Energy Shelters V2[1].1

Embed Size (px)

Citation preview

  • 7/27/2019 Energy Shelters V2[1].1

    1/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Construction

    Primary

    Procedures Chapter 1Equipment Room

    System Construction

    1. Installing Shelter

    2. Equipment Room Power

    Distribution

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    2/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Install the

    base

    Install

    guide railInstall

    wallboardInstall

    top frame

    Next step

    Install

    top plate

    1. Installing shelter

    Self-supporting tower - equipment room system construction

    Install

    floor

    Install

    antistatic

    floor

    Install

    bottom

    plate

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    3/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelter - primary tools

    Adjustable wrench Percussion drill MultimeterScrewdriver

    Steel tapeSteel saw Horizontal ruler Torque spanner

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    4/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelter - primary auxiliary materials

    Antistatic copper foil Expansion bolt

    Plastic welding rod Sealant

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    5/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. The parts of the base are connected with bolts that expose two to three threads after being fastened.2. Once the base is installed, it must be measured horizontally and with diagonal, at a variation within2 mm.

    3. The base spacing is allowed to have a variation of1 mm.

    4. The spacing should be measured at the same.

    5. Spacing is the central distance between two adjacent angles.

    6. To measure the spacing is to make sure the shelter base is a rectangle or square (each angle is a right angle).

    Installing shelterinstalling shelter base

    Measuring

    diagonal

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    6/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelterinstalling bottom plate

    Note: 1.The bottom plate is assembled with several boards that are tightened on H-shaped steel.

    2.The bottom plate is fixed with tapping screws that are staggered at a spacing of 200 mm.

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    7/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1.After the bottom plate is installed.

    2.Install the guide rail by connecting with the bottom plate through long screws in a nice looking and leveled

    manner.

    3.The gaps between the guide rail and the bottom plate should be regulated under 5 mm, and two or three threads

    should be exposed after the screws are tightened.

    Installing shelterinstalling guide rail

    Gaps between

    guide rail and

    bottom plate 5

    mm

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    8/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. Wallboards are connected to each other by H-shaped aluminum and fixed with rivets that are staggered at a

    spacing of 200 mm.

    2. Each wallboard is fully embedded into the base and the connections should be painted with waterproof

    glue evenly and completely.

    Installing shelterinstalling guide rail

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    9/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1.The top frame is connected to the flange on the column by bolts.

    2.The wallboards and top frame should be checked for verticality before the bolts are tightened, and those bolts

    exceeding the top frame should be leveled.

    3.The wallboards and top frame are connected with rivets in a reliable, leveled and beautiful manner.

    Installing shelterinstalling top frame

    Flange on the

    column

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    10/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. Waterproof trough (in stainless steel structure)

    should be installed for top plate at its joints with rivets (Figure 1)

    at a spacing of 200 mm between rivets that should be staggered.

    2. And the connection between waterproof trough

    with color steel plate (pressed and colored) should be brushed

    evenly with waterproof glue.

    Installing shelterinstalling top plate

    Water proof

    trough

    Figure 2

    Figure 3

    Top plate joint

    Install waterprooftrough

    One of

    top plates

    Figure 1

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    11/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: The battens for wrap angles, seams and blank holders must be secured firmly and pressed flatly without any gap at

    ends.

    Wrap

    angle of

    shelter

    Installing shelterinstalling batten

    Batte

    n

    Edges at

    the ends of

    batten

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    12/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1.The walls drilled with wrong holes must be made up with waterproof and corrective measures, without

    affecting its function.

    2.Failure to take corrective measures for wrong holes drilled will lead rain water into the walls, thus

    affecting the service life and functions.

    Wrong holes

    drilled

    Installing shelter

    Wrong bolts

    fixed

    Incorrect

    MethodGreenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    13/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1.Once all shelter parts are installed, clean the floor and lay copper foils on it to build a copper mesh.

    2.The copper foil can be stuck on the shelter floor or cover a layer of wood plates which should be sealed tightly.

    3.The number of copper foils is subject to the area of the room, but the spacing between horizontal and vertical directions as

    per design requirements. Use copper foil to cover the wall foundation near the grounding copper bar to form a thin copper strip and a certain

    length of copper strip is reserved to be exposed on the ground surface to connect with the grounding copper bar (or tape-controlled angle

    steel or aluminium batten).

    Installing shelterinstalling antistatic floor

    Copper

    foil

    reserved

    Thin copper

    strip, 5 cm to

    10 cm from

    ground

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    14/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelterinstalling antistatic floor

    Note: 1.Apply the rubber evenly on a PVC antistatic

    floor with rubber friction tool and wait for 15 minutes

    before laying the antistatic floor

    2. Keep the floor clean.

    Antistatic

    floor

    PVC

    Antistatic

    floor

    PVC

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    15/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelterinstalling antistatic floor

    Note: 1.In figure 1, the reserved length of copper foil is not enough so that the connection with batten is not stable.

    2.In figure 2, applying rubber on the bottom plate may easily involve dusts, staining the floor and

    compromising the effect of antistatic floor ad the installation.

    Incorrect

    Method

    Apply rubber on

    the bottom plate

    directly

    Reserved copper foil

    length not enough

    Figure 1 Figure 2

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    16/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelterinstalling antistatic floor

    Note: 1. Each PVC antistatic rubber should be closely connected (size of PVC near the wall foundation should be

    measured and cut in advance).

    2. After installing the antistatic rubber, apply sealant rubber evenly and squarely on the perimeter and the

    seams of walls.

    3. Figure 1 Applying sealant

    4. Figure 2 Part of sealant is leveled.

    Figure 1 Figure 2

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    17/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelterinstalling antistatic floor

    Note: Level the sealant above ground with blade to be aligned with floor surface.

    Figure1 Figure2

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    18/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelterinstalling antistatic floor

    Note: 1.The indoor grounding copper strip is made of the

    same materials for horizontal grounding of grounding grids, ata size of 25*3 mm.

    2.The grounding copper foil extension (batten) on

    the anti-lightning grounding board is connected with the walls

    using screws and connected with outdoor grounding grids.

    Grounding

    copper strip in

    shelter

    Grounding copper

    strip in shelter

    Connection of grounding

    copper strip with

    grounding grids

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    19/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Installing shelterinstalling antistatic floor

    Note: 1.The installed antistatic floor should be leveled with evenly distributed wires. (PVC floor is actually

    conductive floor.

    2.Recommendation is to have a resistance of not lower than 1.0*106ohm, and the viscose used is also a

    non water soluble conductive rubber to conduct static electricity).

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    20/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    2. Equipment room

    power distribution

    Feederwin

    dow

    Cablingr

    ack

    ACDB

    ACdistribu

    tion

    cabinet

    AVR

    Laying

    of

    powerca

    bles

    Switchoutletand

    emergencylightsfor

    indoorlighting

    Outdoorlig

    hting

    Alarm

    system

    Intelligent

    ventilationsystem

    Airconditioningsystem

    Firefightingsystem

    Grounding

    system

    31 2

    Self-supporting tower - equipment room system construction

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    21/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    2. Equipment room

    power distribution

    ACDB

    ACdistribution

    cabinet

    AVR

    Layingofpower

    cables

    Switchoutletand

    emergencylightsfor

    indoorlighting

    Outdoorlighting

    Alarmsystem

    Intelligentventilation

    system

    Airconditioning

    system

    Firefighting

    system

    Grounding

    system

    1 32

    Feederwindow

    Cablingrack

    Self-supporting tower - equipment room system construction

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    22/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room -(1)installing feeder window

    Notes: 1. The opening of feeder window should meet design requirements and the

    following principles:

    2. Take a comprehensive consideration of the opening direction of equipment

    room doors and position of tower to get a straight line for the feeders and connect the

    connectors of feeder 7/8 and 1/2 by opening the feeder window towards to the tower

    wherever possible.

    3. The feeder window should be placed where the feeders are connected

    behind the soft jumper to get the soft jumper straight to the main equipment.

    4. Install the feeder window stably and tightly.

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    23/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room - (1)installing

    feeder window

    Notes: 1. Figure 1 shows the cross-section of outdoor feeder window in which M8 expansion bolts are used to

    secure the sealing bottom plate.

    2. Figure 2 shows front view of outdoor feeder.

    Feeder penetration

    sealing bottom plate

    Various sealing devices

    Fastening hoop

    Plate sealing cover

    M8 expansion bolt

    Figure2Figure1

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    24/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room - (1)installing feeder window

    Note: 1.Insert the penetration sealing board

    2.The outdoor part of feeder window, into the pre-chiseled window on the wall (according to design

    requirements)

    3.Use rivets between outdoor feeder window plate of unit equipment room and walls.

    Rivet Closing plug

    for feeder

    window

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    25/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room - (1)installing feeder window

    Note: 1. When the penetration sealing bottom plate is installed inside the feeder window.

    2. The indoor sealing bottom plate is located inside the outdoor sealing bottom plate (the external diameter

    of outdoor penetration sealing bottom plate is greater than that of indoor one.

    3. So the outdoor one is installed against the wall) to guard against water.

    Inside

    feeder

    window

    Indoor sealing

    bottom plate

    Greenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    26/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room - (1)installing feeder window

    Note: 1. When the installation is finished.

    2. Sealant should be applied at the external part of feeder window.

    3. For tight sealing the sealant should be spread evenly and tidily.

    The outside of the feeder

    window is closed with

    sealants.

    Greenf ield SiteEquipment Room System

    G fi ld Si E i R S

  • 7/27/2019 Energy Shelters V2[1].1

    27/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room -(1)installing cabling rack

    Note: 1.The indoor cabling rack is fixed on the wall with bolts. Before that, cables are drawn on the wall to facilitate the

    straight installation of the cabling rack.

    2.Because the cabling rack bears heavy cables, some places should be fixed with hangers, such as shelter frame,

    ceiling suspension, bypass support and terminal and wall reinforcement.(In wiring, strong and weak current cables are placed

    separately at a certain spacing.)

    Support Complete

    outside view of

    cabling rack

    Cabling

    stairs

    Shelter

    frame

    Greenf ield SiteEquipment Room System

    G fi ld Sit E i t R S t

  • 7/27/2019 Energy Shelters V2[1].1

    28/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room -(1)installing cabling rack

    Note: 1. Grounding wires are connected between cabling racks

    2. Another yellow green grounding wire is prepared to connect with grounding copper bar.

    Between cabling racksthere are grounding wire

    connections Yellow green

    grounding wire

    Greenf ield SiteEquipment Room System

    IncorrectG fi ld Sit E i t R S t

  • 7/27/2019 Energy Shelters V2[1].1

    29/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. The indoor cabling rack must be firmly fixed on the wall or rooftop.

    2. The Cabling Rack must be parallel and even secured with bolts for stability.

    The cabling rack

    direction is wrong. The

    diagram is upside down

    and the plane should faceupward.

    Incorrect

    Method

    Power distribution in equipment room -(1)installing cabling rack

    Greenf ield SiteEquipment Room System

    G fi ld Sit E i t R S t

  • 7/27/2019 Energy Shelters V2[1].1

    30/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    2. Equipment Room

    Power Distribution

    Feederwind

    ow

    Cablingrack

    A

    C

    D

    B

    A

    T

    S

    A

    V

    R

    Layingofp

    ower

    cables

    Switchoutletand

    emergencylightsfor

    indoorligh

    ting

    Outdoorlighting

    Smokedetector,tem

    perature

    detector,doorcontr

    ol,water

    alarmandoutdooralarm

    Intelligentventilation

    system

    Airconditionin

    gsystem

    Groundingsystem

    31 2

    Firefigh

    ting

    system

    Self-supporting tower - equipment room system construction

    Greenf ield SiteEquipment Room System

    G fi ld Sit E i t R S t

  • 7/27/2019 Energy Shelters V2[1].1

    31/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2) - schematic diagram of power

    supply (1)

    Mains

    Diesel engine

    Electric

    meter

    lightning

    proof boxATS ACDB

    AC

    Power cabinet

    Outdoor

    lighting

    Aviationobstruction

    lamps

    Air conditioner

    Indoor lightingTelecomequipment

    Environment monitor Emergent ventilator Battery

    Outdoor part Indoor part (power distribution) Indoor part (equipment)

    AVR

    DC

    Greenf ield SiteEquipment Room System

    G fi ld Sit E i t R S t

  • 7/27/2019 Energy Shelters V2[1].1

    32/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2) - schematic diagram of power

    supply (2)

    ACvoltage

    regulator

    Standbyelectric

    generator set

    Moveablepowerstation

    Monitoring

    Grounding

    AC

    distributionpanel

    Solar cellarray

    Rectifier

    Windgenerator

    DC controlpanel

    Battery

    Other loads

    (a) Uninterruptible(b) Interruptible for short time

    Mains

    AC220V/380V

    (a)

    DC-12V(DC-48V) (a)

    AC220/380V (b)

    Greenf ield SiteEquipment Room System

    G fi ld Sit E i t R S t

  • 7/27/2019 Energy Shelters V2[1].1

    33/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2) - schematic diagram of power

    supply (3)

    1. There are several Backup Power Supply modes available depending on areas and design requirement: Mains,

    Diesel Engine, Battery and Solar Energy.

    2. When there is a Power Failure from mains: -

    a. the Diesel Engine in the site will automatically provide Power through the ATS.

    b. If the Diesel Engine fails, the Battery can provide Power for Equipment for eight

    hours as expected.

    c. In some areas with good Mains Power Supply, there are no diesel engines during

    the site construction.

    d. However movable diesel engines are configured to prevent Mains Failure.

    3. Some functions of the equipment can be integrated or optional:

    1. Lightning proof box (optional): add when no lightning proof system is available in ACDB;2. AVR (AC voltage regulator) (optional): install when the mains changes unstably;

    3. ATS (optional): use with diesel engine, not available in the base stations without diesel engine;

    4. Other power distributions are provided and laid as per design requirements.

    Greenf ield SiteEquipment Room System

    o

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    34/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Mains

    Diesel engine

    Electric meter,

    lightning proof and

    voltage regulator

    ATS ACDB

    Aviation

    obstructionlamps

    Equipment room power distribution -(2) -

    working diagram of pipes and wires (1)

    Indoorpower

    distributionand

    equipment

    Inside

    shelter

    Outdoor

    cabling

    rack

    Oil tank

    For description of 1, 2, 3, 4 and 5 in the figure, see

    point 4 on the next page.

    Embedded

    underground

    1 2 3 4

    5

    Greenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    35/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2) - working diagram of pipes

    and wires (2)

    1. Cable: power cable and feeder;

    2. Pipe: diesel oil pipes, power PVC cabling pipe;

    3. Pipes and cables are routed in three ways: underground, ground surface inside shelter and on

    the cabling rack;

    4. In the figure above:

    1 Connect power cables from mains to the shelter through PVC pipeembedded underground;

    2 Connect power cables from diesel engine to the shelter through PVC pipe

    embedded underground;

    3 Connect the diesel engine to the diesel oil pipe of diesel oil tank (with ends

    exposed and middle part embedded underground);

    4 When the electric meter is far from shelter, connect the power cables from

    electric meter to the shelter through underground; The electric meter ofsome base station is placed near the ATS, so it is no need to connect the

    power cables through underground;

    5 Connect the power cables of aviation obstruction lamps through the feeder

    rack.

    Greenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    36/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2) - 3-phase 5-line power supply

    Power

    distributionbox

    lightning

    proof box

    Powercabinet

    Other

    distribution

    equipment

    L1L2L3N

    PGND

    L1-one of three phases power supply

    L2-one of three phases power supply

    L3-one of three phases power supply

    N-zero line in the three phases power supply

    PGND-protection grounding wire

    Note: If the color of lines is inconsistent with the design, the design shall prevail.

    Greenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    37/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2)general rules and requirements

    for power distribution in equipment room

    1. The indoor air switch capacity must be 1.5 or 2 times of the current capacity of

    respective tributary;

    2. The diameter, size and number of indoor power distribution cables should

    match those for tributary cables, and comply with related standards;

    3. The cables for indoor power distribution should not be randomly appended, andthere should be no joints in between and the cables should not be exposed;

    4. Avoid crossover and intertwining among indoor distribution cables and signal

    cables;

    5. The indoor power distribution equipment should be installed in consideration of

    heat shrinking and maintenance, and the space should be reserved for easy

    opening of side doors;6. The indoor power distribution equipment should have grounding protection by

    connecting the yellow green grounding wire to the grounding bar.

    Greenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    38/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution (2)installing AVR (AC voltage

    regulator)

    Note: 1. AVR should be installed as per actual drawing.

    2. It should be configured in the areas where the mains voltage is unstable.

    3. Do not use it in the areas with stable power supply.

    4. The current new ACDB has integrated AVR.

    Greenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    39/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution (2)installing ACDB (AC distribution

    box)

    Note: 1. ACDB: AC distribution box.

    2. First fix the distribution box according to the actual drawing, if there are no specific requirement in thedrawing, the bottom edge of distribution box should be 1200 mm above the ground.

    3 The distribution box is mounted on the cabling trough at upper, middle and lower positions.

    4. The distribution box must be grounded and the lead-out grounding wires are connected with the grounding bar.

    5. All facilities/cables in the distribution box must be installed reliably and cables must be routed straightly

    without intertwining each other.

    6. The box is placed firmly against water and theft.

    Greenf ield SiteEquipment Room System

    IncorrectGreenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    40/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. In Figure 1, the power cables are not connected by a copper lug and crimped with bolts.

    2. This connection may lead to over current short circuits.

    3. In Figure 2, cables should not pass from the rear side of the grounding bar.

    4. The outdoor power distribution box is fixed and wired irregularly without safety measures against water and theft

    5. This could result in short circuits and theft of components, in serious cases, fire may occur.

    Figure 1 Figure 2

    No copper lug is used

    for connection. The

    section is trimmed

    manually.

    Method

    Equipment room power distribution (2)installing ACDB (AC

    distribution box)

    No measures

    against rain

    and theft

    Cables are

    intertwined

    together.

    Greenf ield SiteEquipment Room System

    IncorrectGreenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    41/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2) - laying of power cables

    Note:

    1. The DC and AC power cables

    should be placed separately fromsignal cables.

    2. Avoid putting them in the same

    bundle.

    3. It is best to have the whole cable

    with intact surface, without joints

    or bend.

    4. The cables are routed easily andneatly and bundled evenly.

    5. The connection with related parts

    are firm and welded smoothly, no

    grounding, short circuit and

    broken circuit.

    Power cables and signal cables are

    bundled together.

    The standard laying of power andsignal cables

    MethodGreenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    42/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2)installing indoor lighting,

    switches, outlets and emergency lights

    Note: 1.The indoor lighting is installed in the middle of the ceiling;

    2.The emergency light is generally installed in the middle of top door frame, with an outlet beside;

    Convenience and safety should be considered when installing the switches and outlets for lighting equipment.

    Emergency light

    Indoor lighting

    Greenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    43/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room -(2)installing

    outdoor lighting

    Notes: 1. The indoor lighting is installed in the middle of ceiling.

    2. Over door lights are installed against rain and theft.

    Over door lightsOver door lights

    Greenf ield SiteEquipment Room System

    IncorrectGreenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    44/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. The over door lights should be installed under eaves or awnings.

    2. Improper installation will reduce the service life of lights, and even cause short circuits.

    3. Emergency lights are generally installed on the top middle of door frame.

    Wrong position ofinstallation

    Method

    Power distribution in equipment room -(2)outdoor lighting

    Emergency lights are generally

    installed on the top middle of

    door frame.

    Greenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    45/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room -(2)alarm system

    Door control

    Outdoor alarm

    Note: 1. The door control is placed between the over door frame and door

    2. Infrared sensor is placed in a big range of detection, over 1.5 m above ground

    3. Water detector is put in the place which is prone to water or is lower in altitude

    4. EAC is also placed 1.5 m above ground to facilitate the construction and near the terminal

    monitoring unit (TMU), the remote monitoring module in the base station), and the EAC inside the shelter needs to

    be connected with TMU in the base station for remote monitoring.

    Smoke sensor

    Infrared sensor Infrared

    Temperature and humidity

    Smoke detector

    EAC

    Water detector

    Door control

    Base station equipment

    Greenf ield SiteEquipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    46/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(2)installing intelligent

    ventilation system and firefighting equipment

    Note: 1. The air vent is installed as per design, and blow air from lower part and take away heat from higher part.

    2. The firefighting equipment is installed as per design requirement, generally on or near the ground and

    apparent and accessible place.

    Greenf ield Site Equipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    47/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. In Figure 1, the outdoor unit of air conditioner is installed stably and protected with an anti-theft net.

    2. The antitheft for air conditioner is fixed with bolts.

    3. In Figure 2, the indoor unit is hung at a height not less than 1.8 m.

    4. Make sure the installing surface is firm and strong to hold adequately when installing it.

    Outdoor

    unit of air

    conditioner

    Indoor unit of

    air conditioner

    Figure 1 Figure 1

    Power distribution in equipment room -(2)Installing air conditioning

    system

    Greenf ield Site Equipment Room System

    IncorrectGreenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    48/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. The indoor unit is too low.

    2. Normally, the height should not be less than 1.8 m; otherwise the refrigeration is impossible (hot

    air from low to high, cold air from high to low).

    Air conditioners

    are hung not high

    enough.

    Method

    Power distribution in equipment room -(2)installing air conditioning

    system

    Greenf ield Site Equipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    49/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Shelter installation and power distribution

    2. Equipment room

    power distribution

    Feederwindow

    Cablingrack

    ACDB

    ACdistribution

    cabinet

    AVR

    Layingofpowercables

    Switchoutletand

    emergencylightsforindoor

    lighting

    Outdoorlighting

    smokedetector,temperature

    detector,doorcontrol,water

    alarm

    andoutdooralarm

    Intelligentventilation

    system

    Airconditioning

    system

    Firefightingsystem

    Groundingsystem

    1 32

    Greenf ield Site Equipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    50/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Lightning

    proofbox

    BTS

    wirelessba

    se

    station

    AC/DCrelat

    ed

    equipment

    DDF

    Monitoring

    equipment

    Racksystem

    andother

    distributionframes

    ODF

    Feeder window

    Outdoor

    grounding bar

    Indoor grounding bar in equipment room

    Antistatic floor

    GPS lightning arrestor

    Equipment room

    Grounding grids

    Equipment room power distribution -(3) grounding system

    indoor grounding cabling diagram (1)

    Insulators

    Bolt with copper lug

    Greenf ield Site Equipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    51/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution -(3) grounding systemindoor

    grounding cabling diagram (2)

    Precautions for indoor and outdoor grounding:

    1. The indoor and outdoor grounding wires are not connected in series;

    2. In the grounding system, there should be two grounding bars for equipment: -

    a. Working ground (lower)

    b. Protection ground (higher)

    3. The indoor and outdoor grounding bars are connected in parallel to the base station

    grounding grids;

    4. The general grounding bar (also called main grounding bar or grounding bus bar)

    should be connected by leading out two copper wires from the two vertical grounding

    object of the central area of grounding grids;

    5. The down-lead of lightning arrestor to the grounding grids should be far from thegrounding grids of the equipment room, normally at least greater than 5 m;

    6. Copper lugs are used between grounding wires and grounding bar for bolting.

    Greenf ield Site Equipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    52/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Equipment room power distribution - (3)-3 phase, 5 line power supply

    grounding

    Power

    distributionbox

    Lightning

    proof box

    Power

    cabinet

    Other

    Distribution

    equipment

    L1L2L3N

    PGND

    L1-one of three phases power supply

    L2-one of three phases power supply

    L3-one of three phases power supply

    N-zero line in the three phases power supply

    PGND-protection grounding wire

    Note: If the color of lines is inconsistent with the design, the design shall prevail.

    Greenf ield Site Equipment Room System

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    53/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Outdoor lightning proof box

    Note: 1. Install the box near the cable (cables must go through lightning proof box before connecting into the

    equipment room)

    2. Connection as per design requirements, and connect it with outdoor grounding bar.

    Power distribution in equipment room -(3)installing lightning

    proof box

    G ee e d S e qu p e oo Sys e

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    54/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Indoor lightning proof box

    Note: 1. Install the box near the cable connection as per design requirements (not too near, within the allowable

    bend of cables because the cables are thick)

    2. Connect with indoor grounding bar.

    Power distribution in equipment room -(3)installing lightning proof box

    q p y

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    55/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Power distribution in equipment room -(3)installing grounding bar

    Note: 1. Depending on different design requirements, the installation of indoor and outdoor grounding bar may

    be included.

    2. The indoor grounding bar may have two grounding bars, one installed higher as the protection

    grounding, and the other installed lower as the working grounding.

    3. Installation specification requires that the grounding bar should be connected directly with the main

    grounding grids

    4. Copper lugs and bolts are used between grounding wires and grounding bar.

    Come from

    general

    grounding grids

    Come from

    general grounding

    grids

    Indoor grounding copper bar connects withoutdoor grounding grids

    q p y

    Greenf ield Site Equipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    56/57

    HUAWEI TECHNOLOGIES CO., LTD. Huawei Confidential

    Note: 1. The grounding copper bar is fixed on the wall at a distance of 50 mm from the wall and cushioned

    with insulators.

    2. The height from the ground should comply with design requirements.

    Power distribution in equipment room -(3)installing grounding bar

    Insulators

    Copper lugs

    and bolts for

    connection

    q p y

    Incorrect

    MethodGreenf ield SiteEquipment Room System

  • 7/27/2019 Energy Shelters V2[1].1

    57/57

    Note: In figure 1, cables should not pass from the rear side of the grounding bar.

    Figure 1

    Cables should not pass from

    the rear side of the grounding

    bar

    Method

    Power distribution in equipment room -(3)- indoor grounding bar

    q p y