Upload
nsprasad88
View
235
Download
1
Embed Size (px)
Citation preview
8/29/2013
1
Dalmia Cement (Bharat) Limited, Kadapa
Founded in 1935 by Shri Jaidayal Dalmia. The Group established India’s first Cement Plant with 250
TPD in 1939. The Group interests includes Cement, Sugar, Power and
Refractory. Put up Cement Plants in Tamil Nadu and Andhra Pradesh.
Kadapa Unit Commissioned in Mar 2009 with a Capacity
of 2.5MTPA Cement. Overall Cement Manufacturing Capacity 17.9 MTPA.
8/29/2013
2
• OPC 53
• OPC 43
• SRPC
We Manufacture:
• PPC
ISO 9001:2008,ISO 14001:2004,OHSAS 18001:2007
8/29/2013
3
We are committed to produce cement of required Quality & Quantity, by Continuous Improvement on Energy Performances through effective implementation of Energy Management System, also by Effective utilization of available Energy resources by
Optimization and alternates. Enhancing the Energy efficiency, Reduction in Energy
Wastage Strive to be a bench marking organization in the Cement
Industry. Abide to all the applicable legal requirements and other
requirements M.C. Gautam Date : 10/07/2013 Executive Director
Plant Ordering Stage – Took Initiative for Energy Efficient Equipments
Plant Execution Stage – Considered Energy Saving Equipments
Commissioning Stage – Developed EMS Software in Plant Automation
Energy Saving by Efficient Eqpt. & Energy Savers: 85.5 Lakhs U/Annum
1st Year Operation Stage – Optimized Startup Time, Idle Run
Solar Heaters & Solar Lights at Mines
Energy Saving by Case Studies : 11.5 Lakhs Units/Annum
2nd Year Operation Stage – Improved the Equipt Perfor.
Energy Saving : 114.77 Lakhs Units/Annum
3rd Year Operation Stage – Improved
Energy Saving : 43.88 Lakhs Units/Annum
Current Plan & Actions
1. EnMS 50001
2. Enhancement of Alternative Fuel Feeding
3. Development of Renewable Power
8/29/2013
4
MV Drive for Pre Heater Fan & Bag House Fan
Damper less Process Fans with Variable Speed Drive
AC Variable Speed Drive for Coal Mill Main Drive
AC Variable Speed Drive for Kiln Main Drive
Cross Country Belt Conveyor for Lime Stone Transportation
8/29/2013
5
Expert Optimizer for Efficient Operation
Intelligent MCC for the Motors
Energy Efficiency Series Motors for the Complete Plant
P20 Lighting Energy Saver Panels
Energy Management System in DCS through Digital Meters
Particle Size Analyser
Cross Belt Analyser
Robo Lab
Lowest Pressure Drop for 6 Stage Pre Heater (460 to 480mmwg)
Lowest Specific Power Consumption of PH Fan (4.6 U/T of
Clinker)
Lowest False Air levels
8/29/2013
6
We do not use any natural mineral resources except Limestone AFR We use Red mud : As corrective in Raw mix Fly ash : As additive in PPC Material Petcoke & AF : As fuel Chemical Gypsum : As Additive in Cement Grinding
Unit Head
Technical Head
Unit Energy Task
Force Leader
Unit Energy Manager
Team Members (from)
Mechanical
Electrical
Process
Instrumentation
Utilities
(Engineers & Technician Categories)
Task Force Leader
Dalmia - Trichy
Task Force Leader
Dalmia - Ariyalur
Task Force Leader
OCL, Rajganpur
8/29/2013
7
Unit Without
Investment With
Investment
Total No. of Projects No. 35 26
Electrical Energy Saving / Annum
Million Units
6.2 6.84
Fuel Energy Saving / Annum
Million Kcal
6200 100
Cost Saving / Annum Rs.
Million 31.2 33.74
No Investment
8/29/2013
8
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Units in Million
Rs. In Million
1 Daily Monitoring and control of Section Wise Idle Power Consumption through DCS
0.35 1.75
2 Cement Mill Transport group stopped during the Mill Heat up.
0.06 0.3
3 Reduction of Cement Heat up Idling time duration from 2 Hours to 45 Minutes
0.84 4.2
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved Units in Million
Rs. In Million
4 Relocation of VFD for Compressor from Pyro to Cement Mill and avoided the unloading operation of the Compressor
0.16 0.81
5 Increased the Electrical System Power Factor from 0.97 to 0.98 by Auto Operation of HT Bus Capacitors
0.14 0.72
6 Kiln Shell Cooling Fans Operation with Temperature Interlock
0.18 0.9
8/29/2013
9
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved Units in Million
Rs. In Million
7
Coal Mill Hydraulic Pump Operation interlocked with Oil Temperature after Mill Stoppage and reduced the Idle Running.
0.01 0.015
8 Star Connection for Shell Cooling Fans 0.07 0.36
9 GRR Cooling Fan Stop Interlock at 100% Speed & SPRS Mode
0.38 1.90
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Units in Million
Rs. In Million
10 Reduction of Raw Mill Power Consumption by Dam Ring & Nozzle Ring Modification
1.46 7.31
11 Modification in LS Crusher Wobbler Ribs to reduce the gap and achieved Reduction in Lime Stone Size
1.13 5.63
12 Reduction of Idle Power in RMH Section by No Material Sensors
0.16 0.80
8/29/2013
10
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Units in Million
Rs. In Million
13 Reduction of Bore well Power by using STP Water for Cement Mill
0.06 0.30
14 Bag House in DP Mode and Reduction of BH Fan & RA Fan Power
0.50 2.52
15 Intermittent Timing Operation for LS Crusher Spillage Conveyor
0.02 0.12
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved Units in Million
Rs. In Million
16
Packing Plant Dust Collector Fans Speed Interlocked with Packer Main Drive. (Reducing Speed to 20% when Packer Stops)
0.11 0.56
17 Conducted Compressor Leak Test & Reducing the Leak of Compressed Air.
0.01 0.05
18 Auto Start Stop Time Interlock for Office Area Centralised AC
0.15 0.73
8/29/2013
11
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved Units in Million
Rs. In Million
19 Switching Off the Distribution Transformers & Drive Transformers during Plant Shutdown
0.03 0.17
20 Time Delay Interlock for RABH Rotary Air Locks
0.01 0.06
21 Operating of Plant Lighting according to the Seasonal Variations
0.01 0.07
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved Units in Million
Rs. In Million
22 Auto Stop Interlock for Circular Stacker Slew with respect to the Material Flow
0.01 0.05
23 Auto Stop Interlock for Coal Stacker & Additive Stacker Travel with respect to the Material Flow
0.01 0.07
24 Automatic Speed Reduction of Blending Silo Top Bag Filter with respect to the Raw Mill Operation
0.01 0.06
8/29/2013
12
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Units in Million
Rs. In Million
25 Operating the Raw Mill Hopper Bag Filter Fan with respect to material property
0.13 0.69
26 Auto Start Stop Interlock for Water Fountain Pumps with Office Timing
0.005 0.025
27 Optimized the Wagon Loading Time duration from 15Hrs. to 8 Hrs.
0.01 0.06
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved Units in Million
Rs. In Million
28 Switching OFF Alternative Street Lights at Plant & Colony after late Night
0.01 0.07
29 Reduction of Distribution Transformer Voltage from 435V to 415V by Tap Changing
0.003 0.013
30
Operating the LS Crusher during Day time and minimizing the Lighting requirement. Also, Stopping the Mine Haulage Road Lighting according to the LSC Operation
0.01 0.05
8/29/2013
13
No Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved Units in Million
Rs. In Million
31 Intermittent Operation of Truck Tippler Spillage Conveyor
0.02 0.12
32 By reducing the False Air Level (3% Reduced), Coal Mill Fan Power reduced
0.13 0.66
No Investment
Sl. No.
Energy Saving Projects
Annual Fuel Saving Achieved /
Annum Fuel Qty.
Rs. In Million
33
Reduction of Fuel Consumption in Pyro Section (False Air, Outlet Temp., O2 Optimization, Exhaust Gas Volume, Insulation Bricks)
17 Kcal/Kg Clinker
2.23
34 Reduction of Specific Diesel Consumption in Cement Mill
450 KL 26.1
35 Reduction of Diesel Consumption during Kiln Start-up.
14 KL/Start
9.75
8/29/2013
14
With Investment
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back
in Mont
hs Units in Million
Rs. In Million
1 Installed VFD for VRM Reject belt & Reduction of Idle Power
0.11 0.53 0.70 16
2 Modification of PH Down comer Expansion Joint and Sustained Lowest False Air
0.32 1.58 0.1 1 1
Kcal/Kg 0.13
3 Silo Aeration Blower Drive Pulley size Reduction
0.04 0.18 0.01 1
8/29/2013
15
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Months Units
in Million
Rs. In Million
4 Tower AC Installed for Robo Lab and Optimized Centralised AC Temp.
0.29 1.46 0.20 2
5 Operation of STP Water Pumps through Mobile Phone Starter
0.01 0.03 0.01 4
6 Installed Air Control Module for Flyash Unloading System
0.03 0.15 0.1 8
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Month
s Units in Million
Rs. In Million
7
Raw Mill Inlet duct modification with chute and improved productivity
0.66 3.3 0.1 1
8 Packing Plant Blower Capacity Reduced from 30KW to 22 KW
0.07 0.35 0.04 2
8/29/2013
16
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Months Units
in Million
Rs. In Million
9 Installed HT Bus Capacitor and Improved the PF from 0.98 to 0.992
1.5 7.3 0.7 2
10 Speed Reduction of Coal Crusher Belt Conveyors
0.05 0.25 0.08 4
11
Replacement of Low Efficient old Pumps with Efficient Pumps in Centralised AC System
0.07 0.35 0.04 2
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Month
s Units in Million
Rs. In Million
12 Optimization of Cement Mill Power by rebuilding the Rollers & Table
2.80 14.00 0.30 1
13 Decentralised 30KW Compressors for Individual Packers
0.39 1.96 2.80 18
14 Installed LED Street Lights in Colony
0.01 0.03 0.19 80
8/29/2013
17
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Month
s Units in Million
Rs. In Million
15
Installed Hydraulic Scrapper for unloading of Raw Material in Truck Tippler and reduced the Truck unloading Time & Truck Tippler Group Operating Hours
0.02 0.1 0.25 30
16
Converted of 200W Incandescent to 70W HPSV Lamp in the SF Cooler Inspection Chamber
0.03 0.13 0.02 2
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Month
s Units in Million
Rs. In Million
17 Manual Switch Control for Packing, Workshop, Silo Lightings
0.02 0.04 0.01 3
18 Permanent Speed Reduction of Raw Coal Hopper BF Fan
0.06 0.3 0.05 2
19
Interconnected Bag Filter Suction & Stopped 2 Nos. of 11KW BF Fan (491FN8 & 391FN9)
0.14 0.66 0.04 1
8/29/2013
18
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Month
s Units in Million
Rs. In Million
20
Usage of Hand Driven LED Torch Light for Securities, in place of Inspection Hand Lamp for Maintenance
0.006 0.03 0.03 12
21 Installation of Solar Water Heaters for Athiti & Swagath Guest Houses
0.04 0.18 0.20 12
22 Installation of Solar Street Lights with LED Light Fittings at Mines Magazine
0.01 0.04 0.15 45
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Month
s Units in Million
Rs. In Million
23
Installed Chute at Pre Heater to shift the Scrap Material from 3rd /2nd /1st Floor to Ground. Hence, Lift Operation reduced.
0.0005 0.0025 0.05 240
24 Occupancy Sensor for Load Centre Lighting Auto Control
0.04 0.19 0.01 1
8/29/2013
19
Sl. No.
Energy Saving Projects
Annual Electricity
Saving Achieved
Invest ment (Rs.
Million)
Pay Back in Month
s Units
in Millio
n
Rs. In Million
25
Replacement of 60W Incandescent Lamp with 11W CFL Lamps at Colony & Guest Houses
0.04 0.2 0.05 4
26
Replacement of 36W Fluorescent Lamps to T5 Lamps & CFL Lamps at Offices
0.08 0.4 0.05 2
690
695
700
705
710
715
720
725
730
2010-11 2011-12 2012-13 2013-14
725
721
707
702
Kcal / Kg Clinker
8/29/2013
20
64
66
68
70
72
74
76
78
80
82
84
86
2010-11 2011-12 2012-13 2013-14
84.45
82.64
76.5
72.14
Overall Units / Ton of Cement
50
51
52
53
54
55
56
57
2010-11 2011-12 2012-13 2013-14
56.02
55.25
54.20
52.00
KWH/T of Clinker
8/29/2013
21
70
72
74
76
78
80
82
84
86
88
90
2010-11 2011-12 2012-13 2013-14
88.70
86.10
80.10
77.12
KWH/T of Cement (OPC)
60
61
62
63
64
65
66
67
68
69
2010-11 2011-12 2012-13 2013-14
68.2
66.3
63.4 63.2
Kwh/Ton of Cement (PPC)
8/29/2013
22
5
10
15
20
25
2009-10 2010-11 2011-12 2012-13
10.50
16.50
20.80
23.50
Energy Savings (Million Units / Annum) Cumulative Trend
0
0.02
0.04
0.06
0.08
0.1
0.12
0.14
0.16
0.18
2008-09 2009-10 2010-11 2011-12 2012-13 2013-14
0.17
0.15
0.11 0.1
0.09 0.08
Explosives Kg/MT of Limestone
8/29/2013
23
SEC DCBL Actual (FY 2012-13)
National Benchmark
***
International Benchmark
***
Specific Energy Consumption – Thermal (KCal/Kg of Clinker)
707* 667 660
Specific Energy Consumption – Electrical (KWh/T of Cement)
76.5 67 65
*** Source of Information : 12th Planning Commission Report
*Specific heat consumption is : 686 Kcal/Kg Clinker
60
61
62
63
64
65
66
67
68
69
2010-11 2011-12 2012-13 2013-14
68.2
66.3
63.4 63.2
Kwh/Ton of Cement (PPC)
NB
INB
NB – National Benchmark INB – International Benchmark
8/29/2013
24
1
• Installation of Waste Heat Recovery Power Plant. Generation Potential : 4.3 MW/Hr.
•Ordered to M/s Techpro Systems Ltd.
•Target : September 2014
2
•Retrofitting of Cement Mill Fan Impeller for Energy Efficiency Improvement
•Study Completed. Saving Potential 250KW/Hr. Ordering Stage, Target : March 2014
3
•Replacement of High Pressure Compressor to Energy Efficient Turbojet Blower for Flyash Handling
•Ordering Stage. Target : March 2014
4
•Reduction of Pressure Loss b/w Raw Mill Cyclone to Raw Mill Fan duct. Saving Potential 100mmwg.
•Study Completed. Saving Potential is 60KW/Hr. (Rs. 24 Lakhs / Annum) Target : September 2014
5
• Improving the PPC Cement Dispatches
•Launched New PPC Product “Dalmia Ultra” to boost the PPC Sales. Shall reduce the SEC. 6
•Retrofitting of RABH Fan Impeller for Energy Efficiency Improvement
•Study Completed, Savings Potential 50KW/Hr. (Rs. 20 Lakhs / Annum) Target : June 2014
8/29/2013
25
Objective: Reduction of Fuel Consumption from 721 kcal/kg to 700 kcal/kg
Approach: 2R principle that is
Reduce
Replace
IP - 1
8/29/2013
26
Variation in Kiln Feed Process
Operation
Limestone
Limestone size 90mm >5%
Segregation of material in Pile
Low Burnability
High False Air
High Loss through PH Exist Gases
High Silica
Secondary Temp. Variation
High Clinker Temp.
Reduction of K.Cal/kg of Clinker
Coal
Silo Blending Efficiency
Uneven Flow Of Correctives
IP - 1
Mines
•Control the Fragmentation Size in Blast Muck Pile
•Two point Loading for better blending
Crusher
• Reduction of output size less than 90mm
• Remove the clay in the Limestone to reduce Silica Variations
Stock Pile
• Height of Fall in Limestone Stocking
• Pile Sequencing in Limestone Stocking
• Pile formation in Coal and correctives
IP - 1
8/29/2013
27
Raw Mill
•Desired Flow of corrective material that is Red Mud.
•Optimum residue for good Burnability.
Pre Heater
•Proper dispersion of raw meal into Pre-Heater
•False Air Management
IP - 1
Challenges:
High moisture up to 30% in the Red mud the corrective material affect the material flowability in the system.
Circular Stock Pile for Limestone which is having less blending efficiency
Limestone with relatively High Bond Index
Used varieties of coal of origin Indonesia, South Africa, US and Petcoke
IP - 1
8/29/2013
28
Sl. No.
Area Problem Improvement Actions
1 Mines Control the Fragmentation Size in Blast Muck Pile
Optimising the Powder Factor (Explosive Energy Consumed per MT of Limestone)
2 Crusher
Remove the clay in the Limestone To reduce Silica Variations
Installation of Screening Plant in the Limestone crushing Circuit
Reduce the crusher output size less than 90mm
Wobbler Feeder Gap reduced from 85mm to 60mm by introducing the additional rib on the rollers
IP - 1
Sl. No.
Area Problem Improvement Actions
3 Stock Pile
Height of Fall in Limestone Stocking
Maintaining the Luffing Action of Limestone Stacker
Pile Sequencing in Limestone Stocking
Interlocking the horizontal movement of Limestone Stacker with respect to the Material
Pile formation in Coal and correctives
Linear Pile system for correctives and coal instead of point stocking
IP - 1
8/29/2013
29
Sl. No.
Area Problem Improvement Actions
4 Raw Mill
Desired Flow of corrective material that is Red Mud.
• Additional Hopper for Red mud for quick change over and continuity of flow. • Polymer Lining to the storage hoppers
Optimum residue for good Burnability.
Conducted the Burnability studies and fixed the optimum residue for good burnability
Raw mix residue optimized to 23% on 90 µ and 2.5% on 212 µ
IP - 1
Sl. No.
Area Problem Improvement Actions
5 Blending Silo
Blending Efficiency
Raw Meal silo extraction cycle pattern changed from normal to alternate cycle and timer changed from 3 minute to 2 minutes
Blending Silo extraction Air Slide Cloth Changed
Raw Meal silo top filling timer changed from 7 minutes to 3 minutes
Filling of Silo more than 70%
IP - 1
8/29/2013
30
Sl. No.
Area Problem Improvement Actions
6 Pre Heater
Proper dispersion of the raw meal into the Pre Heater
Adjustment of the dispersion plate in the feed box of cyclone 4 and 5 to optimize the Heat Transfer Profile
IP - 1
IP - 1
Retrofitting of Screening Plant in the Existing Crusher Circuit
8/29/2013
31
Benefits of Screening Plant Improved quality of limestone by separating the clay
from limestone. Reduction in Reject of low grade limestone, hence the
cost saving is Rs. 0.60/ton of material. (Saving Rs. 12 Lakhs / Annum) Life of the limestone mine increased. (Mineral
Conservation)
IP - 1
Optimization of Preheater Exit Oxygen level from 3.0 %to 2.5% despite of using Petcoke by close & regular monitoring of all major expansion joints.
Preheater down comer duct modified with telescopic design expansion joint to avoid thermal losses.
Calciner Exit temperature optimised to the range of 880 to 885 deg C as against earlier of 900 deg C by consistent Raw mix quality.
Installed Insulation Bricks (Alite – Dalmia Refractory) in Calcination zone of kiln to reduce Kiln radiation.
IP - 1
8/29/2013
32
Because of all these actions, remarkable reduction in Preheater Exit temperature from 270 to 250 C to reduce the heat losses through PH exit gases.
Cooler bed height increased from 600 to 720 mmwg, for better heat recuperation.
Physical inspection and false air measurements every week in each section. • Achieved Best Figure for False Air %, which is
witnessed by CII Energy Audit Team during their visit in May-2013 Raw Mill : 7.2% Coal Mill : 6.2% Cement Mill : 7.4%
IP - 1
Improved the reliability and availability of kiln inlet analyser by increasing the probe length and by changing the angle.
Reduction in diesel consumption for kiln light up from 12 KL to 4 KL per each light up.
(Cost Saving 557 Lakhs / Annum)
IP - 1
8/29/2013
33
Our Focus are
Liquid Alternate Fuel
(from Pharmaceutical Industry)
Dolachar (from Steel Rerolling Mills)
Spent Carbon (from Pharmaceutical Industry)
IP - 1
Developed Inhouse system for the feeding of Liquid Alternative fuel.
IP - 1
8/29/2013
34
0
0.5
1
1.5
2
2.5
2012-13 2013-14
2.01 1.86
Alternative Fuels in TSR%
IP - 1
Installed VFD for Alternative Fuel Pump for effective combustion. Separate Feeding arrangement for Solid alternate fuel. Spent Carbon utilization by spreading in Raw Coal Pile.
IP - 1
8/29/2013
35
690
695
700
705
710
715
720
725
730
2010-11 2011-12 2012-13 2013-14
725
721
707
702
Kcal / Kg Clinker
IP - 1
Result:
Current Status of Heat Consumption in Pyro
Heat of Formation 410 Kcal/Kg Clinker
Heat loss through PH Exit gases 114 Kcal/Kg Clinker
Heat loss through Cooler Exit Gases 88 Kcal/Kg Clinker
Heat Loss through Clinker 31 Kcal/Kg Clinker
Heat Loss through Radiation 43 Kcal/Kg Clinker
Total Heat Consumption 686 Kcal/Kg Clinker
IP - 1
Result:
8/29/2013
36
59.8 16.6
12.8
4.5 6.3
Formation PH Exit Cooler Exit Clinker Radiation
IP - 1
Objective: Improve the Raw Mill Productivity from 370 to 400 TPH
Background:
To maintain kiln feed quality consistently it is desirable to maintain the Raw Meal silo level more than 70%. To achieve this raw mill output requires 400MT per Hour for the Kiln output of 5200TPD.
Achieved 6000TPD as highest Clinker Production, but optimized at 5200 TPD, keeping in view of Power & Fuel Economy
IP - 2
8/29/2013
37
Challenges: To maintain the Raw Meal residue 23% on 90 micron and 2.5% on 212 micron for better burnability.
Designed capacity of mill is 375TPH at
23% residue on 90 microns
Limestone with relatively High Bond Index
Maximise the Alternative Raw Materials in place of minerals as correctives
To avoid Running of Raw Mill in Peak Hrs
IP - 2
Lime Stone size is higher (5% more than 90mm Size)
High Reject from the Raw Mill
High Mill Main Drive load while increase Mill feed.
Heavy Material deposition at Mill Inlet Duct.
IP - 2
8/29/2013
38
Reduction of Lime Stone Size
Increase the Raw Mill Grinding Pressure
Increase of Nozzle Ring Velocity
Optimization of Dam Ring Height
Optimization of Water Spray
IP - 2
Consistent feeding of Red mud.
Solution for material accumulation at Mill inlet duct
Optimization of Classifier Operation
IP - 2
8/29/2013
39
To reduce the Lime stone Crusher output size less than 90mm
• Blow Bar gap reduced from 90 mm to 80 mm.
• Extra Ribs provided in Wobbler Rollers to avoid any
escape of higher size Lime Stones.
IP - 2
Additional Wobbler Ribs Provided to reduce the sieve size.
Additional Ribs
IP - 2
Before After
8/29/2013
40
To maintain the consistent flow of Red Mud
• Stacker operation converted to auto linear stacking instead of point stacking.
• Iron ore hopper converted to stand by Red mud hopper for quick change over in case of jamming.
• Provided Vibrator and Blasters for better flow of high moisture Red mud.
• Polymer lining provided for better flow.
• Extra hopper for Red mud feeding, provided at reclaimer belt for dry Red mud during critical condition.
IP - 2
Optimized Nozzle Ring Velocity
• Nozzle Ring area between two Rollers of Raw Mill blocked.
• Total Nozzle ring area 7.99 M2
• Blocked nozzle ring area 1.83 M2 (23%)
• Nozzle Ring Velocity : 36.21 M/Sec
IP - 2
8/29/2013
41
Nozzle Ring Blocked
IP - 2
Nozzle Ring Blocked
Dam Ring reduced from 65 mm to 25 mm in two phase, which reduced Mill Main Drive load from 3700 to 3400 KW.
Optimized the Grinding Pressure.
Raw Mill Separator Seal gap reduced by applying felt to avoid escaping of raw meal from separator seal.
After increasing grinding pressure & applying felt for Separator, Separator speed optimized from 63% to 59% to achieve Raw Meal residue 22-23% on 90 µ & 2.8% on 212 µ.
IP - 2
8/29/2013
42
Raw Mill Feed chute length extended by 200 mm to avoid material rejection due to centrifugal force.
Raw Mill water spray nozzle location optimized to minimize the water consumption from 6 M3/Hr. to 2.5 M3/Hr.
IP - 2
Extended Chute
IP - 2
Feed Chute Extended 200mm
8/29/2013
43
Heavy Material Deposition
Inlet Duct Outer View
IP - 2
Installed Chute below the Inlet Duct to drain the deposition
No Material Deposition
IP - 2
8/29/2013
44
382
388
406
360
365
370
375
380
385
390
395
400
405
410
2011-12 2012-13 2013-14
Raw Mill TPH
Design Capacity 375 TPH
IP - 2
18 17.7
16.7
14
15
16
17
18
19
20
2011-12 2012-13 2013-14
Raw Mill Specific Power
OEM Guaranteed 19 Units/Ton of Material
Units / Ton of Material
IP - 2
8/29/2013
45
1.5
2
2.5
3
3.5
4
2011-12 2012-2013 2013-2014
3.5
3.0 2.8
% Residue on 212µ
IP - 2
Objective: Capacity Utilization of VRM (Raw Mill & Cement Mill) at all the Times and Reduction of VRM Power due to unexpected Tripping.
IP - 3
8/29/2013
46
Problem Faced:
After the Unexpected Tripping of VRM, Mill unable to Operate at rated capacity due to Reject Bucket Elevator Overloading. (Due to Handling of Reject Hopper Material & VRM Reject Material).
Hence, Mill Idle Power is High due to Operating at Under Capacity.
IP - 3
Action Taken :
Installed the Variable Frequency Drive for the Reject Handling Belt Conveyor.
Reject Material in the Hopper is handled to the VRM at
10% Speed of the Reject Belt with the help of VFD.
IP - 3
8/29/2013
47
Benefits:
Overloading of Reject Belt Conveyor and Jamming of Reject Bucket Elevator avoided. Hence, avoided Mill Stoppage.
VRM shall Operate at Rated Capacity with in a very short period.
Idle Run Time, Productivity, Idle Power Consumption and Mill Performance were improved.
IP - 3
Summary:
Investment : 3.5 Lakhs / VRM
Unexpected Tripping : 2 Tripping per month / VRM
Production Loss : 70 Tons Prod. / Trip / VRM i.e. 140 Tons Production Loss / Month in Raw Mill 140 Tons Production / Month in Cement Mill Idle Power Loss:
Raw Mill : 1600 Units Loss / Trip
Cement Mill : 1700 Units Loss / Trip
Tentative Power Loss : 6600 Units Loss / Month
IP - 3
8/29/2013
48
Results Achieved: Savings:
Power Cost Saving : 6600 Units X Rs. 5.00 : Rs. 33,000 per Month Total Power Cost Saving : Rs. 4 Lakhs / Annum Payback : 2 Years Note: Savings excluding the Truck Handling Charges
IP - 3
IP - 4
Objective: Optimizing the Cement Mill Operation with Minimum Hot Gas and Smooth Operation. Actions Taken:
1. Optimized the Temperature of Cement Mill VRM during Startup
2. Optimized the Water Spray able to retain the Temperature generated during the Grinding.
8/29/2013
49
Action Taken :
3. Optimizing the Recirculation Damper to avoid the heat
loss.
4. Reducing the Start-up Idle Operation Time by One Hour due to Optimized with low temperature
5. Eliminated the requirement of Hot Gas during Operation (after Start up)
6. Stopped the Booster Fan Operation after Start up
IP - 4
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
2009-10 2010-11 2011-12 2012-13
1.98
1.4
0.21 0.15
0.6
Specific DieselConsumption(Ltr./Ton of Cement)
Cluster Specific DieselConsumption(Ltr./Ton of Cement)
IP - 4
8/29/2013
50
IP - 5
Objective: Optimizing the KVAH Consumption by Improving the Power Factor from 0.975 to 0.990. Actions Taken:
1. Measured the Capacitor Requirement at the Individual Load Centres with the Help of Digital Multi Function Meter available in all the Feeders.
IP - 5
Actions Taken:
2. Provided Auto Start Stop Interlock for the HT Bus Capacitors through DCS
3. Arrived the Capacitor Requirement and Installed the additional HT Bus Capacitor
4. Controlled the HT Bus Capacitors operation through DCS as per the Mills Operation.
5. Ensured No Leading Power Factor all the Conditions
8/29/2013
51
0.965
0.970
0.975
0.980
0.985
0.990
0.995
0.97
0
0.97
0
0.97
2
0.98
0
0.98
0
0.98
7 0.99
0
0.99
1
0.99
2
0.99
1
0.99
1
0.99
2
0.99
0
0.99
0
Grid Power Factor
IP - 5
0.97
0.98
0.99
0.96
0.965
0.97
0.975
0.98
0.985
0.99
0.995
2010-2011 2011-2012 2012-2013
Continual Power Factor Improvement
IP - 5
8/29/2013
52
IP - 6
Objective: Reduction of Packing Plant Specific Power Consumption from 3.0 U/T of Cement to 1.2 U/T of Cement Actions Taken:
1. Installed & Operating 30KW Individual Compressor for Individual Packer instead of Operating 160KW Centralised Compressor
IP - 6
Actions Taken:
2. Arrested the Compressed Air Leakages & Optimized the Bag Filters Purging Frequency & Time
3. Monitoring & Controlling of Idle Power Consumption on daily basis
4. Reduced the Idling Time by Training given to Truck Loader Operators.
5. Optimised the Operating Speed of Bag Filter Fans through VFD.
6. Automatic Speed Interlocking to Bag Filter Fan with respect to Packer Main Drive Operation
7. Operation Interlock for Bag Cleaning Fans
8/29/2013
53
Result:
Specific Power Consumption of Packing Plant reduced from 3.0U/T to 1.2 U/T of Cement
Energy Saving of 2.5 Lakh Units / Annum
IP - 6
Sp. Power Reduction in Packing Plant
IP - 6
8/29/2013
54
• Reuse of STP water
• Water Conservation Task Force
• Rain Water Harvesting and Use of Mine Pumped out Water
Water
• Energy Conservation Projects Energy
• Solar Power
• Bio-Diesel
• Wind Power
Non-Convention
al Energy
• Jetropa Plantation
• Mass Tree Plantation on June 5th & providing sapling to neighbouring
• Department wise ownership
Plantation
8/29/2013
55
• Stack Emissions
• Recycling of Floor Spills
• Gypsum Un loader
• Reuse of Waste
Environment
• Vermi-compost
• Common Vehicle for commuting in Plant & Colony
• Use of Bicycles by movement in the Plant
• Form pond
• Rain water harvesting structures
• Distribution of Solar lamps
• Practice of integrated Pest Management
• Awareness on Environment
Community
• Installation of Waste Heat Recovery Power Plant at Pyro Section Vent
CDM Project
Green Development
Neerium Neem
Pungam Pungamia
8/29/2013
56
Konocarpus
Tacoma
Yellow
Green Development
Green Development
8/29/2013
57
Green Development
Green Development
8/29/2013
58
Involvement of Employees, Families & Children
Involvement of Employees, Families & Children
8/29/2013
59
10000
15000
15000
16000
2010-11 2011-12 2012-13 2009-10
20000
TARGET
(2013-14)
Green Development in the Plant & Colony
1. Celebrated Energy Conservation Week during the National Energy Conservation Day 14th December 2012
2. Conducted Campaign at nearby Villages about the Energy Conservation and Methods to Save Energy
3. Sharing Energy Conservation Tips for the day during Energy Conservation Campaign
8/29/2013
60
8/29/2013
61
1. Utilizing 100% STP Generated Water to the Plant for VRM Water Spray.
2. Generated water storage pond for capacity 180000 M3 with an Investment of Rs.20.0 lakhs (Mines Pond Water)
3. Reduced Water Consumption in Clinker Cooler by improving the Heat recuperation from Cooler Fans (Fan No. 1, 2 & 3) and Optimized the fresh air entry by installing Fresh Air Damper at cooler ESP duct. Reduced Water consumption from 16 M3 to 3.5 M3.
Water Management Award received from CII
0
2
4
6
8
10
12
14
16
Before At Present
Cooler Water Consumption (M3/Hr.)
16
3.5
8/29/2013
62
CII’s National Excellence in Water Management Award - 2012
Electrical Energy Saving Projects 19505 Ton of CO2
Reduction / Annum
Thermal Energy Saving Projects 640 Tons of CO2
Reduction / Annum
Greenary Development 56,000 Nos. of Plantation
(Survived)
Summary
Major Future Plan Waste Heat Recovery Plant Installation & Commissioning.
Ordering Completed. Target for Commissioning : September 2014
8/29/2013
63
Employee Involvement & Opportunities for sharing Encon Ideas
1. Employee Suggestion Scheme from Workmen to Management Staff
2. Section wise Monthly Performance Meeting from Workmen to HOD
3. Employee Communication for Suggestions & Ideas to Corporate Management & Unit Management
4. Selection of Monthly Campaign for Energy Conservation, Environment, Health, Safety…ggestion to Managing Director
Employee Involvement & Opportunities for sharing Encon Ideas
5. Capturing of Essays, Slogans, Essays from Workmen and awarding during Monthly Gate Safety Meeting
6. Weekly Section Wise Plant Review Meeting with Engineer Level to Top Management for the Improvement Jobs
7. Hotline Mail ID for Ideas & Suggestion to Managing Director
8/29/2013
64
Total No. of Suggestions (from Employees to Workmen)
No. 231
Suggestions Related to Energy Conservation
No. 79
Validated Suggestions related to Energy Conservation
No. 72
Total No. of Energy Conservation Suggestions Implemented
No. 69
Note : Including Minor Suggestions
Sl. No.
Name of the Training Programme
No. of Employees
Participated
Training days
Total Man Days
1 Energy Management Systems
39 1 39
2 Energy Conservation & Audit Methods
18 1 18
3 ENCON mission to world class energy efficient cement industries
4 1 4
4 Energy Management Systems
2 2 4
5 Training Program On Energy Management
2 5 10
8/29/2013
65
Sl. No.
Name of the Training Programme
No.Of Employees Particpated
Training days
Total Man Days
6 Energy Conservation & Management in Cement Industry
5 2 10
7 Energy Conservation & Energy Audits in Cement Plants
2 3 6
8 Energy Management in Cement Industry 2 2 4
Sl. No
Source of EnCon idea * Idea
originated in FY
Extent of man-power
involved
Progress of implementation
1 Power Factor Improvement from 0.975 to 0.992
2012-13 Shift
Technicians & Engr.
Completed & Achieved
2 Conversion of Delta Conn. to Star Conn. for Shell & Tyre Cooling Fan
2012-13 Elect.
Technician & Engineer
Completed. Project Identified during Section Review Meeting
3 Silo Aeration blower Speed Reduction by Changing Pulley
2012-13 Encon Team
& Section Engineer
Completed. Project Identified during Encon Team Rounds & Reviewed with Section Meeting involved Foreman, Supervisor, CCR Operator & Engineers
8/29/2013
66
Sl.
No Source of EnCon idea *
Idea
originated
in FY
Extent of
man-power
involved
Progress of
implementation
4
Relocated VFD from Pyro
Comp. to Cement Mill
Comp.
(Avoided Unloading Operation of Comp.)
2012-13 Section
Engineer &
Section Head
Completed. Project
Identified during Encon
Team Rounds &
Reviewed with Section
Meeting involved
Foreman & Supervisor
5 Installed VFD for VRM
Reject Belts and Improved
Equipment Availability 2012-13
Fitter,
Engineer &
Management
Completed. Project
Identified during Section
Review Meeting involved
Foreman, Supervisor,
CCR Operator &
Engineers
Sl. No
Source of EnCon idea * Idea
originated in FY
Extent of man-power
involved
Progress of implementation
6 GRR Cooling Fan Stop
Interlock with 100% Speed 2011-12
Elect.
Techncian &
Engr.
Completed. Project
Identified through
Employee Suggestion
Scheme
7 Operation of Bag Filter in DP mode instead of Timer Mode
2011-12
Section Engineer &
Section Head
Completed. Suggested by Section Engineer
8 Regular Monitoring of False Air Level in the Mills & Pyro section
2011-12
Fitters, Attenders, Welders & Engineers
Continuous Process.
8/29/2013
67
Sl. No
Source of EnCon idea * Idea
originated in FY
Extent of man-power
involved
Progress of implementation
9 Plant Lighting Time tuning as per the Seasonal Variation
2010-11 Electrical
Technician
Completed. Project Identified During Daily Morning Meeting with Technicians
10 Coal Crusher Belt Conv. Speed Reduced & Improved Belt Life
2012-13
Fitter, Welder, Engr. & HOD
Completed. Identified & Proposed the Workmen Team from RMH Section
Sl. No.
Energy Saving Projects
Investment in
Rs. Million
Energy Saving
Potential (Million
Units/Annum)
1 Installation of Waste Heat Recovery System for Pre Heater Exit Gas
40 18.08
2 Retrofitting of Cement Mill Fan to Save the Power of 250KW/Hr.
4 1.34
3 Lower Cyclone Dispersion Box height in riser duct and increase heat transfer
4 0.80
8/29/2013
68
Sl. No.
Energy Saving Projects
Investment in
Rs. Million
Energy Saving
Potential (Million
Units/Annum)
4 Reduce Pressure drop across Cyclones outlet to fan inlet duct in Raw Mill
1.5 0.56
5 Cooler Fan Silencer Pressure Drop is more hence Replace with Less Pressure Drop silencer
0.5 0.27
6 Load Center A/C Chillier Thermostat to be replace with Electronic Thermostat
0.5 0.12
Sl. No.
Energy Saving Projects
Investment in
Rs. Million
Energy Saving Potential (Million
Units/Annum)
7 Replacement of High Pressure Compressor with High Eff. Turbojet Blowers for Flyash Handling
0.8 0.09
8 Avoid air venting in packer Aeration blower by Providing VFD and Common Header
0.5 0.02
9 Install New efficient Process Flow Pump Pumps at Water Treatment Plant
0.2 0.02
10 Installation of Wind Power Generator at Pre Heater
1 0.01
8/29/2013
69
Non Conformities – 3 Nos.
SL.
NO NON CONFORMITIES CORRECTIVE & PREVENTIVE
ACTION
1.
Senior Engineer position defined
but the authorities &
Responsibilities not defined in the
process manual reference doc no:
F-1(SP-5, AM-5) Issue 02, Rev
no:00 dated 12.08.11
CORRECTIVE: Amend the format with
respect to the responsibilities of Senior
Engineer
PREVENTIVE: Periodical Review
Mechanism developed
2.
Chain pulley 3 MT capacity
(equipment id no: BR 60068)
periodical testing details not
evidenced
CORRECTIVE: The Chain Pulley will be
tested.
PREVENTIVE: List of Equipment's with their
schedule to be made.
3.
Aspect of Generation and disposal
of E wastes during the Maintenance
of Instruments found not identified
and evaluated.
CORRECTIVE: Aspects of generation &
disposal of E waste will be identified
PREVENTIVE: Periodical Review of Aspect
Register shall be followed.
8/29/2013
70
Dalmia Cement (Bharat) Limited. Kadapa Project Daily Power Consumption Report
132Kv Main Incoming Units 374595 Kwhr Avg PF: 0.990 Report Date: XX.06.2013
DG Generation Units 0 Kwhr Consumption Date: XX.06.2013
Peak Hour Consumption 20715 Kwhr (MD) KVA 22500 OLTC Opn. Count 9
Sl. No.
Section Description Units Consumption Running
Hrs Prodn.
Production Rate
Avg Kw Guaranteed U/T of Matl.
Actual U/T of Matl.
1 LS Crusher 16.17 11445 707.79 628
LS Crusher Main Drive 3771 233 0.38 0.33
LS Crusher Auxiliaries 1938 120 0.46 0.17
211BC2 Long Belt 2386 148 0.42
0.21
211BC2A Long Belt 2060 127 0.18
LS Crusher & Transport-Total 10155 1.25 0.89
2 Raw Mill 16.92 7105 419.92 7106
Raw Mill Main Motor 63158 3733
17.42
8.89
Raw Mill Fan Motor 44628 2638 6.28
Raw Mill Classifier 1523 90 0.21
MCC - 02 (LS Transport) 1957 116
2.07
0.28
MCC - 03 (RM Grinding Aux.) 6936 410 0.98
Additive Reclaimer 327 19 0.05
LS Stacker & Reclaimer 1706 101 0.24
RM Fan SPRS Recovery 0 0 0.00
Total 120235 19.49 16.92
3 Coal Mill 14.33 577 40.27 877
Coal Mill Main Motor 5197 363
25.51
9.01
Coal Mill Fan Motor 3577 250 6.20
Coal Mill Classifier 272 19 0.47
MCC - 07 (Coal Mill Grinding Aux.) 2169 151 16.73
3.76
RMH & Coal Crusher 1349 94 2.34
Total 12564 25.51 21.77
Daily Power Consumption Report
4 Kiln & Cooler 24.00 5282 220.08 4175
Kiln Main Drive 9244 385
15.60
1.75
Pre Heater Fan 25092 1046 4.75
Cooler Fans & PA Fan VFD 32221 1343 6.10
Bag House Fan 5208 217 2.61 0.99
MCC - 04 (RABH Dust Tpt.) 960 40
9.33
0.18
MCC - 05A (CF Silo Ext. & Kiln Feed BE) 15257 636 2.89
MCC - 05B (Kiln Shell Cool & Lub) 2092 87 0.40
MCC - 08 (Coal Firing) 2597 108 0.49
MCC - 09 (SF Cooler, ESP & DPC) 5057 211 0.96
Utilities (Water Treatment) 2461 103 0.47
Total 100189 27.54 18.97
5 Cement Mill OPC PPC OPC RH 11.33 OPC KW PPC KW OPC U/T PPC U/T
Cement Mill Main Drive 52877 17305 OPC Prod. 3739 4667 5197
27.00
14.14 16.74
Cement Mill Fan Drive 26340 5945 Prod. Rate 330 2325 1785 7.04 5.75
Cement Mill Classifier Drive 1296 701 114 211 0.35 0.68
MCC - 10 (Clinker Silo Ext.) 909 450 PPC RH 3.33 80 135
5.20
0.24 0.44
MCC - 11 (Fly Ash Aux. & Comp.) 0 257 PPC Prod. 1034 0 77 0.00 0.25
Compressors 1314 1303 Prod. Rate 311 116 391 0.35 1.26
MCC - 12 (Mill Grinding Aux.) 3841 963 339 289 1.03 0.93
CM Fan Recovery Power -2942 0 Total RH 14.66 -260 0 -0.79 0.00
Total 83635 26924 Total Prod. 4773 7382 8085 32.20 22.37 26.04
6 Packing Plant 24.00 4672.00 194.67 208
MCC - 13 (Silo Extraction & Comp.) 2343 98
1.33
0.50
Compressors 0 0 0.00
MCC - 14A (Packer - 1) 831 35 0.18
MCC - 14B (Packer - 2) 797 33 0.17
MCC - 14C (Packer - 3) 1026 43 0.22
Total 4997 1.33 1.07
Daily Power Consumption Report
8/29/2013
71
7 Plant Services: 24.00 5282 220.08 465
Plant Lighting 1469 61
2.50
0.28
Plant Aux. Power (Welding) 2140 89 0.41
RMBH AC Power 2082 87 0.39
CCR AC Power 4327 180 0.82
CMBH AC Power 1153 48 0.22
Total 11171 2.50 2.11
8 Distribution Losses 2452 24.00 5282 220.08 102 0.46
Gross Units Consumption 372143
Total for Pre - Clinker 243143 24.00 5282 10131 73.79 60.67
Total for Post - Clinker 115556 0.00 0 #DIV/0! 24.23
Daily Power Consumption Report
ENERGY CONSERVATION (IDLE POWER CONSUMPTION REPORT)
SECTION SECTION DESCRIPTION OPTIMUM
SATRT UP
TIME
ACTUAL
RUNNING
HOURS
XX.06.2013 ENERGY IN KWH
IDLE
RUNING
TIME
IDLE /SHUT
DOWN UNITS ACTUAL
U/Ton
WITHOUT
IDLE
RUNNING
U/Ton
Kwh
LS CRUSHER
APRON FEEDER 0.00 16.17
0.89 0.86
CRUSHER MAIN DRIVE 0.17 17.67 1.33 106.40 80.00
211BC2 0.50 17.92 0.00 0.00 145.00
211BC2A 0.50 17.92 1.25 181.25 145.00
MINES DEWATERING PUMP 66.00
IDLE/SHUT DOWN POWER 287.65
No of Start/ Stops 3.00
16.92 16.88
Raw Mill
WEIGH FEEDER 0.00 16.92
MAIN DRIVE 0.03 16.90 -0.05 0.00 150.00
FAN 0.30 16.90 -0.32 0.00 2600.00
LS RECLAIMER FEED GROUP 12.20 16.50 4.30 335.40 78.00
AD. RECLAIMER FEED GROUP 10.10 12.70 2.60 0.00 49.00
TOTAL DCS IDLE / SHUT DOWN POWER 335.40
No of Start/ Stops 0.00 Dcs Idle Power 331.00
19.44 19.06
Coal Mill
WEIGH FEEDER 0.00 14.33
MAIN DRIVE 0.03 14.40 0.04 2.00 50.00
FAN 0.17 14.70 0.13 32.50 250.00
COAL STACKER FEED GROUP 3.30 3.30 0.00 0.00 54.00
COAL RECLAIMER FEED GROUP 3.80 5.30 1.50 180.00 120.00
RAW MATERIAL HANDLING 1349.00
TOTAL DCS IDLE / SHUT DOWN POWER 214.50
No of Start/ Stops 4.00 Dcs Idle Power 75.00
Daily Idle Power Consumption Report
8/29/2013
72
KILN
KILN 24.00
18.50 18.50
COMPRESSOR 24.00 0.00 0.00 160.00
ALL DRIVES 0.00 -24.00 0.00
TOTAL DCS IDLE / SHUT DOWN POWER 0.00
No of Start/ Stops 0.00
CEMNT MILL
WEIGH FEEDER 0.00 14.66 1.24
MAIN DRIVE 0.08 14.90 0.00 0.00
23.16 23.14
250.00
FAN 1.00 15.90 -1.00 0.00 2449.00
CLASSIFIER 1.00 16.00 0.34 71.06 209.00
SILO FEEDG ROUP 1.00 15.30 -0.60 0.00 185.00
COMPRESSERS 1.00 16.60 0.30 52.80 176.00
BOOSTER FAN 1.00 2.00 0.00 0.00 45.00
IDLE /SHUT DOWN POWER 123.86
No of Start/ Stops 2.00 Dcs Idle Power 3348.00
PACKING PLANT
PACKER-1 12.64 0.00 0.00
1.07 1.00
621MD1 18.75 6.11 61.10 10.00
641FN1+641FN2 18.75 6.11 183.30 30.00
PACKER-2 10.27 0.00 0.00 6.00
622MD1 13.55 3.28 32.80 10.00
642FN1 13.55 3.28 65.60 20.00
PACKER3 12.06 0.00 0.00
BULK LOADING 1212.04 12.15 0.00 0.00
623MD1 TON 20.00 -4.21 0.00 10.00
643FN1+643FN2 20.00 -4.21 0.00 20.00
PACKING PLANT COMPRESSOR-CP1 0.00
-2.42 0.00
38.00
PACKING PLANT COMPRESSOR-CP2 20.90
PACKING PLANT COMPRESSOR-CP3 21.40
PACKING PLANT COMPRESSOR-CP4 2.40
CEMENT MILL COMPRESSOR 0.00 0.00 0.00
IDLE/SHUT DOWN POWER 342.80
UTILITIES UTILITIES 11171.00
TOTAL UNITS
FLY ASH 331.52 U/T 3.17
Daily Idle Power Consumption Report
Compressor R Hours Units Consumption Avg. KW % Loading
441CP1 0.00 0.00 #DIV/0! #DIV/0!
441CP2 0.00 0.00 #DIV/0! #DIV/0!
441CP3 24.00 4171.00 173.79 98.47
441CP4 0.00 0.00 #DIV/0! #DIV/0!
421CP1 0.00 0.00 #DIV/0! #DIV/0!
421CP1 A 0.00 0.00 #DIV/0! #DIV/0!
K21CP1 0.00 0.00 #DIV/0! #DIV/0!
K21CP2 16.60 1733.00 104.40 59.15
K21CP3 0.00 0.00 #DIV/0! #DIV/0!
K21CP4 9.30 1050.00 112.90 63.97
K21CP5 0.00 0.00 #DIV/0! #DIV/0!
K21CP6 0.00 0.00 #DIV/0! #DIV/0!
621CP1 0.00 0.00 #DIV/0! #DIV/0!
621CP2 20.90 249.00 11.91 6.75
621CP3 21.40 708.00 33.08 18.74
621CP4 2.40 81.00 33.75 19.12
Units Run Hours Avg. KW
Comp. Energy Consumed for Pyro 4171.00 24.00 173.79
Comp. Energy Consumed for Cement Mill 1733.00 16.60 104.40
Comp. Energy Consumed for Fly Ash 1050.00 9.30 112.90
Comp. Energy Consumed for Packing Plant 1038.00 44.70 23.22
Total Compressed Air Energy Consumption 7992.00 24.00 333.00
Daily Idle Power Consumption Report
8/29/2013
73
Power units / MT of Material
Description XX-XX-13 XX-XX-13 XX-XX-13 XX-XX-13 XX-XX-13 XX-XX-13 XX-XX-13 XX-XX-13 Month Total Pvs mnth May
L S Crusher 0.97 1.07 0.88 0.89 0.87 0.91 0.93 0.84 0.94 0.95
Raw Mill 17.21 17.04 16.11 17.09 16.19 16.88 16.66 17.03 17.37 16.43
Coal Mill 20.07 22.29 20.51 21.60 19.05 20.80 18.89 19.78 20.84 19.89
Coal Crusher 1.83 2.11 2.14 1.67 2.13 2.09 1.93 2.01 3.37 2.89
Kiln & Cooler 19.00 18.98 18.20 18.52 18.51 18.40 18.82 18.77 20.35 18.48
Power units / MT of Clinker
Description 6-17-13 6-18-13 6-19-13 6-20-13 6-21-13 6-22-13 6-23-13 6-24-13 Month Total Pvs mnth May
L S Crusher 1.36 1.50 1.24 1.25 1.22 1.28 1.30 1.18 1.32 1.33
Raw Mill 26.16 25.91 24.49 25.98 24.61 25.66 25.32 25.89 26.41 24.98
Coal Mill & Crusher 2.41 2.66 2.60 2.58 2.37 2.48 2.30 2.50 2.69 2.68
Kiln & Cooler 19.00 18.98 18.20 18.52 18.51 18.40 18.82 18.77 20.35 18.48
Utilities & Others 2.16 2.17 2.28 2.09 2.24 2.29 2.17 2.13 3.23 3.10
Power Upto Clinkerization 51.09 51.21 48.82 50.42 48.96 50.11 49.90 50.47 54.01 50.57
Cement Mill 26.11 23.84 24.16 24.74 27.37 25.40 26.37 25.53 25.50 25.23
OPC 27.07 23.73 24.66 24.67 28.28 24.92 26.13 21.86 25.37 24.72
PPC 23.65 0.00 23.27 0.00 26.78 26.36 0.00 26.12 26.05 26.79
Packing Plant 1.15 1.21 1.07 1.17 1.12 1.15 1.24 1.20 1.17 1.27
Cement - Overall
OPC 77.51 74.53 72.93 74.70 76.66 74.54 75.60 71.75 78.59 74.65
PPC 61.88 0.00 59.52 0.00 63.31 63.70 0.00 63.63 66.17 64.14
Overall 73.12 74.63 68.15 74.77 68.59 70.92 75.84 64.76 76.13 72.09
Monthly Energy Monitoring Report
Plant DCS Report Formats Idle Run Report Section Specific Energy Consumption Data
Online Specific Energy Consumption
Online Electrical SEC
Online Thermal SEC
8/29/2013
74
Type of Renewable
Energy Source
Installed Capacity
in KW
Savings (Last 3 Years)
Energy Generated
(Lakhs Unit)
Cost Saving (Rs. Lakhs)
* Wind Power 16525 884 4420
Portable Wind Power
1.5 0.03 0.15
Solar Power 2 0.044 0.22
Solar Water Heater
36 0.15 0.75
Note: * Wind Power Generation from the Dalmia Group (Dalmia Bharat Power)
Solar power Pack
Solar Water Heater
Wind Power Generator
Solar Street Lights
8/29/2013
75
Wind Power Generator
Slogans
Reminders
8/29/2013
76
Pet Coke Using 100% Petcoke for Clinkerization
Red Mud Waste From Alumina Industry as the Additive for Raw Mix, Which boost up utilization of Pet coke 100%
Chemical Gypsum
Chemical Gypsum for Additive for Cement Grinding ( 2%)
Alternate Fuels
2 % of Alternative Fuel for Clinkerization. By using the Hazardous Waste of Pharmaceutical Industry
Flyash Utilization of Flyash 32% for Cement Grinding
STP Water Utilizing the STP Water for the Cement Mill Water Spray
8/29/2013
77
Sewage Water
Installation of Sewage Water Treatment Plant at Jammalamadugu (Near by Town) and Pumping the Treated water for Process Feasibility Study Completed. Under Engineering Stage
Municipal Waste
Collection of Municipal Waste and use as alternative fuel in Pyro Under Process with Pollution Control Board
Other Industry
Waste
Identification of Waste (Agro Waste and Other Waste Generating from Industries). Identified Waste & Pollution Control Board Obtained
Vendor : Sri Sai Devine Mining Pvt. Ltd.
Service: Supply of Lime Stone from Mines to Crusher
Prior to Encon: Specific Fuel Consumption : 0.42/T of Lime Stone
After Encon: Specific Fuel Consumption : 0.40/T of Lime Stone
Improvement: 4.7% of Fuel Consumption Reduced.
Encon Efforts : Reduced the Hauling distance by making straight haul road Controlled the Idle time of Loading Machine and Dumper
8/29/2013
78
Vendor : RR Transport & Sri Subramaniswar Transport
Service: Logistics Services for Cement Dispatch by Road
Prior to Encon: Specific Fuel Consumption : 0.33 Ltr./KM
After Encon : Specific Fuel Consumption : 0.29 Ltr./KM
Improvement: 14% of Fuel Consumption Reduced.
Encon Efforts : Training to all Drivers on Defensive Driving Educating Drivers on Clutch / Brake Usage, Ramp up,
Ramp down & Free Running Speed Utilization of Vehicle arriving with Red Mud for
dispatching the Cements
Vendor : Meen Bahadhur Thakur
Service: Maintenance of Guest House
Prior to Encon: Consumption of LPG Cylinders 25 Nos. / Month
After Encon : Consumption of LPG Cylinders 20 Nos. / Month
Improvement: 20% of LPG Consumption Reduced / Month.
Encon Efforts : Educated for avoiding the Idling of Gas Stove Educated on Preheating by Keeping the Vessels on the Vessels Usage of Pressure Cooker
8/29/2013
79
Distribution of Solar Lamps to the Surrounding Communities
8/29/2013
80
Won the following Mines Zonal Safety Competitions 2012
Drilling & Blasting 1st Prize
Overall Performance 1st Prize
Mines Lighting & Electrical 1st Prize
Hazard Identification & Risk Assessment 1st Prize
Mine Working 2nd Prize.
Photographs of Mines Award Ceremony – Year 2012
8/29/2013
81
CII’s 5S Excellence Award - 2012
CII’s EHS Award - 2012
8/29/2013
82
Group Award
Safety, Environment & Housekeeping Award
Go Green Award
360° Value Feedback Award
CSR Award
Group Award
8/29/2013
83
Save Energy - Save Money - Save the Planet.