  • Romanian owned & run since 1998

    Flexibility

    Efficiency

  • As a regional leader in power T&D and turn-key projects emons mission is:

    to deliver high voltage solutions using state-of-the-art technology

    to provide high product quality

    superior customer service

    by continuously investing in man power,

    technology and research

    encouraging initiative and innovation

    practicing sustainable development

    to permanently improve our products &

    services

    answer the increasing needs of our clients

    develop and consolidate as a reliable company

    Our Mission

  • Five years from now emon will be:

    supplier for turn key solution for HV in Western Europe

    developer of SMART-GRID & Energy Storage projects

    developer and investor of renewable energy projects

    Our Vision

  • Contractor Consulting & engineering Service & maintenance

    Manufacturer & supplier Installer

  • Project management engineering and technical support time & resource management health quality and safety communication platform

  • Risk Management Developer Investor Design quality Permits Authorities Project finance Suppliers noncompliance Logistics restrictions Weather hazards

  • The SCADA System & Smart Grid challenges:

    Protection

    Control

    Automation

    Measurements

    Monitoring

    Recording P&C :over 200 P&C panells

    manufactured & commissioned

    ~ 21 substation full SCADA system implemented by Emon

    SCADA, P&C, Smart Grid

  • The Project was co-financed by emon & EU funds

    Evolving through a better way to manage

    Compete better in a fast-changing world

    Integrate the entire companys processes

    Gain a complete, timely view of the business

    Real time resource planning

    SAP Resource Management

  • GSM Infrastructure VODAFONE, ORANGE, Romtelecom

    TRAM of Athens, 15 TPS , Energy Control center, SCADA

    TRAM of Athens Maintenance contract

    Metro TERNA Energy 4 TPS L4, Anthoploly Peristeris

    Secheron Switzerland ATTIKO Metro Haidary

    SIEMENS AG TPS for railway CFR Ploiesti Vest Columbia

    SIEMENS SRL Ploiesti Cring, Busteni SS 110/MT

    SIEMENS AG Austria L12 TRAM of Bucharest

    AREVA T&D ALSTOM Grid SS 220/110kV Tirgoviste

    SS 220/110kV Paroseni

    SS 110/20kV Brasov Centru

    SS 110/20kV Tractorul

    SS 400 Tariverde Transelectrica

    SS 110 kV Tariverde CEZ wind farm main transformer station

    TOSHIBA Corporation SS 400/220/110kV Brazi Vest GIS

    Wind farm developers: Engineering & design more than 10 projects >500 MW

    Key References

  • Eastern markets continue to provide a solid source of demand in the wind sector

    Romania will become a wind power center >8GW

    Renewable quota for Romania 20%

    Barclays Capital Renewables Outlook

    11 January 2011

    Renewable Outlook for Romania

  • 240 wind turbines (installed capacity of 600MW)

    3 SS 110/33kV

    1 MTS 110/400kV, 3x250MVA

    Tariverde - CEZ Wind Farm

    Wind farm specs and schematics

  • Emon & Alstom Consortium

    400/110 kV, 3x 250 MVA

    MTS Tariverde is designed to connect five wind parks

    The time schedule planned was 36 months

    The wind parks deliver electricity into the grid with a rated capacity of 200 MW

    The total contract value was 31,5 million

    Tariverde - CEZ Wind Farm

    Main Transformer Station

  • Emon & Toshiba Consortium

    400/220 kV, 3x 250 MVA

    MTS Brazi Vest is designed as an extension for PETROM Gas Power Plant 900 MW

    GIS Technology

    Primary circuits & Secondary circuits P&C System

    Technical assistance at Test Checking, Commissioning and start-up

    Brazi Vest PETROM Gas Power Plant

    Main Transformer Station

  • Electrical Infrastructure for Athens Tram -Olympic Games 2004

    Electrical Infrastructure for Line 2 Attico Metro Antoupoli Peristeris - 2012

    emon Electric Abroad Turn Key Projects

  • Main Goal: continuous improvement of customer satisfaction through an implemented and certified IMS

    Transparency of our policy

    Continuous improvement of the activity & service quality

    Implication & commitment of employees through periodical training

    Permanent monitoring of customer satisfaction

    Compliance of the applicable legal and regulated requirements

    *IMS (Integrated Management System Manual) pg.20 Declaration of Policy in Quality, Environment, Work Safety and Health

    HSE Philosophy Quality Policy

  • Restless in achieving our goals

  • Quality is our no.1 priority

  • Continuous improvement of the environment performance:

    by avoiding pollution and ecological accidents

    by preserving the ambient and natural resources

    by respecting the right to a healthy life of the local community and our employees

    by preventing soil, air & water contamination through proper and selective waste management

    * IMS (Integrated Management System Manual) pg.20 Declaration of Policy in Quality, Environment, Work Safety and Health

    HSE Philosophy Environment Policy

  • Protecting the quality of the environment

  • Providing the employees a safety and healthy work environment through :

    identifying the dangers that might occur

    permanent monitoring and control of the unavoidable risks

    minimizing or isolating the risks for our own employees, suppliers, clients & visitors

    promptness in taking actions to improve the safety levels

    * IMS (Integrated Management System Manual) pg.20 Declaration of Policy in Quality, Environment, Work Safety and Health

    HSE Philosophy Health & Safety Policy

  • Providing a healthy & safety environment

  • Romania: TRANSELECTRICA, TSO Energy distribution operators Renewable industry Railway & city infrastructures Industry - energy solutions Telecom infrastructures

    Switzerland: SECHERON Delivery Electrical

    equipment for LV DC cubicle for traction substation

    Greece: TRAM ATEHNS turn key Projects ATTIKO METRO turn key Projects

    Germany: Siemens Delivery Electrical equipment P&C ALSTOM GRID Delivery of electrical