Upload
alousteve
View
226
Download
0
Embed Size (px)
Citation preview
7/27/2019 Energy Shelters V2[1].1
1/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Construction
Primary
Procedures Chapter 1Equipment Room
System Construction
1. Installing Shelter
2. Equipment Room Power
Distribution
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
2/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Install the
base
Install
guide railInstall
wallboardInstall
top frame
Next step
Install
top plate
1. Installing shelter
Self-supporting tower - equipment room system construction
Install
floor
Install
antistatic
floor
Install
bottom
plate
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
3/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelter - primary tools
Adjustable wrench Percussion drill MultimeterScrewdriver
Steel tapeSteel saw Horizontal ruler Torque spanner
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
4/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelter - primary auxiliary materials
Antistatic copper foil Expansion bolt
Plastic welding rod Sealant
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
5/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. The parts of the base are connected with bolts that expose two to three threads after being fastened.2. Once the base is installed, it must be measured horizontally and with diagonal, at a variation within2 mm.
3. The base spacing is allowed to have a variation of1 mm.
4. The spacing should be measured at the same.
5. Spacing is the central distance between two adjacent angles.
6. To measure the spacing is to make sure the shelter base is a rectangle or square (each angle is a right angle).
Installing shelterinstalling shelter base
Measuring
diagonal
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
6/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelterinstalling bottom plate
Note: 1.The bottom plate is assembled with several boards that are tightened on H-shaped steel.
2.The bottom plate is fixed with tapping screws that are staggered at a spacing of 200 mm.
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
7/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1.After the bottom plate is installed.
2.Install the guide rail by connecting with the bottom plate through long screws in a nice looking and leveled
manner.
3.The gaps between the guide rail and the bottom plate should be regulated under 5 mm, and two or three threads
should be exposed after the screws are tightened.
Installing shelterinstalling guide rail
Gaps between
guide rail and
bottom plate 5
mm
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
8/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. Wallboards are connected to each other by H-shaped aluminum and fixed with rivets that are staggered at a
spacing of 200 mm.
2. Each wallboard is fully embedded into the base and the connections should be painted with waterproof
glue evenly and completely.
Installing shelterinstalling guide rail
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
9/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1.The top frame is connected to the flange on the column by bolts.
2.The wallboards and top frame should be checked for verticality before the bolts are tightened, and those bolts
exceeding the top frame should be leveled.
3.The wallboards and top frame are connected with rivets in a reliable, leveled and beautiful manner.
Installing shelterinstalling top frame
Flange on the
column
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
10/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. Waterproof trough (in stainless steel structure)
should be installed for top plate at its joints with rivets (Figure 1)
at a spacing of 200 mm between rivets that should be staggered.
2. And the connection between waterproof trough
with color steel plate (pressed and colored) should be brushed
evenly with waterproof glue.
Installing shelterinstalling top plate
Water proof
trough
Figure 2
Figure 3
Top plate joint
Install waterprooftrough
One of
top plates
Figure 1
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
11/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: The battens for wrap angles, seams and blank holders must be secured firmly and pressed flatly without any gap at
ends.
Wrap
angle of
shelter
Installing shelterinstalling batten
Batte
n
Edges at
the ends of
batten
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
12/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1.The walls drilled with wrong holes must be made up with waterproof and corrective measures, without
affecting its function.
2.Failure to take corrective measures for wrong holes drilled will lead rain water into the walls, thus
affecting the service life and functions.
Wrong holes
drilled
Installing shelter
Wrong bolts
fixed
Incorrect
MethodGreenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
13/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1.Once all shelter parts are installed, clean the floor and lay copper foils on it to build a copper mesh.
2.The copper foil can be stuck on the shelter floor or cover a layer of wood plates which should be sealed tightly.
3.The number of copper foils is subject to the area of the room, but the spacing between horizontal and vertical directions as
per design requirements. Use copper foil to cover the wall foundation near the grounding copper bar to form a thin copper strip and a certain
length of copper strip is reserved to be exposed on the ground surface to connect with the grounding copper bar (or tape-controlled angle
steel or aluminium batten).
Installing shelterinstalling antistatic floor
Copper
foil
reserved
Thin copper
strip, 5 cm to
10 cm from
ground
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
14/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelterinstalling antistatic floor
Note: 1.Apply the rubber evenly on a PVC antistatic
floor with rubber friction tool and wait for 15 minutes
before laying the antistatic floor
2. Keep the floor clean.
Antistatic
floor
PVC
Antistatic
floor
PVC
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
15/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelterinstalling antistatic floor
Note: 1.In figure 1, the reserved length of copper foil is not enough so that the connection with batten is not stable.
2.In figure 2, applying rubber on the bottom plate may easily involve dusts, staining the floor and
compromising the effect of antistatic floor ad the installation.
Incorrect
Method
Apply rubber on
the bottom plate
directly
Reserved copper foil
length not enough
Figure 1 Figure 2
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
16/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelterinstalling antistatic floor
Note: 1. Each PVC antistatic rubber should be closely connected (size of PVC near the wall foundation should be
measured and cut in advance).
2. After installing the antistatic rubber, apply sealant rubber evenly and squarely on the perimeter and the
seams of walls.
3. Figure 1 Applying sealant
4. Figure 2 Part of sealant is leveled.
Figure 1 Figure 2
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
17/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelterinstalling antistatic floor
Note: Level the sealant above ground with blade to be aligned with floor surface.
Figure1 Figure2
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
18/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelterinstalling antistatic floor
Note: 1.The indoor grounding copper strip is made of the
same materials for horizontal grounding of grounding grids, ata size of 25*3 mm.
2.The grounding copper foil extension (batten) on
the anti-lightning grounding board is connected with the walls
using screws and connected with outdoor grounding grids.
Grounding
copper strip in
shelter
Grounding copper
strip in shelter
Connection of grounding
copper strip with
grounding grids
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
19/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Installing shelterinstalling antistatic floor
Note: 1.The installed antistatic floor should be leveled with evenly distributed wires. (PVC floor is actually
conductive floor.
2.Recommendation is to have a resistance of not lower than 1.0*106ohm, and the viscose used is also a
non water soluble conductive rubber to conduct static electricity).
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
20/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
2. Equipment room
power distribution
Feederwin
dow
Cablingr
ack
ACDB
ACdistribu
tion
cabinet
AVR
Laying
of
powerca
bles
Switchoutletand
emergencylightsfor
indoorlighting
Outdoorlig
hting
Alarm
system
Intelligent
ventilationsystem
Airconditioningsystem
Firefightingsystem
Grounding
system
31 2
Self-supporting tower - equipment room system construction
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
21/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
2. Equipment room
power distribution
ACDB
ACdistribution
cabinet
AVR
Layingofpower
cables
Switchoutletand
emergencylightsfor
indoorlighting
Outdoorlighting
Alarmsystem
Intelligentventilation
system
Airconditioning
system
Firefighting
system
Grounding
system
1 32
Feederwindow
Cablingrack
Self-supporting tower - equipment room system construction
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
22/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room -(1)installing feeder window
Notes: 1. The opening of feeder window should meet design requirements and the
following principles:
2. Take a comprehensive consideration of the opening direction of equipment
room doors and position of tower to get a straight line for the feeders and connect the
connectors of feeder 7/8 and 1/2 by opening the feeder window towards to the tower
wherever possible.
3. The feeder window should be placed where the feeders are connected
behind the soft jumper to get the soft jumper straight to the main equipment.
4. Install the feeder window stably and tightly.
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
23/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room - (1)installing
feeder window
Notes: 1. Figure 1 shows the cross-section of outdoor feeder window in which M8 expansion bolts are used to
secure the sealing bottom plate.
2. Figure 2 shows front view of outdoor feeder.
Feeder penetration
sealing bottom plate
Various sealing devices
Fastening hoop
Plate sealing cover
M8 expansion bolt
Figure2Figure1
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
24/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room - (1)installing feeder window
Note: 1.Insert the penetration sealing board
2.The outdoor part of feeder window, into the pre-chiseled window on the wall (according to design
requirements)
3.Use rivets between outdoor feeder window plate of unit equipment room and walls.
Rivet Closing plug
for feeder
window
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
25/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room - (1)installing feeder window
Note: 1. When the penetration sealing bottom plate is installed inside the feeder window.
2. The indoor sealing bottom plate is located inside the outdoor sealing bottom plate (the external diameter
of outdoor penetration sealing bottom plate is greater than that of indoor one.
3. So the outdoor one is installed against the wall) to guard against water.
Inside
feeder
window
Indoor sealing
bottom plate
Greenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
26/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room - (1)installing feeder window
Note: 1. When the installation is finished.
2. Sealant should be applied at the external part of feeder window.
3. For tight sealing the sealant should be spread evenly and tidily.
The outside of the feeder
window is closed with
sealants.
Greenf ield SiteEquipment Room System
G fi ld Si E i R S
7/27/2019 Energy Shelters V2[1].1
27/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room -(1)installing cabling rack
Note: 1.The indoor cabling rack is fixed on the wall with bolts. Before that, cables are drawn on the wall to facilitate the
straight installation of the cabling rack.
2.Because the cabling rack bears heavy cables, some places should be fixed with hangers, such as shelter frame,
ceiling suspension, bypass support and terminal and wall reinforcement.(In wiring, strong and weak current cables are placed
separately at a certain spacing.)
Support Complete
outside view of
cabling rack
Cabling
stairs
Shelter
frame
Greenf ield SiteEquipment Room System
G fi ld Sit E i t R S t
7/27/2019 Energy Shelters V2[1].1
28/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room -(1)installing cabling rack
Note: 1. Grounding wires are connected between cabling racks
2. Another yellow green grounding wire is prepared to connect with grounding copper bar.
Between cabling racksthere are grounding wire
connections Yellow green
grounding wire
Greenf ield SiteEquipment Room System
IncorrectG fi ld Sit E i t R S t
7/27/2019 Energy Shelters V2[1].1
29/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. The indoor cabling rack must be firmly fixed on the wall or rooftop.
2. The Cabling Rack must be parallel and even secured with bolts for stability.
The cabling rack
direction is wrong. The
diagram is upside down
and the plane should faceupward.
Incorrect
Method
Power distribution in equipment room -(1)installing cabling rack
Greenf ield SiteEquipment Room System
G fi ld Sit E i t R S t
7/27/2019 Energy Shelters V2[1].1
30/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
2. Equipment Room
Power Distribution
Feederwind
ow
Cablingrack
A
C
D
B
A
T
S
A
V
R
Layingofp
ower
cables
Switchoutletand
emergencylightsfor
indoorligh
ting
Outdoorlighting
Smokedetector,tem
perature
detector,doorcontr
ol,water
alarmandoutdooralarm
Intelligentventilation
system
Airconditionin
gsystem
Groundingsystem
31 2
Firefigh
ting
system
Self-supporting tower - equipment room system construction
Greenf ield SiteEquipment Room System
G fi ld Sit E i t R S t
7/27/2019 Energy Shelters V2[1].1
31/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2) - schematic diagram of power
supply (1)
Mains
Diesel engine
Electric
meter
lightning
proof boxATS ACDB
AC
Power cabinet
Outdoor
lighting
Aviationobstruction
lamps
Air conditioner
Indoor lightingTelecomequipment
Environment monitor Emergent ventilator Battery
Outdoor part Indoor part (power distribution) Indoor part (equipment)
AVR
DC
Greenf ield SiteEquipment Room System
G fi ld Sit E i t R S t
7/27/2019 Energy Shelters V2[1].1
32/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2) - schematic diagram of power
supply (2)
ACvoltage
regulator
Standbyelectric
generator set
Moveablepowerstation
Monitoring
Grounding
AC
distributionpanel
Solar cellarray
Rectifier
Windgenerator
DC controlpanel
Battery
Other loads
(a) Uninterruptible(b) Interruptible for short time
Mains
AC220V/380V
(a)
DC-12V(DC-48V) (a)
AC220/380V (b)
Greenf ield SiteEquipment Room System
G fi ld Sit E i t R S t
7/27/2019 Energy Shelters V2[1].1
33/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2) - schematic diagram of power
supply (3)
1. There are several Backup Power Supply modes available depending on areas and design requirement: Mains,
Diesel Engine, Battery and Solar Energy.
2. When there is a Power Failure from mains: -
a. the Diesel Engine in the site will automatically provide Power through the ATS.
b. If the Diesel Engine fails, the Battery can provide Power for Equipment for eight
hours as expected.
c. In some areas with good Mains Power Supply, there are no diesel engines during
the site construction.
d. However movable diesel engines are configured to prevent Mains Failure.
3. Some functions of the equipment can be integrated or optional:
1. Lightning proof box (optional): add when no lightning proof system is available in ACDB;2. AVR (AC voltage regulator) (optional): install when the mains changes unstably;
3. ATS (optional): use with diesel engine, not available in the base stations without diesel engine;
4. Other power distributions are provided and laid as per design requirements.
Greenf ield SiteEquipment Room System
o
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
34/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Mains
Diesel engine
Electric meter,
lightning proof and
voltage regulator
ATS ACDB
Aviation
obstructionlamps
Equipment room power distribution -(2) -
working diagram of pipes and wires (1)
Indoorpower
distributionand
equipment
Inside
shelter
Outdoor
cabling
rack
Oil tank
For description of 1, 2, 3, 4 and 5 in the figure, see
point 4 on the next page.
Embedded
underground
1 2 3 4
5
Greenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
35/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2) - working diagram of pipes
and wires (2)
1. Cable: power cable and feeder;
2. Pipe: diesel oil pipes, power PVC cabling pipe;
3. Pipes and cables are routed in three ways: underground, ground surface inside shelter and on
the cabling rack;
4. In the figure above:
1 Connect power cables from mains to the shelter through PVC pipeembedded underground;
2 Connect power cables from diesel engine to the shelter through PVC pipe
embedded underground;
3 Connect the diesel engine to the diesel oil pipe of diesel oil tank (with ends
exposed and middle part embedded underground);
4 When the electric meter is far from shelter, connect the power cables from
electric meter to the shelter through underground; The electric meter ofsome base station is placed near the ATS, so it is no need to connect the
power cables through underground;
5 Connect the power cables of aviation obstruction lamps through the feeder
rack.
Greenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
36/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2) - 3-phase 5-line power supply
Power
distributionbox
lightning
proof box
Powercabinet
Other
distribution
equipment
L1L2L3N
PGND
L1-one of three phases power supply
L2-one of three phases power supply
L3-one of three phases power supply
N-zero line in the three phases power supply
PGND-protection grounding wire
Note: If the color of lines is inconsistent with the design, the design shall prevail.
Greenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
37/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2)general rules and requirements
for power distribution in equipment room
1. The indoor air switch capacity must be 1.5 or 2 times of the current capacity of
respective tributary;
2. The diameter, size and number of indoor power distribution cables should
match those for tributary cables, and comply with related standards;
3. The cables for indoor power distribution should not be randomly appended, andthere should be no joints in between and the cables should not be exposed;
4. Avoid crossover and intertwining among indoor distribution cables and signal
cables;
5. The indoor power distribution equipment should be installed in consideration of
heat shrinking and maintenance, and the space should be reserved for easy
opening of side doors;6. The indoor power distribution equipment should have grounding protection by
connecting the yellow green grounding wire to the grounding bar.
Greenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
38/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution (2)installing AVR (AC voltage
regulator)
Note: 1. AVR should be installed as per actual drawing.
2. It should be configured in the areas where the mains voltage is unstable.
3. Do not use it in the areas with stable power supply.
4. The current new ACDB has integrated AVR.
Greenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
39/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution (2)installing ACDB (AC distribution
box)
Note: 1. ACDB: AC distribution box.
2. First fix the distribution box according to the actual drawing, if there are no specific requirement in thedrawing, the bottom edge of distribution box should be 1200 mm above the ground.
3 The distribution box is mounted on the cabling trough at upper, middle and lower positions.
4. The distribution box must be grounded and the lead-out grounding wires are connected with the grounding bar.
5. All facilities/cables in the distribution box must be installed reliably and cables must be routed straightly
without intertwining each other.
6. The box is placed firmly against water and theft.
Greenf ield SiteEquipment Room System
IncorrectGreenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
40/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. In Figure 1, the power cables are not connected by a copper lug and crimped with bolts.
2. This connection may lead to over current short circuits.
3. In Figure 2, cables should not pass from the rear side of the grounding bar.
4. The outdoor power distribution box is fixed and wired irregularly without safety measures against water and theft
5. This could result in short circuits and theft of components, in serious cases, fire may occur.
Figure 1 Figure 2
No copper lug is used
for connection. The
section is trimmed
manually.
Method
Equipment room power distribution (2)installing ACDB (AC
distribution box)
No measures
against rain
and theft
Cables are
intertwined
together.
Greenf ield SiteEquipment Room System
IncorrectGreenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
41/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2) - laying of power cables
Note:
1. The DC and AC power cables
should be placed separately fromsignal cables.
2. Avoid putting them in the same
bundle.
3. It is best to have the whole cable
with intact surface, without joints
or bend.
4. The cables are routed easily andneatly and bundled evenly.
5. The connection with related parts
are firm and welded smoothly, no
grounding, short circuit and
broken circuit.
Power cables and signal cables are
bundled together.
The standard laying of power andsignal cables
MethodGreenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
42/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2)installing indoor lighting,
switches, outlets and emergency lights
Note: 1.The indoor lighting is installed in the middle of the ceiling;
2.The emergency light is generally installed in the middle of top door frame, with an outlet beside;
Convenience and safety should be considered when installing the switches and outlets for lighting equipment.
Emergency light
Indoor lighting
Greenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
43/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room -(2)installing
outdoor lighting
Notes: 1. The indoor lighting is installed in the middle of ceiling.
2. Over door lights are installed against rain and theft.
Over door lightsOver door lights
Greenf ield SiteEquipment Room System
IncorrectGreenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
44/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. The over door lights should be installed under eaves or awnings.
2. Improper installation will reduce the service life of lights, and even cause short circuits.
3. Emergency lights are generally installed on the top middle of door frame.
Wrong position ofinstallation
Method
Power distribution in equipment room -(2)outdoor lighting
Emergency lights are generally
installed on the top middle of
door frame.
Greenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
45/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room -(2)alarm system
Door control
Outdoor alarm
Note: 1. The door control is placed between the over door frame and door
2. Infrared sensor is placed in a big range of detection, over 1.5 m above ground
3. Water detector is put in the place which is prone to water or is lower in altitude
4. EAC is also placed 1.5 m above ground to facilitate the construction and near the terminal
monitoring unit (TMU), the remote monitoring module in the base station), and the EAC inside the shelter needs to
be connected with TMU in the base station for remote monitoring.
Smoke sensor
Infrared sensor Infrared
Temperature and humidity
Smoke detector
EAC
Water detector
Door control
Base station equipment
Greenf ield SiteEquipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
46/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(2)installing intelligent
ventilation system and firefighting equipment
Note: 1. The air vent is installed as per design, and blow air from lower part and take away heat from higher part.
2. The firefighting equipment is installed as per design requirement, generally on or near the ground and
apparent and accessible place.
Greenf ield Site Equipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
47/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. In Figure 1, the outdoor unit of air conditioner is installed stably and protected with an anti-theft net.
2. The antitheft for air conditioner is fixed with bolts.
3. In Figure 2, the indoor unit is hung at a height not less than 1.8 m.
4. Make sure the installing surface is firm and strong to hold adequately when installing it.
Outdoor
unit of air
conditioner
Indoor unit of
air conditioner
Figure 1 Figure 1
Power distribution in equipment room -(2)Installing air conditioning
system
Greenf ield Site Equipment Room System
IncorrectGreenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
48/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. The indoor unit is too low.
2. Normally, the height should not be less than 1.8 m; otherwise the refrigeration is impossible (hot
air from low to high, cold air from high to low).
Air conditioners
are hung not high
enough.
Method
Power distribution in equipment room -(2)installing air conditioning
system
Greenf ield Site Equipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
49/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Shelter installation and power distribution
2. Equipment room
power distribution
Feederwindow
Cablingrack
ACDB
ACdistribution
cabinet
AVR
Layingofpowercables
Switchoutletand
emergencylightsforindoor
lighting
Outdoorlighting
smokedetector,temperature
detector,doorcontrol,water
alarm
andoutdooralarm
Intelligentventilation
system
Airconditioning
system
Firefightingsystem
Groundingsystem
1 32
Greenf ield Site Equipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
50/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Lightning
proofbox
BTS
wirelessba
se
station
AC/DCrelat
ed
equipment
DDF
Monitoring
equipment
Racksystem
andother
distributionframes
ODF
Feeder window
Outdoor
grounding bar
Indoor grounding bar in equipment room
Antistatic floor
GPS lightning arrestor
Equipment room
Grounding grids
Equipment room power distribution -(3) grounding system
indoor grounding cabling diagram (1)
Insulators
Bolt with copper lug
Greenf ield Site Equipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
51/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution -(3) grounding systemindoor
grounding cabling diagram (2)
Precautions for indoor and outdoor grounding:
1. The indoor and outdoor grounding wires are not connected in series;
2. In the grounding system, there should be two grounding bars for equipment: -
a. Working ground (lower)
b. Protection ground (higher)
3. The indoor and outdoor grounding bars are connected in parallel to the base station
grounding grids;
4. The general grounding bar (also called main grounding bar or grounding bus bar)
should be connected by leading out two copper wires from the two vertical grounding
object of the central area of grounding grids;
5. The down-lead of lightning arrestor to the grounding grids should be far from thegrounding grids of the equipment room, normally at least greater than 5 m;
6. Copper lugs are used between grounding wires and grounding bar for bolting.
Greenf ield Site Equipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
52/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Equipment room power distribution - (3)-3 phase, 5 line power supply
grounding
Power
distributionbox
Lightning
proof box
Power
cabinet
Other
Distribution
equipment
L1L2L3N
PGND
L1-one of three phases power supply
L2-one of three phases power supply
L3-one of three phases power supply
N-zero line in the three phases power supply
PGND-protection grounding wire
Note: If the color of lines is inconsistent with the design, the design shall prevail.
Greenf ield Site Equipment Room System
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
53/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Outdoor lightning proof box
Note: 1. Install the box near the cable (cables must go through lightning proof box before connecting into the
equipment room)
2. Connection as per design requirements, and connect it with outdoor grounding bar.
Power distribution in equipment room -(3)installing lightning
proof box
G ee e d S e qu p e oo Sys e
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
54/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Indoor lightning proof box
Note: 1. Install the box near the cable connection as per design requirements (not too near, within the allowable
bend of cables because the cables are thick)
2. Connect with indoor grounding bar.
Power distribution in equipment room -(3)installing lightning proof box
q p y
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
55/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Power distribution in equipment room -(3)installing grounding bar
Note: 1. Depending on different design requirements, the installation of indoor and outdoor grounding bar may
be included.
2. The indoor grounding bar may have two grounding bars, one installed higher as the protection
grounding, and the other installed lower as the working grounding.
3. Installation specification requires that the grounding bar should be connected directly with the main
grounding grids
4. Copper lugs and bolts are used between grounding wires and grounding bar.
Come from
general
grounding grids
Come from
general grounding
grids
Indoor grounding copper bar connects withoutdoor grounding grids
q p y
Greenf ield Site Equipment Room System
7/27/2019 Energy Shelters V2[1].1
56/57
HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential
Note: 1. The grounding copper bar is fixed on the wall at a distance of 50 mm from the wall and cushioned
with insulators.
2. The height from the ground should comply with design requirements.
Power distribution in equipment room -(3)installing grounding bar
Insulators
Copper lugs
and bolts for
connection
q p y
Incorrect
MethodGreenf ield SiteEquipment Room System
7/27/2019 Energy Shelters V2[1].1
57/57
Note: In figure 1, cables should not pass from the rear side of the grounding bar.
Figure 1
Cables should not pass from
the rear side of the grounding
bar
Method
Power distribution in equipment room -(3)- indoor grounding bar
q p y