1 EMERGENCY GENERATORS Bill Lauzon, PE Heather Werner, BS Lauzon Life Safety Consulting, LLC 262-945-4567 Website: Lauzon-LSC.com JAN ‘15 - LUNCH & LEARN

EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

1

EMERGENCYGENERATORS

Bill Lauzon, PEHeather Werner, BS

Lauzon Life Safety Consulting, LLC262-945-4567

Website: Lauzon-LSC.com

JAN ‘15 - LUNCH & LEARN

Page 2: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

Lauzon Life Safety Consulting, LLC262-945-4567

[email protected]

Heather Lauzon Werner• Experienced Life Safety Inspector• Current Director of Environment of Care

Lakeview Specialty Hospital & CBRF• Experienced with CMS, Joint Commission & CARF Surveys

JAN ‘15 - LUNCH & LEARN

YOUR PRESENTERS:

Page 3: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

3

Bill Lauzon, PE

1973-2006“Facility Engineer”

Tomah – Fargo- Madison Kenosha - Racine

2006-2011DHS-DQA

2011-presentLauzon Life Safety

Consulting, LLCStatewide Consultant

YOUR PRESENTERS:

Page 4: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

4

EMERGENCY GENERATORS

Page 5: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

5

EMERGENCY GENERATORS

Page 6: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

6

1. PRIMARY

2. BACK-UP

CO-GENERATION

EMERGENCY GENERATORS

Page 7: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

7

JAN ‘15 - LUNCH & LEARN

Page 8: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

8

JAN ‘15 - LUNCH & LEARN

Jan

Generators

Feb

Life Safety Plans

Mar

Waste Streams

Apr

TBD

May

TBD

Jun

TBD

Jul

Marge’s Hot Topic

Aug

TBD

Sep

TBD

Oct

TBD

Nov

TBD

Dec

TBD

TENTATIVE 2015 LUNCH & LEARN CALENDAR

Page 9: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

9

JAN ‘15 - LUNCH & LEARN

Jan

Generators

Feb

Life Safety Plans

Mar

Waste Streams

Apr

TBD

May

TBD

Jun

TBD

Jul

Marge’s Hot Topic

Aug

TBD

Sep

TBD

Oct

TBD

Nov

TBD

Dec

TBD

TENTATIVE 2015 LUNCH & LEARN CALENDAR

Topics Under Development:

• NFPA 99 Risk Assessment• Record Keeping• Fire Drills• LSC 2012 Update• Fire Dampers• Energy Conservation

• OSHA’s Health Care Issues• Humidification• Electrical Testing• Infection Control• Interim Life Safety Measures• Others

Page 10: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

10

EMERGENCY GENERATORS

Agenda1. REGULATIONS (NFPA 101, 99, 110; TJC, NEC)

2. COMPLIANCE CONFUSIONS

3. INSTALLATION requirements

4. INSPECTIONS requirements

Page 11: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

11

EMERGENCY GENERATORS

I wonder if there will many questions

this month?

Page 12: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

12

Agenda

1. REGULATIONS (NFPA 101, 99, 110; TJC, NEC)

2. COMPLIANCE CONFUSIONS

3. INSTALLATION requirements

4. INSPECTIONS

EMERGENCY GENERATORS

Page 13: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

13

3 Big AHJs follow the same Code

(but different editions)

GENERATOR REGULATORS

Page 14: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

14

3 Big

AHJs

GENERATOR REGULATORS

Page 15: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

15

GENERATOR REGULATIONS

Page 16: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

16

GENERATOR REGULATIONS

10199 110

Page 17: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

17

1. LSC 18.2.9.2 – Emergency Lighting2. LSC 7.9.2.3 – Emergency Lighting3. LSC 18.2.10.2 – Exit Signs4. LSC 18.5.1.2 – Alarm, Comm, Gen Lite5. LSC 18.5.1.3 – Life Support6. 99 3-4.1.1 – Gen Set - Level 1 EES7. 99 3-4.4.1.1 – Gen Maintenance8. 99 3-5.1 – Gen Set – Level 2 EES9. 99 3-6.1 – Gen Set – Level 3 EES10. 110 Emergency Standby Systems

At least 10 Locations

GENERATOR REGULATIONS

New

Existing

Page 18: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

18

18.2.9.2: “Buildings equipped with or in which patients require the use of life-support systems shall have EMERGENCY LIGHTING equipment supplied by the life safety branch of the electrical system as described in NFPA 99”

This wording in NOT in Chapter 19

GENERATOR REGULATIONS

Page 19: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

19

7.9.2.3: “Emergency generators providing power to EMERGENCY LIGHTING systems shall be installed , tested, and maintained in accordance with NFPA 110”

(ALSO applies to Existing Health Care)

GENERATOR REGULATIONS

Page 20: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

20

18.2.10.2: “Buildings equipped with or in which patients require the use of life-support systems shall have ILLUMINATION OF THE REQUIRED EXIT AND DIRECTIONAL SIGNS supplied by the life safety branch of the electrical system as described in NFPA 99” This wording in NOT in Chapter 19

GENERATOR REGULATIONS

Page 21: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

21

18.5.1.2: “Power for ALARMS, emergency communication systems, and illumination of generator set locations shall be in accordance with the essential electrical system requirements of NFPA 99”

This wording in NOT in Chapter 19

GENERATOR REGULATIONS

Page 22: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

22

18.5.1.3: “Any health care occupancy…that normally uses LIFE-SUPPORT DEVICES shall have electrical systems designed and installed in accordance with NFPA 99”(Exception: “Not apply to a facility that uses life-support equipment for emergency purposes only)

This wording in NOT in Chapter 19

GENERATOR REGULATIONS

Page 23: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

23

3-4.1.1: GENERATOR SET• One or more alternative sources

for use when the normal source is interrupted”

• On-Site• Under the Control• Comply with NFPA 110• Exclusive Use• 10 Sec Transfer• Safety Devices & Annunciators• ATS Features

Does NOT apply to Existing HC

GENERATOR REGULATIONS

Page 24: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

24

3-4.4.1.1: GENERATOR MAINT.• Maintenance shall be

performed in accordance with NFPA 110

Does NOT apply to Existing HC

GENERATOR REGULATIONS

Page 25: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

25

3-5.1: TYPE 2 EES (Nursing H)“The requirements for sources for Type 2 essential electrical systems shall confirm to those listed in 3-4.1”

Does NOT apply to Existing HC

GENERATOR REGULATIONS

Page 26: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

26

3-6.1: TYPE 3 EES (Ambulatory)“Generators shall confirm to 3-4.1.1”

Does NOT apply to Existing HC

GENERATOR REGULATIONS

Page 27: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

27

NFPA 110: Emergency & Standby Power Systems

• 3 - Generator Requirements• 4 – Switching Requirements• 5 – Install Requirements• 6 – Test Requirements

Apply to Existing HC via LSC 7.9.2.3

GENERATOR REGULATIONS

Page 28: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

28

CATEGORICAL WAIVERS

1. Unoccupied Stair Openings 2. Door Locking3. Delayed Egress Locking4. Suite Size & TD5. Sprinkler Testing6. Fire Pump Testing7. OR Humidity8. Fireplaces-Direct Vent

9. Fireplaces-Solid Fuel10. Corridor Kitchens11. Corridor Obstruction12. Combustible Decorations13. Waste Container Size14. Med Gas Alarms15. GENERATOR LOAD BANKING16. Strip Plugs

Page 29: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

29

CATEGORICAL WAIVERCHECKLIST

Page 30: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

30

CATEGORICAL WAIVERCHECKLIST

2-Hr

1-1/2 Hr Run Time

Page 31: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

31

2012 Adoption Impact on GENERATORS

Page 32: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

32

1. LSC 18.2.9.2 – Emergency Lighting2. LSC 7.9.2.3 – Emergency Lighting3. LSC 18.2.10.2 – Exit Signs4. LSC 18.5.1.2 – Alarm, Comm, Gen Lite5. LSC 18.5.1.3 – Life Support6. 99 3-4.1.1 – Gen Set - Level 1 EES7. 99 3-4.4.1.1 – Gen Maintenance8. 99 3-5.1 – Gen Set – Level 2 EES9. 99 3-6.1 – Gen Set – Level 3 EES10. 110 Emergency Standby Systems

SameSameSameSameSame

ExpandedExpanded

SameSame

Expanded

In At least 10 Locations

2012 Adoption Impact on GENERATORS

Page 33: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

HEALTH CARE CODEChapter 6 – Electrical

Section 6.4.3—Performance Criteria &Testing Covers EES Type 1 performance criteria to assure that the EES is safe and reliable. Includes:

• Maintenance, inspection and testing of the EES alternate power source, including generator testing criteria, test conditions, and testing personnel qualifications

• Specific maintenance, inspection and testing requirements are also required through reference to NFPA 110, Standard for Emergency and Standby Power Systems

• Maintenance & testing of EES circuitry

• Record keeping requirements. 33

Page 34: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

34

RECOMMENDATION:

Buy the Handbook

Page 35: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

35

If the Past is any Indication:Steps

1. Proposed Rule2. Final Rule Action3. S&C Adopt Ltr4. Effective Date 5. Survey Start

Biggest Question: WHEN will

The 2012 LSC be effective?

Projected2012 LSC Adoption

Apr 2014 (+13 mo) May 2015(+2 mo) Jul 2015(+2 mo) Sep 2015(+6 mo) Mar 2016

2000 LSC AdoptionOct, 2001Nov, 2002Jan, 2003Mar, 2003Sep, 2003

Page 36: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

36

3 Big

AHJs

GENERATOR REGULATORS

Page 37: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

37

Environment of Care

Page 38: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

38

Environment of Care-1Generators

EC.02.05.01 – RISK MANAGEMENT• EP 1 – Installed per Code• EP 2 – Utility Sys Inventory• EP 3 – Maintenance Sys• EP 4 – Frequencies• EP 7 – Drawings• EP 8 – Shut-down Info• EP 9 – Disruption Plans• EP 12 – Repair Service

Page 39: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

39

Environment of Care-2Generators

EC.02.05.03 – EMERGENCY SYS• EP 1-9 – Feeds Required Areas

EP.02.05.05 – SYS MAINTENANCE• EP 1-5 – Per Code Requirements

Page 40: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

40

Environment of Care-3Generators

EC.02.05.07 – ELECTRICAL MAINT.• EP 4- Monthly Gen Exercise• EP 5 – 30% Load• EP 6 – Monthly ATS Test• EP 7 – 3 Yr, 4 Hr Test (110-2005)• EP 8 – 3 Yr Test @ 30% (110-2005)• EP 9 – Failure Protective Measures• EP 10 – Retest After Repairs

Page 41: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

41

Environment of Care-4Generators

EM.02.02.09 – EMERG OP PLAN • EP 2 – Alternate Elect Provision

LS.02.01.20 – MEANS OF EGRESS• EP 32 – All Other Code

Requirements

Page 42: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

42

EMERGENCY GENERATORS

Agenda1. REGULATIONS (NFPA 101, 99, 110; TJC, NEC)

2. COMPLIANCE CONFUSIONS3. INSTALLATION requirements

4. INSPECTIONS requirements

Page 43: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

43

GENERATORCompliance Confusions

Often Confused Conditions

1 - NEW vs EXISTING• LSC Chapter 18 is Different than Chapter 19• NFPA 99 Applies to New Installation • NFPA 70, Art 715 Applies to New Installation

Page 44: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

44

1- NEW vs EXISTING

DQA: Likes to enforce the NEW CONSTRUCTION CODE THAT WAS IN EFFECT

when the facility was built or remodeled

RATHER THANthe existing code (chapter 19)

• TJC does not• CMS does not

Page 45: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

45

2 – FUEL SOURCE

• On-Site Storage (Diesel) vs Reliable Service (NG)• 30% Exception for Diesel only

GENERATORCompliance Confusions

Page 46: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

46

3 – CODE EDITION

• 2000 LSC vs newer editions• NFPA 110 – 1999 edition vs 2005 edition (TJC)• NFPA 70 (NEC) – 2011, 2008, 2005 by Wis

GENERATORCompliance Confusions

Page 47: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

47

4 – LEVEL vs TYPE

GENERATORCompliance Confusions

• NFPA 110 – LEVEL = Stringency of Performance1 – Failure has serious life consequences2 - Failure less critical

• NFPA 99 – TYPE = Kind of Essential Elect Sys1 – Life Support 2 – No Life Support3 - Ambulatory

Page 48: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

48

5 – EPS, EES vs EPSS• EPS = Emergency Power Supply

(generator/ancillary equip, NFPA 110)• EES = Essential Electrical Sys

(the Alternate source of power & all distribution equipment, NFPA 99)

• EPSS = Emerg Power Supply System (the Alternate source of power & all distribution equipment-NFPA 110)

Often Confused Conditions

GENERATORCompliance Confusions

Page 49: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

49

Often Confused Conditions

GENERATORCompliance Confusions

EES/EPSS

EPS

Page 50: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

50

EMERGENCY GENERATORS

Agenda1. REGULATIONS (NFPA 101, 99, 110; TJC, NEC)

2. COMPLIANCE CONFUSIONS

3. INSTALLATION requirements

4. INSPECTIONS requirements

Page 51: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

51

GENERATORINSTALLATION

110: Emergency & Standby Power Systems

Chapters:• 3 - Generator Requirements• 4 – Switching Requirements• 5 – Install Requirements• 6 – Test Requirements

Apply to Existing HC via LSC 7.9.2.3

Page 52: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

52

3-1 - Level 1 – Energy Source

On Site Fuel Storage required if probability of interruption is high

110: EMERGENCY & STANDBY POWER SYSTEMS

GENERATORINSTALLATION

Page 53: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

53

NATURAL GAS FUEL SOURCECMS Region 5 Release (5/29/2009)

“If a facility uses a natural gas generator to provide backup power to LSC required systems (i.e., emergency lights, exit lights, fire alarm system, etc.), the facility may obtain a letter from its natural gas vendor to demonstrate the fuel source is reliable and to meet the requirements for an on-site backup power source.

The letter of reliability from the vendor regarding the fuel supply must contain all of the following:1. A statement of reasonable reliability of the natural gas delivery 2. A brief description that supports the statement regarding the

reliability 3. A statement that there is a low probability of interruption of the

natural gas 4. A brief description that supports the statement regarding the

low probability of interruption 5. The signature of technical personnel from the natural gas

vendor “

Page 54: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

54

SAMPLE Natural Gas Provider Letter

Page 55: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

55

SAMPLE Natural Gas Provider Letter

Page 56: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

56

3-5.4.5 – TYPE OF BATTERY“ Starting batteries for Level 1 installations shall NOT be of the maintenance-free variety”

110: EMERGENCY & STANDBY POWER SYSTEMS

* 3-5.4.5 – (Appendix A)“It is recommended that lead-acid starting batteries be replaced every 24 to 30 months.”

GENERATORINSTALLATION

Page 57: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

57

3-5.5 – CONTROL FUNCTIONS: Control panel shall have:

• Auto remote start capability• Run-Off-Auto switch• Shutdowns• Alarms• Controls• Remote Stop switch

110: EMERGENCY & STANDBY POWER SYSTEMS

GENERATORINSTALLATION

Page 58: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

58

3-5.6 – REMOTE CONTROL & ALARMS:• Remote, common audible alarm• Powered by storage battery• 20 specified indicators/functions

110: EMERGENCY & STANDBY POWER SYSTEMS

GENERATORINSTALLATION

Page 59: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

59

5-2 – EPS LOCATION:• Separate room (level 1), 2-hr enclosure• EPSS not in room with normal power• Minimize flood potential

110: EMERGENCY & STANDBY POWER SYSTEMS

GENERATORINSTALLATION

5-3 – EPS LIGHTING• Battery powered emergency lite

Page 60: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

60

5-13 – ACCEPTANCE:• Full load test for 2 hrs• Cycle Crank test• Documentation to AHJ

110: EMERGENCY & STANDBY POWER SYSTEMS

GENERATORINSTALLATION

Page 61: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

61

Agenda1. REGULATIONS (NFPA 101, 99, 110; TJC, NEC)

2. COMPLIANCE CONFUSIONS

3. INSTALLATION requirements

4. INSPECTIONS

EMERGENCY GENERATORS

Page 62: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

62

6-1.1: “The routine maintenance and operational testing program shall be based on the MANUFACTURER’S RECOMMENDATIONS, instruction manuals, and the minimum requirements of this chapter and the authority having jurisdiction.”

Usually not a Document Review issue because most use a mfgr rep for

annual maintenance.

110: EMERGENCY & STANDBY POWER SYSTEMS

EMERGENCY GENERATORS

Page 63: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

63

6-2 – Manuals, Tools & Parts• Manuals near Level 1 sys• High mortality Parts on-site

110: EMERGENCY & STANDBY POWER SYSTEMS

GENERATORINSPECTIONS

Page 64: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

64

6-3 – EPSS Maintenance Program• Written schedule• Written record• Transfer switch program• Batteries inspected every 7 days, (including

electrolyte levels)

EPSS = Emerg Power Supply System

(the Alternate source of power & all distribution equipment-NFPA 110)

110: EMERGENCY & STANDBY POWER SYSTEMS

GENERATORINSPECTIONS

Page 65: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

65

GENERATORINSPECTIONS

Page 66: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

66

ALL Inspection documents must show:

1. WHO did the inspection? (have documentation of qualifications; if using Initials, a conversion to names)

2. WHAT was inspected? (If multiple devices, list each one w/location)

3. WHEN was the inspection performed?

4. HOW was the inspection performed? (describe method used & criteria for pass/fail)

5. DEFICIENCIES were corrected? (Document Who, What, When of correction)

Joint Commission:EC.02.03.05, EP25

CMS:Instructions to Surveyors

Page 67: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

67

6-4.1 – Weekly Inspection

• Includes all appurtenant components

110: EMERGENCY & STANDBY POWER SYSTEMS

XX

XX

GENERATORINSPECTIONS

Page 68: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

68

Zero in on GENERATOR INSPECTIONS

Page 69: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

69

Generator Inspection - WEEKLY

XX

XX

XX

X

Compare the FORM

(left)

The Code REQUIREMENTS

(right)Against

Page 70: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

70

Generator Inspection - WEEKLYWeekly exercise is not required

Page 71: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

71

Generator Inspection - WEEKLY

XXXX

XX

Compare the FORM

(left)

The Code REQUIREMENTS

(right)Against

Page 72: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

72

Generator Inspection - WEEKLY

XX

Page 73: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

73

Recommended

WEEKLY

FormPDF Available for FREE at:Website: Lauzon-LSC.com

Code Central Members can download the excel version

that is editable

Page 74: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

74

6-4.2 – Monthly Exercise• 30 Minute, Under Load• Load measured by:

• 30% of Nameplate rating, or• Min exhaust gas temperature, or• Annual 2 hr load bank (diesel only)

(25%-30m, 25%-30m, 75%-60m)

110: EMERGENCY & STANDBY POWER SYSTEMS

GENERATORINSPECTIONS

Page 75: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

75

110: EMERGENCY & STANDBY POWER SYSTEMS

6-4.4 – Time Delays• Min 5 min restore to normal• Min 5 min shut-down

GENERATORINSPECTIONS

Page 76: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

76

110: EMERGENCY & STANDBY POWER SYSTEMS

6-4.5 – Auto Transfer Switches• Operate Monthly

GENERATORINSPECTIONS

Page 77: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

77

Generator Exercise - MONTHLY

Shows the Who & When but not any of the DETAILS of the Exercising

Compare the FORM

(left)

The Code REQUIREMENTS

(right)Against

Page 78: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

78

Generator Exercise - MONTHLY

What does it take to ‘earn’ an

“OK”?

Page 79: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

79

Generator Exercise - MONTHLY

Total Run TimeMust be at least 35 Min; .5-Hr is not enough

Need to confirm 30% calc, since nameplate

isn’t shown

Compare the FORM

(left)

The Code REQUIREMENTS

(right)Against

Page 80: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

80

Generator Exercise - MONTHLYTotal Run TimeMust be at least 35 Min; .5-Hr is not enough

Need to confirm 30% calc, since nameplate isn’t shown & checks are easy to duplicate

Page 81: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

81

Generator Exercise - MONTHLYSatisfactory as a summary sheet, but specific monthly data is required

Page 82: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

82

Generator Exercise - MONTHLY

Total Run TimeMust be at least 35 Min; .5-Hr is not enough

Show the # Seconds

Show the # Actual Amps & FLA

30 min under load + cool down (per mfgr)

Page 83: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

83

Generator Exercise - MONTHLY

Less Complicated Calc:Target = >.3 x FLAAvg Amps > Target

Page 84: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

84

Recommended

MONTHLY

FormPDF Available for FREE at:Website: Lauzon-LSC.com

Code Central Members can download the excel version

that is editable

Page 85: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

85

Recommended

MONTHLY

Form

PDF Available for FREE at:Website: Lauzon-LSC.com

Code Central Members can download the excel version that is

editable

Page 86: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

86

TOP PORTION

Page 87: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

87

CENTER PORTIONCriteria for Pass

Page 88: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

88

BOTTOM PORTION

Page 89: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

89

Load Bank Test

XX

Page 90: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

90

110: EMERGENCY & STANDBY POWER SYSTEMS

6-4.6 – EPSS Circuit Breakers (Level 1 sys)• Operate Annually with EPS Off• Operate Semi-Annual if Med & Hi-voltage• Test every 2 yr if Med & Hi-voltage

GENERATORINSPECTIONS

Page 91: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

91

6-4.6 – EPSS Circuit Breakers (Level 1 sys)• Operate Annually with EPS Off• Operate Semi-Annual if Med & Hi-voltage• Test every 2 yr if Med & Hi-voltage

Page 92: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

92

WHAT WE COVERED1. REGULATIONS (NFPA 101, 99, 110; TJC, NEC)

2. COMPLIANCE CONSIDERATIONS

3. INSTALLATION requirements

4. INSPECTIONS

EMERGENCY GENERATORS

Page 93: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

93

EMERGENCY GENERATORS

Page 94: EMERGENCY GENERATORS - WHEA · Steps 1. Proposed Rule 2. Final Rule Action 3. S&C Adopt Ltr 4. Effective Date 5. Survey Start Biggest Question: WHENwill The 2012 LSC be effective?

94

EMERGENCYGENERATORS

Bill Lauzon, PEHeather Werner, BS

Lauzon Life Safety Consulting, LLC262-945-4567

Website: Lauzon-LSC.com

JAN ‘15 - LUNCH & LEARN