54
Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

Embed Size (px)

Citation preview

Page 1: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

Energy Security Masterplan – Phase 1

Parliament Portfolio Committee Presentation

18 June 2008

Page 2: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

2

Introduction - Energy Masterplan

• Developing an integrated energy Masterplan in 2 phases (electricity and liquid fuels)– Some issues in liquid fuels sector could

not wait

• Phase 1– Energy Security framework– Energy planning approach– Liquid fuels short to medium plan

• Phase 2– Presented in October 2007

Page 3: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

3

Introduction – Masterplan (Phase 1)

• In the short-term– the Master Plan focuses on developing

supply chain solutions to South Africa’s liquid fuels supply challenges, management of liquid fuels demand and emergency response tactics.

• In the medium to long-term– the approach is broader and begins to

integrate supply, demand, macroeconomics, geopolitics and climate change

Page 4: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

4

Introduction – Masterplan (Phase 1)

• The Masterplan seeks to allow for the making of well-informed choices in respect of energy supply, energy carriers, demand sector strategies, as well as energy transformation approaches, cognisant of the need to minimise negative impacts on the environment and the economy

Page 5: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

5

Presentation Outline

• Energy security framework

• Energy planning approach

• Liquid fuels industry short to medium plan

– Review of key findings

– Proposed interventions

• Special considerations

Page 6: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

6

Energy Security

Page 7: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

7

Energy Security - definition

• “Energy security means ensuring that diverse energy resources, in sustainable quantities and at affordable prices, are available to the South African economy in support of economic growth and poverty alleviation, taking into account environment management requirements and interactions among economic sectors.”

Page 8: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

8

GDP loss due to fuel supply interruptions

• Based on 2005 terms, South Africa would lose R925 million per day if there is no fuel

Calculation Element 2005 Nominal Value Result Share of GVA of Petroleum by other sectors (lost if no fuel available)

R 129,078 million

+ Share of GVA of Transport by other sectors (lost if no fuel powered transport available)

R 64, 791 million

+ GVA share for Petroleum sector itself (loss if Petroleum sector not producing)

R 30.077 million

= Total Economic Impact 2005 figures R 223,945 million x Total GVA / GDP Ratio 1.509 = Total Impact in GDP terms R 337,890 million ÷ GDP Current Price 2005 R 1,523,255 million = Ratio 22.2%

Page 9: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

9

Whilst dealing with growth in electricity demand, we need to also worry about replacing existing capacity

H E X R IV E RS A LT R IV E R

C E N T R A L W E S T B A N K

C O LE N S O

C O N G E LLOS O U T H C O A S T

U M G E N I

B R A K P A N

K LIP

R O S H E R V ILLE

T A A IB O S

V A A LV E R E E N IN G IN G

W ILG EW IT B A N KG E O R G E

V IE R F O N T E INH IG H V E LD

K O M A T I

IN G A G A N E

C A M D E N

G R O O T V LE I

H E N D R IN A

A R N O T

G A R IE P

K R IE L

A C A C IA P O R T R E X V A N D E R K LO O F

M A T LA

D U H V A

C A H O R A B A S S A

D R A K E N S B E R G

K O E B E R G

T U T U K A

LE T H A B O

M A T IM B A

K E N D A L

P A LM IE T

M A J U B A

0

5 , 0 0 0

1 0 , 0 0 0

1 5 , 0 0 0

2 0 , 0 0 0

2 5 , 0 0 0

3 0 , 0 0 0

3 5 , 0 0 0

4 0 , 0 0 0

5 5 6 0 6 5 7 0 7 5 8 0 8 5 9 0 9 5 0 0 0 5 1 0 1 5 2 0 2 5 3 0 3 5 4 0 4 5 5 0 5 5 6 0

Y e a r

Me

ga

wa

tt I

ns

tall

ed

5 5 6 0 6 5 7 0 7 5 8 0 8 5 9 0 9 5 0 0 0 5 1 0 1 5 2 0 2 5 3 0 3 5 4 0 4 5 5 0 5 5 6 0

Electricity supply options

Page 10: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

10

Economy “drives” Energy (Oil)

1st Oil crisis, OPEC

2nd Oil crisisAsian crisis

Kuwait war

Page 11: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

11

World Oil Reserves

ThousandMillionbarrels

Page 12: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

12

Liquid fuels supply issues

End of oil will demand a change in how we deal with transport

Page 13: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

13

Supply Transform Transport End UseOil

Natural Gas

Coal

Gas

ElectricityEskom

and Others

Coal

PetroSA

Export

Sasol

Road/Rail

Pipeline

OilRefineries

RailRoad

Pipeline

LiquidFuels

Biomass WoodPerson/Road

HydroNuclear

Transmission Wires

“Washing”

Koeberg

RSA primary energy supply

Page 14: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

14

0

50

100

150

200

250

300

1980 1985 1990 1995 2000 2005 2010 2015 2020 2025 2030

Qua

drill

ion

Btu

Oil

Natural Gas

Coal

33%

27%

9%Renewables

Nuclear

26%

5%

Share of WorldTotal

History Projections

38%

24%

24%

8%

6%

World projected energy use by fuel type(1980 - 2030)

Page 15: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

15

World Liquids Production

Non-OPEC Conventional

Non-OPEC Unconventional

OPEC Conventional

OPEC Unconventional

0

20

40

60

80

100

120

2000 2010 2020 2030

(mil

lio

n b

arr

els

per

day)

Source: eia March 2007

Page 16: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

16

World Liquids ProductionUnconventional Liquids

Canadian Oil Sands

Ultra Heavy Crudes

Biofuels

Coal-To-Liquids

Gas-To-Liquids

Shale Oils

0

2

4

6

8

10

12

2000 2010 2020 2030

(mil

lio

n b

arr

els

per

day)

Source: eia, March 2007

Page 17: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

17

0

10

20

30

40

50

60

70

80

Oct

'04

Nov

Dec

Jan '0

5Fe

bM

arApr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan '0

6Fe

bM

arApr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

Jan '0

7Fe

b

US$ p

er

barr

el

Estimated bitumen price netback

Light crude oil price quoted in media(West Texas Intermediate)

Heavy crude oil price at Hardisty

Comparative light, heavy and bitumen crude oil price

Source: eia, March 2007

Page 18: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

18

Energy Security Framework

Energy security is not only about security of supply

Energy infrastructure

planning Energy security

Macro-economic

framework

Climate change (mitigation & adaptation)

Demand management

Standards & specifications

Local production

Reserve margins

Diversity of supply

Import & Export

policies

Foreign relations

Page 19: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

19

Energy modelling & planning

Page 20: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

20

The proposed energy modelling & planning approaches

• Provision of high-quality, energy information, in a manner that promotes sound policymaking, efficient markets and public understanding, to– Cabinet– National, provincial & local governments– Markets – the public

• Meeting of this challenge requires– Adoption of transparent approach, methodology

and presentation of results– Avoidance of developing or advocating positions

Page 21: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

21

Integrated Energy Planning and Modelling

• Provision of high-quality, unbiased energy information, in manner that promotes sound policymaking, efficient markets and public understanding, to– Cabinet– National, provincial & local governments– Markets – the public

PlanningAn integrated planning approach is to ensure that all the constituting elements are addressed in a coordinated manner

ModellingAn integrated energy modeling capability which would be instrumental in the development of energy plans and evaluation of options that are proposed by policy-makers

RequiresRequires

Page 22: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

22

Integrated Energy Planning and Modelling

Separation of modeling, planning and coordination• Decentralised planning by various entities• Coordination and integration of such planning done centrally

Entity 1 Entity 2 Entity ...Entity 3

Coordination

Entity... Entity n

Integrated Energy Planning

Policy Options,

Strategies

Other Factors

Unbiased- Modelling

Government Depts, SOEs

Modelling Agency

Individual Policies, Strategies, Plans, Infrastructure

Page 23: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

23

The modelling process

• Collect, compile and publish reliable energy data, information and analyses

• Produce short and medium-term energy projections

• Analyse impact of proposed energy programs and policies– Prepare reports on energy issues and

legislation for Cabinet– Prepare special analyses on energy issues

and legislation for the Minister– Prepare special analysis for policy making

departments

Page 24: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

24

Energy Modelling System (NIEMS)

Page 25: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

25

ModellingScenarios/

Options

Policy Decisions

Political & Other Factors

Integrated Plan

Individual Sectoral

Plans

Energy Planning and Modelling Process

Annual Forecasts

Political & Other Factors

Page 26: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

26

Modelling vs Planning

• Should be descriptive and “policy-neutral” (i.e. avoid policy advocacy)

• Modeling should, as a basis for the development of energy plans, be undertaken in such a way as to use– prevailing policy,– legislative arrangements,– proven or almost proven

technology or industry structural conditions

• Is essentially prescriptive, and not policy-neutral.

• Involves deliberate policy choices, which may go beyond empirical evidence

• Should be about handling of sometimes conflicting objectives

Modelling Planning

Page 27: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

27

Refining

Page 28: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

28

Refining Competition for Available Flows

Africa

FSUNorth America

Latin America

Europe

Middle East

Pacific Asia

MT in 2004

RSAIsolated

from available

flows

Petrol

6

19

4

4

25

33

Diesel & Jet

South Africa is a PRICE TAKER – our level of oil trade is far too small to influence global or regional Crude or Product prices

Inter Regional Flows OnlyInter Regional Flows OnlyNot Intra Regional FlowsNot Intra Regional Flows

Page 29: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

29

Key refining issues

South Africa has run out of refining capacity

Total Market Demand / Supply

-50.00

-30.00

-10.00

10.00

30.00

50.00

70.00

2005

2006

2007

2008

2009

2010

2011

2012

2013

2014

2015

2016

2017

2018

2019

2020

2021

2022

2023

2024

2025

Bil

lio

ns

Lit

res

-50.00

-30.00

-10.00

10.00

30.00

50.00

70.00

Bil

lio

ns

Lit

res

Nett Product Required Product Supply Product Demand

Supply surplus

Supply shortage

Page 30: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

30

•In order to meet demand a new 85000 BPCD CTL plant is needed every 3-4 years

•If we relied on a 200000 BPCD crude refineries, two refineries can be absorbed.

•Prior to investments in new capacity, significant imports are expected

•In order to meet demand a new 85000 BPCD CTL plant is needed every 3-4 years

•If we relied on a 200000 BPCD crude refineries, two refineries can be absorbed.

•Prior to investments in new capacity, significant imports are expected

Analysis Graphs

Refinery Capacity - Long term supply solutions

The impact of new CTL plants on Imports - 100% utilization on Day 1

•High imports are still periodically required if one assumes start-up coincides with 100% utilisation

•Refinery economics improve with high initial utilisation

•Government might have to incentive CTL/GTL to minimise Balance of Payment concerns

•High imports are still periodically required if one assumes start-up coincides with 100% utilisation

•Refinery economics improve with high initial utilisation

•Government might have to incentive CTL/GTL to minimise Balance of Payment concerns

Key Issues

Net imports with 200 kbpcd crude refineries

0

5000

10000

15000

20000

25000

Mlp

a

.

P90

P50

Net imports with 80 kbpcd CTL plants

0

5000

10000

15000

20000

25000

Mlp

a

.

P90

P50

Source: FSSTT study (November 2006)

Page 31: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

31

Ports

Page 32: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

32

•Initial analysis indicated problems at the ports, but further indicates…

– inadequate interconnections between industry facilities and berths

– In adequate discharge and loading rates in the system

– Discharge and loading rates much lower than those of vessels and berth loading arms

•Not all oil companies have access to all berths

– Berth 9 only - Sasol and Total– Berth 7 and 8 - Shell, BP and Engen

•Management of unplanned incidents– Significant volumes when ship cargo is

offspec•Limited ability to move product out of Durban

Ports issues

Page 33: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

33

Ports issues

Ports have adequate capacity until 2025

0

2

4

6

8

10

12

2006

2008

2010

2012

2014

2016

2018

2020

2022

2024

Number of Ships Into / Out of Durban for the Period 2006 to 2025

Namibia exDurban

PE and EastLonden exDurban

Imports intoDurban

Berth Capacity at 1500 m3/hr [Ship Dependant] Discharge Rate ~ 9 ships per week

Page 34: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

34

Ports proposed interventions

• Oil vessels should be afforded as high a priority as

container vessels

• The use of the “back of port” tanks for anything

other than offloading and loading need to be

prohibited

• Back of the port should be operated by an

independent player

• TNPA has to address concerns raised by industry

participants with respect to the current lease

agreement held by the various oil companies

• DME to provide regulatory certainty

Page 35: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

35

Fuel Storage

Page 36: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

36

Storage issues

• Inability of most storage facilities to receive the large pipeline parcels

– New pipeline capacity expected to exacerbate the situation

• Further depot capacity required for

– Strategic stock (60 days: crude and products)

– Commercial stock (28 days)

• Most airports operating at maximum five days stockholding versus 30 days global best practise

• Fuel stock holding for Eskom OCGT’s

– Diesel fuel demand can increase six fold from 5% load factor to 30% load factor

Page 37: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

37

Proposed storage facility interventions

• Enforce the stock holding by all customer groups

• Ensure that consumers pay for the stock holding

costs

– Include unregulated commercial consumers

– Correct past inequities

• Complete review of petroleum pricing framework

– Limit cross subsidisation: all customer groups

to pay for their own insurance

Page 38: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

38

Inland supply

Page 39: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

39

Inland supply – short term pipeline issues

Pipeline capacity

Page 40: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

40

Analysis Graphs

Rail status quo

0

1000

2000

3000

4000

5000

6000

2006 2007 2008 2009 2010

Mlp

a

.

0

50

100

150

200

250

300

350

40 K

l lo

ads

per

day

.

Rail

Road

*4.5% growth and excludes jet by rail to ORTIA

Potential rail improvement plan

0

1000

2000

3000

4000

5000

6000

2006 2007 2008 2009 2010

Mlp

a

.

0

50

100

150

200

250

300

350

40 K

l loa

ds p

er d

ay

.

Rail

Road

• At present ~25% of the non-pipeline product* moved inland is by rail

• Only 30% of deliveries are for coast to inland

• Unless inland rail transport is increased, more than 10 road tankers per hour will have to leave Durban for inland in 2010

Source: FSSTT study (November 2006)

Inland supply (road & rail)

Page 41: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

41

Inland supply – real rail issues

Total Journey Times (Days)

1

19

27

36

44

42

28

30

1617

7

4

12

10

1

0

5

10

15

20

25

30

35

40

45

50

4.00 6.09 8.19 10.28 12.38 14.47 16.56 18.66 20.75 22.85 24.94 27.03 29.13 31.22 33.32 35.41 More

Time - days

Fre

qu

ency

of

Occ

ure

nce

Page 42: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

42

Inland supply – real rail issues

Rail Tank Cars Standing Full

1

16

29

21

28

26

32

28

18 18

9

14

11

78

54

0

5

10

15

20

25

30

35

0.00 0.68 1.35 2.03 2.71 3.39 4.06 4.74 5.42 6.09 6.77 7.45 8.13 8.80 9.48 10.16 More

Time (days)

Fre

qu

ency

of

Occ

ure

nce

Page 43: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

43

Inland supply - Proposed rail interventions

• Operational improvements to alleviate potential congestion along the supply chain, through

– Consolidation of the route tankers and route substitution

– Switching to block trains/ block loads thus exiting inefficient routes

• Turnaround time improved from 14 days to 4 days

• Re-allocation of capacity to the Durban-Gauteng corridor

• Additional costs to be borne by Oil industry

– Investments in rail sidings

– Weekend and overtime work

Page 44: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

44

INDIANOCEAN

FYNNLAND

HOWICK

LADYSMITH

BETHLEHEM

VOLKSRUST

NEWCASTLEKROONSTAD

KLERKSDORP

WITBANKKENDAL

WALTLOOPRETORIA WEST

SECUNDA

STANDERTONCOALBROOKSASOLBURG

SCHEEPERSNEK

MAHLABATINI

HILLCREST

TARLTON

LESOTHO

NATAL

FREE

STATE

GAUTENG

ø406,4 (16”)

ø323,8 (12”)

QUAGGA

ø457,2 (18”)

N

RUSTENBURG

MAGDALA

NORTH - WESTMPUMALANGA

KWAZULU /

VRYHEID

RICHARDS BAY

BHT

MEYERTON

VAN REENEN

DUZI

INGOGO

WILGE

LANGLAAGTE

FORT MISTAKE

EMPANGENI

MOOIRIVER

JAMESON

ø502 (20”)

ø457,2(18")

ø323,8 (12”)

Ø219,1 (8”)

Ø219,1 (8”)

ø323,8 (12”)

Ø219,1 (8”)

Ø406,4 (16”)

Ø457,2 (18”)

18”

ø323,8 (12”)

Ø457,2 (18”)

DURBAN

DOUBLE PUMP STATION

DELIVERY STATIONS / METERS

PUMP STATIONS

REFINED PRODUCTS

CRUDE OIL

GAS

AVTUR

ø323,8 (12”)

ø457,2 (18”)Ø406,4(16”)

PARK

ø457,2 (18”)

ø406,4 (16”)

ø323,8 (12”)

CAPE TOWN

INTAKE STATIONS

NMPP PIPELINES

NMPP PUMPSTATIONS

NMPP TERMINALS

Ø

MNGENI

ELARDUS PARK

AIRPORT

DECOMMISSIONED DJP

PPT-1645-/B

ALRODE

VREDE“T”

Inland supply – beyond 2010

Page 45: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

45

Inland supply – beyond 2010

• The approval of the NMPP is the most critical project for the liquid fuels industry– Some changes required to Petronet’s design– Cannot leave the approval process to external

processes

Page 46: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

46

Pipeline sizes costs

Page 47: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

47

Current state of affairs

• Current growth in demand for petroleum products used for electricity generation is unsustainable

• Potential diesel shortagesProduct Volumes in

millions of Litres3rd Quarter

2005 3rd Quarter

2006 % Change

2006/05 3rd Quarter

2007 % Change

2007/06 PETROL 2797 2754 -1.5 2908 5.6

DIESEL 2026 2200 8.6 2495 13.4

JET FUEL 523 545 4.2 581 6.6

ILLUM PARAFFIN 200 192 -4 190 -1

FUEL OIL 125 124 -0.8 124 0

BITUMEN 71 72 1.4 79 9.7

LPG 154 167 8.4 191 14.4

SUM OF ABOVE 5896 6054 2.7 6568 8.5

Page 48: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

48

Inland supply – proposed pipeline intervention

• Expedite approval and implementation of the NMPP

• Implement split tariff approach

– Direct usage tariff levied on all users

– Initial reserve capacity financed through security of supply levy on all product

• Raise required state equity participation through dedicated levy

Page 49: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

49

Summary of recommendations of phase 1 Masterplan

• Manufacturing of petroleum products– Recommend promotion of local production of

petroleum products– Recommend that at least 30% of products be

manufactured from indigenous raw materials

• Climate change be considered an important component of integrated energy planning– Will require data collection and climate change

monitoring

• Alignment of our fuels specification and other standards (including housing and building standards) to global standards

Page 50: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

50

Summary of recommendations of phase 1 Masterplan

• 30% of all crude consumed in South Africa be procured through PetroSA

• Policy of limited imports of petroleum products be re-endorsed

• Energy efficiency be strongly promoted in all energy consuming sectors of the economy– The energy demand management approach

should include appropriate selection of energy carriers

– Demand management requires appropriate demand sectors’ strategies, starting from the industrial strategy through to appropriate transport strategies

• Level of coordinated infrastructure investments planning

Page 51: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

51

Summary of recommendations of phase 1 Masterplan

• Keep certain levels of strategic stocks – Airlines to be forced to keep certain

stocks– Eskom to keep stocks for OCGTs

• Approve Petronet’s new Multi Product Pipeline project

• In the short term, rail should be operated in “block train” format, so as to improve rail turn around times– Also prioritise Durban to Gauteng route

Page 52: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

52

Summary of recommendations of phase 1 Masterplan

• The management of the “back-of-the-port” operations should be run by an independent operator

• Most importantly, South Africa must build– an ability to develop properly thought-out

energy plans– a tool to evaluate proposed energy

related policies

Page 53: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

53

Overall Project Status

• Consultants appointed to manage overall implementation of programme in September 2007

• Initial briefing meeting with oil industry executives in December 2007– Governance structure formalised

• Project kick-off workshop in December 2007– Key deliverables identified– Task teams for each stream identified

• High-level steering committee in March 2008– Accession to PDR

• Follow up project workshop in March 2008– Task teams for each workstream formalised

• Task-team project meeting currently in progress– Detailed implementation schedule from each task team

due end May 2008• Ongoing implementation and monitoring

Page 54: Energy Security Masterplan – Phase 1 Parliament Portfolio Committee Presentation 18 June 2008

I Thank You