29
Bickleigh Down, Eco Village, Land off Towerfield Drive, Plymouth On behalf of ZeroC Revision C Date: 16 th March 2017 Energy Statement

ENERGY STATEMENT · BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT 1 REVISION HISTORY Revision Issue Date Description Issued By Checked By A 15/02/2017

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

  • Bickleigh Down, Eco Village, Land off Towerfield Drive, Plymouth

    On behalf of ZeroC

    Revision C

    Date: 16th March 2017

    Energy Statement

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    1

    REVISION HISTORY

    Revision Issue Date Description Issued By Checked By

    A 15/02/2017 Original Document NS SJC

    B 13/03/2017 Revision B NS JP

    C 16/03/2017 Revision C NS SJC

    This report has been produced by Energist UK Ltd for the private use of the client and solely

    in relation to the named project. It should neither be reproduced in part nor in whole nor

    distributed to third parties, without the express written permission of both Energist UK LTD

    and the Client.

    Calculations contained within this report have been produced based on information supplied

    by the Client and the design team. Any alterations to the technical specification on which this

    report is based will invalidate its findings.

    Energist College Farm Tetbury Road Cirencester GL7 6PY Tel: 08458 386 387 [email protected] www.energistuk.co.uk

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    2

    CONTENTS

    1. EXECUTIVE SUMMARY ................................................................................................................... 3

    2. INTRODUCTION ............................................................................................................................... 8

    3. BASELINE ENERGY DEMAND ....................................................................................................... 10

    4. FABRIC-FIRST APPROACH - REDUCED ENERGY DEMAND ......................................................... 12

    5. LOW-CARBON AND RENEWABLE ENERGY ..................................................................................... 15

    6. ACHIEVING ZERO CARBON ON THE ECO-VILLAGE SHOW HOME .................................................. 17

    7. CONCLUSIONS .................................................................................................................................. 18

    8. APPENDICES ................................................................................................................................... 21

    APPENDIX 1: LIST OF ABBREVIATIONS ................................................................................................ 21

    APPENDIX 2: PLANNING POLICY AND DESIGN GUIDANCE ................................................................. 22

    APPENDIX 3: SAP DATA. ..................................................................................................................... 24

    APPENDIX 4: PV ALLOCATION. ............................................................................................................ 26

    APPENDIX 5: ZERO CARBON REPORT – SHOW HOME ....................................................................... 28

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    3

    1. EXECUTIVE SUMMARY

    1.1 Purpose of the Statement

    This Energy Statement has been produced by Energist UK on behalf of ZeroC (‘the

    Applicant’).

    It will set out the measures designed by the Applicant to achieve CO2 reductions at

    the development site: Bickleigh Down Eco-Village, on Land off Towerfield Drive,

    Plymouth (‘the Development’) and will demonstrate compliance with:

    i) National Planning Policy Framework.

    ii) Approved Document Part L of the Building Regulations 2013.

    iii) The energy standard for the development scheme written in the planning agreement

    (as amended) between the Applicant and Plymouth City Council for planning

    applications 14/00223/FUL and 12/01504/FUL and as follows:

    Clause 4.1(a) of the “agreement” shall be amended to read as follows “Before

    commencement of development the Applicant shall provide evidence to the Council to demonstrate that all the dwelling houses will achieve a minimum of a 100% reduction in the dwelling emissions rate/target emissions rate(DER/TER) when compared to the Building Regulations, and all of the houses will be Zero Carbon, for the regulated emissions. This reduction will be achieved in accordance with the proposals in the Zero C sustainability statement and the Zero C data sheets dated the…………….

    Clause 4.1(b) of the “agreement” shall be amended to read as follows “The first show home will achieve a minimum of a 100% reduction in the DER/TER when compared to the Building Regulations, and will be Zero Carbon for the regulated and unregulated emissions. This reduction will be achieved in accordance with the proposals in the ZeroC sustainability statement, and the ZeroC data sheet dated the………Upon completion of the first dwelling house the Applicant shall carry out a post construction assessment to verify this by a qualified assessor. The Applicant will send a copy of the assessment to the Council within 14 days of the Applicant receiving it. Upon receipt, the Council shall confirm in writing whether or not the first dwelling house meets the DER/TER for regulated and unregulated supply (such confirmation by the Council shall not be unreasonably withheld or delayed) For the avoidance of doubt the Applicant shall not be required to carry out any further assessments other than set out in Clause….…. in relation to the standards of construction of the dwelling houses.

    A new clause numbered 4.1c shall be incorporated within the “agreement” and will

    read as follows “Before commencement of the development the Applicant shall provide evidence to the Council to demonstrate that all the dwelling houses shall be designed so that they are capable of being future proofed, to upgrade to achieve a minimum of a 100% reduction in the DER/TER when compared to the Building Regulations, to be Zero Carbon for the unregulated, as well as the regulated emissions, through the use of additional solar photovoltaic panels or equivalent.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    4

    A new clause numbered 4.1(d) shall be incorporated within the “agreement” and will read as follows “the Applicant shall provide marketing information to all buyers of the dwelling houses that they are capable of achieving a minimum of a 100% reduction in the DER/TER when compared to the Building Regulations to be Zero Carbon for the unregulated, as well as regulated emissions and can be upgraded to this standard from day one, for an additional cost should the Purchaser opt for this. Prior to commencement of development the Applicant shall provide evidence to the Council of the marketing information.

    The Energy Statement reviews and updates the pre-approved design specification for

    the Development and confirms that the energy standard required by Plymouth City

    Council can be achieved on-site and across all Phases of the Scheme.

    1.2 Impact of the Adopted Energy Strategy

    This report concludes that the following combination of measures, summarised below

    in Table 1, will be incorporated by the Application and will successfully demonstrate

    how the energy standard will be delivered at Bickleigh Down Eco-Village.

    Table 1: Measures incorporated to deliver the energy standard.

    Fabric first:

    Demand-reduction

    measures

    High standards of sustainable and energy-efficient

    building fabric and insulation to all heat loss floors,

    walls and roofs including timber-framed walls.

    High-efficiency triple-glazed windows throughout.

    Quality of build will be confirmed by achieving good

    air-tightness results throughout.

    Efficient-building services including high-efficiency gas

    boilers and ventilation systems (Mechanical

    Ventilation and Heat Recovery)

    Low-energy lighting throughout the building.

    Renewable and

    low-carbon energy

    technologies

    A total of 329 kWp of Solar PV across the site, based

    on either a southerly, south-westerly or south-easterly

    orientation at a 20-degree tilt. This is equivalent to a

    site-wide area of approximately 2,139–2,632 sqm of

    Solar PV.

    The impact of these design measures in terms of how the Applicant is predicted to

    deliver the energy standard is illustrated in Figure 1 overleaf.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    5

    Figure 1: How the Development meets the energy standard.

    The calculated reduction in regulated CO2 emissions and the percentage reduction

    over ADL 2013 for all dwellings at Bickleigh Down Eco-Village is set out in Table 2.

    Table 2: Regulated CO2 emissions and percentage reduction over ADL 2013.

    Regulated CO2 emissions

    Kg/CO2 per

    annum

    % reduction

    Target Emission Rate: Compliant with ADL

    2013

    180,343

    -

    Fabric first: Demand-reduction measures

    145,505

    19.32%

    Low-carbon and renewable energy

    -4,645

    83.26%

    Total savings

    184,989

    102.58%

    It is concluded in this Energy Statement that the design approach now adopted by

    the Applicant achieves an enhanced standard when compared to the pre-approved

    approach set out in the ZeroC Sustainability Statement.

    180,343

    145,505

    -4,645

    -25,000

    25,000

    75,000

    125,000

    175,000

    225,000

    Target Emission Rate Fabric-First Approach Low-Carbon & RenewableEnergy

    Kg

    CO

    2 p

    er a

    nn

    um

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    6

    1.3 Impact of the Pre-Approved Energy Strategy

    The original ZeroC specification incorporated a Nilan Air Source Heat Pump and

    Mechanical Ventilation and Heat Recovery System with Solar PV.

    For the purposes of comparison, the ZeroC design measures have been modelled as

    a reference for how the Applicant would have achieved the energy standard and via

    the pre-approved approach.

    The calculated reduction in regulated CO2 emissions using the ZeroC specification is

    illustrated in Figure 2 below and in Table 3 overleaf.

    On review, it can be demonstrated that similar carbon reduction levels can be

    achieved through the use of gas-fired heating systems, in lieu of the Nilan system.

    On this basis, the Applicant wishes to proceed with a gas-fired heating system. This

    energy assessment now demonstrates how this approach is in full compliance with

    the requirements of the section 106 agreement.

    Figure 2: How the Development would have met the energy standard with the ZeroC

    specification.

    20,795 20,737

    0

    5,000

    10,000

    15,000

    20,000

    25,000

    Target Emission Rate Fabric-First Approach Low-Carbon & RenewableEnergy

    Kg

    CO

    2 p

    er a

    nn

    um

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    7

    Table 3: Regulated CO2 emissions and percentage reduction over ADL 2013.

    Regulated CO2 emissions

    Kg/CO2 per

    annum

    % reduction

    Target Emission Rate: Compliant with ADL

    2013

    20,795

    -

    Fabric first: Demand-reduction measures

    20,737

    0.28%

    Low-carbon and renewable energy

    -1,154

    105.26%

    Total savings

    21,949

    105.55%

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    8

    2. INTRODUCTION

    2.1 Site Description

    This Energy Statement has been prepared in support of the Bickleigh Eco-Village on

    Land Off Towerfield Drive, Plymouth. This falls under the jurisdiction of Plymouth City

    Council.

    This Energy Statement relates to the following, approved development proposals: 12/01504/FUL: Full planning permission for a maximum 91 residential Code 6 dwellings with an overall gross internal floor area of 12,520 m2 (Class C3); a 672 m2 assembly area with covered arcade (Class B1) to be used for flexible Class A3/A4/B1/D1 use on completion of development ((Blocks A & B); 117 m2 of flexible Class A3/A4/B1/D1 use (Block C); 368 m2 of Class B1/live-work accommodation fronting Tavistock Road together with associated carparking, community green open space and landscaping, village square and new vehicular access off Woolwell Crescent and Towerfield Drive.

    14/00223/FUL: Erection of 11 houses on the western part of the larger site granted planning permission including up to 91 dwellings and the erection of employment live-work units, parking and access under references 12/01504/FUL and 14/00135/FUL. The proposal replaces 7 approved houses but will not increase the total of the larger site.

    Map 1: Site layout for Bickleigh Down, Plymouth.

    Source: ZedFactory 15/06/2016

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    9

    2.2 Purpose of the Energy Statement

    This Statement sets out how the Applicant intends to meet:

    i) National Planning Policy Framework.

    ii) Approved Document Part L of the Building Regulations 2013.

    iii) The energy standard for the development scheme written in the planning

    agreement (as amended) between the Applicant and Plymouth City Council for

    planning applications 14/00223/FUL and 12/01504/FUL.

    For an overview of the planning policy requirements specific to this development,

    refer to Appendix 2.

    The way in which the Applicant meets the energy standard at Bickleigh Down Eco-

    Village, Plymouth, will be set out in this Statement as follows:

    Baseline energy demand: The Development’s Target Emission Rate (TER) will

    be calculated to establish the minimum on-site standard for compliance with ADL

    2013.

    Fabric first – reduced energy demand: The Development’s Dwelling Emission

    Rate (DER) will be calculated to explain how the Applicant’s design specification

    will lead to a reduced energy demand and an improved fabric energy efficiency.

    The better the design of the building fabric in terms of, for example, insulation, air

    tightness and orientation to maximise solar gain, the less energy required to heat

    the dwelling and so the better the fabric energy efficiency.

    Low-carbon and renewable energy: Low-carbon and renewable energy

    technologies are described for the development with the resulting savings in

    regulated CO2 emissions.

    2.3 Methods

    Energist UK has used SAP 2012 methodology to calculate energy demand for 93 of

    the 100 new dwellings within the Bickleigh Down Eco-Village. Until plans for Block C

    are available for assessing, data from seven Block D apartments has been

    extrapolated to provide a more accurate set of results.

    This data provides the Applicant with the regulated CO2 emission rates and energy

    demand for all dwellings included in the development proposals.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    10

    3. BASELINE ENERGY DEMAND

    3.1 Introduction

    In order to measure the effectiveness of demand-reduction measures, it is first

    necessary to calculate the baseline energy demand and this has been done using

    SAP 2012 methodology. This can also be referred to as the Target Emission Rate

    (TER.)

    The resulting ADL 2013 TER for Bickleigh Down Eco-Village, Plymouth, has been

    calculated using Part L model designs which have been applied to the Applicant’s

    Development details. The TER, or baseline energy demand, represents the

    maximum regulated CO2 emissions that are permitted for the Development in order to

    comply with ADL 2013.

    3.2 The Development Baseline

    The resulting TER, representing the total maximum CO2 emissions permitted for the

    Development, has been calculated as 180,343 Kg/CO2 per annum. To ensure

    compliance with ADL 2013, regulated CO2 emissions should not exceed this figure.

    The baseline design specification is referred to in Table 4.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    11

    Table 4. Baseline design specification.

    Element Baseline Design Specification

    Ground Floor U-Value (W/m2.K) 0.13

    External Wall U-Value (W/m2.K) 0.18

    Party Wall U-Value (W/m2.K) 0 (fully filled and sealed)

    Roof – insulated at ceiling U-Value (W/m2.K) 0.13

    Roof – insulated at slope U-Value (W/m2.K) 0.13

    Roof – flat, U-Value (W/m2.K)

    0.13

    Glazing U-Value, including frame (W/m2.K)

    1.4

    Door U-Value (W/m2.K)

    1.2

    Design Air Permeability

    5

    Space Heating

    Mains Gas

    Heating Controls

    Heating System Controls

    Domestic Hot Water

    Mains Gas

    Ventilation

    Natural ventilation with intermittent extract fans

    Low Energy Lighting

    100%

    Thermal Bridging

    Appendix R values

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    12

    4. FABRIC-FIRST APPROACH - REDUCED ENERGY DEMAND

    4.1 Introduction

    Many Local Planning Authorities are now recognising the benefits of a fabric-first

    approach, where the lifetime energy consumption of a building takes precedence over

    the use of bolt-on renewable energy technologies.

    It is clear that the fabric-first approach can create buildings with a very comfortable living

    and working environment. The internal temperature is consistent and fuel bills are kept

    to a minimum. One key advantage of a fabric-first approach is that it does not require

    changes to the behavioural patterns of the occupants and, as such, a building designed

    using a fabric-first approach will often perform more effectively once completed than a

    building that incorporates a low-carbon or renewable-energy technology that requires

    behavioural change (e.g. solar thermal). This becomes an increasingly important

    consideration as energy costs rise and the issue of fuel poverty becomes commonplace.

    Energist UK has considered a fabric-first approach as the priority solution for this

    Development.

    4.2 The Development - Reduced Energy Demand

    The Applicant will integrate the following sustainable design measures to reduce

    energy demand:

    High standards of sustainable and energy-efficient building fabric and

    insulation to all heat loss floors, walls and roofs including timber-framed walls.

    High-efficiency triple-glazed windows throughout.

    Quality of build will be confirmed by achieving good air-tightness results

    throughout.

    Efficient-building services including high-efficiency heating and ventilation

    systems (Mechanical Ventilation and Heat Recovery)

    Low-energy lighting throughout the building.

    The Applicant’s design specification and intended demand-reduction measures for

    the Development have been modelled using the same SAP 2012 methodology as

    before. This allows us to assess the effectiveness of demand-reduction measures as

    a percentage reduction in CO2 emissions over the Baseline.

    The regulated CO2 emissions all new dwellings within the Bickleigh Down Eco-

    Village, Plymouth, is 145,505 Kg/CO2 per annum, which is a reduction of 19.32% or

    34,838 Kg/CO2 per annum over the Baseline. Refer to Appendix 3 for the SAP Data

    and Table 5 for the fabric-first design specification.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    13

    Table 5. The fabric-first design specification at Bickleigh Down Eco-Village, Plymouth.

    Element Fabric-First

    Design Specification

    Ground Floor U-Value (W/m2.K) 0.15

    (Suspended concrete floor, carpeted)

    External Wall U-Value (W/m2.K) 0.14

    (Timber-framed wall with single

    plasterboard)

    Party Wall U-Value (W/m2.K) 0 (fully filled and sealed)

    Roof, Insulated at Pitch, U-Value (W/m2.K) 0.15

    Glazing U-Value – including Frame (W/m2.K)

    1.4 (triple-glazed)

    Rooflights U-Value – including Frame (W/m2.K)

    1.4 (triple-glazed)

    Door U-Value (W/m2.K)

    1.2

    Design Air Permeability

    3.0

    Space Heating

    Mains Gas Boilers: Vaillant ecoTEC plus 624 H System A

    (89.4% efficiency)

    Heating Controls

    Time and temperature zone controls

    Domestic Hot Water

    Mains Gas Heating System

    Ventilation

    System 4: Mechanical Ventilation and Heat Recovery (Vent Axia Ltd)

    Low Energy Lighting

    100%

    Thermal Bridging

    ACDs

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    14

    4.3 Conclusion

    By incorporating high standards of sustainable design and demand reduction

    measures at Bickleigh Down Eco-Village, the Applicant reduces regulated CO2

    emissions by 19.32% over the Baseline for ADL 2013. This is illustrated in Table 6

    and in Figure 3 below.

    Table 6: The Regulated CO2-emissions baseline and fabric-first, demand-reduction

    measures.

    Regulated CO2 emissions

    Kg/CO2 per

    annum

    % reduction

    Target Emission Rate: Compliant with ADL

    2013

    180,343

    -

    Fabric first: Demand-reduction measures

    145,505

    19.32%

    Figure 3: Baseline and fabric-first regulated CO2-emissions summary.

    180,343

    145,505

    0

    20,000

    40,000

    60,000

    80,000

    100,000

    120,000

    140,000

    160,000

    180,000

    200,000

    Target Emission Rate Fabric-First Approach

    Kg

    CO

    2p

    er a

    nu

    m

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    15

    5. LOW-CARBON AND RENEWABLE ENERGY

    5.1 Introduction

    The Applicant adopts a fabric-first approach as the priority solution for this Development

    and steps have been taken to reduce energy demand through high-quality sustainable

    design. The planned integration of efficient building fabric and building services has

    been modelled and is predicted to lead to a considerable enhancement over Part L of

    the Building Regulations 2013.

    The Applicant’s preferred approach is to then incorporate renewable energy to ensure a

    sustainable, energy supply to the site. Solar PV has been selected at Bickleigh Down

    Eco-Village and will successfully implement the full requirement for a 100% reduction in

    regulated CO2 emissions over AD L 2013.

    5.2 Solar PV

    The ability to generate energy (electricity) through harnessing

    natural solar energy. This includes the use of solar

    photovoltaic (PV) panels. PV panels, similarly to turbines, can

    be considered both on and offsite.

    Solar Photovoltaics convert solar radiation into electricity

    which can be used on site or exported to the national grid.

    Installation

    considerations

    Operate most efficiently on a south-facing sloping roof

    (between 30 and 45-degree pitch.)

    Shading must be minimal (one shaded panel can impact

    the output of the rest of the array.)

    Panels must not be laid horizontally on a flat roof as they

    will not self-clean. Panels will therefore need to be

    installed at an angle and with appropriate space between

    them, to avoid over-shading.

    Large arrays may require upgrades to substations if

    exporting electricity to the grid.

    Local planning requirements may restrict installation of

    panels on certain elevations.

    Installation must take into account pitch and fall of the roof,

    along with any additional plant on the roof to ensure there

    is sufficient room.

    The average domestic solar PV system is 4kWp and costs

    £5,000 - £8,000 (including VAT at 5 per cent) - (taken from

    the Energy Saving Trust, TBC by supplier.)

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    16

    Advantages

    Relatively straightforward installation, connection to

    landlord’s supply and metering.

    Linear improvement in performance as more panels are

    installed.

    Maintenance free.

    Installation costs are continually reducing.

    Can benefit from the Feed in Tariff to improve financial

    payback.

    Disadvantages

    Not appropriate for high-rise developments, due to lack of

    roof space in relation to total floor area, though this is not

    an issue at Bickleigh Down.

    Development

    feasibility

    The suitability of Solar PV has been considered for this

    Development and is concluded as a technically-viable

    option.

    There are areas of roof space suitable for the positioning

    of unshaded Solar PV arrays.

    The Development is not on land which is protected or

    listed, so it is considered that Solar panels would not

    have a negative impact on the local historical

    environment or the aesthetics of the area.

    The occupants may be entitled to claim the Feed-In-

    Tariff for any energy which is generated.

    The commercial viability of Solar PV has been

    considered by the Applicant and is concluded a

    beneficial, economical investment.

    A total of 329 kWp of Solar PV is to be installed on

    unshaded and well-orientated roofs across the site,

    based on either a southerly, south-westerly or south-

    easterly orientation at a 20-degree tilt. This is equivalent

    to a site-wide area of approximately 2,139–2,632 sqm of

    Solar PV. For a plot-by-plot PV allocation, refer to the PV

    allocation in Appendix 4.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    17

    6. ACHIEVING ZERO CARBON ON THE ECO-VILLAGE SHOW HOME

    6.1 Introduction

    Plymouth City Council require the Applicant to confirm their Energy Strategy

    demonstrating compliance with:

    “The first show home will achieve a minimum of a 100% reduction in the DER/TER

    when compared to the Building Regulations, and will be Zero Carbon for the

    regulated and unregulated emissions.

    6.2 Measures for Compliance

    The Applicant will achieve further reductions over the baseline for the Eco-Village Show

    Home by increasing the Solar PV specification. By incorporating 9.75 kWp of Solar PV,

    in a southerly orientation and at a 20-degree pitch, the Show Home will achieve a 100%

    reduction in both regulated and unregulated CO2 emissions over AD L 2013 and will

    successfully implement the full LPA requirement.

    Refer to Appendix 5 for a report confirming a 100% reduction in DER/TER in both

    regulated and unregulated energy for the Show Home.

    If there is a market requirement from home buyers requesting an equivalent-standard

    property to the Eco-Village Show Home, then there is the potential to increase the Solar

    PV specification and further reduce on-site CO2 emissions. The viability of progressing

    onto a standard of 100% reduction in both regulated and unregulated CO2 emissions

    over AD L 2013 has been assessed for each plot at Bickleigh Down Eco-Village and a

    Solar PV specification calculated accordingly and as part of the energy assessment.

    Refer to Appendix 4 for reference to the PV allocation by plot, uplifting the on-site

    energy standard from a 100% reduction in regulated CO2 emissions to a 100%

    reduction in both regulated and unregulated CO2 emissions over AD L 2013.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    18

    7. CONCLUSIONS

    The Applicant demonstrates commitment to delivering the energy standard at

    Bickleigh Down Eco-Village, Plymouth, as follows:

    The Development will generate a total reduction in regulated CO2 emissions of

    102.58% over the TER ADL 2013 which meets the requirement:

    Before commencement of development the Applicant shall provide evidence to

    the Council to demonstrate that all the dwelling houses will achieve a minimum of

    a 100% reduction in the dwelling emissions rate/target emissions rate (DER/TER)

    when compared to the Building Regulations.

    This energy standard is delivered through high standards of sustainable design,

    through passive and active design measures. Renewable energy is also

    incorporated to provide a sustainable, energy supply across the Scheme.

    The Applicant provides confirmation that they will achieve an energy standard in

    the Eco-Village Show Home that is equivalent to a 100% reduction in both

    regulated and unregulated CO2 emissions over the TER ADL 2013. Furthermore,

    it can be concluded that there is further potential to uplift the current Solar PV

    specification in new dwellings across the Scheme and if potential home-buyers

    were to request this option.

    A combination of demand-reduction measures, energy-efficiency measures and

    renewable energy will deliver the Applicant’s target for on-site reduction in regulated

    CO2 emissions.

    Design measures, summarised overleaf in Table 7, are incorporated in the

    Development.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    19

    Table 7. Measures incorporated to deliver the energy standard.

    Fabric first:

    Demand-reduction

    measures

    High standards of sustainable and energy-efficient

    building fabric and insulation to all heat loss floors,

    walls and roofs including timber-framed walls.

    High-efficiency triple-glazed windows throughout.

    Quality of build will be confirmed by achieving good

    air-tightness results throughout.

    Efficient-building services including high-efficiency gas

    boilers and ventilation systems (Mechanical

    Ventilation and Heat Recovery)

    Low-energy lighting throughout the building.

    Renewable and

    low-carbon energy

    technologies

    A total of 329 kWp of Solar PV across the site, based

    on either a southerly, south-westerly or south-easterly

    orientation at a 20-degree tilt. This is equivalent to a

    site-wide area of approximately 2,139–2,632 sqm of

    Solar PV.

    The way in which these design measures deliver the Applicant’s commitment to the

    energy standard is illustrated in Figure 4 below and Table 8 overleaf.

    Figure 4: How the Development delivers the energy standard.

    180,343

    145,505

    -4,645

    -25,000

    25,000

    75,000

    125,000

    175,000

    225,000

    Target Emission Rate Fabric-First Approach Low-Carbon & RenewableEnergy

    Kg

    CO

    2p

    er a

    nn

    um

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    20

    Table 8: How the Development reduces regulated CO2 emissions.

    Regulated CO2 emissions

    Kg/CO2 per

    annum

    % reduction

    Target Emission Rate: Compliant with ADL

    2013

    180,343

    -

    Fabric first: Demand-reduction measures

    145,505

    19.32%

    Low-carbon and renewable energy

    -4,645

    83.26%

    Total savings

    184,989

    102.58%

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    21

    8. APPENDICES

    APPENDIX 1: LIST OF ABBREVIATIONS

    ADL 2013 Approved Document Part L of Buildings Regulations 2013

    ASHP Air Source Heat Pump

    CHP Combined Heat & Power

    DER Dwelling Emission Rate

    DHN District Heat Network

    DHW Domestic Hot Water

    ESCO Energy Services Company

    GSHP Ground Source Heat Pump

    LPA Local Planning Authority

    PV Photovoltaics

    SAP Standard Assessment Procedure

    TER Target Emission Rate

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    22

    APPENDIX 2: PLANNING POLICY AND DESIGN GUIDANCE

    The Climate Change Act (2008)

    Passed in November 2008, the Climate Change Act mandated that the UK would reduce

    emissions of six key greenhouse gases, including Carbon Dioxide, by 80% by 2050.

    As a consequence, the reduction of carbon dioxide emissions is at the forefront of

    National, Regional and Local Planning Policy, along with continuing step changes in

    performance introduced by the Building Regulations Approved Document L (2013).

    Approved Document L (2013)

    This development is subject to the requirements of Approved Document L (2013). ADL

    2013 represented an approximate reduction of 6% in the Target Emission Rate

    (Kg/CO2/sqm per annum) over the requirements of Approved Document L (2010) for

    residential development and an aggregate 9% reduction for non-residential development.

    ADL (2013) also sees the introduction of a Fabric Energy Efficiency Target, a measure of

    heating demand (kW hrs/sqm per annum) to ensure new-build dwellings with low-carbon

    heating systems still meet satisfactory energy-efficiency standards.

    National Policy

    The National Planning Policy Framework encourages Local Planning Authorities to “Have

    a positive strategy to promote energy from renewable and low-carbon sources” (NPPF

    paragraph 97), whilst “Ensuring that the adverse impacts are addressed satisfactorily,

    including cumulative landscape and visual impacts”. This suggests that although LPAs

    should encourage renewable technology, the merits of such should be assessed on a site-

    by-site basis.

    The NPPF also requires that policy-making and planning obligations do not threaten the viability of a development, by maintaining competitive returns for developers and landowners alike. In this respect flexibility is encouraged by LPAs to ensure sustainability standards can be met without incurring unreasonable development costs.

    The Housing Standards Review and implications on Local Planning Policy

    On March 25th 2015 the Government confirmed its policy to limit energy-efficiency targets

    that can be imposed on a development as a result of the Housing Standards Review. New

    developments should not be conditioned to achieve a reduction in Carbon Emissions

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    23

    exceeding a 19% improvement over the requirements of Approved Document L (2013) –

    the equivalent energy performance of a Code for Sustainable Homes Level 4 dwelling.

    In addition the Government confirmed that the Code for Sustainable Homes is no longer

    an applicable standard for planning permissions granted on or after March 26th 2015. If a

    Local Planning Authority has an existing policy requirement for the CSH it may still

    condition the Ene 1 and Wat 1 requirements for CSH Level 4, but cannot require

    assessment against the remaining categories and full CSH Certification.

    Sites with planning permission granted prior to March 25th 2015 can still be assessed and

    certified against the Code for Sustainable Homes, where there is a requirement to do so

    (known as legacy sites).

    A CSH requirement can also apply where a previously approved Outline Planning

    Permission has been granted prior to March 25th 2015.

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    24

    APPENDIX 3: SAP DATA.

    Dwelling TypeNo. Of HT on

    siteFloor Area

    Target

    Emissions

    (TER)

    Fabric-First

    Approach

    (DER)

    Low-Carbon

    & Renewable

    Energy (DER)

    Total Target

    Emissions

    Fabric-First

    Approach

    Low-Carbon

    & Renewable

    Energy

    Plot 001 1 162 15.11 11.81 -0.64 2,447.82 1,913.22 103.68-

    Plot 002 1 162 14.84 11.61 -0.84 2,404.08 1,880.82 136.08-

    Plot 003 1 162 14.73 11.5 -0.26 2,386.26 1,863.00 42.12-

    Plot 004 1 162 14.84 11.61 -0.15 2,404.08 1,880.82 24.30-

    Plot 005 1 162 14.73 11.5 -0.26 2,386.26 1,863.00 42.12-

    Plot 006 1 162 14.73 11.5 -0.26 2,386.26 1,863.00 42.12-

    Plot 007 1 162 14.84 11.61 -0.15 2,404.08 1,880.82 24.30-

    Plot 008 1 162 14.73 11.5 -0.26 2,386.26 1,863.00 42.12-

    Plot 009 1 162 14.73 11.5 -0.26 2,386.26 1,863.00 42.12-

    Plot 010 1 162 14.73 11.5 -0.26 2,386.26 1,863.00 42.12-

    Plot 011 1 162 14.73 11.5 -0.26 2,386.26 1,863.00 42.12-

    Plot 012 1 162 14.71 11.55 -0.21 2,383.02 1,871.10 34.02-

    Plot 013 1 74.2 19.34 16.02 -0.59 1,435.03 1,188.68 43.78-

    Plot 014 1 74.2 17.93 14.85 -0.25 1,330.41 1,101.87 18.55-

    Plot 015 1 74.2 19.73 16.44 -0.18 1,463.97 1,219.85 13.36-

    Plot 016 1 99.2 16.42 13.29 -0.26 1,628.86 1,318.37 25.79-

    Plot 017 1 99.2 14.92 12.05 -0.38 1,480.06 1,195.36 37.70-

    Plot 018 1 99.2 16.44 13.41 -0.14 1,630.85 1,330.27 13.89-

    Plot 019 1 99.2 16.42 13.29 -0.26 1,628.86 1,318.37 25.79-

    Plot 020 1 99.2 14.92 12.05 -0.38 1,480.06 1,195.36 37.70-

    Plot 021 1 99.2 16.56 13.54 -0.02 1,642.75 1,343.17 1.98-

    Plot 022 1 162 14.78 11.56 -0.2 2,394.36 1,872.72 32.40-

    Plot 023 1 162 14.82 11.59 -0.17 2,400.84 1,877.58 27.54-

    Plot 024 1 94.2 17.47 14.5 -0.24 1,645.67 1,365.90 22.61-

    Plot 025 1 94.2 16 13.23 -0.38 1,507.20 1,246.27 35.80-

    Plot 026 1 94.2 16.12 13.36 -0.25 1,518.50 1,258.51 23.55-

    Plot 027 1 94.2 16.12 13.36 -0.25 1,518.50 1,258.51 23.55-

    Plot 028 1 94.2 16 13.23 -0.38 1,507.20 1,246.27 35.80-

    Plot 029 1 94.2 16.38 13.54 -0.07 1,543.00 1,275.47 6.59-

    Plot 030 1 103.5 16.17 13.39 -0.03 1,673.60 1,385.87 3.11-

    Plot 031 1 103.5 15.28 12.76 -0.66 1,581.48 1,320.66 68.31-

    Plot 032 1 103.5 16.99 14.23 -0.22 1,758.47 1,472.81 22.77-

    Plot 033 1 93.4 19.01 15.52 -0.49 1,775.53 1,449.57 45.77-

    Plot 034 1 139.5 14.95 11.86 -0.39 2,085.53 1,654.47 54.41-

    Plot 035 1 139.5 13.78 10.84 -0.65 1,922.31 1,512.18 90.68-

    Plot 036 1 139.5 13.78 10.84 -0.65 1,922.31 1,512.18 90.68-

    Plot 037 1 139.5 14.83 11.73 -0.52 2,068.79 1,636.34 72.54-

    Plot 038 1 99.2 17.21 13.94 -0.06 1,707.23 1,382.85 5.95-

    Plot 039 1 99.2 15.92 12.89 -0.03 1,579.26 1,278.69 2.98-

    Plot 040 1 99.2 15.92 12.89 -0.03 1,579.26 1,278.69 2.98-

    Plot 041 1 99.2 15.92 12.89 -0.03 1,579.26 1,278.69 2.98-

    Plot 042 1 99.2 16.04 13.03 -0.97 1,591.17 1,292.58 96.22-

    Plot 043 1 99.2 16.04 13.03 -0.97 1,591.17 1,292.58 96.22-

    Plot 044 1 99.2 17.25 14.08 -1 1,711.20 1,396.74 99.20-

    Plot 045 1 161.7 14.12 11.08 -0.15 2,283.20 1,791.64 24.26-

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    25

    Plot 046 1 93.4 18.47 15.16 -0.44 1,725.10 1,415.94 41.10-

    Plot 047 1 162 14.71 11.48 -0.39 2,383.02 1,859.76 63.18-

    Plot 048 1 162 14.82 11.59 -0.28 2,400.84 1,877.58 45.36-

    Plot 049 1 162 14.82 11.59 -0.28 2,400.84 1,877.58 45.36-

    Plot 050 1 162 14.82 11.59 -0.28 2,400.84 1,877.58 45.36-

    Plot 051 1 162 14.82 11.59 -0.28 2,400.84 1,877.58 45.36-

    Plot 052 1 162 14.82 11.59 -0.28 2,400.84 1,877.58 45.36-

    Plot 053 1 162 14.82 11.59 -0.28 2,400.84 1,877.58 45.36-

    Plot 054 1 162 14.82 11.59 -0.28 2,400.84 1,877.58 45.36-

    Plot 055 1 162 14.94 11.7 -0.17 2,420.28 1,895.40 27.54-

    Plot 056 1 140.7 15.95 12.89 -0.78 2,244.17 1,813.62 109.75-

    Plot 057 1 140.7 15.82 12.77 -0.89 2,225.87 1,796.74 125.22-

    Plot 058 1 140.7 15.82 12.77 -0.14 2,225.87 1,796.74 19.70-

    Plot 059 1 140.7 15.82 12.77 -0.14 2,225.87 1,796.74 19.70-

    Plot 060 1 140.7 15.82 12.77 -0.14 2,225.87 1,796.74 19.70-

    Plot 061 1 162 14.93 11.66 -0.21 2,418.66 1,888.92 34.02-

    Plot 062 1 162 14.93 11.66 -0.21 2,418.66 1,888.92 34.02-

    Plot 063 1 162 14.93 11.66 -0.21 2,418.66 1,888.92 34.02-

    Plot 064 1 162 14.84 11.63 -0.24 2,404.08 1,884.06 38.88-

    Plot 065 1 93.4 19.01 15.52 -0.49 1,775.53 1,449.57 45.77-

    Plot 066 1 161.7 14.06 11.09 -0.14 2,273.50 1,793.25 22.64-

    Plot 067 1 139.5 14.89 11.75 -0.5 2,077.16 1,639.13 69.75-

    Plot 068 1 139.5 13.96 10.99 -0.5 1,947.42 1,533.11 69.75-

    Plot 069 1 139.5 13.96 10.99 -0.5 1,947.42 1,533.11 69.75-

    Plot 070 1 139.5 15.01 11.88 -0.37 2,093.90 1,657.26 51.62-

    Plot 072 1 103.5 15.28 12.68 -0.74 1,581.48 1,312.38 76.59-

    Plot 072 1 103.5 15.01 12.53 -0.89 1,553.54 1,296.86 92.12-

    Plot 073 1 103.5 15.55 12.94 -0.48 1,609.43 1,339.29 49.68-

    Plot 074 1 94.2 16.03 13.25 -0.36 1,510.03 1,248.15 33.91-

    Plot 075 1 94.2 15.77 13.07 -0.54 1,485.53 1,231.19 50.87-

    Plot 076 1 94.2 15.91 13.19 -0.41 1,498.72 1,242.50 38.62-

    Plot 077 1 94.2 16.08 13.32 -0.29 1,514.74 1,254.74 27.32-

    Plot 078 1 74.8 17.78 14.72 -0.99 1,329.94 1,101.06 74.05-

    Plot 079 1 74.2 20.45 17.4 -0.72 1,517.39 1,291.08 53.42-

    Plot 080 1 74.2 19.41 16.18 -0.43 1,440.22 1,200.56 31.91-

    Plot 081 1 74.2 17.78 14.72 -0.38 1,319.28 1,092.22 28.20-

    Plot 082 1 74.2 17.93 14.85 -0.25 1,330.41 1,101.87 18.55-

    Plot 083 1 74.2 17.93 14.85 -0.25 1,330.41 1,101.87 18.55-

    Plot 084 1 74.2 17.78 14.72 -0.38 1,319.28 1,092.22 28.20-

    Plot 085 1 74.2 19.41 16.18 -0.43 1,440.22 1,200.56 31.91-

    Plot 093 2 58.4 20.73 17.32 -1.44 2,421.26 2,022.98 168.19-

    Plot 094 2 56.1 20.41 17.85 -1.19 2,290.00 2,002.77 133.52-

    Plot 095 2 58.4 19.74 16.02 -0.45 2,305.63 1,871.14 52.56-

    Plot 096 2 58.4 17.84 15.09 -1.38 2,083.71 1,762.51 161.18-

    Plot 097 2 47.1 20.68 18.97 -1.44 1,948.06 1,786.97 135.65-

    Plot 098 2 58.4 17.81 15.02 -1.44 2,080.21 1,754.34 168.19-

    Plot 099 2 78.6 18.09 15.73 -0.58 2,843.75 2,472.76 91.18-

    Plot 100 1 78.6 18.07 15.74 -0.57 1,420.30 1,237.16 44.80-

    - - -

    Total Plots 100 Total Site Wide CO2 180,343 145,505 -4,645

    Reductions 19.32% 102.58%

    19.32% 83.26%

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    26

    APPENDIX 4: PV ALLOCATION.

    Dwelling TypeNo. Of HT on

    siteFloor Area

    PV by plot to

    achieve 100%

    reduction in

    regulated CO2 emissions

    PV by plot to

    achieve 100%

    reduction in

    regulated &

    unregulated

    CO2 emissions

    PV uplift

    required

    Plot 001 1 162 4.5 9.25 4.75

    Plot 002 1 162 4.5 9.25 4.75

    Plot 003 1 162 4.25 9.00 4.75

    Plot 004 1 162 4.25 9.25 5.00

    Plot 005 1 162 4.25 9.00 4.75

    Plot 006 1 162 4.25 9.00 4.75

    Plot 007 1 162 4.25 9.00 4.75

    Plot 008 1 162 4.25 9.00 4.75

    Plot 009 1 162 4.25 9.00 4.75

    Plot 010 1 162 4.25 9.00 4.75

    Plot 011 1 162 4.25 9.00 4.75

    Plot 012 1 162 4.25 9.00 4.75

    Plot 013 1 74.2 2.75 6.00 3.25

    Plot 014 1 74.2 2.50 6.00 3.50

    Plot 015 1 74.2 2.75 6.00 3.25

    Plot 016 1 99.2 3.00 6.75 3.75

    Plot 017 1 99.2 2.75 6.50 3.75

    Plot 018 1 99.2 3.00 6.75 3.75

    Plot 019 1 99.2 3.00 6.75 3.75

    Plot 020 1 99.2 2.75 6.50 3.75

    Plot 021 1 99.2 3.00 7.00 4.00

    Plot 022 1 162 4.25 9.00 4.75

    Plot 023 1 162 4.25 9.25 5.00

    Plot 024 1 94.2 3.25 7.50 4.25

    Plot 025 1 94.2 3.00 7.00 4.00

    Plot 026 1 94.2 3.00 7.00 4.00

    Plot 027 1 94.2 3.00 7.00 4.00

    Plot 028 1 94.2 3.00 7.00 4.00

    Plot 029 1 94.2 3.00 7.00 4.00

    Plot 030 1 103.5 3.25 7.50 4.25

    Plot 031 1 103.5 3.25 7.50 4.25

    Plot 032 1 103.5 3.50 7.50 4.00

    Plot 033 1 93.4 3.50 7.50 4.00

    Plot 034 1 139.5 4.00 9.00 5.00

    Plot 035 1 139.5 3.75 9.50 5.75

    Plot 036 1 139.5 3.75 9.50 5.75

    Plot 037 1 139.5 4.00 8.75 4.75

    Plot 038 1 99.2 3.25 7.25 4.00

    Plot 039 1 99.2 3.00 7.00 4.00

    Plot 040 1 99.2 3.00 7.00 4.00

    Plot 041 1 99.2 3.00 7.00 4.00

    Plot 042 1 99.2 3.25 7.00 3.75

    Plot 043 1 99.2 3.25 7.00 3.75

    Plot 044 1 99.2 3.50 7.25 3.75

    Plot 045 1 161.7 4.25 9.25 5.00

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    27

    Plot 046 1 93.4 3.25 7.00 3.75

    Plot 047 1 162 4.50 9.50 5.00

    Plot 048 1 162 4.50 9.50 5.00

    Plot 049 1 162 4.50 9.50 5.00

    Plot 050 1 162 4.50 9.50 5.00

    Plot 051 1 162 4.50 9.50 5.00

    Plot 052 1 162 4.50 9.50 5.00

    Plot 053 1 162 4.50 9.50 5.00

    Plot 054 1 162 4.50 9.50 5.00

    Plot 055 1 162 4.50 9.50 5.00

    Plot 056 1 140.7 4.50 9.50 5.00

    Plot 057 1 140.7 4.50 9.50 5.00

    Plot 058 1 140.7 4.25 9.50 5.25

    Plot 059 1 140.7 4.25 9.25 5.00

    Plot 060 1 140.7 4.25 9.25 5.00

    Plot 061 1 162 4.50 9.50 5.00

    Plot 062 1 162 4.50 9.50 5.00

    Plot 063 1 162 4.50 9.50 5.00

    Plot 064 1 162 4.50 9.50 5.00

    Plot 065 1 93.4 3.50 7.50 4.00

    Plot 066 1 161.7 4.25 9.25 5.00

    Plot 067 1 139.5 4.00 9.00 5.00

    Plot 068 1 139.5 3.75 8.50 4.75

    Plot 069 1 139.5 3.75 8.50 4.75

    Plot 070 1 139.5 4.00 8.75 4.75

    Plot 072 1 103.5 3.25 7.50 4.25

    Plot 072 1 103.5 3.25 7.25 4.00

    Plot 073 1 103.5 3.25 7.25 4.00

    Plot 074 1 94.2 3.00 7.00 4.00

    Plot 075 1 94.2 3.00 7.00 4.00

    Plot 076 1 94.2 3.00 7.00 4.00

    Plot 077 1 94.2 3.00 7.00 4.00

    Plot 078 1 74.8 2.75 6.25 3.50

    Plot 079 1 74.2 3.00 6.00 3.00

    Plot 080 1 74.2 2.75 6.00 3.25

    Plot 081 1 74.2 2.50 6.00 3.50

    Plot 082 1 74.2 2.50 6.00 3.50

    Plot 083 1 74.2 2.50 6.00 3.50

    Plot 084 1 74.2 2.50 6.00 3.50

    Plot 085 1 74.2 2.75 6.00 3.25

    Plot 093 2 58.4 2.50 5.00 2.50

    Plot 094 2 56.1 2.50 5.00 2.50

    Plot 095 2 58.4 2.25 5.00 2.75

    Plot 096 2 58.4 2.25 5.00 2.75

    Plot 097 2 47.1 2.25 5.00 2.75

    Plot 098 2 58.4 2.25 5.00 2.75

    Plot 099 2 78.6 3.00 6.75 3.75

    Plot 100 1 78.6 3.00 6.75 3.75

  • BICKLEIGH DOWN ECO-VILLAGE, LAND OFF TOWERFIELD DRIVE, PLYMOUTH ENERGY STATEMENT

    28

    APPENDIX 5: ZERO CARBON REPORT – SHOW HOME