Upload
others
View
8
Download
0
Embed Size (px)
Citation preview
ELEMENTS OF A EFFECTIVE
CATHODIC PROTECTION
PROGRAM
Diego Politano
Con Edison
Agenda
• Design
• Coatings
• Coating Resistance
• Cathodic Protection
• Test Stations
• Isolation
• Existing Transmission Mains
Design
• Try to keep it consistent
– Contractors/employees are familiar with materials
– Installation practices are similar
– Coatings
• Mill
– Extruded Polyethylene
• Field
– Cold applied tape
– Coal tar
– Epoxy
Design (continued)
• Boiler plated approach on
– Short segments of distribution mains
– Services
• Transmission and Distribution installation of long segments of pipe
– Review of layouts
– Technicians are present on site when requested by company inspector
– Technicians log daily activity
• Work done – one line sketch
• Resistance of coating to ground4
Coatings
• Mill Coating - Extruded polyethylene
– Predominately used on our system
– Durable coating
– 40-60 mils thick
– Holiday Detector set at 12kV to 15kV
• Pipe type feeders 18 kV to 20 kV
– Repairs are minimal
Coatings (continued)
• Welded joints– Pipe preparation is key for any coating
– Clean surface
– Cold applied tapes• “X” test QA - technicians
– Two part epoxy - Cost
• Welded offsets– Clean surface
– Coal tar – still effective• Visual and Holiday Detected
– Cold applied tape • with primer if needed
– Two part epoxy
Coatings (continued)
• Be present at the site when requested
• Monitoring coating operation
– Cleaning
– Application
– If coal tar – kettle temperature
– Two – part epoxies – ensure that the thickness readings are taken
7
Coating Resistance
• Gas mains
– 1,000,000 ohms per square foot – Transmission
– 500,000 ohms per square foot – DistributionExample:
2πr = πd x L (Backfilled Surface Area)
ΩSq.ft.₌ required measured Ω
Sq.ft (backfilled)
Coating Resistance (continued)
• The more resistant/the less current needed to protect (polarize) the pipe
• Any coating faults are minimal in size
• Faults can be located
– Over-ground survey
– ACCA – A-Frame
• Technicians present
– Witness the holiday detection
– Inspect conditions
– Monitor backfill operation
Cathodic Protection
• Pipe has a highly resistant to ground
• Galvanic anodes
– At the test stations
– Pipe and anodes leads in test station
– Individual anode current measured
• Current in the negative direction
– Anode current effect can be recorded at other stations
Test Stations
• Spaced according to lengths of pipe installed
– Isolating Joint test stations ( approx. 1,000’- 2,500’)
• Color coded test leads
– Magnesium Anode test stations typically placed 500’ apart.
• Detailed drawings
– Locations
– Landmarks
– Other details
Test Stations Continued
• Pipe test leads
• Anode leads
• Test stations are positioned next to pipe and for access near the
surface of the pipe
• 4-32 lbs. anodes at each IJ station
• 2-32 lbs. anodes at test station
• WHY?
– It costs less than opening the street again 12
13
Isolation
• Gas Transmission
– 2,500 feet
• Sometimes closer
– Any regulator inlet line
– Isolation between two different vintages
– Regulator vaults
• Distribution
– Isolation joints are installed at:
• Service tee
• Separate different vintages
• Above ground piping14
Existing Transmission Mains
• Transmission system
– Early as1948 coal tar coated pipe
– 97% protected by impressed current
– All test points tested annually (300’ - 500’ apart)
• From original mag-anode system
– Inspected whenever exposed (Inspection Form)
• Third party excavations
• Exposed by company forces
• Condition of coating is documented
• Pipe to soils recorded
• Soil resistivity and pH tested15
Existing Transmission mains (continued)
• Transmission (cont.)
– More information taken the better
– Ensure CP is at or above criteria
• At pipe level
• Four readings taken at each wall
– Coating is intact – no anomalies
16
Existing Transmission mains (continued)
• ECDA
– Yields good information
• Get hands on the pipe at excavations
• Thorough inspection
– Investigate areas of pipe to soil readings below criteria taken during ECDA surveys
• Only the close interval survey
– Resurvey
• install more protection
17
Technicians
• Eyes and ears in the field
• Training
• Share their experiences with group
– Investigations
– Observations
18
19
Thank you
2007 tape coat
20