the Organic Chemical Industries are
listed at S. No. 5(f), the general and specific conditions given in the Notification
are applicable to the unit. Further, the project site falls within the 10 km of
Haryana- Punjab State boundary, so the project is to be treated as Category ‘A’
and thus the Environmental Clearance is to be given by the Central Govt. (MoEF).
Earlier, the project was appraised by the EAC in their 6th meeting dated 7th March,
2013 and TORs were issued by them for preparation of final EIA report. One of
the conditions of the TOR is to have Public Hearing which has been organized by
PPCB on dated 15th January, 2014. Result of the same has been included in EIA
report as Annexure-I. Key plan of the site is attached as Fig 1.1. The location
details of the site are given in Table 1.1.
41
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
FIGURE – 1.1
KEY - PLAN
42
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Table – 1.1
Location Details
S.No Particulars Details
1 Location
a Village/ Town/Plot No. Behra
b Tehsil Dera Bassi
c District S.A.S. Nagar Mohali
d State Punjab
e Latitude 30º34’17” North
d Longitude 76º53’07” East
2 Elevation 315 mts.
3 Land use at the project site Industrial
4 Climatic Conditions
Temperature
Rainfall
Relative Humidity, %
Wind speed, Kms/hour
Min: 6oC, Max:40 oc
1000-1100 mm (average)
Min: 23%, Max:80%
10 Km (approx.)
5 Nearest highway National Highway-22
(Chandigarh – Ambala about 6 km)
6 Nearest railhead Lalru (about 7 km)
7 Nearest airport Chandigarh (about 20 km)
8 Nearest major city Mohali (about 25 km)
9 Nearest major settlement Dera Bassi (about 6 km)
10 Features with 10 km :
i) Defence installations Nil
ii) Archaeological important
places
Nil
iii) Wild life sanctuaries Nil
Iv) Reserved/Protected forest Bir Kheri PF about 3 km, Bir Dadrala PF
about 4km, Bir Baqarpura PF about 7 km
from site.
v) Industries Industrial Focal Point Dera Bassi
vi) Rivers Dangri Nadi about 6 km in Haryana State &
Ghaggar Nadi about 8 km in Punjab.
vii) Hill ranges Nil
viii) State Boundary Haryana State (about 2 km)
43
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-2.0
SCOPE AND METHODOLOGY
2.1 Scope
This report contains various information on the environmental factors viz-a-viz
contribution of pollution by the proposed unit. These factors include air, water,
noise, health and welfare facilities, land use and agricultural pattern etc., and
discuss the predicted impact of the proposed plant activities on these factors.
Broadly under the scope of this E.l.A. report it is envisaged:-
To assess the present status of air, water, land, noise,
biological & Socio economic components of
environment.
To identify, quantify &. Evaluate positive or negative impacts of
various operations on different environmental components.
To evaluate proposed pollution control measures and to suggest
additional control strategies, if any, to mitigate the adverse
effects.
To prepare Environmental Management Plan for utilization and
adoption of safety measures.
To delineate future Environmental quality monitoring programme.
Suggest safety measures against possible industrial hazards.
2.2 Methodology
Various steps involved in Environmental Impact Assessment study of the
proposed project are divided into the following phases:
Identification of significant environmental parameters and to study the
existing status within the impact zone with respect to air, water, noise, soil
and socioeconomic components of the environment.
44
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Study of various activities of the proposed project for manufacture of
Sulphuric Acid, Alum, Oleum, Di-Methyl Sulphate, Sodium, Bi-Sulphite,
Sulphamic acid & Liquid SO3 and to indentify the area leading to
impact/change in environmental quality.
Identification/Prediction of impacts for identified activities and to study
levels of impact on various environmental components.
Evaluation of impacts after superimposing the predicted impact over the
baseline quality.
Formulation of Environmental Management Plan for implementation in the
proposed project.
45
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-3.0
PROFILE OF THE COMPANY & PROMOTORS
M/s Punjab Acids-Chem. (Pvt.) Ltd is a Private Limited Company. The Directors of the
company are as under:
1. Sh. Inderjit Singh Bal
Father's Name Late S. Balwant Singh
Date of Birth 18.04.1960
Address # 3106, Sector 32 D, Chandigarh
Qualification Graduation
Experience Director in M/s D. K. Chemicals Pvt. Ltd.
since 1986
Director in M/s Balwant Singh & Sons Pvt.
Limited since 1987
Partner in M/s Punjab Chemical Agency
Partner in M/s Delhi Kota Roadways
Director in M/s Punjab Acids-Chem Pvt. Ltd.since 2001
2. Mrs. Inderpal Kaur
Husband's Name S. Harvinder Singh
Date of Birth 17.08.1964
Address # 49A/41, Punjabi Bagh, New Delhi
Qualification Graduation
Experience Director in M/s Punjab Acids-Chem Pvt. Ltd.
since 2001
3. Mrs. Jagvinder Kaur
Husband's
Name
S. Inderjit Singh Bal
Date of Birth 06.08.1967
Address # 3106, Sector 32 D, Chandigarh
Qualification Graduation
Experience Director in M/s Punjab Acids-Chem Pvt. Ltd. since 2001
46
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4. Mr. Harvinder Singh
Father's Name Late S. Jagir Singh
Date of Birth 18.04.1954
Address # 49A/41, Punjabi Bagh, New Delhi
Qualification Graduation
Experience Director in M/s D. K. Chemicals Pvt. Ltd.
since 1986
Director in M/s Balwant Singh & Sons Pvt.
Limited since 1987
Partner in M/s Punjab Chemical Agency
Partner in M/s Delhi Kota Roadways
Director in M/s Punjab Acids-Chem Pvt. Ltd.
since 2001
47
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-4.0
BASELINE ENVIRONMENTAL SETTING
4.1 The State
Punjab is one of the progressive States in the Northern part of India. It
derives its name from five rivers which used to flow through the State
before partition of the Country in 1947 viz Sutlej, Beas, Ravi, Chenab, and
Jhelum. After partition two of the rivers i.e. Chenab and Jhelum went to
Pakistan Punjab and the other three remained in Indian Punjab. It has one of
the oldest irrigation systems of the country known as Sir Hind Canal with
recent addition of Bhakhra Canal System. The economy of the State is
dependent mainly on Agriculture. It, along with Haryana, contributes about
50% food grains to the common pool of the country. Punjab has over 2.04
lakh small and medium industries and about 600 large scale industries. It
leads in the manufacture of machine and hand tools; printing and paper
cutting machinery; auto parts and electrical switch gear. The State also
provides more than 75% of the country's requirement for bicycles, sewing
machines, hosiery and sports goods. At par with the highest quality
standards in the world, these products have carved a niche for themselves in
markets across the globe.
It has also made big strides towards industrialization. A number of
Industrial areas have been developed by the State. Ludhiana, Jalandhar,
Amritsar and Mohali are famous for Large and Medium scale industrial
units. Many small Industrial areas & Focal Points have also been developed
in different towns for small scale units.
48
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.2 District S.A.S Nagar
S.A.S. Nagar District has been carved out of areas falling in Roper and
Patiala District as 18th District of Punjab on 14th April 2006. It is
contiguous to the union territory of Chandigarh. The district has been
formed to achieve growth of development as this area is emerging as major
I.T hub of Northern India. The district includes Mohali, Kharar and Dera
Bassi Tehsil. It is located in the South Eastern part of Punjab and is part of
Patiala division. The District includes 414 villages. The important
townships in the district are Kharar, Kurali, Mohali, and Zirakpur & Dera
Bassi. Kharar Tehsil is the largest administrative unit of the new district
with 154 villages followed by Dera Bassi Tehsil with 44 villages. The
district is spread over geographical area of 1092.64 sq. kms. The rural area
constitutes 1021.77 sq. kms as compared to urban area of 70.87 sq. kms.
Mohali town is the Head Quarter of the District and forms part of
Chandigarh Tricity which includes Chandigarh, Panchkula and Mohali.
4.3 Project Site
The Plant site is in FEZ (Free Enterprises Zone) Derabassi, Dist. S.A.S.
Nagar Mohali of Punjab. It is on Chandigarh-Ambala Highway NH-22.
Dera Bassi block has number of small scale and medium scale units.
Chemical, paints, Steel tubes, plywood, handlooms knitting and dairy are
some of the industries which have offered good employment to a number of
persons. Project site lies near Long 76° 53' 17" East and Lat: 30° 34' 07"
North and is at an altitude of about 315 m. above mean sea level. It is well
connected with Mohali, Chandigarh & Zirakpur through well maintained
metalled roads. It is about 25 K.M. from Mohali; Chandigarh Bus stand is
at a distance of about 20 K.M. by road. The nearest rail head is Lalru,
49
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
which is at a distance of about 7 km from the site. Location & Layout Plan
of the unit is given in Fig. 4.1 & 4.2
FIGURE – 4.1
LOCATION – PLAN
50
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
FIGURE – 4.2
LOCATION ON SATELLITE IMAGERY (COURTESY
GOOGLE EARTH)
51
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
FIGURE – 4.3
SITE – PLAN
52
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
FIGURE – 4.4
LULC MAP
LULC Classes Area in km2 Percentage
Dense Forest 3.20 1.02 Open Forest 98.91 31.40 Non Forest 24.80 7.87 Agriculture Land 177.17 56.25 Built-up Land 8.70 2.76 Water Body 2.21 0.70 Total 314.98 100
53
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.4 Study Area
In order to establish bench mark conditions near the unit an area of 10 km
around the site has been selected which is shown in Fig. 4.5 Detail of
villages falling in the study area has been given in Table 4.1.
FIGURE – 4.5
Details of the Study Area
(Within 10 kms radius area)
54
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-4.1 DETAILS OF THE STUDY AREA
(Within 10 kms radius area)
Sr.
No.
Name of the Village Distance Direction
1 Project Site 0.0 -
2 Mirpur 6.25 NW
3 Mubarakpur 6.0 NW
4 Derabassi 6.0 N
5 Pandwala 5.0 NW
6 Bhagwanpur 5.5 SE
7 Samgauli 5.5 SW
8 Mukandpur 6.5 SW
9 Bijarpur 7.5 SW
10 Bahadurgarh 2.0 NW
11 Mankan 5.45 N
12 Bhanun 4.75 N
13 Ramgarh 7.25 N
14 Mor Tikri 6.0 N
15 Sultanpur 3.25 E
16 Kakrali 6.05 NW
17 Kheri Gujran 4.5 SW
18 Mahiwala 4.5 W
19 Dadrala 6.0 SW
20 Haripur 6.65 W
21 Haibatpur 4.75 NW
22 Dafarpur 7.0 NW
23 Gulabgarh 5.25 W
24 Kheri 4.5 NW
25 Nagal 3.25 NE
26 Alipur 4.75 NE
27 Babupur 1.75 NE
28 Khatauli 5.0 E
29 Toka 6.5 NE
55
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.5 Climate
There is a meteorological observatory at Chandigarh which is at a distance of
about 20 km from the site. Its data is fairly representative of the conditions in
the District in general.
Chandigarh falls under Koeppen’s Cwg category i.e. it has cold dry winder,
hot summer and sub tropical monsoon. Evaporation usually exceeds
precipitation and the weather is generally dry. The area experiences four
seasons: (i) Summer or hot season (mid- March to Mid-June) (ii) Rainy
30 Devi Nagar 7.45 SW
31 Knauli 7.25 NE
32 Khangesra 5.25 NE
33 Dhandaru 7.0 E
34 Haripur Hindua 1.85 W
35 Saidpur 3.85 W
36 Debkanuri 8.75 NE
37 Sandran 4.0 N
38 Khurhanwala 2.75 W
39 Jalauli 2.35 E
40 Sundarpur 1.75 SE
41 Rahawar 5.5 SE
42 Sarkpur 7.75 SE
43 Barwala 3.35 SE
44 Batawar 4.5 SE
45 Mauli 8.0 SE
46 Nayagaon 7.35 SE
47 Bharali 5.0 S
48 Bhagsi 6.45 S
49 Bera 2.5 S
50 Mianpur 8.25 SW
51 Rampur Sainian 0.75 W
56
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
season (late-June to mid-September); (iii) Post mansoon autiumn/transition
season (mid September to Mid- November); (iv) Winter (mid November to
mid-March). The dry spell of summer is long but with occasional drizzles or
under storms (City Development Plan Chandigarh).
4.6 Temperatures
The area is fairly plain. December and January are the coldest months
whereas in May and June the heat is quite intense. The wettest months of the
seasons are July, August and September. The temperature varies from 6oC
minimum to 40oC maximum during the year. Monthly average temperatures
of the area are given in Table-4.2.
TABLE-4.2
MONTHLY AVERAGE TEMPERATURE
Months Maximum oC Minimum oC
January 20 6 February 23 10 March 28 14 April 34 20 May 38 24 June 40 26
July 34 25 August 32 24
September 33 17
October 32 17
November 27 11
December 22 7 Source: IMD Data – Chandigarh (2004-‘09)
57
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.7 Rainfall
The rainfall in the Zone is caused by the South-West monsoon. It starts in
the month of July and extends up-to the end of September. During this
period the monsoon rain-fall contributes about 75 to 80% of the total annual
rainfall. The average annual rain fall is in the range of 1000 to 1100 mm.
The annual number of rainy days on an average is about 51 in a year, out of
which about 31 falls in the monsoon period of July to September. Monthly
rainfall data for this zone is given in Table-4.3
TABLE-4.3
MONTHLY AVERAGE RAINFALL
Months Rainfall (mm) Avg. no. of rainy days
January 44 3
February 41 2.5
March 30 2.0
April 12 0.1
May 24 2.0
June 110 5.0
July 290 12.0
August 295 13
September 184 6
October 43 2
November 7 1
December 20 2
Total 1100 51
Source: 2004-2009 IMD, Chandigarh
58
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.8 Humidity
In summer months of April, May and June, which is the driest part of the
year, the afternoon humidity comes down to 23% to 25% while the relative
humidity during monsoon months goes up-to 75% to 80%. Monthly
humidity is given in Table-4.4
TABLE-4.4
MONTHLY HUMIDITY
Months Humidity (%)
08.30 Hrs. 17.30 Hrs.
January 70 44
February 63 41
March 50 33
April 38 25
May 35 23
June 10 25
July 75 64
August 81 69
September 76 58
October 57 40
November 58 40
December 67 45
Total 1100 51
Source: 2004-2009 IMD, Chandigarh
59
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.9 Cloudiness
During monsoon season skies are over cast with moderate to heavy clouds.
During rest of the year, the sky is mostly clear. It is lightly clouded
occasionally during winter season.
4.10 Winds
The Wind direction in the area is mostly from North-West to South-East.
During January to May the winds are quite strong while July to October is
calm months. The general trends of various meteorological data from
meteorological observatory at Chandigarh and field observations are used
to draw Wind Rose Diagram. The Wind rose diagram is shown in Figure-
4.6
60
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
FIGURE-4.6
WIND-ROSE DIAGRAM
Source: IMD, Chandigarh
61
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.11 Drainage
The area is fairly plain and has good slope from North-East to South-West.
The area is well drained and takes the entire rain water flows to local
Choes.
4.12 Land Use
The total area of the District is 1092.64 sq km. 68% is net sown area and
32% is under non-agricultural use. Agriculture is mostly dependent on
tube-wells. Rice and wheat are the main crops in the area.
4.13 Forest
There are no reserved forests near the project site. In the entire district, area
under forest is about 18,000 Ha. The company also proposes to plant about
150 trees and shrubs within the project area.
4.14 Flora and Fauna
Ecological system consists of varieties of interrelationship between both
biotic and abiotic components. Biotic components comprise of both plant
and animal communities, which interact not only between them but also
with the abiotic components. Animal plant communities in their natural
habitat exist in a well organized manner. The project does not disturb any
natural setting and is coming up in an already existing Industrial area.
Flora in the area generally consists of Dalbergia, Prosopis, Albizzia, Ficus,
Azolla, Hydrilla, Nelumbo, Typha, Phragmites, Zizyphus Mauritiana,
Syzgium cumini, Ipomoea aquatica, Cyprus and Grasses. Animals like
Wild Boar, Flying Fox, Wildcat, Squirrel, Fruit bat, and Common
Mongoose are found in the area.
62
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4.15 Demography and Socio-Economic Scenario
Quite a good Industrial and Residential development has taken place in this
area, especially near Dera Bassi & Zirakpur etc. The socio-economic
profile has been studied through random sample primary surveys and
secondary data. The significant demographic and socio economic statistics
of the district are summarized and given in Table- 4.5
TABLE-4.5
Summary of Key Demographic Statistics
Punjab Mohali
Particulars 2011 2011 Male Population 14,634,819 5,24,989
Female Population 13,069,417 4,61,158
Total Population 27,704,236 9,86,147
Sex Ratio 893/1000 878/1000
Density of
Population/Km2 550 830
Literacy Rate: Average 76.68 % 84.90%
Male 81.48% 89.20%
Female 71.34% 80.00%
63
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-4.6
OCCUPATIONAL STRUCTURE IN THE AREA
Occupation 2011 Percentage in the
District Agriculture Labour 21,638 8.0 %
Cultivators 40,445 14.9 %
House Hold Industry 6,539 2.5 %
Others covering:
Transport and
Communication
Trade & commerce
Govt. Services
Construction
Industry
2,01,401
74.6 %
Total 2,70,023 100%
64
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-5.0
ENVIRONMENTAL BENCH MARK CONDITIONS
IN THE STUDY AREA
The study has been carried out for 3 months i.e. March, April & May 2013.
Various Environmental factors have been checked at selected stations
around the project site and the results of their quality have been
documented. The monitoring locations have been identified considering
drainage pattern, habitation and croplands and likely areas that represent
base line conditions. These will be frequently checked after the project
comes into operation and remedial measures taken, if any of the parameters
goes beyond the permissible limits. These are discussed as below:
5.1 Ambient Air Quality
The Status of Ambient Air Quality in the study area has been determined by
monitoring air quality in the Area at different Locations. The study area is a
mix of rural, urban and industrial area and the various sources of pollution
are dust arising from agricultural activities, vehicular traffic and industries.
The Locations are given in Table-5.1. & Figure 5.1
The ambient Air Quality results fall between Low for gases and moderate
for RSPM in Project Area. The Ambient Air Quality results are given in
Table-5.2
65
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
FIGURE – 5.1
Location of Monitoring Stations
(Ambient Air)
Project Site, AA1 AA2
AA3
AA4
AA5
AA6
66
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE- 5.1
AMBIENT AIR MONITORING STATIONS
S.No. Sample
Code
Name of
Village/Location
Co-ordinate Distance from
site (KM)
1. AA-1 Project Site
30o34’07” N
76o53’17” E
0
2. AA-2 Sundarpur 30o34’28” N
76o55’19” E 3 (E)
3. AA-3 Bharaili 30o32’31” N
76o55’25” E 4.2 (SE)
4. AA-4 Kheri gujran 30o33’17” N
76o52’31” E 2.5 (SW)
5. AA-5 Mahiwala 30o34’17” N
76o51’49” E 3.2 (W)
6. AA-6 Bahadurgarh 30o35’36” N
76o53’58.4” E 2.9 (N)
67
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-5.2
Summary of Ambient Air Quality Monitoring Results (parameter of concern)
AMBIENT AIR QUALITY (ug/m3)
Location MONTH Concentration of Pollutants (µg/m3) 24-Hour
Average Value
Parameters SO2 NOX VOC PM2.5 PM10
Permissible Limits 80 80 --- 60 100
AA1
Project Site
Mar.-2013 5.6 20.5 1.6 42.6 86
Apr.-2013 5.6 21.4 1.8 43 85.6
May. -2013 5.5 20.5 1.7 43.3 84.3
Average 5.5 20.8 1.7 42.9 85.3
AA2
Sundarpur
Mar.-2013 5.1 21.3 1.1 45 84.3
Apr.-2013 5.0 22.3 1.1 44.3 86.3
May. -2013 5.1 22.3 1.2 46.3 85.6
Average 5.0 21.9 1.1 45.2 85.4
AA3
Bharaili
Mar.-2013 4.4 18.1 0.8 42 68.6
Apr.-2013 4.2 18.2 0.9 43.6 72.6
May. -2013 4.6 19.4 0.9 42.3 78
Average 4.4 18.5 0.9 42.6 73
AA4
Kheri
Gujran
Mar.-2013 4.5 17.3 0.5 38 66.6
Apr.-2013 4.2 17.0 0.4 37.3 66.6
May. -2013 4.2 17.1 0.6 40 66.3
Average 4.3 17.1 0.5 38.4 66.5
68
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-5.2 (Contd.)
Summary of Ambient Air Quality Monitoring Results
AMBIENT AIR QUALITY (µg / m3)
Location MONTH Concentration of Pollutants (µg/m3) 24-Hour
Average Value
Parameters SO2 NOX VOC PM2.5 PM10
Permissible Limits 80 80 --- 60 100
AA5
Mahiwala
Mar.-2013 4.4 16.9 0.7 40 74
Apr.-2013 4.3 17.3 0.6 40 70.6
May. -2013 4.1 17.1 0.6 39.3 72
Average 4.2 17.1 0.6 39.7 72.2
AA6
Bahadurgarh
Mar.-2013 4.0 17.3 0.5 39.3 68.6
Apr.-2013 4.1 17.2 0.5 38 74.6
May. -2013 4.1 17.3 0.6 38.6 68
Average 4.0 17.2 0.5 38.7 70.4
The monitoring for PM10, PM2.5, VOC, SO2 and NOX has been undertaken for the months
March, April & May 2013 as per CPCB guidelines.
69
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Table-5.3
Ambient Air Quality Monitoring Results
PROJECT SITE
S.NO DATE OF
MONITORING
PM2.5
ug/m3
PM10
ug/m3
SO2
ug/m3
NOX
ug/m3
CO
mg/m3
LEAD
ug/m3
NICKEL
ng/m3
ARSENIC
ug/m3
O3
ug/m3
NH3
ug/m3
VOC
µg/m3
1. 04-03-2013 46 90 5.7 20.5 0.6 <0.1 8.0 <0.5 50.2 17.2 1.7
2. 16-03-2013 42 82 5.4 20.4 0.8 <0.1 8.4 <0.5 51.4 17.4 1.5
3. 28-03-2013 40 86 5.8 20.6 0.6 <0.1 8.3 <0.5 52.0 17.0 1.6
4. 02-04-2013 46 91 5.8 21.4 0.8 <0.1 8.8 <0.5 52.0 17.5 1.8
5. 13-04-2013 40 78 5.5 21.3 0.6 <0.1 8.4 <0.5 51.0 17.4 1.7
6. 23-04-2013 43 88 5.5 21.6 0.7 <0.1 8.5 <0.5 50.8 16.8 1.7
7. 06-05-2013 45 82 5.5 20.5 0.7 <0.1 8.8 <0.5 51.4 17.0 1.6
8. 18-05-2013 44 87 5.6 20.6 0.8 <0.1 8.9 <0.5 50.9 17.2 1.8
9. 25-05-2013 42 84 5.4 20.4 0.6 <0.1 8.6 <0.5 51.2 17.0 1.8
MIN.
MAX.
40
46
78
91
5.4
5.8
20.4
21.6
0.6
0.8
<0.1
<0.1
8.0
8.9
<0.5
<0.5
50.2
52.0
16.8
17.5
1.5
1.8
PERMISSIBLE LIMITS 60 100 80 80 4 1 20 6 100 400 __
SUNDARPUR
S.NO DATE OF
MONITORING
PM2.5
ug/m3
PM10
ug/m3
SO2
ug/m3
NOX
ug/m3
CO
mg/m3
LEAD
ug/m3
NICKEL
ng/m3
ARSENIC
ug/m3
O3
ug/m3
NH3
ug/m3
VOC
µg/m3
1. 04-03-2013 42 84 5.2 21.1 0.6 <0.1 8.2 <0.5 46 14.0 1.0
2. 16-03-2013 45 82 5.3 21.4 0.8 <0.1 8.0 <0.5 48 14.3 1.2
3. 28-03-2013 48 87 5.0 21.6 0.6 <0.1 8.1 <0.5 46 14.3 1.0
4. 02-04-2013 42 83 5.0 22.6 0.8 <0.1 8.0 <0.5 44 14.0 1.2
5. 13-04-2013 43 86 5.0 22.0 0.5 <0.1 8.3 <0.5 47 14.0 1.0
6. 23-04-2013 48 90 5.2 22.3 0.7 <0.1 8.4 <0.5 50 14.1 1.1
7. 06-05-2013 44 86 5.3 22.2 0.6 <0.1 8.2 <0.5 49 14.4 1.2
8. 18-05-2013 48 87 5.1 22.8 0.7 <0.1 8.3 <0.5 44 14.1 1.3
9. 25-05-2013 47 84 5.1 22.1 0.8 <0.1 8.1 <0.5 45 14.2 1.0
MIN.
MAX.
42
48
82
90
5.0
5.3
22.0
22.8
0.5
0.8
<0.1
<0.1
8.0
8.4
<0.5
<0.5
44
50
14.0
14.4
1.0
1.3
PERMISSIBLE LIMITS 60 100 80 80 4 1 20 6 100 400 __
70
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
BHARAILI
S.NO DATE OF
MONITORING
PM2.5
ug/m3
PM10
ug/m3
SO2
ug/m3
NOX
ug/m3
CO
mg/m3
LEAD
ug/m3
NICKEL
ng/m3
ARSENIC
ug/m3
O3
ug/m3
NH3
ug/m3
VOC
µg/m3
1. 04-03-2013 42 68 4.5 18.0 0.4 <0.1 6.3 <0.5 42.1 10.2 0.9
2. 16-03-2013 40 70 4.4 18.1 0.5 <0.1 6.0 <0.5 42.3 10.0 0.8
3. 28-03-2013 44 68 4.5 18.2 0.4 <0.1 6.3 <0.5 42.0 10.0 0.8
4. 02-04-2013 42 68 4.2 18.0 0.6 <0.1 6.0 <0.5 42.1 10.3 1.0
5. 13-04-2013 46 72 4.2 18.4 0.4 <0.1 6.1 <0.5 42.3 10.4 1.0
6. 23-04-2013 43 78 4.3 18.3 0.4 <0.1 6.3 <0.5 42.4 10.0 0.8
7. 06-05-2013 44 88 5.1 21.4 0.6 <0.1 8.4 <0.5 42.8 10.2 1.1
8. 18-05-2013 43 74 4.4 18.6 0.5 <0.1 6.3 <0.5 42.7 10.2 0.9
9. 25-05-2013 40 72 4.5 18.3 0.6 <0.1 6.2 <0.5 42.0 10.3 0.9
MIN.
MAX.
40
46
68
78
4.2
5.1
18.0
21.4
0.4
0.6
<0.1
<0.1
6.0
8.4
<0.5
<0.5
42.0
42.8
10.0
10.4
0.8
1.1
PERMISSIBLE LIMITS 60 100 80 80 4 1 20 6 100 400 __
KHERI GUJRAN
S.NO DATE OF
MONITORING
PM2.5
ug/m3
PM10
ug/m3
SO2
ug/m3
NOX
ug/m3
CO
mg/m3
LEAD
ug/m3
NICKEL
ng/m3
ARSENIC
ug/m3
O3
ug/m3
NH3
ug/m3
VOC
µg/m3
1. 02-03-2013 38 66 4.6 17.4 0.5 <0.1 5.8 <0.5 41.0 9.8 0.6
2. 15-03-2013 36 70 4.5 17.2 0.5 <0.1 5.9 <0.5 41.2 9.6 0.4
3. 22-03-2013 40 64 4.6 17.4 0.5 <0.1 5.6 <0.5 41.2 9.4 0.5
4. 04-04-2013 40 66 4.3 17.0 0.6 <0.1 5.9 <0.5 41.0 9.2 0.6
5. 13-04-2013 36 64 4.2 17.0 0.4 <0.1 5.2 <0.5 41.3 9.3 0.4
6. 27-04-2013 36 70 4.1 17.1 0.5 <0.1 5.4 <0.5 41.0 9.5 0.3
7. 07-05-2013 40 66 4.2 17.0 0.5 <0.1 5.7 <0.5 41.3 9.7 0.6
8. 16-05-2013 42 68 4.4 17.1 0.6 <0.1 5.2 <0.5 41.2 9.8 0.6
9. 24-05-2013 38 65 4.0 17.4 0.4 <0.1 5.8 <0.5 41.2 9.0 0.6
MIN.
MAX.
36
42
64
70
4.0
4.6
17.0
17.4
0.4
0.6
<0.1
<0.1
5.2
5.9
<0.5
<0.5
41.0
41.3
9.0
9.8
0.3
0.6
PERMISSIBLE LIMITS 60 100 80 80 4 1 20 6 100 400 __
71
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
MAHIWALA
S.NO DATE OF
MONITORING
PM2.5
ug/m3
PM10
ug/m3
SO2
ug/m3
NOX
ug/m3
CO
mg/m3
LEAD
ug/m3
NICKEL
ng/m3
ARSENIC
ug/m3
O3
ug/m3
NH3
ug/m3
VOC
µg/m3
1. 02-03-2013 40 78 4.5 16.8 0.5 <0.1 5.4 <0.5 42.0 9.2 0.6
2. 15-03-2013 38 74 4.4 16.9 0.5 <0.1 5.2 <0.5 42.5 9.0 0.8
3. 22-03-2013 42 70 4.5 17.0 0.4 <0.1 5.3 <0.5 42.3 9.1 0.7
4. 04-04-2013 38 68 4.4 17.4 0.5 <0.1 5.2 <0.5 42.3 9.1 0.5
5. 13-04-2013 42 72 4.5 17.3 0.5 <0.1 5.2 <0.5 42.5 9.1 0.5
6. 27-04-2013 40 72 4.0 17.4 0.5 <0.1 5.2 <0.5 42.2 9.3 0.7
7. 07-05-2013 40 78 4.0 17.0 0.4 <0.1 5.1 <0.5 42.5 9.0 0.8
8. 16-05-2013 36 72 4.2 17.2 0.4 <0.1 5.4 <0.5 42.0 9.0 0.7
9. 24-05-2013 42 66 4.1 17.3 0.5 <0.1 5.0 <0.5 42.3 9.2 0.5
MIN.
MAX.
36
42
66
78
4.0
4.5
16.8
17.4
0.4
0.6
<0.1
<0.1
5.0
5.4
<0.5
<0.5
42.0
42.5
9.0
9.3
0.5
0.8
PERMISSIBLE LIMITS 60 100 80 80 4 1 20 6 100 400 __
BAHADURGARH
S.NO DATE OF
MONITORING
PM2.5
ug/m3
PM10
ug/m3
SO2
ug/m3
NOX
ug/m3
CO
mg/m3
LEAD
ug/m3
NICKEL
ng/m3
ARSENIC
ug/m3
O3
ug/m3
NH3
ug/m3
VOC
µg/m3
1. 02-03-2013 40 66 4.0 17.1 0.5 <0.1 5.0 <0.5 41.3 8.3 0.5
2. 15-03-2013 40 72 4.1 17.6 0.6 <0.1 5.3 <0.5 41.0 8.2 0.6
3. 22-03-2013 38 68 4.0 17.3 0.5 <0.1 5.0 <0.5 41.3 8.0 0.5
4. 04-04-2013 38 74 4.1 17.4 0.6 <0.1 5.1 <0.5 41.0 8.3 0.6
5. 13-04-2013 36 76 4.3 17.3 0.5 <0.1 5.0 <0.5 41.3 8.3 0.6
6. 27-04-2013 40 74 4.0 17.0 0.4 <0.1 5.0 <0.5 41.2 8.1 0.4
7. 07-05-2013 38 66 4.3 17.5 0.4 <0.1 5.0 <0.5 41.8 8.1 0.5
8. 16-05-2013 36 68 4.0 17.3 0.5 <0.1 5.2 <0.5 41.5 8.1 0.6
9. 24-05-2013 42 70 4.2 17.2 0.5 <0.1 5.0 <0.5 41.2 8.6 0.6
MIN.
MAX.
36
42
66
76
4.0
4.3
17.0
17.6
0.4
0.6
<0.1
<0.1
5.0
5.3
<0.5
<0.5
41.0
41.8
8.0
8.6
0.4
0.6
PERMISSIBLE LIMITS 60 100 80 80 4 1 20 6 100 400 __
72
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-5.4
FREQUENCY DISTRIBUTION OF PM10, PM2.5, SO2 AND NOx IN
STUDY AREA
PM10
Range (µg/m3) Frequency Cumulative
Frequency
% Cumulative
Frequency
64.0-66.7 9 9 16.7
66.7-69.4 7 16 29.6
69.4-72.1 11 27 50
72.1-74.8 4 31 57.4
74.8-77.5 1 32 59.3
77.5-80.2 4 36 66.7
80.2-82.9 3 39 72.2
82.9-85.6 4 43 79.6
85.6-88.3 8 51 94.4
88.3-91.0 3 54 100
54
P98 = 88.9
PM2.5
Range (µg/m3) Frequency Cumulative
Frequency
% Cumulative
Frequency
36.0-37.2 6 6 11.1
37.2-38.4 7 13 24.1
38.4-39.6 0 13 24.1
39.6-40.8 13 26 48.2
40.8-42.0 11 37 68.5
42.0-43.2 4 41 75.9
43.2-44.4 4 45 83.3
44.4-45.6 2 47 87.0
45.6-46.8 3 50 92.6
46.8-48.0 4 54 100
54
P98 = 47.9
73
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
SO2
Range (µg/m3) Frequency Cumulative
Frequency
% Cumulative
Frequency
4.0 – 4.18 11 11 20.4
4.18 – 4.36 10 21 38.9
4.36 – 4.54 12 33 61.1
4.54 – 4.72 2 35 64.8
4.72 – 4.9 0 35 64.8
4.9 – 5.08 3 38 70.4
5.08 – 5.26 5 43 79.6
5.26 – 5.44 4 47 87.0
5.44 – 5.62 4 51 94.4
5.62 – 5.8 3 54 100
54
P98 = 5.7
NOx
Range (µg/m3) Frequency Cumulative
Frequency
% Cumulative
Frequency
16.8 – 17.4 25 25 46.3
17.4 – 18.0 4 29 53.7
18.0 – 18.6 6 35 64.8
18.6 – 19.2 0 35 64.8
19.2 – 19.8 0 35 64.8
19.8 – 20.4 2 37 68.5
20.4 – 21.0 4 41 75.9
21.0 – 21.6 7 48 88.9
21.6 – 22.2 3 51 94.4
22.2 – 22.8 3 54 100
54
P98 = 22.6
74
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
5.2 Water Quality
Water quality of ground as well as surface resources in the study area has
been studied for assessing the water environment and to evaluate the
anticipated impact of the project. The location of the surface water and
ground water stations are given in Figure 5.2. The results of surface water
are given in Table-5.5 and of ground Water quality are given in Table-5.7
TABLE- 5.5
WATER MONITORING STATIONS
S.N
o.
Sample
Code
Name of
Village/Location
Distance from
site (KM)
1.
GW-1
Project Site
0
2. GW-2 Derabassi 6 (N)
3. GW-3 Mahiwala 3.2 (W)
4. GW-4 Mianpur 8.25 (SW)
5. GW-5 Bera 2.5 (S)
6. GW-6 Nagal 3.25 (NE)
75
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Figure 5.2
Surface water /Ground water Monitoring Stations
76
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-5.6
RESULT OF SURFACE WATER SAMPLES
Parameter Ghaggar River (SW-1)
pH 7.2
TSS 122 mg/l
TDS 390 mg/l
BOD 12 mg/l
Chloride 30 mg/l
Sulphate 42 mg/l
Iron ND
Lead ND
Total Chromium ND
77
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-5.7
RESULTS OF GROUND WATER SAMPLES (mg/l except pH)
GW-1
Project Site
GW-2
Dera Bassi
GW-3
Mahiwala
Colour, Hazen, units,. <5 <5 <5
Odour Unobjectionabl
e
Unobjectionable Unobjectionable
Taste Agreeable Agreeable Agreeable
Turbidity, NTU <5 <5 <5
pH 6.5 7.1 7.0
Total Hardness (as CaCO3)
mg/I.
212 218 209
Iron (as Fe), mg/I, 0.1 0.12 0.08
Chloride (as CI), mg/I, 35 34 32
Magnesium as mg/I, 8 12 14
Sulphate (as SO4), mg/I, 94 83 91
Calcium , mg/I, 17 31 22
Fluoride (as F), mg/I, < 0.1 < 0.1 < 0.1
Sodium (as Na) mg/I 18 26 20
Cadmium(as Cd), mg/I <0.01 <0.01 <0.01
TDS , mg/I 385 358 362
Arsenic (as As), mg/I ND ND ND
Cyanide (as CN), mg/I ND ND ND
Lead (as Pb), mg/I 0.001 0.001 0.001
Chromium (as Cr), mg/I 0.01 0.01 0.01
Ecoli/Total Coliforms Absent Absent Absent
78
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-5.7
RESULTS OF GROUND WATER SAMPLES (mg/l except pH)
GW-4
Mianpur
GW-5
Bera
GW-6
Nagal
Colour, Hazen, units. <5 <5 <5
Odour Unobjectionable Unobjectionable Unobjectionable
Taste Agreeable Agreeable Agreeable
Turbidity, NTU <5 <5 <5
pH 6.5 7.2 7.3
Total Hardness (as
CaCO3) mg/I.
210 216 232
Iron (as Fe), mg/I, 0.13 0.08 0.15
Chloride (as CI), mg/I, 35 37 41
Magnesium as mg/I, 13 10 11
Sulphate (as SO4), mg/I, 12 88 95
Calcium , mg/I, 22 23 31
Fluoride (as F), mg/I, < 0.1 < 0.1 < 0.1
Sodium (as Na) mg/I 20 28 24
Cadmium(as Cd), mg/I <0.01 <0.01 <0.01
TDS , mg/I 369 389 375
Arsenic (as As), mg/I ND ND ND
Cyanide (as CN), mg/I ND ND ND
Lead (as Pb), mg/I 0.001 0.001 0.001
Chromium (as Cr), mg/I 0.01 0.01 0.01
Ecoli/Total Coliforms Absent Absent Absent
79
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
5.3 Ambient Noise Quality
Noise is defined as unwanted sound due to any operation. It has become a
common problem and ambient noise levels are on the rise all around. Noise
levels were measured at various locations and are reported in Table-5.8.
The Location of monitoring stations for noise is shown in Figure 5.3.
80
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
FIGURE – 5.3
Location of Monitoring Stations
(Noise)
81
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Table-5.8
NOISE LEVELS
S. No. Stations Noise Level, dB (A)
Day Time
(9.00 a.m. – 12.00 Noon)
Night Time
(9.00 p.m. – 12.00 Mid-
night)
1 Project site (AN1) 47 44
2 Dera Bassi (AN2) 51 49
3 Pandwal (AN3) 43 40
4 Mianpur (AN4) 46 42
5 Sundarpur (AN5) 41 38
6 Nagal (AN6) 42 40
7 Kheri Gujran (AN7) 44 41
8 Bhagwanpur (AN8) 41 37
Permissible Limits: Day Time: 75, Night time: 70
5.4 Soil
Soil is generally sandy loam almost all over the District and soil depth is
generally shallow except in areas having good vegetative cover. It is
generally dry, shallow and deficient in organic matters. The study area
comprises mostly of alluvial deposits of Quaternary age. The geological
formations in the area comprise of sandstone largely micaceous and form
major features. The top zone of this stage consists of maroon clays and buff
clays alternating one by one.
82
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Figure 5.4
Soil Monitoring Stations
83
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
TABLE-5.9
RESULT OF SOIL SAMPLES TEST
Characteristic Project Site
(SS1)
Behra
(SS2)
Sundarpur
(SS3)
pH (1:2) 6.5 6.8 7.1
Electrical Conductivity of
Saturation Extract (1:2)
mmhos/cm
0.75 0.68 0.85
Soil Moisture Content (%) 30.5 27.6 31.26
Soil Texture Sandy loam Sandy loam Sandy loam
Bulk Density (gm/cc) 1.12 1.21 1.30
Organic Matter (%) 0.8 0.71 0.72
84
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-6.0
PROJECT DESCRIPTION
6.1 General
The Punjab Acids-Chem. (P) Limited located at Village Behra, Tehsil Dera
Bassi, Dist. S.A.S. Nagar Mohali, and Punjab is about 6 Kms from Dera
Bassi Bus Stand and about 26 Kms from Chandigarh Bus Stand (U.T). It is
about 6 km from Chandigarh – Ambala Highway. The unit has 10 acres
existing land. No additional land is required for expansion. Location details
are given in Table 1.1. The total cost of the project is 4426 lacs.
6.2 Raw Materials
S.No. Raw
Materials
Source Mode of storage Mode of
Transport
1 Sulphur Oil Rifineries,
Panipat,Bhatinda
Designated storage
at plant premises
By Truck
2 Sulphuric Acid Captive Designated storage
at plant premises
Pipeline
3 Sulphur
Trioxide
Captive Designated storage
at plant premises
Pipeline
4 Liquid SO3 Captive Designated storage
at plant premises
Pipeline
5 Methanol NFL, GSFC Designated storage
at plant premises
By Tanker
6 Urea NFL, Market Designated storage
at plant premises
By Truck
7 Caustic Soda GSFC, SIEL,
Market
Designated storage
at plant premises
By Truck
6.3 Finished products & Installed Capacity
The units will manufactures following Product:
i. Sulphuric Acid
ii. Alum
iii. Oleum
85
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
iv. Sulphur Trioxide (SO3)
v. Di-Methyl Sulphate
vi. Sulphamic Acid
vii. Sodium Bi-sulphite
6.4 Installed Capacity:
The total installed capacity of the plant for the product will be as per details
given below:-
NAME OF PRODUCT EXISTING PROPOSED TOTAL
(TPD) (TPD) (TPD)
Sulphuric Acid = 75 125 200
Alum = 200 NIL 200
Oleum = NIL 70 70
Di-Methyl Sulphate = NIL 30 30
Sodium Bi-Sulphite = NIL 30 30
Sulphamic Acid = NIL 30 30
Liquid SO3 = NIL 30 30
The unit will operate for an effective period of 300 days in a year on three
shift basis of 8 hrs each.
6.5 Facilities at the Plant
The firm has already acquired 10 acres of land where part factory building
has been constructed and remaining building, and some other ancillary
structures are proposed to be constructed for expansion. It provides
adequate space for the following areas of working:-
1. Storage for raw material and finished goods.
2. Plant and Machinery
86
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
3. Store
4. Offices
5. Toilets
6. Water storage tanks
Open space will be landscaped and trees will be planted in due
course of time.
6.6 Machinery
Following machinery will be finally in position within the unit:
S.NO. EQUIPMENT NAME
1 Reaction Vessels
2 Condensers
3 Decanters
4 Cooling Tower
5 Storage Tanks
6 Steam Boiler (6 TPH)
6.7 Power
The requirement of Power for the unit is 699 KW which will be supplied
by PSPCL.
6.8 Water Supply
The water requirement of the unit will be met from ground water through existing
tube-well. The daily requirement of water for existing unit is 60 & after expansion
total water requirement will be about 245m3. About 85 KLD water will be required
87
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
in process & make up water required for cooling purpose will be 30KLD. Water
required for boiler will be 120KLD and for domestic purpose 10KLD. The
capacity of storage tank for cooling purpose is about 500.0m3. Another tank of
about 50 m3 has also been provided for firefighting which shall be kept always
full. Flow chart of water use is given in fig. 6.1
6.9 Manpower
The requirement of personnel for the proposed plant has been made
keeping in view of the following:
Technical concept of plant, including process control and
instrumentation.
Smooth and efficient operation of the plant.
Effective co-ordination between the various departments within
the plant.
Optimum organization will well defined and judicious job
distribution
Optimum utilization of different grades of workmen and
supervisory staff and
Maximum capacity of the facilities.
Unit will work on three shift basis and manpower needed will be about 100-125 persons.
88
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Figure: 6.1
WATER BALANCE FLOW DIAGRAM
(KLD)
WATER TANK
245
245
BOILER
120
120
COOLING
1500
1500
PROCESS
85
85
DOMESTIC
10
10
EVAPORATION
30
30
CONSUMTION
2
2
STP
8+2
8+2
RE-USE
1470
470
USE IN PROCESS
85
85
IRRIGATION
STEAM
GENERATION
GENERATION
BLOW DOWN
2
2
89
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
6.10 Manufacturing Process
1) Sulphuric Acid Manufacturing Process:
The manufacturing process for Sulphuric Acid as practiced in the plant at
the present time is described as under:
(a) Sulphur: Solid sulphur of 99% purity from sulphur storage yard is
charged by wheel-barrows to the sulphur melter-cum-settler. The molten
sulphur from the melter compartment flows to the sulphur settler
compartment. The melter has capacity equivalent to more than two days
consumption at the rated sulphur utilization. The melter chamber is
divided into three compartments for removal of any ash particles
(suspended solids) by settling. With an initial ash content of 0.2% in the
dirty molten sulphur, the ash content in the sulphur in the last compartment
of sulphur settler will not exceed 0.02% (200ppm).
From the last pumping compartment molten sulphur at about 1350C. is
pumped by means of one of the submerged centrifugal sulphur pumps to
the sulphur burner. The molten sulphur is pumped to the burner through a
steam jacketed and insulated pipe line and is controlled by a flow
regulating valve. The sulphur burner is of a horizontal type lined with
refractory and insulating material. The combustion of molten sulphur is
fully completed in the burner.
(b) Air and Gas System: The combustion air for burning of the
sulphur and for conversion of SO2 to SO3 is provided by the air blower via
the drying chamber. The air blower after the filtration of air on its suction
side forces clean air through a drying tower where 98.4% sulphuric acid is
circulated. The filtered and dried air goes to the sulphur burner.
90
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
The gases leaving the sulphur burner have around 11% SO2 at a
temperature of around 980 deg. C. These gases pass through waste heat
boiler No. 1 where saturated steam is produced at a pressure of about
32kg/cm2. The waste heat boiler no. 1 and super heater are designed
according to the process requirement and the temperature control of the
outlet gases is achieved through by-passing of a part of the hot gases
leaving the burner through a refractory lined duct line fitted with heat
resisting valve. It is thus possible to control the temperature of the gases
entering the first bed of the converter at the desired level.
Before entering the converter the gases pass through a special type of pad
bed type HGF filter which removes minor quantities of dust which might
reach this point. The filter is loaded with crushed and cleaned filter media
and is completely insulated. The gases leaving the HGF filter enter the first
bed of the converter at around 430 deg. C and come out at around 600 deg.
C. Vanadium pent oxide (V205) catalyst is used for the conversion of SO2
to SO3. These gases are cooled in a waste heat boiler No. 2 where steam is
raised at around 32 kg/cm2 and superheated to 370 deg. C. For proper
control of temperature, gas entering the second bed of the converter at
around 525 deg. C. is cooled to around 440 deg. C before entering the third
pass by passing the gas on the tube side of the hot heat exchanger which in
turn heats the gases coming from the cold heat exchanger. A by-pass valve
is provided on the tube side of the hot heat exchanger for proper control of
the gases entering the third bed of the converter. The gases come out of the
third bed of the converter at around 4650 C. are cooled on the tube side of
the cold heat exchanger to a temperature of around 2500 C which after
further cooling enter the interpass absorption tower where SO3 is absorbed
by means of sulphuric acid (98.4%) and the remaining gases coming out of
91
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
the interpass absorption tower at about 700 C are first heated on the shell
side of cold heat exchanger where the temperature is raised to around 3300
C. the gases then pass through the shell side of the hot heat exchanger
where the temperature is raised to around 425 deg. C. before entering the
fourth bed of the converter. For proper control of temperature of the gases
entering the fourth bed of the converter, a by-pass on the tube side of the
cold heat exchanger is provided.
The fourth bed of catalyst is the largest of all the beds. The relative higher
contact time (lower space velocity) with negligible initial SO3
concentration causes a very high deg. of SO2 conversion to SO3. The
overall conversion of SO2 to SO3 obtain in the converter is more than
99.7%. The gasses pass through an economizer where they are cooled to
around 200 deg. C. These gases after further cooling enter the final
absorption tower then SO3 in the gases gets absorbed in the tower. The
remain gases containing mostly N2 (93%) and O2 (7%) is passes through
demister and are vented through the stack. The condition is of operation
are controlled in such a manner that this remaining gases escaping through
the chimney are kept as per MINAS standard.
A caustic alkali scrubber has been installed before the vent to chimney, for
absorbing any excessive quantity of unconverted SO2 gas that may
otherwise be released during the start-up for shutdown of such units as
well as during any plant disturbances.
(c) Acid System: 98.4% sulphuric acid is circulated in the air drying
tower, interpass absorption tower and final absorption tower. This ensures
optimum drying in case of drying tower and maximum absorption
efficiency of SO3 in the absorption towers. All the towers have common
92
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
acid pump tank. The air drying tower is used for drying of air coming from
the main air blower so that the moisture content in the dried air is removed
as per the process requirements. Interpass absorption tower removes SO2
coming from the third bed of the converter so that the gases entering the
fourth and final bed is free of SO3. This enhances the conversion of SO2 to
SO3 in such a way that the exhaust gases coming from the final absorption
tower are free of SO2.
The circulating acid is collected in a common acid pump tank. The acid
strength in the pump tank is controlled automatically by feeding the
required quantity of water through automatic control valve. The acid pump
tank is fitted with a vertical submerged acid circulation pump which feeds
acid to the towers via respective acid coolers. These acid coolers cool the
acid before feeding the towers. The acid is cooled by using sprays over
trombone type coolers, fed with circulation cooling water. The tapping for
the product acid is taken from the outlet of the acid coolers.
93
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Fig.6.2
MANUFACTURING PROCESS
94
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
2) Oleum:
Oleum is a dense colorless liquid which is formed by absorbing sulphur
trioxide gas in sulphuric acid. Oleum reacts like a mixture of sulphur
trioxide and Sulphuric acid but contains Pyro-sulphuric Acid (H2S2O7), the
composition of which corresponds to 45% sulphur trioxide. The sulphur
Trioxide gas is to be taken after the 3rd pass of converter of existing
Sulphuric acid plant to the Oleum absorption Tower from the bottom &
concentrated 98.4% Sulphuric Acid is to be fed from the top of the Oleum
absorption tower. The feed of sulphuric acid in the Oleum absorption
tower is to be maintained through Rota Meter, Oleum strength Monitor &
continue circulation of Oleum in the absorption tower. During the proper
Mixing/absorption of SO3 gas with H2SO4, the temperature will also
increased with exothermic reaction, to cool down the Oleum and maintain
the proper required temperature, the Oleum is to be cooled through Plate /
Shell type Oleum cooler.
3) Sulphur Trioxide (Liquid):
The Oleum Liquid is to be fed to SO3 Generator through Oleum Heater.
The evaporation with the help of steam is to be achieved to get the pure
gaseous vapours, which will be condensed in the SO3 condenser. The cold
water will be fed to SO3 condenser to get the proper production of liquid
sulphur trioxide & which will be stored in the jacketed Storage Tanks. The
liquid sulphur trioxide (24%) SO3 will be supplied to DMS plant from
these tanks only.
95
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Fig.6.2
MANUFACTURING PROCESS
96
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
4) Di-Methyl-Sulphate
1. Methanol is vaporized & the pre-heated Vapors are fed continuously in a
Catalyst Bed Reactor (Temp 240 to 250oc) to convert the methanol into Di-
Methyl-Ether (DME).
2. Di-Methyl-Ether thus formed is Sulphonated with Liquid SO3 to get crude
Di-Methyl-Sulphate (DMS) which is further purified by Vacuum
distillation to get pure DMS.
REACTION:
CAT
1. 2CH3OH > CH3OCH3+H2O
2. CH3OCH3+SO3 > (CH3)2 SO4 {DMS}
3. Methanol is pumped from main storage tank continuously into methanol
vaporizer, vapors of methanol is passed thru two nos. heat exchangers to
superheat the methanol vapors which then fed continuously into catalytic
reactor containing alumina catalyst temp. of 250-260o C. is maintained in
the reactor for conversion of methanol to Di-Methyl-Ether, unconverted
methanol is 15-20%. This DME+UN converted methanol +water of
reaction is taken into stripping col. To get pure DME vapors, methanol +
water mix. Is fed to methanol recovery col. To get pure methanol which is
reused?
4. DME from DME STRIPPING COL. Is fed into a sulphonater where it
reacts with liq. SO3 to get crude DMS.
5. Crude DMS from storage tank is fed into DMS distillation unit
continuously to get pure DMS which is stored in storage tanks as finished
product.
97
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
6. Bottom residue of distillation kettle containing some DMS and spent acid is
taken into another DMS recovery unit to recover left over DMS, spent acid
& small quantity of water is to be used alum plant and for cooling in
sulphuric acid plant.
Fig.6.2
MANUFACTURING PROCESS
98
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
5) Sulphamic Acid (SMA)
Chemical Reaction:
NH2CO2 + H2SO4 = 2NH3SO3H + CO2
(Urea + Sulphuric Acid) = (SMA)
98%
Urea is reacted with mixture of 98% Sulphuric Acid & 65% Oleum at
elevated temp. SMA thus formed is separated by diluting the reaction mass
& then filtering the slurry of SMA Thus formed wet cake of SMA is dried
and packed.
CO2 formed during reactions is vented out after scrubbing. Spent dilute
Sulphuric Acid is used in the manufacture of Alum etc.
99
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Fig.6.2
MANUFACTURING PROCESS
6) Sodium Bi-Sulphite:-
Sulphur dioxide gas is purged in a Reactor containing Caustic solution
under agitating and circulation. Reaction takes place and crystallization
started after saturation of Mother Liquor. Then entire material is
centrifuged to separate solid wet cake of Sodium bi-sulphite which is
dried in Flash Dryer get dry Sodium bi-sulphite pure product. The Mother
liquor collected and recycled to prepare next batch.
100
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Chemical Reaction:-
NaOH + SO2 NaHSO3
Fig.6.2
MANUFACTURING PROCESS
101
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
OTHER FEATURES:
The plant would incorporate the most modern control system
using the latest Pollution Control System
Cooling water circuit is close circuited, whereby ensuring no
generation of waste water
The process, selected envisages re-cycling all the material
collected in the pollution control equipment whereby
ensuring no generation of solid waste.
The plant lay out is so arranged that the major production
units are laid in a straight line whereby minimizing / avoiding
the various transfer points.
Capacity of the units is planned so as to minimize the number
of equipment.
6.11 Waste Handling
6.11.1 Liquid waste
There will be no generation of waste from manufacturing process. The domestic
effluent shall be treated through STP. The domestic treated water will be used
for plantation.
6.11.2 Solid waste
Solid wastes in the unit are from the following sources.
i) Solids from APCD.
ii) Ash from the Boiler furnace
102
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Solids from APCD will be disposed off at designated TSDF Site. Ash from
boiler will be used for land fill site.
6.11.3 Hazardous waste
The Hazardous wastes generated from the unit are Sulphur Sludge, Catalyst dust
and used DG Set oils. The Sulphur sludge & Catalyst Dust will be sent to TSDF
site Nimbuan Dera Bassi for final disposal & used oil from D.G. Set shall be
sold to recyclers. There are no other hazardous wastes.
6.12 Pollution Control Measures
The main sources of likely pollution from the unit & measures
adopted for their control are discussed as under:
6.12.1 Air Pollution
There are 3 No. stacks already exist in the industry and one no.
more stack will be installed on boiler. The existing stacks are
attached with alum plant, and with DG sets. The fuel used for boiler
will be biomass. Diesel is used for DG set. The main pollutants are
particulate matter and gaseous emissions. Process flow chart is given
in Figure 6.3
6.12.2 Water Pollution
It is existing unit. Water is already used in the manufacturing process
as well as domestic purpose. After expansion the consumption of
water will be increased. Waste water from the toilets will be treated
through septic tank. The domestic effluent shall mainly be used for
plantation.
103
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Fig: 6.3
PROCESS FLOW CHART OF AIR POLLUTION CONTROL SYSTEM
Boiler
Duct
Multi-cyclone
ID Fan
Stack
104
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
6.12.3 Noise Pollution
There is some noise producing machineries such, as ID Fan, Blowers
etc. All these machines are spread at different places within the
covered sheds. Thus no noise of significant level shall go outside the
working area which may disturb the general noise environment. DG
set installed shall be noise free & with canopy.
105
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-7.0
ENVIRONMENTAL IMPACT ASSESSMENT
7.1 Present Environment:
Various Environment factors as existing in the project area which
possibly could be affected by the activities have been assessed &
identified as below:
i) Ambient Air
ii) Water Quality
iii) Noise
iv) Land use pattern
v) Soil and Agricultural
vi) Demography and socio-economic pattern.
7.2 Probable Impact on Environment:
The above factors will be checked after the implementation of the
project to cross check the probable impact discussed hereunder and
remedial measures taken wherever necessary. Broadly the impacts
may be classified in two categories as under:-
i) Short term - during construction/development stage
ii) Long term - during operational stage.
Both these categories have been considered while predicting and
evaluating the impacts as given herein after:-
106
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
7.3 Development Stage: - (Short Term)
This is a construction phase of the project and the impacts are
temporary due to construction related activities which are as under:-
i) Air Environment:
There is no point source of Air Pollution. The only source will be
the dust generation due to excavation, construction and plying of
vehicles within unit. Some emission may be expected from vehicles
plying in the area for transportation of material etc. Kerosene oil
shall be provided to the labour so that they do not burn wood for
cooking etc.
ii) Water Environment :
Requirement of water during construction activity will be about 1.0
m3/day and there will be no waste discharge as the same will be used
completely. However, during monsoon some malba etc may get
washed due to run off from the site. There is a natural ‘nallah’ near
the land which takes the entire run off from the area.
Labour during construction is not very large. Hardly about 10
persons may be working daily on an average who may be using
water for drinking and bathing etc. Toilet facilities with septic tank
will be provided to labour @ 1 toilet for 20 persons who will be used
by the labour.
In view of this there is no likelihood of any significant impact on the
general environment of water in the area.
107
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
iii) Noise Environment:
Some noise may be expected from the working of the machinery for
replacement and repair purposes and movement of vehicles. Steps
will be taken to reduce its effect by resorting to staggering of various
operations. Even otherwise since there will not be any large scale
machinery; the activity is not likely to have any significant effect on
the overall noise environment.
iv) Land Environment:
It is an approved FEZ area; the land at site is leveled as such no
leveling is required. Natural drainage will not be disturbed. Solid
waste from construction activities will be used within the premises
under roads & refilling. There will not be any significant impact on
land in general.
v) Socio Economic:
The project does not involve any displacement of population or
rehabilitation of any kind. Rather it will provide employment to local
people in the shape of additional man power required for the units, &
will and boost the economy of the area. It will have some positive
impact, although not to a large extent.
7.4 Operational Stage: - (Long Term)
After completion, when the unit starts production, the operational
impacts on the various parameters are considered as under:-
108
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
i) Air Environment:
There is the source of likely pollution which is PM emission from
the Boiler furnaces & mist from Sulphuric Acid plant/Alum Plant.
All the processes are closed circuits as such emissions to the open
atmosphere will be minimum. However, APCD, Multi –Cyclone will
be provided on boiler. Alkali Scrubber has already been installed on
Sulphuric Acid/Alum plant to neutralize Acid mist.
ii) Water Environment:
The existing domestic waste water discharge is 8.0m3/day. After
expansion waste water discharge will be 10.0m3/day and same will
be treated through STP. There is no other discharge of water from
industrial process. Treated domestic water will be discharged on
land for irrigation. Treated effluent will not be thrown in any water
body. Thus water environment is not likely to be affected. Further,
ground water will be balanced through recharge by rain water
harvesting from the roof top to the extent about 12960m3/annum
through recharge wells. Thus pressure on underground water will be
reduced.
iii) Land Environment:
It is an existing unit already in production. No additional land will
required for expansion. The unit is located in Free Enterprises Zone.
Thus there will not be any significant adverse effect on the existing
general land environment with the coming up of the project.
109
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
iv) Noise Environment:
There will be no noise producing machinery or equipment except ID
fans & Blower etc. which will be placed at different places within
the closed sheds causing least disturbance in the area. There is no
likelihood of any significant change in noise environment.
v) Socio Economic Pattern
The project will provide employment to local people in the field of
running plants and maintenance of machinery, APCD & security etc.
Thus it will have positive effect on the employment potential in the
area.
110
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-8.0
ENVIRONMENT MANAGEMENT PLAN
8.1 General
Environment Management Plan (E.M.P) in a project is prepared to mitigate
the possible adverse effect of various activities on the existing
environmental factors, during construction as well as in operational stages,
to avoid their deterioration, if any. It is desirable that necessary steps are
taken right from the beginning of the project to be more effective. As a
social and moral obligation on the part of everybody it becomes our
bounden duty to leave our environment to the next generation in a state at
least what we inherited from our ancestors, if not in a better condition.
E.M.P. for this project has been prepared keeping in view the existing
conditions and likely changes which may occur due to the proposed project.
The implementation and monitoring of different control measures have also
been covered. These are discussed as under:-
8.2 Air Environment
During construction stage water will be sprinkled on the soil to avoid
dust generation, if any.
The debris and unused construction malba shall be removed
immediately for recycling, if any, or for land fill.
Cyclone & Alkali Scrubber shall be provided to arrest PM from flue
gases to keep it within permissible limits.
All vehicles for service activities at the project site shall be checked
for vehicular emission.
The agencies will be asked to keep them within prescribed limits.
They will also be asked to maintain them properly.
111
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Tree plantation shall be resorted to for further improving the air
environment in general and minimize noise levels, if any.
8.2.1 Flue Gas Emission/Fugitive Emission Control
The volatile matters getting released from the storage tanks, process piping,
reactors, fuel storage & combustion will be handled by various preventive
measures mentioned below:
1. Coal during combustion is completely burnt by providing sufficient air
for combustion and is released to atmosphere through high-rise stack.
Keeping in mind the CPCB guideline for controlling flue gas/fugitive
emission following arrangement will been done.
2. Each & Every process emission will be passed through scrubber and
finally released in to atmosphere through adequately designed stack height.
3. Preventive maintenance will be done so as to prevent any leakage and
spillage and thereby reducing the fugitive emission sources.
4. Storage tank will be provided with level gauge, dyke wall, automated
loading and unloading for the chemicals to avoid human contact.
5. All storage tanks will be designed and placed according to the Industrial
Safety & Health Department.
8.3 Water Environment:
Water shall be drawn from existing tube well.
During construction toilet facilities shall be provided to labour with
septic tank. Finally, waste water from the toilets shall be taken to septic
tank through underground delivery system and treated to tertiary level.
The treated water will be discharged on land for irrigation within the
premises. It will not be thrown outside either on land or in any water body.
Roof top rain water shall be harvested and used for ground water
recharge to minimize effect of withdrawal of water from the underground.
112
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
8.4 Land Environment:
To avoid erosion of the top soil the development is planned in the
shortest possible time and land-clearing activity shall be kept to the
absolute minimum by working at the specific sites one by one where
construction is to take place so as to increase detention and infiltration.
Natural waterways/drainage pattern shall be maintained by providing
culverts where needed.
The requirements of sand and aggregates for the construction works
will be met through venders. The land use is thus so planned that there is
minimum adverse impact.
8.5 Solid Waste:
The solid waste generated from the construction activities shall be
effectively recycled within the project.
The other solid wastes from the APCD shall be dumped in a
dumping pit of R.C.C. and disposed off in the designated land fill places.
8.6 Noise Environment
During Construction stage “NO HORN” signs will be displayed at
prominent places.
The drivers shall be directed not to blow horn unnecessarily.
Vehicle owners will be asked to maintain them in proper condition.
During operational stage noise creating machinery such as blower, ID
Fans etc will be housed different places within closed sheds so as not to
disturb the noise level in the area.
113
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
8.7 Green Belt:
The main objective of the green belt is to provide a barrier between the
source of pollution and the surrounding areas.
The green belt helps to capture the fugitive emission and to attenuate
the noise generated, apart from improving the aesthetics.
Development of green belt and other forms of greenery shall also
prevent soil erosion and washing away of topsoil besides helping in
stabilizing the functional ecosystem and further, to make the climate more
conducive and to restore water balance.
It is planned that the selected plants will be grown as per normal
horticultural (or forestry) practice and authorities responsible for plantation
will also make sure that adequate provision for watering and protection of
the saplings exists at site.
Species of trees shall be selected in consultation with the forest
Department officers. In all about 200 trees & shrubs are proposed to be
planted within the unit premises.
114
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-9.0
ENVIRONMENT MONITORING PROGRAMME
9.1 Regular monitoring of all significant environmental parameters is essential
to check the compliance status vis-à-vis the environmental laws and
regulation. The objectives of the monitoring will be as follows:
To verify the results of the Impact Assessment Study with respect to the
proposed projects.
To study the trend of concentrated values of the parameters, which have
been identified as critical and then planning the mitigating measures.
To check and assess the efficacy of pollution control equipment.
To ensure that any additional parameters, other than those identified in
the impact, do not turn critical after the commissioning of proposed
project.
9.2 To implement the EMP, a structured Environment Management Cell
(EMC) interwoven with the existing management system will be created.
EMC will undertake regular monitoring of the environment and conduct
yearly audit of the environmental performance during the construction of
the project. It will also check that the stipulated measures are being
satisfactorily implemented and operated. It shall also co-ordinate with local
authorities to see that all environmental measures are well coordinated.
9.3 A comprehensive Environmental Monitoring Program that has been
prepared for the purpose of implementation in the proposed Industrial unit
by the EMC is described below:
115
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
The ambient Air quality shall be monitored at project site and to
upstream and downstream locations once every quarter for RSPM,
SPM, NOx & SO2, and CO levels during the construction phase and
operational phase. The ambient noise levels shall also be monitored
once every six months.
The vehicles shall be checked for PUC once every quarter during the
development period and records shall be maintained.
Groundwater quality of the Tube-wells in site area will be regularly
monitored preferably once in a quarter.
Air Pollution Control System shall be provided and weekly monitoring
of the parameters shall be undertaken. In addition monitoring shall be
got done from an independent agency as laid down by State Pollution
Control Board.
All the above observations will be compiled and documented by the EMC
to serve the following purposes.
Identification of any environmental problems that are occurring in the
area.
Initiating or providing solution to those problems through designated
channels and verification of the implementation status.
Controlling activities inside the project, until the environmental problem
has been corrected.
Suitably responding to emergency situations.
9.4 Environment Management Cell:
The Environment Management Cell shall include:
Representative of Management (Head of Environment Cell)
Process Incharge
116
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Incharge Maintenance Department
A representative of Environmental Consultants
The cell shall be constituted immediately at the start of the project so that
appropriate actions to protect the Environment are taken from the very beginning.
All actions taken by the cell shall be documented.
117
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-10.0
OCCUPATIONAL HEALTH
10.1 General
Occupational Health basically relates to protecting the Industrial Workers from the
ill effects of various parameters at the work place or in other words,” Occupational
Environment”. It is synonymous with `Preventive Medicine’ as both aim at
prevention of diseases & physical discomfort. This in the long run increases their
efficiency and ultimately results in better production. Thus, both the workers and
the industrialists are gainers.
10.2 Occupational Environment
Occupational Environment includes external conditions and influences which
prevail at the place of work and which have a bearing on the health of workers.
These are of three type’s i.e.
a) Man and physical, chemical & biological agents.
(b) Man and Machine
(c) Man & Man.
Details of these factors are as under:-
10.2.1 Man & Physical, Chemical & Biological Agents
i) Physical Agents: Physical factors which affect the health of the workers
adversely are heat & cold, humidity, air movement, light, noise and vibration.
These factors act in different ways on the health and efficiency of the workers,
singly or in different combinations.
118
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
ii) Chemical Agents: These comprise chemicals, toxic dust and gases which are
potential hazardous to the health of the workers.
iii) Biological Agents: These consist of viral, bacterial and parasitic agents
who may result from close contact with animals or their products, contaminated
water, soil or food.
10.2.2 Man and Machine
Every industry or factory uses machines driven by power to improve production.
Unguarded machines, protruding & moving parts, lack of safety measures are the
major causes of the accidents in the industries.
10.2.3 Man and Man
These factors include human relationship among workers themselves on the one
hand and those in authority over them on the other. In case of discord in either of
them, the health of the workers & efficiency suffers and may result in sleep &
mental disorders.
10.3 Occupational Hazards
Keeping in view the above environmental factors, the workers may be exposed to
following types of hazards depending upon his occupation.
(a) Physical hazards
(b) Chemical hazards
(c) Mechanical hazards
(d) Biological hazards
These are discussed as under:-
119
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
(a) Physical hazards
(i) Heat: Common physical hazard in most of the industries is heat. The direct
affects of heat exposure are burns, heat exhortations, heat strokes and heat cramps.
The indirect effects are decreased efficiency, increased fatigue etc. Radiant heat
from the ovens & furnaces is the main problem in some of the industries. Thus for
gainful work a reasonable temperature has to be maintained at each work place.
Normally, temperatures between 70° to 80° F are considered as the Comfort Zone
in this country and temperature above 80° F causes discomfort.
(ii) Light: In some of the industries, the workers are exposed to poor
illumination. This causes eye-strain, headache, eye pain and eye fatigue etc.
Similarly, excessive brightness or glare causes discomfort, annoyance & visual
fatigue. Intense direct glare may also result in blurring of vision and lead to
accidents.
(iii) Noise: Noise is a big health hazards in many industries. Its effects are of
two types:-
(a) Auditory effects – which result in temporary or permanent hear loss.
(b) Non-Auditory effects like nervousness, fatigue, inference with
communication by speech, decreased efficiency and annoyance.
(iv) Vibration: In some heavy industries where pneumatic tools such as drills
and hammers are used, vibration affects the hands & arms. With long exposure
fine blood vessels of the fingers may become increasingly sensitive. Joints of the
hands limbs & shoulders can be affected.
120
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
(b) Chemical hazards: In almost all industries chemicals are used at one
place or the other. They affect the health of workers in three ways depending on
the duration and quantum of exposure as under:-
(i) Local Action
(ii) Inhalation
(ii) Ingestion
(c) Mechanical hazards: Mechanical hazards in the Industries centre round
machinery, protruding and moving parts. With proper planning these can be taken
care of.
(d) Biological hazards: These hazards occur in Units dealing with animals
and animal products like hair, wool, hides etc. These cause fungal infection and
some others also.
10.4 Mitigation Measures:
The main aim of occupational health is the promotion & maintenance of the
highest degree of physical, mental and social well being of workers in all
occupations. Thus, different measures are required to control ill-effects of
the various activities in the industries. Following measures therefore, are
required to be taken in this respect.
10.4.1 Environmental Sanitation:
(i) Water supply: A sufficient supply of whole-some drinking water is
one of the basic requirements in all Industrial Units. Installation of drinking
water fountains or taps should be provided at convenient points.
121
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
(ii) Toilets: There should be sufficient number of latrines & urinals, separate
for males & females, preferably at the rate of 1 Toilet for 20 workers.
(iii) Sufficient space: Sufficient floor space & cubic space should be
provided to prevent not only the respiratory infections but to ensure a
comfortable working environment. A provision of 500 cft. Of space per
worker is considered comfortable.
10.4.2 Physical Agents:
(i) Heat: Ill-effects of high temperature can be prevented by observing
following precautions:-
(a) Replacement of water: Persons working under condition of high
temperature and humidity should drink cold water frequently, preferably
one litre per hour.
(b) Regularization of work: The duration of exposure to hot
environment should be cut-down. Persons should be rotated on such duties.
(c) Clothing: Clothing should be light, loose and of light colour.
(d) Protective Devices: Protective goggles, shields and helmets should
be encouraged.
(e) Work Environment: Temperature and humidity in working
environment may be controlled by proper ventilation & air-conditioning.
(ii) Humidity: Although humidity does not directly affect the workers
physical health it causes discomfort as the comfortable value ranges from 30% to
65%. Anything above or below these limits is unpleasing. Humidity can be
122
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
controlled through proper ventilation in the work place. 4 to 6 air changes per
hour are considered appropriate to make it a comfort zone.
(iii) Light:
(a) Sufficiency: Good light is essential for efficient functioning. Poor
lighting causes strain which leads to eye fatigue & loss of efficiency.
Illumination of 15 to 20 foot candles is an accepted basic norm.
(b) Distribution: Distribution of light should be uniform having the same
intensity over the whole area of work; otherwise it will strain the eyes and
affect visual acuity.
(c) Absence of glare: Glare has an excessive contrast. Direct glare from
a light source should be avoided & camouflaged, otherwise it causes
annoyance.
(d) Steadiness: The source of light should be constant and not flickering.
(e) Colour of light: Since day light has a soothing affect on the eye,
artificial light, as far as possibly, be approximately of day light.
(iv) Noise: Noise is defined as unwanted sound or more precisely as “wrong
sound, in wrong place, at the wrong time”. It has now become a very important
stress factor in the environment of man. Acceptable norms in industries may be 40
to 60 dBA. Annoyance can be controlled as under:-
- By segregating the noisy machines, application of Mufflers or other noise
reducers to machines.
- Transmission of noise can be controlled by applying enclosures and
covering the room walls with sound absorbing materials.
123
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
- Protection of workers can be achieved by providing ear plugs & air muffs.
Employees should be regularly rotated from noisy areas to comparatively
calm areas in the Factories.
10.4.3 Chemical Hazards: Chemical agents act in 3 ways as under:-
i) Local action: Some chemicals which come directly in contact with skin
cause, irritation and other problems. Hand gloves can be used where there is
possibility of the chemicals coming in contact with hands.
(ii) Inhalation: Dust, Gases & Metals and their compounds are the biggest
health hazards in the industry. They are absorbed in the body through
inhalation. Although, dust particles larger than 10 Microns settle down in the
air immediately but smaller ones, less than 5 Microns, are inhaled & directly
go into lungs. This is called respirable dust. To avoid their effect face masks
should be provided to the workers at vulnerable places.
(iii) Ingestion: Some chemical substances like Lead, Mercury, Arsenic and Zink
etc. may be swallowed in minute amounts through contaminated hands, food
and cigarettes. Although these are mostly excreted, but a small portion may
reach the blood stream. Use of hand gloves in such areas should be used
extensively.
10.4.4 Mechanical Hazards: These are related to the machinery and other
equipment having moving parts. Following precautions will be necessary for such
hazards.
(i) Proper guards should be provided around of moving parts, so that
accidental touching by the workers is avoided.
(ii) Sufficient space should be available around the machines for the workers to
move freely. All machines should be properly earthed to avoid any
electrical shocks.
124
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
(iii) Safety Boots & Belts should be provided to workers where necessary to
save damage due to accidents.
10.4.5 Biological Hazards: These hazards occur mostly in industries dealing
with the animals and animal products like hair, wool and hides etc. Hand gloves,
face masks, and gum boots can be provided to all the workers to save them from
the infective and parasitic agents.
10.5 Safety Precautions & Suggestions:-
To protect the health of the workers in an Industry, following measures shall
be taken:-
i) Proper housing shall be provided to workers in large Units for comfortable
& stress free living.
ii) Personal Protection Equipment (PPE) shall be provided to workers, such as
Earplugs, Gloves, Eye Goggles, Helmets, Gum/ Safety Boots & Safety
Belts etc.
iii) Clean & cool drinking water shall be available to workers near work places
especially near hot spots.
iv) Proper ventilation shall be provided in work place, specially where heat is
generated.
v) Employees working near furnaces & other hot areas shall be rotated to
minimize exposure time.
vi) Acoustics shall be provided in rooms where noise creating machines work.
vii) All moving & protruding parts of machinery shall be guarded, so those
workers do not come in contact with them.
125
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
viii) Proper lighting shall be provided in the work place. Glares will be avoided.
ix) Exhaust fans & canopy hoods shall be provided in the areas where dust &
other gases are expected from the operations.
x) First Aid Box shall be kept at prominent place to be used in emergent
cases.
xi) All firefighting equipment shall be frequently checked to see that they are
effective always.
xii) Frequent health check-up of the workers shall be done on regular basis and
the results documented. Timely medical treatment shall be provided to
affected person, if any.
126
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER-11.0
CORPORATE SOCIAL RESPONSIBILITY AND
ENVIRONEMNT POLICY
11.1 Corporate social responsibility is the commitment of businesses to contribute to
sustainable economic development by working with the employees, their families,
local community & society at large to improve their lives in ways that are good for
business as well as overall development. It is a voluntary activity of a company
that supports social interests & environmental issues. It is a principle through
which the business houses contribute to the welfare of the society & not only
maximize their profits. CSR, in fact, is about business giving back to the society.
Some of the CSR related activities are summarized as follows:-
(i) Sustainable livelihood creation – Promoting micro entrepreneurship through
skills development, market linkages & women’s economic empowerment.
(ii) Education – Setting up schools, colleges curriculum development, teacher
training & community involvement.
(iii) Health care – Healthcare awareness camps & setting up hospitals &
dispensaries in areas where these are deficient and arranging equipment needed
by the patients if any. Providing free treatment to poor patients in Hospitals,
specially for life threatening diseases, as per recommendation of the Hospital
authorities.
(iv) Community initiative – Need based services, project/programs for
disadvantage youth, illiterate adults, socially & economically deprived sections
of the society & women self help groups.
(v) Rural development – Water management, housing, sheds, waste land,
agriculture & animal husbandry, genetic improvement & model village
development with all basic amenities.
(vi) Infrastructure developments – Roads, drinking water & sanitation etc.
127
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Keeping in view the above the company proposes to set aside 5% of the cost of the
Project for activities under CSR and creates a corpus for the same. The activities
shall be maintained from the interest of the corpus throughout the life of the
project. Following activities shall be taken up under this programme.
(5% of 4426 Lakhs = 2.213 Cr 2 Cr interest @ 9%= 20 lacs)
Table- 11.1
DETAIL OF CSR AND ITS TIME BOUND IMPLEMENTATION
Over a Period of 15 years
S.No. Name of the Village Welfare action Plan Estimated
Cost (Rs
Lacs)
1.
Behra, Bhagwanpur,
Rampur Sainian,
Khurhanwala
Environmental education cum
awareness campaign through
audio/video in each of these villages
and High schools of these villages
once a year.
1.0
Health check up camps including
vision, audiometry, spirometry,
respiratory disorders and free
medicines whenever required once a
year, also providing & running a free
Dispensary in Village Behra
1.5
Sewing machines, ceiling fans and
tricycles to needy poor and
handicapped once in five years.
1.5
Purified drinking water and separate
toilets in the schools and their upkeep. 2.0
Distribute uniforms, books & bags to
students in the school specially from
weaker section.
2.0
2. Recognized Government
Hospitals
Free medical treatment to very poor
patients as recommended by the
Hospitals whenever required.
12.0
Total
20.0
128
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
11.2 ENVIRONMENTAL POLICY
11.2.1 The Company is very much oblivious of its responsibility in protecting the
Environment. Thus various mitigation measures as given in the report shall
be taken-up and effort will be made to nullify the effect of the Project, on
the Environment, if any. Any action or effort remains incomplete, if it is not
monitored properly at regular intervals and corrective measures taken,
wherever necessary. Regular monitoring has thus, been provided.
11.2.2 The Company has a well defined policy to keep the Environment clean.
The Board of Directors has decided that all effective steps shall be taken to
prevent deterioration of the existing Environment. They have formed an
Environment Committee committed for this cause.
The Committee will consist of following persons:-
(i) General Manager
(ii) Manager Operations
(iii) Maintenance Engineer
(iv) Supervisor - Incharge of STP & APCD
11.2.3 Monitoring and Responsibilities:
(a) For Water Environment
(i) The supervisor shall visit and check the devices daily. He will see
that the STP is working properly and flow measurements are
recorded properly in a register.
(ii) The effluent from the STP shall be got checked by him in the
Laboratory once a week. Any parameter going out of the prescribed
limits will be reported to the General Manager for taking corrective
action. He will pursue the matter at personal level to bring the
parameters within permissible limits.
129
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
(iii) The General Manager will keep in touch with the Environmental
Consultant and seek their guidance for corrective action as and when
required.
(iv) The Committee shall meet once every month to ensure
implementation of the programme.
(v) The General Manager will bring to the notice of the Managing
Director any further action to be taken to ensure environmental
requirements. The Managing Director will report to the Board of
Directors, the action taken to set right deficiency, if any.
(b) For Air Environment
(i) The supervisor will ensure that the APCD provided are functional at
all times. Air emissions from the stack will be got checked by him
once a month from a Laboratory to see that the limits of the various
parameters are not exceeded. In case of any deviation noticed, he
will inform the General Manager to take corrective action.
(ii) The supervisor will ensure that the water is sprinkled on roads
whenever transportation of material is to be done to and from the
factory premises in trucks.
(iii) The General Manager will ensure that all the vehicles coming to the
premises have PUC Certificates and they do not blow horn
unnecessarily within the premises.
(iv) The Manager Operations will ensure that the transportation of raw-
materials and finished goods is done in trucks covered with
Tarpaulins.
11.4 The Board of Directors will discuss at frequent intervals & see that the
environmental policy laid-down by them, is followed meticulously by all persons
in the Unit and the Environment is within the prescribed limits.
130
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER- 12.0
FIRE FIGHTING
12.1 Introduction:
The unit is to come up in an area, which is an approved Industrial Focal
Point. A number of Industrial units exist adjacent to this unit. It falls in
Group G-1 category of Industrial Building and in Fire Zone 2 as per NBC.
Fire is one of the major hazards in factories, specially dealing with inflammable
gases/materials. It is, therefore, necessary that adequate steps are taken to
immediately control fire and reduce damages. Time element is very important
in this case as such immediate action has to be taken.
12.2 Management of fire & other hazards
Industrial fires and explosions cause considerable damage to lives and
property besides impending productivity. This damage may extend to
neighboring areas. The fundamental approach governing fire safety
attempts shall be adopted to ensure that fires do not at all start in the first
place and should they occur, to restrain their spread by quick detection and
extinguishment.
12.3 Prevention of spread of fire:
Despite many precautions taken, fires do break out. Hence every factory
should have established measures to detect a fire and to attack it
immediately. Automatic fire detection has many advantages such as speed
and reliability and is recommended for warehouses, control
rooms/computer rooms and unoccupied areas with high fire hazard.
Depending on the nature of the occupancy and the hazard, a variety of
detection systems are available. They are activated by one of the effects of
fire such as temperature rise, smoke flame or heat and can be coupled to an
131
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
alarm system which would provide visual/audible alarms at designated
manned locations. They can also be designed to automatically actuate fire-
extinguishing systems. The selection/installation of the detection system
shall conform to the applicable National Standards.
12.4 Extinguishing Systems:
Equipment for firefighting shall be chosen with care and suited to the task.
Fires are classified depending on the materials involved and appropriate
extinguishing agents are also recommended. Different kinds of fire fighting
media are suggested as below:
Water
Water acts as a coolant, i.e. it reduces the temperature of the burning
product to a point below its fire point and hence extinguishes the fire.
Water should preferably be used as a fine spray or fog rather than a jet. This
enhances its cooling potential and prevents fire spread. Water should never
be used on water-reactive chemicals.
Dry Chemical Powders
They are generally effective on flammable solvents, aerosols, products
which react adversely with water and electrical fires.
Carbon Dioxide
This is effective on flammable solvents, products which react with water
and electrical wires.
Foam
A number of different types of foams are available commercially. Their
selection should be done after consulting the HSDS of different chemicals.
However, great skill is needed in using foams for effective results. The
classification of fire & recommendation are given in Table 11.1. The
extinguishing agents mentioned are applied to the fire using portable or
fixed appliances. To fight fires at their incipient stage, portable
132
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
extinguishers prove very useful. This type will be provided in adequate
numbers at appropriate locations and employees shall be thoroughly trained
in their use. Insurance regulations, the Factories Act, as well as the Bureau
of Indian Standard provide ample guidance & will be followed.
Underground water storage of 100 m3 shall be provided.
133
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
Table 12.1
Fires Classification & Extinguishing Media
Class of
fire
Description Extinguishing
medium
Indian Standard
A Fires involving ordinary
combustible materials, like
woods, paper textiles, etc.
where the cooling effect of
water is essential for the
extinction of fire
Water 934
940
6234
B. Fire in flammable liquids like
oils, solvents, petroleum
products, varnishes, paints
etc. where a blanketing
effects is essential
Foam
Carbon dioxide
Dry Chemical
933
2878
2171
4308
C Fires involving gaseous
substances under pressure
where it is necessary to dilute
the burning gas at a very fast
rate with an inert gas or
powder.
CO2 , Dry
Chemical Powder.
The best way to
extinguish such fires
is by stopping the
flow of fuel gas to the
fire. Container is kept
cool with water
spray.
2878
2171,4308
D Fires involving metals like
magnesium, aluminum, zinc,
potassium, etc. where the
burning metal is reactive to
water and which requires
special extinguishing media
or technique.
Special dry powders 2171
4861
134
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
12.5 Management Plan:
The task of accident and emergency control can be simplified and made
effective if pre-planned systems and procedures are available. Without
these, important matters may be overlooked at the time of an emergency.
Every management must survey the total operation to identify potential for
fire losses and develop an action plan to put the business back to normal
with minimum loss of time. A fire protection Manual should be prepared,
preferably in 3-parts. The first part should outline the fire risks in terms of
plant locations, equipment and facilities and indicate the ways in which
risks have been minimized. The Second part would set out operating
procedures, standards of fire protection established, maintenance of these
standards, action to be taken in the event of fire by every level of
management, responsibility for inspection and repair. It should also include
instructions for staff responsible for building services. The third part
should outline the training required for existing and new staff, the
inspection schedules and check lists, sources of additional information and
help.
To have effective control a Management Plan has been prepared to alert
and take care of the workers and staff of the unit, in case there is any
fire or other accident in the adjoining Industrial unit. That includes:
Identifying Emergency team Leader and his Deputy and Establishment
of Site Emergency Control Room (SECR).
Emergency teams
Emergency teams shall consist of 2 teams, Action Team A and a Non-
Action Team-B. Action team-A will consist of staff of maintenance
department, security supervisor etc. Non-Action team-B will consist of
135
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
people representative from the unit and other people in management
such as those looking after STP, APCS & water works etc. Team-A will
initiate action in case of emergency. Team-B will help team-A in
preparing to comply with specific instructions. A multi-channel network
shall connect site emergency control room to various district emergency
support centers, i.e. fire department, police department and hospitals and
automatically actuate fire-extinguishing systems. The
selection/installation of the detection system shall conform to the
applicable national standards. All other precautions as per NBC shall be
taken.
During non-emergencies this team A shall engage in following
activities:
1. Identification of hazards, interact with local office of Pollution
Control Board and Industry and find out which unit is using
hazardous chemicals or materials
2. Earmarking area for assembling during emergencies
3. Training programme for the staff on fire, first aid and evacuation
4. Identification of Hospitals
5. Identification and displaying emergency numbers and contacts
6. Displaying emergency symbols
7. Checking display of emergency information in storage area
8. Updating first aid emergency kit.
9. Updating fire control systems
10. Preparation and updating of standard operation procedures (SOP)
In case a staff member on duty spots any emergency and comes to know
about any fire or explosion in the industrial area or any gas leakage, he, as
136
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
per SOP, will go to the nearest emergency alarm station. He will also try his
best to find out about the exact location and nature of emergency from local
authorities. In accordance with the SOP the following activities will
immediately begin:
Team-A and Team-B will be activated
Announcements shall be made on the loudspeaker and workers will
be informed.
Necessary alarms shall be activated to direct the workers to the
emergency assembly area, if needed.
The external network of District Fire Station, Police and Hospital
shall be intimated.
The Emergency Supervisor shall also decide:
Whether the incident requires evacuation of workers.
Whether the workers to be kept indoors or to be evacuated and
assembled at predetermined site.
Whether district authorities are to be activated.
Once the emergency situation is under control, the advisory team will
return to SECR with their observations, report and submit the findings in
writing to Emergency Supervisor. Based on the report Emergency
Supervisor will communicate further directives and communicate
emergency and authorize step-by-step restoration of normal operation.
12.6 Alarm System during Disaster
On receiving the message of disaster from the site, the control room will
sound siren “wailing type” for 5 minutes. The message shall also be
broadcasted through Public Address System. On receiving the message of
emergency over, the alarm shall be sounded for 2 minutes. The features of
137
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
alarm system shall be explained to all during trainings to avoid any
confusion.
12.7 First Aid
First Aid shall be readily available and at the nearest place in case of any
emergency. First aid charts showing actions to be taken in a practice shall
be displayed prominently. Following equipment shall be provided.
First Aid Boxes
Stretchers/Wheel/Chairs
Fire Blankets
Emergency Showers & Eye wash facilities
Emergency lighting
Arrangement shall be made with some local Doctor or Clinic for immediate
assistance in case of Emergency. Antidotes shall either be kept in the
factory of should be available with the Clinic/Doctor. M.S.D. Sheet shall be
sent to the Doctor Along with the patient.
First aid charts showing actions to be taken in case of a particular accident
shall be prominently displayed at the working places. In general following
actions could be taken depending on the injury.
i) Exposure to fumes or vapors’
Remove the affected person to fresh air. If needed try artificial respiration
& consult Doctor immediately.
ii) Eye Contact
Flush with water and get medical advice.
iii) Skin Contact
Remove contaminated clothing and wash off immediately with water.
138
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
iv) Burns
Cool down the affected area with cold water until pain subsides. Apply
some antiseptic and obtain medical advice.
139
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER 13.0
RAIN WATER HARVESTING
13.1 Introduction
Rain Water Harvesting is collecting and using precipitation from a
catchments surface. The rainwater collected can be stored for direct use or
can be recharged into the groundwater. Rain Water Harvesting is thus
becoming essential as it helps to meet our demand for the water either
directly as rain water is stored and put to different uses or indirectly via
replenishing the ground water.
Thus, there are two main techniques of Rain Water Harvesting (RWH)
depending on the end use.
Storage of rain water on surface for direct use
Recharge to ground water
For RWH, the rainwater that falls on a catchment is carried through
pipelines or drains for storage or recharge. The catchment can be a paved
area like a roof, terrace or courtyard of a building, or an unpaved area like a
lawn or open ground.
13.2 Methodology
The decision whether to store or recharge the harvested water depends on:
Hydro-meteorological characters viz. Rainfall duration,
general pattern and intensity of rainfall.
Hydro-geology of the area including nature and extent of
aquifer, soil cover, topography, depth to water levels and
chemical quality of ground water.
140
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
In areas where rain falls throughout the year, barring a few dry periods, one
can make use of small size storage tanks for storing rainwater, since the
period between two spells of rain is short. On the other hand in areas where
the majority of the rainfall occurs during 3 to 4 months of monsoon, the
storage will require large size storage tanks and therefore it may be better to
use rainwater to recharge. However, a combination of two systems may
have to be adopted where hydro-geology of the area makes recharging
uneconomical due to depth to aquifers, nature of strata etc. Both the
approaches are discussed below:
13.2.1 Storage of Rainwater for Direct Use
Rainwater can be stored in an underground RCC/masonry tank. Pre-
fabricated tanks such as PVC can be installed above the ground. Each tank
must have an overflow system for situations when excess water enters the
tank. The overflow can be connected to the drainage system.
In general, runoff from only paved surfaces is used for storing since it will
be relatively less contaminated. Drainpipes that collect water from the
rooftop are diverted to the storage container. Rainwater collected from
rooftops is free of mineral pollutants like fluoride and calcium salts which
may be found in groundwater. But it is likely to be contaminated with
pollutants in air and on surface.
To prevent leaves and debris from entering the system, mesh filters should
be provided at the mouth of the drainpipe.
A first-flush device should be provided in the conduit before it is connected
to the storage container. This is to drain-off the first spell of runoff the
season, which may be more laden with dust and impurities.
141
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
A sedimentation tank can also be provided before the main storage tank to
collect dust and impurities as se settlement. This is particularly useful in
case of underground storage water tanks.
It is preferable to use the stored water for purposes like gardening, flushing,
bathing, augmenting storage for fire-fighting etc. If it is to be used for
drinking purposes it should be used after boiling or disinfecting with
chlorine tablets of after filtration.
13.2.2 Artificial Recharge to Ground Water
Artificial recharge techniques are adopted where:
Adequate space for surface storage is not available especially in
urban areas.
Water level is deep enough (>8m.) and adequate subsurface
storage is available.
Permeable strata are available at shallow/moderate depth.
Where adequate quantity of surface water is available for recharge
to ground water.
Ground water quality is bad and the aim is to improve it.
Where there is possibility of intrusion of saline water especially in
coastal areas.
Where the evaporation rate is very high from surface water bodies.
142
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
13.2.3 Methods of Ground Water Recharge
(i) Recharge Pits
Recharge pits are constructed for recharging the shallow aquifers. These are
constructed 1 to 2 m. wide and 2 to 3 m. deep which are back filled with
boulders, gravels & coarse sand. The size of filter material is generally
taken as below:
Coarse sand : 1 to 5 mm
Gravels : 5 to 10 mm
Boulders : 5 to 20 cm
The filter material should be filled in graded form. Boulders at the bottom,
gravels in between & coarse sand at the top so that the silt content that will
come with runoff will be deposited on the top of the coarse sand layer and
can easily be removed. If clay layer encountered at shallow depth, it should
be punctured with auger hole and that auger hole should be refilled with
fine gravel of 3 to 6 mm size.
(ii) Recharge Trenches
These are constructed when the permeable strata is available at shallow
depths. Trenches may be 0.5 to 1 m. wide, 1 to 1.5 m. deep and 10 to 20 m.
long depending upon availability of water. These are back filled with filter
materials. In case of clay layer encountered at shallow depth, the number of
auger holes may be constructed & back filled with fine gravels.
(iii) Abandoned Dug-wells
Existing abandoned dug wells may be utilized as recharge structure after
cleaning and de-silting the same. For removing the silt contents, the runoff
water should pass either through a de-silting chamber or filter chamber.
143
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
(iv) Hand Pumps / Tube-wells
The existing abandoned hand pumps may be used for recharging the
shallow/deep aquifers, if the availability of water is limited. Water should
pass through filter media before diverting it into hand pumps.
Abandoned tube-well may be used for recharging the shallow/deep
aquifers. These tube-wells should be redeveloped before use as recharge
structure. Water should pass through filter media before diverting it into
recharge tube-well.
(v) Recharge Wells
Recharge wells of 100 to 300mm. Diameter are generally constructed for
recharging the deeper aquifers and roof top rain water is diverted to
recharge well for recharge to ground water. The runoff water may be passed
through filter media to avoid choking of recharge wells.
(vi) Recharge Shafts
For recharging the shallow aquifers, which are located below clayey surface
at a depth of about 10 to 15 m, recharge shafts of 0.5 to 3 m. diameter and
10 to 15 m. deep are constructed depending upon availability of runoff.
These are back filed with boulders, gravels & coarse sand. For lesser
diameter shafts, the reverse/direct rotary rigs are used and larger diameter
shafts may be dug manually. In upper portion of 1 or 2m depth, the brick
masonry work is carried out for the stability of the structure.
(vii) Lateral Shafts with Bore Wells
If the aquifer is available at greater depth say 20 or 30 m, a shallow shaft of
2 to 5 m diameter and 5 to 6 m deep may be constructed depending upon
144
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
availability of runoff. Inside the shaft, a recharge well of 100 to 300 mm
diameter is constructed for recharging the available water to deeper aquifer.
At the bottom of the shaft a filter media is provided to avoid choking of the
recharge well.
For recharging the upper as well as deeper aquifers, lateral trench of 1.5 to
3 m. wide & 10 to 30 m. long depending upon availability of water with
one or more bore wells may be constructed. The lateral trench is back filled
with boulders, gravels & coarse sand.
(viii) Open Spreading
When permeable strata starts from top then open spreading is used. Water
is spread in streams/nalah by making check dams, nalah bunds, cement
plugs, gabion structures or percolation ponds.
13.3 General Arrangements Proposed
In the present case since the land available in the colony is limited and
large tanks cannot be constructed it is proposed to recharge the ground
water through deep bores.
13.4 Recharge Potential
The recharge is proposed to be done from the roof top of the building only.
The recharge potential thus available is as below:-
However, affords will be made to store this water for use in plantation
during non rainy days.
Area of the catchment (Roof Top) A = 16200 m2
Average annual rainfall R = 1.0 m
Runoff coefficient C = 0.8
Annual Roof Top Rain Water Harvesting Potential = 12960 m3
145
PUNJAB ACIDS-CHEM PVT. LTD. VARDAN ENVIRONET,
DERABASSI, PUNJAB. GURGAON
CHAPTER- 14.0
EXPENDITURE ON ENVIRONMENTAL MEASURES
Table-14.1
Cost of environment protection measures
S.No Title Capital Cost
Lacs
Recurring Cost
- Lacs
(Annum)
1 Air Pollution Control 15.0 2.0
2. Noise Pollution Control
(Including cost of
Landscaping, Green Belt)
4.0 ---
3. Solid Waste Management 2.0 0.5
4. Environment Monitoring
and Management (Including
Establishment of
Laboratory)
8.0 0.5
Total 29.0 3.0