Energy Water Work Book

Embed Size (px)

Citation preview

  • 7/30/2019 Energy Water Work Book

    1/33

    Key for Reading Spreadsheets

    Water inputs for all energy sources (EXCEPT coal) are color coded as follows:Agriculture

    Mining

    Transportation

    Processing

    Cooling

    Cleaning

    Evaporative Losses (hydroelectric facilities only)

    Other

    References and sources are identified with their numbers using the following codeW= Withdrawal

    C= Consumption

    H= High figure

    L= Low figure

    At the top of each spreadsheet, the water requirements for each step in the generation prare listed. At the bottom of each spreadsheet, different technological options are combine

    total estimates of water requirements are provided.

  • 7/30/2019 Energy Water Work Book

    2/33

    :

    ocessd and

  • 7/30/2019 Energy Water Work Book

    3/33

    Water Requirements for Bioenergy Power Production

    All Numbers in m3/MWh

    BIOENERGY Withdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High

    Agriculture, Rapeseed 360 630 360 630

    Agriculture, Sugarcane 133 558 133 558

    Agriculture, Sugar Beet 256 677 256 677

    Agriculture, Corn 263 1250 263 1250

    Agriculture, Wheat 144 1260 144 1260

    2.5198 2.5198 2.5198 2.5198

    1.7999 1.7999 1.7999 1.7999

    0.3600 0.3600 0.3600 0.3600

    0.1080 3.2400

    BIOGAS Withdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High

    Simple Cycle 0.0836 0.0836 0.0836 0.0836

    Combined cycle, wet cooli 0.8706 0.8706 0.6813 0.6813

    Combined cycle, dry cooli 0.1514 0.1514 0 0

    Combined cycle, once-thr 9.084 75.7 0.3785 0.3785

    Steam turbine, once-thru 75.7 189.25 1.1355 1.1355

    Steam turbine, wet coolin 1.1355 3.028 0.9084 2.4224Steam turbine, dry cooling 0.1514 0.1514 0 0

    Steam turbine, pond cooli 1.1355 2.271 1.1355 1.8168

    Biomass-based steamplant

    Improved biomass-basedsteam plant

    Gasification-based,combined cyclegeneration

    Quench feed water forwet scrubbing of syngas

    (exiting gasifier)

  • 7/30/2019 Energy Water Work Book

    4/33

    Mining, combined cycle co 0 0 0 0

    Transportation, combined 0 0 0 0

    Other 0 0 0 0

    Inlet fogging (additional o 0.4731 1 0.4731 1

    Bioenergy Power Production Method

    Dedicated Energy Crops

    1 Dedicated energy crops - rapeseed - gasification -2 Dedicated energy crops - sugarcane - gasification -

    3 Dedicated energy crops - Sugar beet - gasification -

    4 Dedicated energy crops - Corn - gasification -

    5 Dedicated energy crops - Wheat - gasification -6 Dedicated energy crops - rapeseed - gasification - syngas

    7 Dedicated energy crops - sugarcane - gasification - syngas

    8 Dedicated energy crops - Sugar beet - gasification - synga

    9 Dedicated energy crops - Corn - gasification - syngas scrub

    10 Dedicated energy crops - Wheat - gasification - syngas scr11 Dedicated energy crops - rapeseed - Biomass-based stea

    12 Dedicated energy crops - sugarcane - Biomass-based stea

    13 Dedicated energy crops - Sugar beet - Biomass-based ste14 Dedicated energy crops - Corn - Biomass-based steam pla

    15 Dedicated energy crops - Wheat - Biomass-based steam pl16 Dedicated energy crops - rapeseed - Improved biomass-ba

    17 Dedicated energy crops - sugarcane - Improved biomass-

    18 Dedicated energy crops - Sugar beet - Improved biomass-

    19 Dedicated energy crops - Corn - Improved biomass-based

    20 Dedicated energy crops - Wheat - Improved biomass-base

    Waste Products

    21Agricultural/Forestry Waste - gasification -22Agricultural/Forestry Waste - gasification - syngas scrubbin

    23Agricultural/Forestry Waste - Biomass-based steam plant24Agricultural/Forestry Waste - Improved biomass-based ste

    Biogas (including landfill gas or WWTP gas - methane)

    25 Biogas - Simple cycle

    26 Biogas - Simple cycle with inlet fogging

    27 Biogas - Combined cycle with wet cooling and inlet fogging

    28 Biogas - Combined cycle with wet cooling

  • 7/30/2019 Energy Water Work Book

    5/33

    29 Biogas - Combined cycle with dry cooling and inlet fogging

    30 Biogas - Combined cycle with dry cooling

    31 Biogas - Combined cycle, once-thru cooling

    32 Biogas - Steam turbine, once-thru cooling

    33 Biogas - Steam turbine, wet cooling

    Biogas - Steam turbine, dry cooling

    34 Biogas - Steam turbine, pond cooling35

    36

  • 7/30/2019 Energy Water Work Book

    6/33

    Notes/Assumptions Sources

    Notes/Assumptions Sources

    Data is originally all in terms of "water useefficiency". We use the same numbers for ratesof withdrawal and consumption, assuming thatall applied water (for irrigation) is evapo-transpired. Original study assumes that, for thelower numbers (more efficient systems) wastebyproducts and harvest residues are used togenerate electricity.

    Berndes, 2002[W,C/H,L]

    Berndes, 2002[W,C/H,L]

    Berndes, 2002[W,C/H,L]

    Berndes, 2002[W,C/H,L]

    Berndes, 2002[W,C/H,L]

    Assumes a 23% specified efficiency and a HHVat 20 Gj/Mg

    USDOE/EPRI,

    1997 and Berndes,2001 [W,C/H,L]

    Assumes a 34% specified efficiency and a HHVof 20 GJ/Mg

    USDOE/EPRI,1997 and Berndes,2001 [W,C/H,L]

    Includes boiler feed water requirements butNOT wet scrubbing. Steam from the steamcycle is injected into the gasifier Asumes aspecified efficiency of 36% and a HHV of 20GJ/Mg.

    USDOE/EPRI,1997 and Berndes,2002 [W,C/H,L]

    For methanol. Hydrogen values are much

    higher.

    Katofsky, 1993 andBerndes, 2002

    [W,C/H,L]

    Assumes a 500 MW plant. Analysis assumesthat water requirements for landfill gas facilitiesare comparable to those for conventionalnatural gas facilities. All data are taken from

    conventional natural gas facilities.

    Maulbetsch 2006,EPRI, CATF et al.

    2003

  • 7/30/2019 Energy Water Work Book

    7/33

    Maulbetsch 2006

    Withdrawal Water Requirement (m3/MWh)

    Low High Low High

    360.3 630.4 360.3 630.4133.4 558.4 133.4 558.4

    256.4 677.4 256.4 677.4

    263.4 1250.4 263.4 1250.4

    144.4 1260.4 144.4 1260.4

    360.4 633.6 360.3 630.4

    133.5 561.6 133.4 558.4

    256.5 680.6 256.4 677.4

    263.5 1253.6 263.4 1250.4

    144.5 1263.6 144.4 1260.4

    362.5 632.5 362.5 632.5

    135.5 560.5 135.5 560.5

    258.5 679.5 258.5 679.5265.5 1252.5 265.5 1252.5

    146.5 1262.5 146.5 1262.5

    361.8 631.8 361.8 631.8

    134.8 559.8 134.8 559.8

    257.8 678.8 257.8 678.8

    264.8 1251.8 264.8 1251.8

    145.8 1261.8 145.8 1261.8

    0.36 0.36 0.36 0.36

    0.47 3.60 0.36 0.36

    2.52 2.52 2.52 2.521.80 1.80 1.80 1.80

    0.08 0.08 0.08 0.08

    0.56 0.69 0.56 0.69

    1.34 1.48 1.15 1.29

    0.87 0.87 0.68 0.68

    Unlike traditional natural gas, we assume noprocessing water needs (because landfill gasfacilities often produce additional water bydrying the captured gas). The processing waterneeded to produce energy from conventional

    natural gas is used in the pumping process.We assume no transportation costs, as energyis typically produced on-site (with landfill gasgeneration).

    Consumptive Water Requirement(m3/MWh)

  • 7/30/2019 Energy Water Work Book

    8/33

    0.62 0.76 0.47 0.61

    0.15 0.15 0.00 0.00

    9.08 75.70 0.38 0.38

    75.70 189.25 1.14 1.14

    1.14 3.03 0.91 2.42

    0.15 0.15 0.00 0.00

    1.14 2.27 1.14 1.82

  • 7/30/2019 Energy Water Work Book

    9/33

    Water Requirements for Coal Power Production

    All Numbers in m3/MWh

    COAL Withdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High Notes/Assumptions Sources

    Surface Mining 0.01 0.49 0.01 0.05

    Underground Mining 0.45 0.45 0.03 0.21

    Coal Washing 0.01 0.02 0.00 0.00 80% of eastern and interior coal is washed [W] (Gleick 1994

    Pulverized Slurry Line 0.03 0.90 0.03 0.90

    Log Slurry Line 0.01 0.27 0.01 0.27 Saves up to 70% water of traditional slurry. [W] & [C] (Liu 20

    IGCC (Gasification) 0.18 0.24 0.09 0.13 500 MW plant [W] & [C] (Klett 2

    IGCC Makeup Water (ex. Cooling) 0.15 0.39 [W] & [C] (Klett 2

    IGCC Process Losses 0.09 0.13 [W] & [C] (Klett 2

    IGCC Flue Gas Water Losses 0.29 0.40 [W] & [C] (Klett 2IGCC Wet Cooling 2.30 2.79 2.30 2.79 [W] & [C] (Klett 2

    IGCC Pond Cooling 0.74 1.48 0.74 1.18 [W] & [C] (Klett 2

    PC Combustion 0.14 0.16 0.00 0.00 600MW pulverized coal plant.

    PC Makeup Water (ex. Cooling) 0.01 0.02

    PC Process Losses 0.03 0.03

    PC Flue Gas Water Losses 0.36 0.41

    PC Flue Gas Desulfurization 0.24 0.40 0.24 0.40

    PC Wet Cooling 3.71 4.16 3.71 3.71 Numbers are thermoelectic averages

    PC Once-Through Cooling 75.70 189.25 1.14 1.14PC Pond Cooling 1.14 2.27 1.14 1.82 Numbers from EPRI are thermoelectric averages [C]&[W] (EPRI 2

    PC Hybrid Wet-Dry Cooling 0.38 3.63 0.36 3.33 [C] (EPRI 2002)

    PC Direct Dry Cooling 0.09 0.23 0.09 0.21 (Queensland Go

    PC Indirect Dry Cooling 0.09 0.23 0.09 0.21 N/A

    Choose consumption higher value if revegetating6150 kWh/ton of coal mined

    [CH] (Gleick 199[CL] Set to Matc[WL]Calculation1994) and NMA [WH] Coal Text

    [C](Gleick 1994)[WL]Calculation1994) and NMA [WH] Coal Text

    [CH](Gleick 1992006)[WL]Coal Textbo[WH]Set to matc[CL]Set to match

    [W] (Ziemkiewicz[C]Hypothesis b

    [CH] (Feeley et a[CL] (EPRI 2002[WH] (Feeley et [WL] (EPRI 2002

    Uses 35% less water when paired with an IGCC

    plant

    [W] (Ziemkiewicz

    [C]Hypothesis b

    Results in about 50% less water consumption thana conventional closed-loop wet cooling systemConsumption is 20-80% of recirculating wetcoolingUses 35% less water when paired with an IGCCplant

    Dry cooling cuts consumption by 95% (Comparedto wet cooling)Uses 35% less water when paired with an IGCCplant

    Uses 35% less water when paired with an IGCC

    plant

  • 7/30/2019 Energy Water Work Book

    10/33

    Water Requirements for Geothermal Power Production

    All Numbers in m3/MWh

    GEOTHERMAL Withdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High

    0 3.49 0 3.49

    0 3.49 0 3.49

    Cooling, once through

    0 54 0 0.246

    Cooling, wet recirculating (cooling towers)0 17.03 0 17.03

    Cooling, dry

    0 0 0 0

    Cooling, Imperial Valley 7.7 14.1 7.7 14.1

    Cooling, other locations in California 0 0.019 0 0.019

    Geothermal Power Production Method

    Low High Low High

    Steam dominated, once through cooling 0 57.49 0 3.736

    Steam dominated, dry cooling 0 3.49 0 3.49

    Water dominated, once through cooling 0 57.49 0 3.736

    Water dominated, dry cooling 0 3.49 0 3.49

    Steam dominated, wet recirculating cooling 0 20.52 0 20.52

    Water dominated, wet recirculating cooling 0 20.52 0 20.52

    Injection from external sources, waterdominated system

    Injection from external sources, steamdominated system

    FOR CALIFORNIA CASE STUDY, MORESPECIFIC NUMBERS:

    WithdrawalWater

    Requirement

    (m3/MWh)

    ConsumptiveWater

    Requirement

    (m3/MWh)

  • 7/30/2019 Energy Water Work Book

    11/33

    Special notes:

    We are no longer considering geothermal fluid or steam in this spreadsheet.

  • 7/30/2019 Energy Water Work Book

    12/33

    Notes/Assumptions Sources

    High number reflects the only externalinjection program of its kind, in the Geysers

    [W, C]Sass and Priest 2002, Dept ofOil, Gas, and Geothermal Resources2005

    High number reflects the only externalinjection program of its kind, in the Geysers

    [W, C]Sass and Priest 2002, Dept ofOil, Gas, and Geothermal Resources2005

    WL, CL from Bagnore, Italy; WH fromNesjavellir, Iceland. CH from Salton SeaUnit 6. The Iceland plant disposes ofwastewater into groundwater flowing to a

    lake; maybe that explains the high. Ibelieve it's like a once-through coolingsystem. Gleick says up to 15 m3/MWh ifyou need external water. The Geysersrequires no external water for cooling(Gleick 1994).

    [WH]Hagedoorn 2006, [CH] Adams etal. 2005[WL]/[CL]Hagedoorn 2006

    [WL]/[CL]Adams et al. 2005, [WH]/[CH]Charles et al. 2006

    Kagel mentions no numbers here; I amassuming the water required is negligible. Iffossil plants withdraw such little water fordry cooling, I am assuming that small

    amount can be easily met with geothermalfluid (which we aren't counting).

    [WH]/[CH]Kagel et al. 2005, USDOE2006

    [WL]/[CL]Kagel et al. 2005, USDOE2006

  • 7/30/2019 Energy Water Work Book

    13/33

  • 7/30/2019 Energy Water Work Book

    14/33

  • 7/30/2019 Energy Water Work Book

    15/33

  • 7/30/2019 Energy Water Work Book

    16/33

  • 7/30/2019 Energy Water Work Book

    17/33

  • 7/30/2019 Energy Water Work Book

    18/33

    Water Requirements for Hydroelectric Power Production

    All Numbers in m3/MWh

    Hydroelectric Withdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High Notes/Ass Sources

    Evaporative Losses, 25 MW plant 162 162.0 0.036 2.520 Gleick 199

    Hydroelectric Power Production Method

    Low High

    1 Reservoir and Dam, < 25 MW capacity - Dam Height < Gross Static Head 208.8 208.8

    2 Reservoir and Dam, < 25 MW capacity - Dam Height > Gross Static Head 208.8 208.8

    3 Reservoir and Dam, > 25 MW capacity - Dam Height < Gross Static Head 162.0 162.0

    4 Reservoir and Dam, > 25 MW capacity - Dam Height > Gross Static Head 162.0 162.0

    5 "Run of River" Facility 0 0

    6 Facilities in aqueducts 0 0

    7

    statisticsfor that

    sizefacility.

    Withdrawal WaterRequirement(m3/MWh)

  • 7/30/2019 Energy Water Work Book

    19/33

    2 [W,C/H,L]

    2 [W,C/H,L]

    Low High

    0.18 82.7

    1.94 209

    0.036 122

    3.6 162

    0 0

    0 0

    Consumptive WaterRequirement(m3/MWh)

    Assumes that"run of river"facilities do notimpound water,increasing ratesof evaporation

    Assumes thatthese facilities donot increase

    rates ofevaporationabove existingrates.

  • 7/30/2019 Energy Water Work Book

    20/33

    Water Requirements for Natural Gas Power Production

    All Numbers in m3/MWh

    NATURAL GAS Withdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High

    Simple Cycle 0.084 0.084 0.084 0.084Combined cycle, wet cooling 0.871 0.871 0.681 0.681

    Combined cycle, dry cooling 0.151 0.151 0.000 0.000

    Combined cycle, once-thru cooling9.084 75.700 0.379 0.379

    Steam turbine, once-thru cooling 75.700 189.251 1.136 1.136

    Steam turbine, wet cooling 1.136 3.028 0.908 2.422

    Steam turbine, dry cooling 0.151 0.151 0.000 0.000

    Steam turbine, pond cooling 1.136 2.271 1.136 1.817

    Inlet fogging (additional option) 0.473 0.606 0.473 0.606

    0.036 0.036 0.036 0.036

    0.060 0.060 0.060 0.060

    0.018 0.018 0.018 0.018

    0.030 0.030 0.030 0.030

    Other (hotel load)

    0.000 0.360 0.000 0.360

    Natural Gas Power Production Method

    Low High Low High

    Simple cycle, no inlet fogging 0.116 0.116 0.116 0.116

    Simple cycle, inlet fogging 0.589 0.722 0.589 0.722

    1.376 1.509 1.187 1.319

    0.903 0.903 0.714 0.714

    0.657 0.789 0.506 0.638

    0.184 0.184 0.032 0.032

    Combined cycle, once-thru cooling9.116 75.733 0.411 0.411

    Steam turbine, once-thru cooling 76.093 189.643 1.528 1.528

    Mining, combined cycle conversiontechnology

    Mining, Simple cycle conversiontechnology

    Transportation, combined cycleconversion technology

    Transportation, simple cycleconversion technology

    Withdrawal WaterRequirement(m3/MWh)

    ConsumptiveWater

    Requirement(m3/MWh)

    Combined cycle, wet cooling, inletfogging

    Combined cycle, wet cooling, noinlet fogging

    Combined cycle, dry cooling, inletfogging

    Combined cycle, dry cooling, noinlet fogging

  • 7/30/2019 Energy Water Work Book

    21/33

    Steam turbine, wet cooling 1.528 3.420 1.301 2.815

    Steam turbine, dry cooling 0.544 0.544 0.392 0.392

    Steam turbine, pond cooling 1.528 2.663 1.528 2.209

  • 7/30/2019 Energy Water Work Book

    22/33

    Assumptions Source

    Assumes a 500 MW plant

    Maulbetsch 2006

    Maulbetsch 2006,EPRI, CATF et al.

    2003

    Assumes a conversion efficiency of60% for combined cycle plants

    Assumes a conversion efficiency of36% (from thermal to electricJoules), source - Gleick (1994)

    Assumes a conversion efficiency of60% for combined cycle plants

    Assumes a conversion efficiency of36% (from thermal to electricJoules), source - Gleick (1994)

    Gleick says 0.36, but I use 0 in otherplaces to avoid mismatching

    sources.

  • 7/30/2019 Energy Water Work Book

    23/33

  • 7/30/2019 Energy Water Work Book

    24/33

    Water Requirements for Nuclear Power Production

    All Numbers in m3/MWh

    NUCLEARWithdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High Notes/Assumptions Sources

    Surface Uranium Mining 0.2323 0.2323 0 0 only for surface mining [W] & [C]: Gleick 1993

    Underground Uranium Mining 0.0023 0.0023 0 0 only for underground mining [W] & [C]: Gleick 1993

    Processing 0.7548 0.9058 0.4522 0.5365 [W] & [C]: Gleick 1993

    BWR

    once-thru cooling94.6253 ### 0.3785 5.0350

    3.0280 5.6775 1.5140 5.6775

    2.7252 4.1635 2.7252 2.7252 [W] & [C]: EPRI 2002

    PWR

    once-thru cooling94.6253 227.101 0.3785 1.5140

    3.02801 5.67752 1.5140 5.6775

    2.7252 4.16351 2.7252 3.2330

    ,conversion, enrichment, fuelfabrication, fuelreprocessing

    for BWR assuming once-through cooling

    [W]: EPRI 2002; [C/L]: Hoff2004; [C/H] Pace UniversitEnvironmental Law Center

    natural draft wetcooling tower

    [W/L]:EPRI 2002; [W/H]:Ho2004; [C/H]:EPRI 2002; [Cet al. 2004

    closed cycle coolingpond, lake, orreservoir

    [W] EPRI 2002; [C/L]: Hoff2004; [C/H]: EPRI 2002

    natural draft wetcooling tower

    [W/L]:EPRI 2002; [W/H]:Ho2004; [C/H]:EPRI 2002; [Cet al. 2004

    closed cycle coolingpond, lake, orreservoir

    [W] EPRI 2002; [C/L]: EPRPace University EnvironmeCenter 1990

  • 7/30/2019 Energy Water Work Book

    25/33

    Water Requirements for Oil Power Production

    All Numbers in m3/MWh

    OILWithdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High

    0.028 0.045 0.028 0.045

    Oil Shale Mining - Indirect AGR 0.035 0.047 0.035 0.047

    Oil Shale Mining - Modified In-situ (MIS)/AGR 0.013 0.014 0.013 0.014

    Oil Shale Mining - Modified In-situ (MIS) 0.020 0.020 0.020 0.020

    0.088 0.111 0.088 0.111

    Oil Shale Processing - Indirect AGR 0.137 0.201 0.137 0.201

    Oil Shale Processing - Modified In-situ (MIS)/AGR 0.121 0.145 0.121 0.145

    Oil Shale Processing - Modified In-situ (MIS) 0.100 0.100 0.100 0.100

    0.077 0.121 0.077 0.121

    Oil Shale (Other) - Indirect AGR 0.181 0.276 0.181 0.276

    Oil Shale (Other) - Modified In-situ (MIS)/AGR 0.072 0.094 0.072 0.094

    Oil Shale (Other) - Modified In-situ (MIS) 0.077 0.077 0.077 0.077

    Combined cycle, once-thru cooling 9.084 75.700 0.379 0.379

    Combined cycle, wet cooling 0.871 0.871 0.681 0.681

    Combined cycle, dry cooling 0.151 0.151 0.000 0.000

    Steam turbine, once-thru cooling 75.700 189.251 1.136 1.136

    Steam turbine, wet cooling 1.136 3.028 0.908 2.422

    Steam turbine, dry cooling 0.151 0.151 0.000 0.000

    Steam turbine, pond cooling 1.136 2.271 1.136 1.817

    Drilling 0.01 32.04 0.01 32.04

    Refining 0.09 0.43 0.09 0.43

    Other (hotel load) 0.25 0.25 0.25 0.25

    Oil Power Production Method

    Low High Low High

    Combined cycle, once-thru cooling 9.437 108.424 0.731 33.103

    Combined cycle, wet cooling 1.223 33.595 1.034 33.405

    Combined cycle, dry cooling 0.504 32.875 0.353 32.724

    Steam turbine, once-thru cooling 76.053 221.975 1.488 33.860

    Steam turbine, wet cooling 1.488 35.752 1.261 35.146

    Steam turbine, dry cooling 0.504 32.875 0.353 32.724

    Steam turbine, pond cooling 1.488 34.995 1.488 34.541

    9.278 75.978 0.572 0.656

    Oil Shale Mining - Direct Aboveground Retorting(AGR)

    Oil Shale Processing - Direct AbovegroundRetorting (AGR)

    Oil Shale (Other) - Direct Aboveground Retorting(AGR)

    Withdrawal WaterRequirement(m3/MWh)

    ConsumptiveWater Requirement

    (m3/MWh)

    Oil Shale - Direct Aboveground Retorting -Combined cycle, once-thru cooling

  • 7/30/2019 Energy Water Work Book

    26/33

    1.064 1.148 0.875 0.959

    0.345 0.429 0.194 0.278

    75.894 189.528 1.329 1.413

    1.329 3.306 1.102 2.700

    1.329 2.549 1.329 2.095

    9.438 76.224 0.732 0.902

    1.224 1.394 1.035 1.205

    0.505 0.675 0.353 0.524

    76.054 189.774 1.489 1.659

    1.489 3.552 1.262 2.946

    1.489 2.795 1.489 2.340

    9.291 75.953 0.585 0.631

    1.077 1.123 0.888 0.934

    0.358 0.404 0.206 0.252

    75.907 189.503 1.342 1.388

    1.342 3.280 1.115 2.675

    1.342 2.523 1.342 2.069

    9.280 75.897 0.575 0.575

    1.067 1.067 0.878 0.878

    0.348 0.348 0.196 0.196

    75.897 189.447 1.332 1.332

    1.332 3.224 1.105 2.619

    1.332 2.467 1.332 2.013

    Oil Shale - Direct Aboveground Retorting -Combined cycle, wet cooling

    Oil Shale - Direct Aboveground Retorting -Combined cycle - Dry cooling

    - -- -

    Oil Shale - Direct Aboveground Retorting - Steam

    turbine - wet coolingOil Shale - Direct Aboveground Retorting - Steamturbine - pond cooling

    Oil Shale - Indirect Aboveground Retorting -Combined cycle, once-thru cooling

    Oil Shale - Indirect Aboveground Retorting -Combined cycle, wet cooling

    Oil Shale - Indirect Aboveground Retorting -Combined cycle - Dry cooling

    a e - n rec ovegroun e or ng - eamturbine - Once-throu h coolinOil Shale - Indirect Aboveground Retorting - Steamturbine - wet cooling

    Oil Shale - Indirect Aboveground Retorting - Steamturbine - pond cooling

    Oil Shale - Modified In-Situ/AGR - Combined cycle,once-thru cooling

    Oil Shale - Modified In-Situ/AGR - Combined cycle,wet cooling

    Oil Shale - Modified In-Situ/AGR - Combined cycle -Dry cooling

    Oil Shale - Modified In-Situ/AGR - Steam turbine -Once-through cooling

    Oil Shale - Modified In-Situ/AGR - Steam turbine -wet cooling

    Oil Shale - Modified In-Situ/AGR - Steam turbine -pond cooling

    Oil Shale - Modified In-Situ - Combined cycle, once-thru cooling

    Oil Shale - Modified In-Situ - Combined cycle, wetcooling

    Oil Shale - Modified In-Situ - Combined cycle - Drycooling

    Oil Shale - Modified In-Situ - Steam turbine - Once-through cooling

    Oil Shale - Modified In-Situ - Steam turbine - wetcooling

    Oil Shale - Modified In-Situ - Steam turbine - pondcooling

  • 7/30/2019 Energy Water Work Book

    27/33

    Notes/Assumptions Sources

    Gleick 1994

    Gleick 1994

    Gleick 1994

    average

    58.931

    17.409

    16.690

    149.014

    18.620

    16.690

    18.242

    42.628

    All calculations assume one barrel ofcrude oil (42 gallons) has an energycapacity of 1700 kWh. Assumes a50,000 bbl/day facility. The citedreference describes all water used as"consumed water" and does notdistinguish from "withdrawn water". Thequality of the water may, indeed, meanthat it is effectively consumed; however,there may be some opportunity forreclaiming water. We do not tackle thatquestion. "Other" uses include water for

    disposal and revegetation, dust controlduring extraction, plant utilities, and on-site power needs.

    EmergingIssues for

    FossilEnergy andWater, 2006

    [W,C/H,L]

    Analysis assumes that oil cooling is thesame as natural gas cooling.

    EPRI, CATFet al. 2003

  • 7/30/2019 Energy Water Work Book

    28/33

    1.106

    0.387

    132.711

    2.317

    1.939

    42.831

    1.309

    0.590

    132.914

    2.520

    2.142

    42.622

    1.100

    0.381

    132.705

    2.311

    1.933

    42.589

    1.067

    0.348

    132.672

    2.278

    1.900

  • 7/30/2019 Energy Water Work Book

    29/33

    Water Requirements for Solar Power Production

    All Numbers in m3/MWh

    SOLARWithdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High Notes/Assumptions Sources

    Parabolic Trough Plant - wet cooling 2.80 2.87 2.80 2.87

    Parabolic Dish-Engine - dry cooling 0 0 0 0 No cooling required. Stoddard, et al.2006 [W,C/H,LPower Tower - wet cooling 2.40 2.80 2.40 2.80

    PV - Distributed (Rooftop) Systems 0 0 0 0 No cooling required.

    PV - Large Centralized Plants 0 0 0 0 No cooling required.

    PV - Concentrating PV Systems 0 0 0 0 No cooling required.

    Parabolic Trough Plant washing 0.14 0.27 0.14 0.27

    Parabolic Dish-Engine washing 0 0 0 0 Stoddard, et al.2006 [W,C/H,

    Power Tower washing 0 0.14 0 0.14

    PV - Distributed (Rooftop) Systems w

    0 0.11 0 0.11

    PV - Large Centralized Plant washing

    0 0.11 0 0.11 AWEA Website 2006

    PV - Concentrating PV Systems washi 0 0 0 0 Stoddard, et al.2006

    Solar Power Production Method

    Withdrawn is equivilant to consumedwhen withdrawn numbers are notavailable.

    Stoddard, et al.2006 [W,C/LThe Last Straw [W,C/H]

    Stoddard et al. 2006 [W,C/H

    The Last Straw; Stoddard et a[W,C/H,L]

    High number found by subtracting thecooling water amt from the coolingand process water amt listed for thistechnology in the Last Straw

    Stoddard, et al.2006 [W,C/LDirect Communication, MikeRoverson, Kramer Junction[W,C/L], Last Straw [W,C/H

    Assumed to be roughly equal towashing needs of a Parabolic Troughplant as both have large mirror fields.

    Number for PV washing requirmentsused for both large plants anddistributed gen (rooftop).

    The Last Straw; AWEA Webs2006

    Number for PV washing requirmentsused for both large plants anddistributed gen (rooftop).

  • 7/30/2019 Energy Water Work Book

    30/33

    Low High Low High

    CSP - Parabolic Trough System 2.94 3.14 2.94 3.14

    CSP - Parabolic Dish-Engine System 0 0 0 0

    CSP - Power Tower Plant 2.540 2.800 2.540 2.800

    PV - Distributed (Rooftop) Systems 0.0038 0.114 0.004 0.114

    PV - Large Centralized Plant 0.000 0.114 0.000 0.114

    PV - Concentrating PV Systems 0 0 0 0

    Withdrawal WaterRequirement(m3/MWh)

    ConsumptiveWater

    Requirement(m3/MWh)

  • 7/30/2019 Energy Water Work Book

    31/33

    Water Requirements for Wind Power Production

    All Numbers in m3/MWh

    WIND Withdrawal Consumption

    m^3/MWh m^3/MWh

    Item Low High Low High Notes/Assumptions Sources

    Cleaning medium sized wind farms 0 0.00379 0 0.00379

    Cleaning large sized wind farms 0 0.00247 0 0.00247

    Wind Power Production Method

    Low High Low High

    Medium sized wind farm 0.0000 0.0038 0.0000 0.0038

    Large sized wind farm 0.0000 0.0025 0.0000 0.0025

    If the wind turbines are never cleaned,then the withdrawal and consumptionequals zero

    [W/L]: van Dam; [W/H]: AWEA2006; [C/L]: van Dam; [C/H]: AW2006

    If the wind turbines are never cleaned,then the withdrawal and consumptionequals zeroWind farms can operate at 30% ofnameplate capacityIf washed, turbines are washed 3times/yearEach turbine uses 40 gallons perwashing

    [W/L]: van Dam; [W/H]: J. Harris2006; [C/L]: van Dam; [C/H]: J.Harris 2006

    WithdrawalWater

    Requirement

    (m3/MWh)

    ConsumptiveWater

    Requirement

    (m3/MWh)

  • 7/30/2019 Energy Water Work Book

    32/33

    Conversion of Units

    Instructions: insert the value you have in the left box, and the coversion will be done automatically to r

    Volume/energy unit Quick refe

    130 gal/kWh = 492.0514762 m^3/MWh 1Energy

    65 gal/MWh = 2.46E-01 m^3/MWh 1

    1.00E+12

    54 liters/kWh = 54 m^3/MWh 1

    1.00E+18

    1.16129 ft^3/MWs = 118.3983337 m^3/MWh 1 barrel cru

    1 barrel cru

    1302083 gal/MWd = 205.3500084 m^3/MWh 1

    Volume

    195 Mg/GJ = 7.02E+02 m^3/MWh 1

    12.62E-06 ac-ft/kWh = 3.23E+00 m^3/MWh 1

    1234

    2.5E-011 m^3/J 9.00E-02 m^3/MWh 1

    1

    70 acre-ft/MWe = 8.64E+01 m^3/kW 1

    45 km^3/10^18 J = 1.62E+02 m^3/MWh

    64.516 m^3/10^12 J = 0.2323 m^3/MWh

    4.32E-06 m^3/kWh = 1.20E-12 m^3/J

    2000 kWh/megagallo = 0.52834 kWh/m^3

    652 kWh/af 0.5285764 kWh/m^3

  • 7/30/2019 Energy Water Work Book

    33/33

    ight box

    rence/conversion

    MW = 1000 kW

    kWh = 3.60E+06 Joules

    J = 2.78E+05 kWh

    GJ = 277.8 kWh

    J = 2.78E+11 kWh

    de oil = 5.80E+06 Btu

    de oil = 1.70E+03 kWh

    J = 2.78E-07 kWh

    m^3 = 1000 liters

    m^3 = 264.2 gallons (U.S.)m^3 = 35.31 ft^3

    m^3 = 1 acre-foot

    km^3 = 1000000000 m^3

    Mg (Million = 1 m^3

    megagallon = 378.541178 m^3