Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
[1]
EN
THIS ACTION IS FUNDED BY THE EUROPEAN UNION
ANNEX
of the Commission Implementing Decision on the financing of the Annual Action Programme
in favour of Viet Nam for 2020
Action Document for the EU-Viet Nam Sustainable Energy Transition Programme
ANNUAL PROGRAMME
This document constitutes the annual work programme in the sense of Article 110(2) of the
Financial Regulation and action programme/measure in the sense of Articles 2 and 3 of
Regulation N° 236/2014.
1. Title/basic act/
CRIS number
EU-Viet Nam Sustainable Energy Transition Programme
CRIS number: ACA/2020/040-898
financed under the Development Cooperation Instrument
2. Zone benefiting
from the
action/location
Viet Nam
The action shall be carried out at the following location: Viet Nam.
The project team will be based in Hanoi.
3. Programming
document Addendum N°1 to Multiannual Indicative Programme for Viet Nam
2014-2020- C(2018)4741
4. SDGs Main SDGs on the basis of section 4.4: 7 & 13
5. Sector of
intervention/
thematic area
Sustainable Energy DEV. Assistance: YES
6. Amounts
concerned Total estimated cost: EUR 142 053 752
Total amount of EU budget contribution: EUR 142 000 000, of which
EUR 121 000 000 for budget support and
EUR 21 000 000 for complementary support.
This action is co-financed in joint co-financing by GGGI for an amount
of EUR 53 752
7. Aid
modality(ies)
and
implementation
modality(ies)
Budget Support
Direct management through:
- Budget Support: Sector Reform Performance Contract
- Grants
- Procurement
Indirect management with:
[2]
- United Nations Industrial Development Organization (UNIDO)
- Global Green Growth Institute (GGGI)
8 a) DAC code(s) 23183 - Energy conservation and demand-side efficiency (50%)
23210 - Energy generation, renewable sources – multiple technologies
(40%)
23110 - Energy policy and administrative management (10%)
b) Main Delivery
Channel
12000 - Recipient government
9. Markers
(from CRIS DAC
form)
General policy objective Not
targeted
Significant
objective
Principal
objective
Participation development/good
governance ☐ ☐
Aid to environment ☐ ☐
Gender equality and Women’s and
Girls' Empowerment
☐ ☐
Trade Development ☐ ☐
Reproductive, Maternal, New born
and child health
☐ ☐
RIO Convention markers Not
targeted
Significant
objective
Principal
objective
Biological diversity ☐ ☐
Combat desertification ☐ ☐
Climate change mitigation ☐ ☐
Climate change adaptation ☐ ☐
10. Global Public
Goods and
Challenges (GPGC)
thematic flagships
Switch to Green
Global Climate Change Alliance +
SUMMARY
In order to sustain its ambitious socio-economic development pathway, Viet Nam needs to
further develop its provision of reliable and sustainable energy services. In light of Viet Nam's
climate change commitments, the need for mainstreaming environmental protection and
concerns about energy security, the Government of Viet Nam aims to accelerate its energy
transition towards a higher share of clean and renewable energy, while at the same time
improving energy performance and reducing energy losses.
Building on the ongoing Energy Sector Policy Support Programme to enhance Access to
Sustainable Energy in Rural Areas of Viet Nam, which started in 2017, this action aims at
contributing to a sustainable energy transition in Viet Nam. Its specific objectives are:
1. Improved energy efficiency;
2. Larger share of renewable energy in the energy mix; and
3. Improved performance of the Viet Nam Energy Information System.
[3]
The action will specifically support the implementation of the third phase of the "Viet Nam
National Energy Efficiency Programme” (VNEEP3) and the "Renewable Energy
Development Strategy" (REDS).
The action falls within the Sustainable Energy focal sector of the EU-Viet Nam Multiannual
Indicative Programme 2014-2020 (MIP). The action is fully in line with the MIP's specific
objectives 1.1 "The production and consumption of energy in Viet Nam is more efficient" and
1.2 "The clean and renewable energy share of the total energy produced in Viet Nam is
increased".
The action will be implemented mainly through a Sector Reform Performance Contract.
Complementary support measures will be provided to enhance institutional capacities and the
legal and technical framework, support the development of the private sector and increase
overall awareness on the benefits of energy efficiency and renewable energy solutions.
1 CONTEXT ANALYSIS
Context Description 1.1
Viet Nam continues to experience high economic growth compared to regional and global
economies. Average gross domestic product (GDP) growth rate reached approximately 7.0 %
during 2001-2010, dropped to around 5.8 % during 2011-2015 and gradually recovered to
6.8 % from 2016 to present. This economic growth, in combination with urbanisation and
rapid population growth, has boosted demand for energy in general and electricity in
particular. In 2015, total primary energy (PE) supply in Viet Nam was 70,588 kiloton of Oil
Equivalent (KTOE). According to forecasts in the current National Power Development Plan
(Revised PDP 7), Viet Nam's power demand will increase on average by 8.7 % annually in
the next 15 years (2016-2030). Accordingly, domestic power supply capacity would need to
increase threefold, from 38,358 MW in 2015 to 60,000 MW in 2020 and 129,500 MW in
2030. Hence, in the next 15 years, power demand would increase 1.5-fold every 5-year cycle.
This growth rate is considered high compared to the region and the rest of the world.
Viet Nam has substantial hard coal reserves as well as oil and gas. However, the demand in
industry and for power generation is so high that the country became a net importer of coal
since 2015. Oil and gas reserves are also substantial and mainly located offshore. Exploration
is ongoing and is expected to increase proven reserves further, although exploration may be
technically and economically challenging. Viet Nam is a net exporter of crude oil, but a net
importer of refined oil and is currently planning the extension of national refining capacity.
All of the country’s gas production is consumed nationally, although the import of LNG is
planned with two import terminals scheduled to be completed by 2023. This trend increases
Viet Nam's exposure to energy market volatility and therefore impacts its energy security.
The Government of Viet Nam is well aware that it needs to balance the need for increasing
energy supply for socio-economic growth with ensuring energy security and environmental
protection. This implies working simultaneously on two strategic dimensions: (i) Enhancing
energy efficiency and improving energy performance to reduce energy losses; and
(ii) Shifting the energy mix towards reducing fossil fuel, promoting efficient exploitation and
increasing the portion of renewable energy in energy production and consumption, and
reducing greenhouse gas emissions from the energy sector.
Policy Framework (Global, EU) 1.2
The action falls within the Sustainable Energy focal sector of the EU-Viet Nam Multiannual
Indicative Programme 2014-2020 (MIP). The action is fully in line with the MIP's specific
[4]
objectives 1.1 (The production and consumption of energy in Viet Nam is more efficient) and
1.2 (The clean and renewable energy share of the total energy produced in Viet Nam is
increased). Moreover, by supporting the establishment of the Viet Nam Energy Information
System (VEIS), the action also contributes to the achievement of the MIP's specific objective
2.2 (The government’s ability for accountable, transparent and cost-effective service delivery
is enhanced).
The action will support directly the achievement of SDG 7 (Ensure access to affordable,
reliable, sustainable and modern energy for all) and will contribute significantly to SDG 13
(Take urgent action to combat climate change and its impacts).
The action is in line with the EU's 2030 climate and energy framework, and the European
Consensus on Development, in particular with its "Planet" dimension on protecting the
environment, managing natural resources and tackling climate change.
Public Policy Analysis of the partner country/region 1.3
Viet Nam’s Socio-Economic Development Strategy (SEDS) 2011-2020 lays the foundation
for Viet Nam to become a modern, industrialized society, well integrated into the international
economy and defines three breakthrough areas: (i) promoting human resources development,
(ii) improving market institutions, and (iii) infrastructure development. A new SEDS
2021-2030 and a new Socio-Economic Development Plan (SEDP) 2021-2025 are under
preparation.
Energy policy is a key element of the Government's development policy. In particular, it is
viewed as a way to promote poverty reduction, social equality and economic development.
Overall energy policy in Viet Nam is guided by the National Energy Development Strategy to
2020, vision to 2050 (NEDS)1, adopted in 2007. An evaluation of the NEDS is on-going and a
new NEDS to 2030, vision to 2050, is expected to be adopted early 2020. The policy focus
over the last 5 years has been on the Electricity Law, adopted in 2004 and amended in 20122,
and on the seventh National Master Plan for Power Development for 2011-2020, vision to
2030 (PDP7) adopted in July 20113 and revised in March 2016
4. This reflects the priority to
increase electricity supply.
In the landmark United Nations Framework Convention on Climate Change (UNFCCC) Paris
Agreement in 2015, Viet Nam committed to 8% GHG emissions reduction by 2030 compared
to the business as usual (BAU) scenario in its Nationally Determined Contributions (NDC)5.
However, with international support GHG reduction could increase up to 25 %. The
Government is currently reviewing its NDC.
(i) Energy efficiency
In Viet Nam, commercial energy intensity, as a measure of the energy efficiency of an
economy calculated as units of energy per unit of GDP, is comparatively high at 270 kilogram
of oil equivalent (kgOE)/USD 1,000 in 2015. This is significantly higher than the global
average commercial energy intensity. Viet Nam is among the most energy intensive countries
in South East Asia.
1 Decision 1855/QĐ-TTg (2007) 2 Decision 28/2004/QH & 24/2012/QH13 3 Decision 1208/QĐ-TTg (July 2011) 4 Decision 428/QĐ-TTg (March 2016) 5 https://www4.unfccc.int/sites/ndcstaging/PublishedDocuments/Viet%20Nam%20First/VIETNAM%27S%20INDC.pdf
[5]
Viet Nam committed to reduce energy intensity by reducing its energy consumption per unit
of GDP by 1-1.5 % (Resolution at the 12th
National Congress of the Communist Party).
Energy efficiency is also one of the key measures to reduce Viet Nam’s greenhouse gas
(GHG) emissions and improve its energy security. It also has social, environmental and
economic benefits including stable energy supply, job creation, improved well-being,
mitigated environmental pollution and reduced production cost towards sustainable and
low-carbon development. Over the past 10 years, Viet Nam has managed to save 3.4% of total
energy consumption (energy efficiency rate) during the period 2006-2010 and 5.65%
equivalent to 11,261 million tonne of oil equivalent (TOE) during the period 2011-2015.
These rather modest results were achieved through the implementation of the “Viet Nam
National Energy Efficiency Programme” (VNEEP) phase I (2006-2010) and phase II (2011-
2015). Viet Nam still has a lot of opportunities to minimize energy losses and waste in the
supply and utilization processes across all sectors, from industrial production, commerce and
service to household consumption and transport. Well aware of this substantial room for
further energy savings, a new National Energy Efficiency Programme, the so-called VNEEP3,
has been approved by the Prime Minister on 13 March 20196. The overall objectives of this
programme are i) To mobilize all the national and international resources for stimulating
economical and efficient use of energy through the synchronous implementation of
assignments and solutions of State management, technical assistance, science and technology
research and product development, market transition, human resource training and
development, and also utilization of support from the international community in the field of
economical and efficient use of energy; and ii) to formulate the habit of using energy
economically and effectively in all social activities; to reduce intensive use of energy in a
variety of economic sectors and industries; energy efficiency becomes a regular activity in
key energy users and key economic sectors that consume a lot of energy, with an aim at green
growth and sustainable development. This new programme is expected to set the efficiency
rate at 8-10 % of total national commercial energy consumption for 2019-2030 in the business
as usual (BAU) scenario.
(ii) Shifting the energy mix
To cope with the increasing electricity demand, new generation capacities need to be
deployed at a rapid pace. The revised PDP77 plans that 116 new power plants would be put
into operation in the period 2016-2030, of which 43 hydro, 57 thermal, 11 renewable energy8,
3 pumped storage hydro and 2 nuclear. However, various projects are incurring delays,
particularly those developed under a build–operate–transfer (BOT) scheme. The reasons put
forward are the lengthy procedures and negotiations in which the biggest challenge is
settlement on currency exchange rates. If large BOT plants are delayed, they will affect the
capability to ensure sufficient electricity supply to the power system. Other challenges and
difficulties identified by the Ministry of Industry and Trade (MOIT) are: i) lack of
harmonisation in the legal & regulatory framework; ii) new OECD regulation requiring only
ultra-supercritical technology for coal-fired thermal projects investments; iii) low electricity
tariffs; iv) primary fuel resources security; and v) increased public awareness on pollution
generated by coal-fired power plants.
The focus of the revised PDP7 on increasing the contribution of coal to power development
from 33 % of power generation capacity in 2015 to 43 % by 2030 (more than twice the 2020
6 Decision 280/QĐ-TTg (March 2019) 7 http://www.erav.vn/userfile/files/428_2016.pdf 8 Expected total installed capacity by 2030: wind 6,000 MW, solar 12,000MW, small hydro 27,800 MW.
[6]
GHG emissions level), represents a challenge for Viet Nam to comply with their international
climate change commitments.
In November 2016, the National Assembly adopted a resolution on abandoning the
construction of the Ninh Thuan nuclear power plant due to economic reasons. Nuclear power
was expected to provide 3.3% of the electricity production in 2030.
Hydropower is still the most important primary energy source for electricity production with
an installed capacity of 15.9 GW which represents 37.6 % of the total installed capacity as of
December 2016. However, hydropower potential is almost fully exploited at present.
Furthermore, recent droughts and decreasing water flows have impacted hydropower
generation output reliability. Apart from large-scale hydropower (above 30 MW), which in
Viet Nam is not counted as renewable energy (RE) source because of the substantial amount
of greenhouse gases released by the reservoirs, renewable energy - including small-scale
hydropower - represented only a minor part of the electricity production (3.7%).
In terms of non-hydro RE development, Viet Nam has enacted various legal documents
aiming at achieving the objectives set out in the Renewable Energy Development Strategy
until 2030, vision to 2050 (REDS)9, which was adopted in 2015 as a basis for delivering on
Viet Nam's commitments at COP 21 in the area of renewable energy. A support mechanism
was approved in April 2017 for the development of solar power projects (feed-in tariff, FIT)
and subsequently a circular was issued regulating solar power project development and
standardized power purchase agreements (PPA) for solar power projects. In September 2018
an increased FIT for wind power was approved.
These new support mechanisms have generated a very strong interest from the private sector
to invest in RE. Despite some remaining investment risks related to standard PPA provisions,
at the end of June 2019, there was a total installed RE capacity of 4,500 MW of solar power,
300 MW of wind power, 350 MW of biomass power and 10 MW of waste-to-energy.
However, new challenges arose such as the need for more robust power planning
mechanisms, improving the grid absorption capacity of variable RE or taking into
consideration externalities. The recent decision to develop in 2019–2020 a new Power
Development Plan (PDP8) which should enter into force in 2021 is significant. It is expected
that PDP8 will adjust the electricity mix by increasing the share of RE and decreasing the
share of coal power. It should also improve and revise the power planning mechanisms.
(iii) Energy data and statistics
Looking at the current status of energy data and statistics, Vietnamese agencies and
institutions are already collecting a fair amount of data and have developed strong technical
expertise. However, there are several shortcomings of the data & statistics framework that
need to be addressed with concrete action in order to meet the key objective of improving the
quality of data and statistics in the energy sector:
- Fragmented legal framework and lack of integrated strategy for energy statistics;
- Absence of a systematic data collection system based on dedicated questionnaires and
procedures;
- Lack of clarity on data sources and methodology;
- Ownership of data still perceived as a source of power;
- Dissemination of energy statistics is not systematic or regular;
- Lack of a comprehensive data quality assurance framework;
9 Decision 2068/QĐ-TTg (November 2015)
[7]
- No “official” international reporting;
- No IT system or database to support and facilitate data collection, processing and
dissemination.
With EU support provided since 2016 through the EU Technical Assistance Facility for the
'Sustainable Energy for All' Initiative (TAF) and the EU-Viet Nam Energy Facility (EVEF),
MOIT is now committed to establish the Viet Nam Energy Information System (VEIS) and
has promulgated on 14 December 2018 an action plan to establish the VEIS by 202410
. In
order to put in motion the VEIS the first two priorities are: i) improving the existing legal
framework; and ii) establishing an institutional framework.
Stakeholder analysis 1.4
Within Government, energy is under the overall responsibility of MOIT. Three main
departments are in charge of energy:
- Electricity and Renewable Energy Agency (EREA);
- Department of Energy Efficiency and Sustainable Development (DEESD); and
- Oil, Gas and Coal Department.
Beside these 3 departments, the Electricity Regulatory Authority of Viet Nam (ERAV), which
falls also under MOIT, acts as the regulator and plays a key role in market-oriented sector
reform, including electricity pricing, monitoring supply and demand balance to ensure secure
and quality power supply, licensing & dispute settlement.
Despite the absence of an overarching management structure, coordination within the sector is
ensured by EREA. Moreover, the close involvement of the Vice Minister of MOIT in charge
of energy contributes to an effective coordination of activities. The establishment of DEESD
at the end of 2017 is a positive development which marks a clear shift in the involvement of
MOIT in important horizontal topics such as the implementation of the NDCs or the National
Green Growth Strategy.
Other key players are the Ministry of Natural Resources and Environment (MONRE), which
leads the Climate Change Action Plan, and the Ministry of Planning and Investment (MPI),
which leads the Green Growth Action Plan, and have therefore a stake in national energy
policy.
The Ministries of Transport, Construction, Agriculture and Rural Development, Science and
Technology, Training and Education, Finance, and Planning and Investment are key
stakeholders of the VNEEP3. In order to ensure proper coordination of the VNEEP3 it is
expected that its steering committee will be chaired by the deputy prime minister in charge of
industry and trade.
Electricity of Viet Nam (EVN), a state-owned enterprise (SOE), and its various operational
subsidiaries play a key role in the implementation of the REDS as, for the time being, sole
buyer of RE generated. It will also have a key role in the implementation of the VNEEP3.
Local and international civil society organisations (CSOs) active in the energy sector
coordinate their activities under the umbrella of the Viet Nam Sustainable Energy Alliance,
established in 2012.
10 Decision 4651/QD-BCT (Dec. 2018)
[8]
The private sector has become extremely active in the development of RE projects. With the
forthcoming implementation of VNEEP3, we can anticipate that the current limited
involvement of the private sector in the energy efficiency business will pick up.
Several development partners, including the EU and some Member States, support the
development of the energy sector in Viet Nam (see section 3.2 below)
Problem analysis/priority areas for support 1.5
Viet Nam is facing a serious risk of power shortage over the period 2020-2025. One of the
main reasons is the delay in the implementation of 16 BOT coal-fired power plant projects.
This risk has been well identified by the Government, which is now seeking for solutions. In
order to compensate for the lack of additional power supply capacity, the promotion of RE
technologies has been significantly improved since 2016. At the same time, the Government
also aims at decreasing the demand for electricity in order to mitigate the need for additional
generation capacity and to reduce the overall energy intensity of the country.
The action aims at supporting Viet Nam to achieve the objectives set in its REDS and
VNEEP3 and will pursue the ongoing EU support to establish the VEIS by 2024.
Other areas of assessment 1.6
1.6.1 Fundamental values
On democracy and human rights, the main risks in Viet Nam are use of death penalty,
challenges with rule of law and restrictions on space for CSOs. The risks are well identified in
the EU's existing budget support programmes and mitigating measures have been established.
Viet Nam is an authoritarian one-party state ruled by the Communist Party of Viet Nam
(CPV). Opposition parties remain illegal and individuals who challenge the legitimacy of the
CPV’s rule or criticise the government are reportedly harassed and arrested. In theory, the
National Assembly, elected by popular vote every five years, has most of the powers and
characteristics of a western-style parliament. However, its role remains strictly delimited by
the political and institutional organisation of the country which vests supreme power in the
CPV.
There is little to no pluralism allowed in CSO and media landscapes in Viet Nam.
Independent media and CSOs are somewhat tolerated and move in a grey area bordering
illegality. CPV maintains a firm grip on power through a combination of stringent legislation,
influence over the military and internal security, tight control of state-run media and internet,
and arrest and imprisonment of political activists and bloggers. Media (print, TV, radio) are
state-owned.
The CPV expects peoples' voices to be heard through the "mass organisations" (farmers'
union, women's union, youth union, etc.). The legal framework for NGOs/associations is
cumbersome and controlled. Whilst overall, there has been increased participation of CSOs
into development cooperation, this excludes political issues and is declining since 2016. There
is an internet blogger community, which exposes cases of corruption and criticises the regime
and has faced severe backlash under national security provisions of the Penal Code.
In light of the above situation, the EU pays close attention to fundamental values in its
relations with Viet Nam at all levels. The implementation arrangements under the Partnership
and Cooperation Agreement, EU-Viet Nam Free Trade Agreement and our cooperation
programmes share the objective of engaging with the Government and CSOs in Viet Nam in
human rights issues. An annual human rights dialogue takes place between the EU and Viet
Nam. Whilst, on balance, the overall situation on fundamental values in Viet Nam has
[9]
remained stable or even improved, over the longer term there are negative trends in some
areas, which will require continuous monitoring and due adaptation of mitigating measures as
the situation evolves.
1.6.2 Macroeconomic policy
Overall, Viet Nam pursues a macroeconomic policy based on stability and sustained levels of
growth. GDP growth has been consistently strong over the medium term, leading Viet Nam to
be increasingly in the spotlight as an example of a well performing country. Growth is
currently underpinned by buoyant domestic demand, increased exports and investment as well
as growing tourism. Export-oriented manufacturing in electronics, telecommunication
products and textiles continued to be key engines of industrial growth.
Viet Nam has an outward-looking economy and its macroeconomic strategy is based on
increase of external trade. The foreign-invested sector accounts for about 18 % of Viet Nam’s
GDP, nearly a quarter of total investment, two thirds of total exports, 18.5 % of total budget
revenue and millions of direct and indirect jobs. It is also a consistent and strong driver of
GDP growth.
The balance of payments remains in surplus, underpinned by a trade surplus, resilient
remittances and large inflows of foreign direct investment (FDI). Viet Nam’s economic
agenda continues to focus on public debt sustainability and building financial reserves while
addressing widespread investment needs and strengthening the banking sector. It has stepped
up market-oriented reforms to reduce the economic role of the state through the continued
equitisation and divestment of SOEs.
Growth is projected to stabilize around 6.5 %, led by export expansion, rising domestic
consumption and strong investment fuelled by FDI and strengthening agriculture. Robust
private consumption is supported by rising incomes and stable inflation. Business sentiment
remains buoyant and the doing business environment is seen as improving.
External balances are projected to benefit from robust exports and FDI inflows. On the fiscal
front, the Government has set a deficit target for 2018 equal to 3.7 % of GDP seeking to
encourage capital investment to support growth while consolidating finances to sustain
macroeconomic stability. In view of these risks, the Government is making efforts to enhance
macroeconomic resilience, including its efforts to build-up foreign reserves, strengthen public
debt management and its recent initiatives to equitise state-owned enterprises.
Risks to the outlook are mostly on the downside. If escalating trade tensions around the world
slow global trade substantially and disrupt global production networks and supply chains, the
growth outlook for Viet Nam will be much dimmer. Not only would such developments hurt
its export prospects, they would also hold back FDI. Heightened volatility in international
financial markets is another downside risk.
1.6.3 Public Financial Management (PFM)
The Financial Development Strategy (FDS) 2010-2020 is the key document guiding the
reform process, which was further elaborated in development strategies of PFM sub-
components. These documents are further broken down into medium-term action plans
(MTAP) and annual work plans, prepared by MOF, with a medium-term perspective on the
solutions and actions to achieve the objectives of the FDS. The reform process is broadly
credible, though delays in some areas have affected overall progress.
The priorities for further reforms of the PFM system during the period 2017-2019 are:
[10]
- Enhancing the effectiveness in domestic resource mobilisation: Government aims to
expand the tax base and restructure tax revenue towards increasing the proportion of
domestic resources to 84-85 % of total state budget revenue by 2020. The target for state
budget revenue is set at the minimum of 23.5 % of GDP for the period 2016-2020.
- Enhancing allocative efficiency in parallel with financial and state budget restructuring.
- Further strengthening the management of public debt: limit the issuance of new
government guaranteed loans, and restructure the loan portfolio toward more
sustainability in terms of sources, currencies and terms. Keep the public debt within the
limit of 65 % of GDP, government debt at a maximum of 54 % GDP and sovereign loans
at a maximum of 50 % of GDP.
- Reforming financial management of public service delivery units: gradually reduce the
financial dependence of public service delivery units on the state budget so that they can
operate as financially independent by 2020.
- Continued tax and customs administrative reforms in order to further improve the doing
business environment.
A long period of economic growth has helped Viet Nam to raise state budget revenue. Whilst
revenue collection during 2011-2015 increased in real terms, it declined as percentage of
GDP, with an average of 23.4 % of GDP during 2011-2015 comparing to 26.4 % during
2006-2010. The reduction in oil and tariff revenues was the main reason for this downward
trend.
Recognising the situation, government has taken measures to reform tax policies toward
higher level of mobilisation and stronger reliance on domestic revenue. Accordingly, the
collection during 2016-2017 increased slightly to 24.6 % of GDP. The share of domestic
revenue in total state revenue increased from 68 % during 2011-2015 to 81 % during
2016-2017.
Government is proposing a number of policy options in order to further increase domestic
mobilisation, including: Broadening the VAT base and unifying the VAT rate; broadening
corporate income tax base; reducing tax rate applied for SMEs; increase excise rates (sin-tax)
on several goods; expanding the personal income tax base; building property tax system; and
increasing environment tax on oil and gas. Government is still in the course of conducting
public consultation on the tax policies changes, nevertheless some of the proposed changes
have faced strong reaction from public and business associations.
The legal framework for State Audit is reasonably well defined. Whilst audit coverage has
been improving over the past few years, State Audit of Viet Nam (SAV) only has the
resources to cover around 60 % of central government units and 50 % of provinces. State
Budget accounts are audited on an annual basis. The audit report is submitted to the National
Assembly and there are mechanisms to follow-up on implementation of audit
recommendations.
1.6.4 Transparency and oversight of the budget
The disclosure of budget information is regulated in the State Budget Law (SBL). The SBL
2002 provided for disclosure of some key budget documents. Nevertheless, the guidance at
sub-law levels was limited. The new SBL 2015 has strengthened the disclosure requirements
and there is a new circular providing detailed guidance on disclosure of budget documents.
Aside from SBL, other laws such as the Law on management of public debt and public
procurement law also have disclosure requirements. This is expected to be reflected in the
next Open Budget Index (OBI) assessments.
[11]
Budget transparency and oversight is an area that needs to be further promoted by the
Government. Since the new SBL came into force, results have been positive as the majority of
key budget documents were published with higher level of quality and comprehensiveness
comparing to previous documents. The website of the Ministry of Finance (MOF) has been
improved with a separate section dedicated to the disclosure of budget documents which are
accessible to the general public. Nevertheless, the analytical information on investment
expenditure and public debt still remain limited and is expected to be improved in medium-
term only, when budget classification for recurrent and investment expenditure are aligned
and the new public debt management law takes stronger effect.
One positive development is the increasing engagement of the government, particularly in
conducting OBI assessment and development of a citizen's budget.
2 RISKS AND ASSUMPTIONS
Risks Risk level
(H/M/L)
Mitigating measures
Persistent low electricity prices
undermine return on investment in
energy efficiency and affect
competitiveness of non-hydro
renewables
H Policy dialogue in the context of the
VEPG will pursue support for the
ongoing energy sector reform and the
implementation of wholesale electricity
market and a more cost reflective
electricity tariff policy.
Cumbersome administrative
procedures and approval process of
the Government which often delay
the achievement of the objectives
M Policy dialogue at sector level in the
context of the VEPG keeps the
momentum
Limited capacities of the
Government to manage and steer
the VNEEP3 which targets various
sectors at central and provincial
level
M Technical Assistance (TA) provided in
the context of the ongoing EU-VN
Energy Sector Policy Support
Programme and this action will enhance
DEESD's capacities to supervise the
implementation of the VNEEP3
Lack of a long-term reliable energy
outlook strategy might limit the
capacity of the Government to
develop a sustainable energy
transition
L Danish support to the Viet Nam Energy
Outlook report (latest report was
published in October 2019).
Current TA support and policy dialogue
under the framework of VEPG provides
assistance in the development of the new
Energy Development Strategy and the
upcoming PDP8
On democracy and human rights,
the main risks are use of death
penalty, rule of law and
authoritarian nature of state
apparatus impeding on space for
civil society.
H Policy dialogue in the new framework of
PCA Joint Committee and human rights
dialogue better informs the EU's analysis
of the situation and allows EU to raise
human rights issues in an appropriate
forum.
EIDHR and CSO projects, along with
implementation of the EU roadmap on
CSO engagement
[12]
On the macroeconomic side, the
main risks are increased levels of
public debt, slow-down in growth
due to instable international
environment on trade and
overreliance on key economic
sectors.
L Policy dialogue linked to budget support
operations is expected to continue, as is
dialogue on the non-cooperative tax
regimes process. The EU Delegation also
organises joint dialogue sessions with
IMF, World Bank, ADB, UN and EU
Member States on macroeconomic issues
On PFM and transparency, the
principal risks are a slow-down in
the pace of PFM reforms, lack of
capacity in external audit and
challenges with transparency and
access to information.
M Policy dialogue on PFM and linked to
budget support programmes, support to
the State Audit Office of Viet Nam via
an ongoing project, the pipeline
Enhancing Economic Governance action
and EU following up with other
development partners on Open Budget
Index and other transparency initiatives
Assumptions
The objectives set in the REDS and the VNEEP3 are pursued by the Government
MOIT remains committed and continues to lead the VEPG
Government pursues its PFM reform
3 LESSONS LEARNT AND COMPLEMENTARITY
Lessons learnt 3.1
Very often, the ambitious objectives set out in the policy documents underestimate the
complexity and the comprehensiveness (e.g. considerations for externalities, maintenance and
operational costs). The absence of concrete implementation plans and adequate financial
resources lead to delays and frequent adjustments. Over the last two years, the EU has
provided TA to support the development of detailed action plans for the establishment of the
VEIS and for the implementation of the VNEEP3.
The complexity of the domestic legal framework, which undergoes frequent revisions, is a
real constraint which generates hurdles in policy development and programme
implementation.
Inter-ministerial coordination remains an issue in Viet Nam. Programmes are more likely to
succeed if they fall under the responsibility of a single ministry.
The on-going energy sector budget support programme demonstrates that budget support is a
suitable modality to influence policy orientations.
In the energy sector, the absence of a coordination mechanism between development partners
and the Government prior to 2017 has been addressed with the support of the EU and its
Member States. The Viet Nam Energy Partnership Group (VEPG) was officially established
in June 2017 and became fully operational in 2018. Through assessments of sub-sectors of the
energy sector, the 5 technical working groups of the VEPG identified key challenges and
priorities (see section 3.2 below for further details on the VEPG).
Complementarity, synergy and donor coordination 3.2
All major Development Partners (DPs) active in Viet Nam, such as WB, ADB, KfW, AFD,
GIZ, USAID and JICA, are supporting the energy sector in Viet Nam since the nineties. The
focus at that time was mainly on rural electrification, electricity generation (hydro) and
[13]
transmission. Now that the electrification rate is reaching 99 % of the households, DPs are
focusing more on the development of renewable energy, the promotion of energy efficiency
and, to a lesser extent, power market reform and energy planning. This shift of priorities is in
line with current challenges faced in the energy sector and is well reflected in the VEPG.
The EU is a fairly new player in the energy sector, but is currently the only DP providing
budget support in the energy sector. As such, EU support is particularly complementary with
interventions in the energy sector by other DPs. The action is also complementary with EU
support provided to the private sector via Climate Investor One and GET-Invest.
Most of the ODA in the energy sector is provided through sovereign loans. However with its
lower middle-income country status, Viet Nam is no longer eligible for concessional loans
from multilaterals (WB, ADB). This, coupled with the current public debt ceiling (65 % of
GDP) and the Government's decision to focus ODA on areas like transportation, health,
education, vocational training, smart urban development and irrigation, makes it challenging
for DPs to get new programmes approved.
A mapping of current donors and international support in the energy sector is available and
updated on a regular basis.
Technical assistance to enhance institutional capacities is still needed, but is rather limited.
EU and DE are the largest TA providers, including through the ongoing EU-Viet Nam Energy
Facility and the EU Technical Assistance Facility (TAF) for the 'Sustainable Energy for All'
Initiative (SE4All).
In order to improve coordination among energy sector stakeholders and to engage in thorough
policy dialogue with the Government on the necessary sector reforms, the VEPG was
launched in June 2017 and gathers all major development partners active in the energy sector
(WB, ADB, KfW, AFD, GIZ, USAID, JICA, KOICA, UNIDO, UNDP, GGGI,…). 5
Technical Working Groups (TWGs) were established on (i) Renewable Energy; (ii) Energy
Efficiency; (iii) Energy Access; (iv) Power Market Reform; and (v) Energy Data & Statistics.
Each TWG is chaired by a high official from MOIT and co-chaired by a DP's high official.
The 5 TWGs have produced a set of 40 policy recommendations to inform Viet Nam's sector
policy development and planning process. These policy recommendations have been adopted
by the VEPG High Level Meeting (chaired by MOIT Minister, EU Ambassador and World
Bank Country Director) in November 2018.
For the purpose of ensuring complementarity, synergy and coordination, the Commission may
sign or enter into joint donor coordination declarations or statements and may participate in
donor coordination structures, as part of its prerogative of budget implementation and to
safeguard the financial interests of the Union.
4 DESCRIPTION OF THE ACTION
Overall objective, specific objective(s), expected outputs and indicative activities 4.1
The overall objective is to contribute to a sustainable energy transition in Viet Nam.
The specific objectives are:
1. Improved energy efficiency (VNEEP3);
2. Larger share of renewable energy in the energy mix (REDS);
3. Improved performance of the Viet Nam Energy Information System (VEIS).
Induced outputs of the policy supported through budget support:
[14]
1. Improved energy efficiency (VNEEP3)
1.1. Legal and technical frameworks on economical and efficient use of energy are
amended and/or supplemented;
1.2. Network of energy efficiency and cleaner production units is expanded;
1.3. Average energy consumption for the industrial sectors/sub-sectors is reduced;
1.4. Key energy users apply the Energy Management System.
2. Larger share of renewable energy in the energy mix (REDS)
2.1. Existing mechanisms to encourage investment in developing RE power generation
(i.e. FIT) are revised;
2.2. Direct Power Purchase Agreements (DPPA) are allowed and the electricity market
is progressively adjusted to allow for an optimised generation and uptake of
renewable energy;
2.3. On-site renewable or hybrid energy supply for remote, deep-lying and offshore
areas are supported.
3. Improved performance of the Viet Nam Energy Information System (VEIS)
3.1. Legal framework set up and prepared for information infrastructure investment;
3.2. VEIS organisational capacity and infrastructure are strengthened.
Direct outputs will include:
- Additional fiscal space created by the transfer of funds and increased predictability
of funds;
- Continued high-level policy dialogue with the Government, jointly with other
development partners, on the energy transition in Viet Nam;
- Strengthened capacities of and coordination among key stakeholders in the energy sector,
like Government, private sector and social organisations.
Intervention Logic 4.2
The action will increase State Budget funding, the size and share of discretionary budget
allocations and aid predictability for the sustainable energy transition in Viet Nam. It will
strengthen energy sector coordination, alignment on priority energy sector policies and reduce
transaction costs. The effectiveness and sustainability of the action relies on the Government's
implementation of reforms and increased resource mobilisation. Policy dialogue between
energy stakeholders is well established and will continue in formal and informal settings, with
a high degree of institutionalization and coordination at all levels. The action will also
enhance institutional capacities and the legal and technical framework, support the
development of the private sector and increase overall awareness on the benefits of energy
efficiency and renewable energy solutions.
The expected outputs will contribute to improve energy efficiency, the share of renewable
energy in the energy mix and the performance of the Viet Nam Energy Information System.
They include strengthened legal and technical frameworks on economical and efficient use of
energy, revised mechanisms to encourage investments in RE generation, improved investment
[15]
procedures and monitoring for RE development, approved legal framework and information
infrastructure investment for the establishment of the VEIS with adequate organisational
capacity in place. These outputs are based on the provisions of respectively the VNEEP3,
REDS and VEIS, aiming to contribute to a sustainable energy transition in Viet Nam.
Mainstreaming 4.3
The action is relevant for several cross-cutting issues identified in the European Consensus on
Development: environmental sustainability, gender equality and good governance.
The overall environmental impact of the VNEEP3 and the REDS is expected to be positive
and to contribute significantly to the achievement of Viet Nam's NDCs. The EU also provides
support to the Ministry of Industry and Trade (MOIT) for the strategic environmental
assessment (SEA) of the next Power Development Plan (PDP8).
In terms of gender equality, increasing gender diversity in the energy sector is a key priority.
The action includes activities to promote this gender diversity among energy sector
stakeholders. In addition, public awareness on energy efficiency and renewable energy will
aim particularly at promoting women and girls to take up their role as drivers of change in the
energy transition. Moreover, women play a key role in household energy use in Viet Nam,
which gives them a strong potential to drive energy transition by advocating for cleaner
energy and increased energy efficiency.
Intensive policy dialogue is expected to contribute to the improvement of governance in the
energy sector. In addition, the establishment of the VEIS will facilitate the release of reliable
data that will improve decision making in the energy sector.
Contribution to Sustainable Development Goals (SDGs) 4.4
This intervention is relevant for the United Nations 2030 Agenda for Sustainable
Development. It contributes primarily to the progressive achievement of SDGs 7 "Ensure
access to affordable, reliable, sustainable and modern energy for all" and 13 "Take urgent
action to combat climate change and its impacts". By supporting the implementation of the
VNEEP3 and enhancing public awareness on energy savings, the action will also contribute to
SDG 8 "Promote sustained, inclusive and sustainable economic growth, full and productive
employment and decent work for all", SDG 9 "Build resilient infrastructure, promote
inclusive and sustainable industrialization and foster innovation", and SDG 12 "Ensure
sustainable consumption and production patterns".
5 IMPLEMENTATION
Financing agreement 5.1
In order to implement this action, it is foreseen to conclude a financing agreement with the
partner country.
Indicative implementation period 5.2
The indicative operational implementation period of this action, during which the activities
described in section 4 will be carried out and the corresponding contracts and agreements
implemented, is 72 months from the date of entry into force of the financing agreement.
Extensions of the implementation period may be agreed by the Commission’s responsible
authorising officer by amending this Decision and the relevant contracts and agreements.
[16]
Implementation of the budget support component 5.3
Rationale for the amounts allocated to budget support 5.3.1
The amount allocated for the budget support component is EUR 121 000 000, and for
complementary support is EUR 21 000 000. This amount is based on available resources
under the MIP, an initial needs assessment and the regular EU policy dialogue during the
implementation of the ongoing Energy Sector Policy Support Programme to enhance Access
to Sustainable Energy in Rural Areas of Viet Nam and in the VEPG.
Criteria for disbursement of budget support 5.3.2
a) The general conditions for disbursement of all tranches are as follows:
- Satisfactory progress in the implementation of the Renewable Energy Development
Strategy and the Viet Nam Energy Efficiency Programme 3 and continued credibility
and relevance thereof;
- Maintenance of a credible and relevant stability-oriented macroeconomic policy or
progress made towards restoring key balances;
- Satisfactory progress in the implementation of reforms to improve public financial
management, including domestic revenue mobilisation, and continued relevance and
credibility of the reform programme; and
- Satisfactory progress with regard to the public availability of accessible, timely,
comprehensive and sound budgetary information.
b) The performance indicators for disbursement that may be used for the variable tranches
are in the following areas: renewable energy, energy efficiency, energy information
system.
The chosen performance indicators and targets to be used for disbursements will apply for the
duration of the action. However, in duly justified circumstances, the Ministry of Industry and
Trade may submit a request to the Commission for the targets and indicators to be changed.
Note that any change to the targets should be agreed ex-ante at the latest by the end of the first
quarter of the assessed year. The agreed changes to the targets and indicators shall be agreed in
advance and may be authorised in writing (either through a formal amendment to the
financing agreement or an exchange of letters).
In case of a significant deterioration of fundamental values, budget support disbursements
may be suspended, reduced or cancelled, in accordance with the relevant provisions of the
financing agreement.
Budget support details 5.3.3
The disbursements under this sector reform performance contract will consist indicatively of
five fixed tranches for an amount of up to EUR 50 000 000, and five variable tranches for an
amount of up to EUR 71 000 000 amounting in total to an amount of up to EUR 121 000 000.
Indicative
breakdown
Total (in
EUR
million)
2021 2022 2023 2024 2025
Fixed tranche 50 10 10 10 10 10
Variable tranche 71 11 15 15 15 15
Total 121 21 25 25 25 25
[17]
The budget support is provided as direct untargeted budget support to the national treasury.
The crediting of the euro transfers disbursed into Viet Nam Dong will be undertaken at the
appropriate exchange rates in line with the relevant provisions of the financing agreement.
Implementation modalities for complementary support to budget support 5.4
The Commission will ensure that the EU appropriate rules and procedures for providing
financing to third parties are respected, including review procedures, where appropriate, and
compliance of the action with EU restrictive measures11
.
Grants (direct management) 5.4.1
(a) Purpose of the grants
Increasing public awareness on the benefits of renewable energy and energy efficiency is a
priority for the Government of Viet Nam. Social and professional organisations are expected
to play a key role to ensure the widespread dissemination of the information. In that context,
the EU will support public awareness activities carried out under the supervision of the
Government of Viet Nam. In addition, increasing gender diversity in the energy sector will be
a key priority in the energy transition in Viet Nam.
This grant would contribute to achieving the overall objective of the action, and more
specifically its specific objectives 1 and 2.
(b) Type of applicants targeted
Potential applicants for funding will be legal entities, priority will be given to organisations
with a strong experience in public awareness raising on sustainable energy development and
on gender diversity.
Expected results include: i) citizens and economic operators have a better understanding of
the socio-economic benefits of renewable energy and energy efficiency; 2) increased gender
diversity among energy sector stakeholders.
Procurement (direct management) 5.4.2
A facility will provide, on a demand-driven basis, expertise and capacity development in areas
such as technology and knowledge transfer through cooperation on areas like research, higher
education and R&D for renewable energy and energy efficiency, renewable energy and
energy efficiency policy, legal and regulatory frameworks, norms and technical standards,
power market analyses, energy governance, energy information systems, energy budgeting
and planning. It would contribute to the achievement of objectives 1, 2 and 3 (see section 2.1
above).
The main beneficiaries/users of the facility will be MOIT and its various subsidiary
institutions, and other energy stakeholders like the Provincial People's Committees, relevant
Committees of the National Assembly, the Ministry of Planning and Investment, the Ministry
of Finance, the Ministry of Science and Technology as well as relevant social organisations.
The facility will ensure the communication and visibility of the action.
11 www.sanctionsmap.eu Please note that the sanctions map is an IT tool for identifying the sanctions regimes.
The source of the sanctions stems from legal acts published in the Official Journal (OJ). In case of discrepancy
between the published legal acts and the updates on the website it is the OJ version that prevails.
[18]
Indirect management with the United Nations Industrial Development 5.4.3
Organization (UNIDO)
A part of this action may be implemented in indirect management with the United Nations
Industrial Development Organization (UNIDO). This implementation entails promotion,
stimulation of market demand and adoption of energy efficiency by industry and SMEs for
their greater energy performance, reduced carbon footprint and enhanced productivity &
competitiveness. This would contribute particularly to the achievement of objective 1 (see
section 2 above). The envisaged entity has been selected using the following criteria: strong
industrial energy expertise, experience from projects on energy management systems and
system optimization and SMEs projects in many parts of the world including South East Asia
and Viet Nam. This complementary support action will build on the good results of the
MOIT-UNIDO project "Promoting Energy Efficiency in Industry through System
Optimization and Viet Nam Energy Management Standards" (IEE project). In addition,
energy efficiency is an integral part of many other UNIDO projects and programmes such as
eco-industrial park, resource-efficiency and cleaner production, greening of various industrial
sectors.
In case the envisaged would need to be replaced, the Commission’s services may select
another replacement entity using the same criteria. If the entity is replaced the decision to
replace it needs to be justified.
Indirect management with the Global Green Growth Institute (GGGI) 5.4.4
A part of this action may be implemented in indirect management with the Global Green
Growth Institute (GGGI). It would contribute to the achievement of objective 1 (see section
2.1 above). It will provide support to local start-ups to create marketable innovative energy
efficiency solutions. More specifically, it will provide accelerating programmes, which
includes engaging with start-up community, providing technical guidance and financial
support. It would also aim at enhancing and creating a national network of innovative energy
efficiency start-ups. The project will act as a catalyst to get access to existing financial
support schemes such as the SME Development Fund. The envisaged entity has been selected
using the following criteria: strong engagement in the energy sector with the Government of
Viet Nam, with local and international private sector. This complementary support action will
build on the GGGI's ongoing global and pacific Greenpreneurs Programme designed to boost
green growth start-ups in developing countries12
.
In case the envisaged would need to be replaced, the Commission’s services may select
another replacement entity using the same criteria. If the entity is replaced the decision to
replace it needs to be justified.
Scope of geographical eligibility for procurement and grants 5.5
The geographical eligibility in terms of place of establishment for participating in
procurement and grant award procedures and in terms of origin of supplies purchased as
established in the basic act and set out in the relevant contractual documents shall apply.
The Commission’s authorising officer responsible may extend the geographical eligibility on
the basis of urgency or of unavailability of products and services in the markets of the
countries concerned, or in other duly substantiated cases where the eligibility rules would
make the realisation of this action impossible or exceedingly difficult.
12 http://gggi.org/greenpreneurs/
[19]
Indicative budget 5.6
EU
contribution
(amount
in EUR)
Indicative
third party
contribution
(amount
in EUR)
5.3 Budget support 121 000 000 N.A.
5.4.1 Grants (direct management) 3 500 000 N.A.
5.4.2 Procurement (direct management): EU-Viet Nam
Sustainable Energy Transition Facility
7 500 000 N.A.
5.4.3 Indirect management with UNIDO 6 500 000 N.A.
5.4.4 Indirect management with GGGI 2 500 000 53 752
5.9 Evaluation and 5.10 Audit 500 000 N.A.
5.11 Communication and visibility* 500 000 N.A.
Total 142 000 000 53 752
* Will be integrated in the EU–Viet Nam Sustainable Energy Transition Facility.
Organisational set-up and responsibilities 5.7
The Ministry of Industry and Trade (MOIT), on behalf of the Government of Viet Nam, holds
the overall responsibility for the implementation of this programme. In particular, this
concerns the preparation and transmission of the request for disbursements and the
compliance with the general eligibility criteria of the Sector Reform Performance Contract,
including budget transparency, PFM reform and macroeconomic stability.
The Electricity and Renewable Energy Authority (EREA) and the Department of Energy
Efficiency and Sustainable Development (DEESD) will cooperate with the entrusted entities
identified in section 3.4 and the EU to develop the complementary support measures'
implementation plans in a manner satisfactory to MOIT. The detailed implementation
modalities and approval mechanisms will be further defined during the inception phase of the
complementary support measures.
A steering committee will supervise the entire action. It will be co-chaired by MOIT and EU
and tentatively include representatives of EREA, DEESD and entrusted entities identified in
section 3.4.
As part of its prerogative of budget implementation and to safeguard the financial interests of
the Union, the Commission may participate in the above governance structures set up for
governing the implementation of the action.
Performance and Results monitoring and reporting 5.8
The day-to-day technical and financial monitoring of the implementation of this action will be
a continuous process, and part of the implementing partner’s responsibilities. To this aim, the
implementing partner shall establish a permanent internal, technical and financial monitoring
system for the action and elaborate regular progress reports (not less than annual) and final
reports. Every report shall provide an accurate account of implementation of the action,
difficulties encountered, changes introduced, as well as the degree of achievement of its
results (outputs and direct outcomes) as measured by corresponding indicators, using as
[20]
reference the Logframe matrix (for project modality) or the partner’s strategy, policy or
reform action plan list (for budget support).
SDGs indicators and, if applicable, any jointly agreed indicators as for instance per Joint
Programming document should be taken into account.
The Commission may undertake additional project monitoring visits both through its own
staff and through independent consultants recruited directly by the Commission for
independent monitoring reviews (or recruited by the responsible agent contracted by the
Commission for implementing such reviews).
Evaluation 5.9
Having regard to the importance of the action, mid-term & final evaluations will be carried
out for this action or its components via independent consultants contracted by the
Commission.
The mid-term evaluation will be carried out for learning purposes, in particular with respect to
the effectiveness and sustainability of the action and will offer recommendations for
improvement.
The final evaluation will be carried out for accountability and learning purposes at various
levels (including for policy revision), taking into account in particular the fact that this action
will provide substantial support for the achievement of Viet Nam's NDCs which need to
reported to the UNFCCC Secretariat.
The evaluation of this action may be performed individually or through a joint strategic
evaluation of budget support operations carried out with the partner country, other budget
support providers and relevant stakeholders.
The Commission shall inform the implementing partner at least one month in advance of the
dates foreseen for the evaluation missions. The implementing partner shall collaborate
efficiently and effectively with the evaluation experts, and inter alia provide them with all
necessary information and documentation, as well as access to the project premises and
activities.
The evaluation reports shall be shared with the partner country and other key stakeholders.
The implementing partner and the Commission shall analyse the conclusions and
recommendations of the evaluations and, where appropriate, in agreement with the partner
country, jointly decide on the follow-up actions to be taken and any adjustments necessary,
including, if indicated, the reorientation of the project.
Evaluation services may be contracted under a framework contract.
Audit 5.10
Without prejudice to the obligations applicable to contracts concluded for the implementation
of this action, the Commission may, on the basis of a risk assessment, contract independent
audits or expenditure verification assignments for one or several contracts or agreements.
It is foreseen that audit services may be contracted under a framework contract.
Communication and visibility 5.11
Communication and visibility of the EU is a legal obligation for all external actions funded by
the EU.
[21]
This action shall contain communication and visibility measures which shall be based on a
specific Communication and Visibility Plan of the Action, to be elaborated at the start of
implementation.
For the purpose of enhancing the visibility of the EU and its contribution to this action, the
Commission may sign or enter into joint declarations or statements, as part of its prerogative
of budget implementation and to safeguard the financial interests of the Union.
In terms of legal obligations on communication and visibility, the measures shall be
implemented by the Commission, the partner country, contractors, grant beneficiaries and/or
entrusted entities. Appropriate contractual obligations shall be included in, respectively, the
financing agreement, procurement and grant contracts, and contribution agreements.
The Communication and Visibility Requirements for European Union External Action (or any
succeeding document) shall be used to establish the Communication and Visibility Plan of the
Action and the appropriate contractual obligations.
[22]
6 APPENDIX – INTERVENTION LOGIC TABLE (FOR BUDGET SUPPORT)
Results chain Indicators
(max. 15)
Baselines
(year)
Targets by the end of the
budget support contract
(year)
Sources of data
Expected
impact of
the policy
(Overall
objective)
To contribute to a sustainable energy transition in
Viet Nam
1.1 Primary Energy Intensity (Energy
consumption converted to standard oil
kilogramme to produce 1 economic value unit
- kgOE/USD)
1.2 Share of renewable energy in total
electricity generated
1.1 270 kgOE/USD 1000
in 2015
1.2 5.37% in 2015
1.1 Minus 1-1.5% per year
1.2 12.5% by 2025
21% by 2030
1.1. VNEEP3
implementation report
1.2 PDP 7 revised /
PDP8 / MOIT
implementation report
Expected
outcomes of
the policy
(Specific
objective(s)
1. Improved energy efficiency (VNEEP3)
2. Larger share of renewable energy in the energy
mix (REDS)
3. Improved performance of the Viet Nam Energy
Information System (VEIS)
1.1 Percentage of power losses
1.2 Percentage of key energy users applying
the energy management system as regulated
1.3 Percentage of national energy
consumption saved
2.1 Status of the mechanism for Direct Power
Purchase Agreement (DPPA)
2.2 Status of the auctioning scheme for RE
3.1 Status of Energy Data & statistics
1.1 6.83 % in 2018
1.2 Not yet available
1.3 4.30% (4.90 mil.
TOE) in period of 2006-
10; 5.65% (11.2 mil.
TOE) in period of 2010 -
15
2.1 DPPA is not yet in
place (2019)
2.2 auctioning scheme for
RE under consideration in
2019
3.1 Sheet balancing
manufacturing / import /
export and energy
consumption are not
available (2018)
1.1 <6.5% by 2025
1.2 100% by 2025
1.3 5.0 -7.0% by 2025
2.1 DPPA template is released
by 2021
2.2 auctioning is in place by
2022
3.1 Sheet balancing
manufacturing / import / export
and energy consumption are
released by 2024
1.1 VNEEP3
implementation report
1.2 VNEEP3
implementation report
1.3 VNEEP3
implementation report
2.1 PDP 7 revised /
PDP8 / MOIT
implementation report
2.2 PDP 7 revised /
PDP8 / MOIT
implementation report
3.1 VEIS action plans in
2018 and 2024
[23]
Induced
outputs
1.1. Legal & technical frameworks on economical
and efficient use of energy are amended and/or
supplemented
1.2. Network of energy efficiency and cleaner
production units is expanded
1.3. Average energy consumption for the industrial
sectors/sub-sectors is reduced
1.4. Key energy users apply Energy Management
System
1.1. Status of Legal documents and
technical standards & guidelines
1.2. Status of the network
1.3.1. Percentage of energy consumption
reduction in steel industry;
1.3.2. Percentage of energy consumption
reduction in the chemical industry
1.3.3. Percentage of energy consumption
reduction in the cement industry
1.3.4. Percentage of energy consumption
reduction in textile and garment
industry
1.4. Status of Energy Management
System
1.1 5 issued Circulars by
the year of 2018
1.2 Some EE units under
DOITs (2019)
1.3.1 8.09% by the year of
2015 in comparison with
the year of 2011
1.3.2. 6.33% by the year
of 2015 in comparison
with the year of 2011
1.3.3. 7.32% by the year
of 2015 in comparison
with the year of 2011
1.3.4. not yet available
1.4. not yet available
1.1. 10 legal documents
(including the energy
efficiency benchmark) on
energy efficiency and
energy conservation are
reviewed &/or
supplemented (2025).
1.2. At least 50 centrally-
affiliated cities and
provinces (2025)
1.3.1. 3 to 10 % depending on
the type of products and
production technologies
(2025)
1.3.2. Min. 7% (2025)
1.3.3. Min. 7.5% (2025)
1.3.4. Min. 5% (2025)
1.4. 100% applied EMS by
2025
1.1 VNEEP3
implementation report
Other MOIT reports
1.2 VNEEP3
implementation report
Other MOIT reports
1.3. VNEEP3
implementation report
Other MOIT reports
1.4. VNEEP3
implementation report
Other MOIT reports
Induced
outputs
2.1. Existing mechanisms to encourage investment in
developing RE power generation (i.e. FIT) are
revised
2.1.1. FIT for waste to energy (W2E)
2.1.2. FIT for biomass
2.1.3. Status of the Auction mechanism
2.1.1. 10.06 USc/kWh for
W2E
2.1.2. 5.8 USc/kWh for
biomass co-generation;
7.46 USc/kWh biomass –
electricity
2.1.3. Auction mechanism
is not in place (2019)
2.1.1. FIT for waste to energy is
revised (2021)
2.1.2. FIT for biomass is
revised (2021)
2.1.3. Auction mechanism is
applied (2022)
2.1.1. & 2.1.2 PM's
decisions and
subsequent MOIT
implementation
circulars
2.1.3. Approved
mechanism by the
relevant authority
[24]
2.2. Direct Power Purchase Agreements (DPPA) are
allowed and the electricity market is
progressively adjusted to allow for an optimised
generation and uptake of renewable energy
2.3. On-site renewable or hybrid energy supply for
remote, deep-lying and offshore areas are
supported
3.1. Legal framework set up and prepared for
information infrastructure investment
3.2. VEIS organisational capacity and infrastructure
are strengthened
2.2. a) Status of DPPA regulation
b) Status of Electricity Reform
Roadmap
2.3. Status of off-grid systems operating in
remote offshore islands
3.1. Status of VEIS investment project
3.2. Status of Staff
2.2. a) DPPA is not
available (2019)
b) Electricity
Wholesale Market
operation phase is
ongoing (2019)
2.3. 3 islands are supplied
by fuel generators (2019)
3.1. Not yet available
(2019)
3.2. To be recruited
(2019)
2.2. a) DPPA regulation is
applied (2021)
b) Electricity Wholesale
Market is fully
operational in 2021.
Electricity Retail Market
pilot operation is
concluded in 2023.
2.3. 3 islands are provided
with cleaner solutions
(2025)
3.1. VEIS investment project
is approved (2021)
3.2. Staff is assigned and
trained (2022)
2.2. MOIT
implementation report
2.3. MOIT
implementation report
3.1. MOIT
implementation report
3.2 MOIT
implementation report
Direct
outputs
1. Additional fiscal space created by the transfer of
funds and increased predictability of funds
2. Continued high-level policy dialogue with the
Government, jointly with other development
partners, on the energy transition in Viet Nam
3. Strengthened capacities of and coordination among
key stakeholders in the energy sector, like
Government, private sector and Social Organisations
1.1 Amount of external assistance made
available through the national budget
2.1 Status of Policy dialogue and
recommendations in the context of VEPG
3.1 Provision of ad-hoc TA on a demand-
driven basis to the institutional stakeholders
involved in the energy sector
1.1 € 100 million (2018-
2020)
2.1 40 policy
recommendations
endorsed (Nov 2018)
3.1 Ongoing EU-Viet
Nam Energy Facility
1.1 Extra €121 million by 2025
2.1 VEPG meetings at high
level follow-up on policy
recommendations at least once
a year
3.1 Approximatively 4,500
person days of short-term TA
are provided by the EU through
the EU-Viet Nam Sustainable
Energy Transition Facility in
2025
1.1 Disbursement files
submitted to the BSSC
2.1 VEPG minutes and
proceedings
3.1 Implementation
report of the
implementing partners